CN104636880A - Method and system for project management process feedback and deviation analysis - Google Patents

Method and system for project management process feedback and deviation analysis Download PDF

Info

Publication number
CN104636880A
CN104636880A CN201510094390.8A CN201510094390A CN104636880A CN 104636880 A CN104636880 A CN 104636880A CN 201510094390 A CN201510094390 A CN 201510094390A CN 104636880 A CN104636880 A CN 104636880A
Authority
CN
China
Prior art keywords
wbs
task
deviation
progress
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510094390.8A
Other languages
Chinese (zh)
Other versions
CN104636880B (en
Inventor
万军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing high beam Guang'an Mdt InfoTech Ltd
Original Assignee
Nanjing Guangan Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Guangan Technology Co Ltd filed Critical Nanjing Guangan Technology Co Ltd
Priority to CN201510094390.8A priority Critical patent/CN104636880B/en
Publication of CN104636880A publication Critical patent/CN104636880A/en
Application granted granted Critical
Publication of CN104636880B publication Critical patent/CN104636880B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a method and a system for project management process feedback and deviation analysis. The method comprises the following steps of 1, progress plan planning; 2, progress feedback; 3, deviation analysis and display. The method and the system have the advantages that the progress feedback realizing quantitative and qualitative combination is realized, meanwhile, the integral progress feedback integrating the generated problem, the current actual progress and the future risk is realized, the progress and the weight of all subordinate tasks are integrally considered, high-level stage WBS (work breakdown structure) and project actual progress are formed through summarizing, the task and WBS actual progress and time plan are used for comparison, and a respective actual execution deviation is formed, and is directly displayed in a Gantt chart.

Description

The method and system of a kind of project management progress feedback and variance analysis
[technical field]
The present invention relates to the method and system of a kind of project management progress feedback and variance analysis, belong to project management techniques field.
[background technology]
Create WBS (Work Breakdown Structure, work breakdown structure (WBS)) and project deliverable achievement and project work are resolved into less, to be easier to the ingredient managed process; WBS take deliverable achievement as the work hierarchical decomposition of guiding, its decompose to as if project team be the work realizing project objective, submit to required deliverable achievement to implement, the WBS level that often declines just means the more detailed definition of project work.WBS tissue also defined item object total size, represents the work of existing scope of project instructions defined.Gantt chart, is also gunter drawing, horizontal axis representing time, longitudinal axis expression activity (project, WBS), represents movable, and indicates movable beginning and Close Date, demonstrate movable expected duration with lateral road; The relative readability of gunter drawing, is usually used in reporting the developments to administration and supervision authorities.
Current, in project management method and system, general to adopt " start-planning-perform-control-ending " five large processes, and combine the thought that " plan-implement-check-take action " (PDCA) circulate and carry out project management control and Continual Improvement.In the implementation of the project scheduling, in time, the actual development of real feedback task and acquisition WBS, and contrast with the period planning of formulating in planning process, draw implementation deviation, this is one of key link of whole PDCA process, has great meaning for the management and control of project, improvement, optimization.
In the progress feedback used at present and analytical approach and system, otherwise the uncomplete content face of progress feedback, the one being only limitted to quantitative Percent Complete or being in progress in explanatory note qualitatively; Only reflect current actual development, to the problem produced in implementation and in the future may faced by risk be described, and detailed solutions of problem is in progress and state, the probability of risk, impact and preparedness plan, alleviation state of progress; Progress can only be fed back in task level, but need repetition manual feedback to be in progress in WBS, project level, when level is many, workload is large, loaded down with trivial details, time-consuming, complicated operation, and because be manual feedback, be not easy to keep subordinate's task and higher level WBS, the synchronism of development of projects and consistance; Only can reflect present actual development, but in Gantt chart, the deviation between actual development and plan can not be shown in visual mode, showing current schedules is intuitively shift to an earlier date or fall behind, how many, backward how many in advance, to facilitate project administrator to carry out management and control, improvement, optimization to project, and finally reach project objective.
[summary of the invention]
The object of the invention is to: for defect and the deficiency of prior art, the method and system that a kind of project management is in progress feedback and variance analysis are provided, can not only quantitatively feed back with the qualitative progress combined, combine the problem produced simultaneously, current actual development, the project of future risk is comprehensively in progress feedback, consider progress and the weight of all subordinates task, gather and form the WBS of high-level and the actual development of project, with task, actual development and the period planning of WBS contrast, form respective actual implementation deviation, and show intuitively in Gantt chart.
For achieving the above object, the technical solution used in the present invention is:
The method of a kind of project management progress feedback of the present invention and variance analysis, is characterized in that: comprise the following steps:
Step 1, schedule is worked out: first project manager formulates WBS and task, the responsible party of definition WBS element and task or person liable, defines each WBS element and the weight of task shared by father's item, and forms PROJECT TIME (progress) plan;
Step 2, progress feedback: in plan implementation, the person liable of task feeds back Percent Complete and the progress explanation of task, feed back problem and the risk of task as required, and be in progress and its weight according to the execution of all direct sub-level tasks of some WBS elements, gather the actual development generating parent WBS;
Step 3, variance analysis and displaying: contrast with the period planning of the actual development fed back in tasks carrying and task, generate tasks carrying deviation; Contrast with the period planning of the WBS actual development and WBS that gather formation, generate WBS implementation deviation; By deviation line in project Gantt chart to illustrate the implementation deviation of display task, WBS simply and intuitively.
In the present invention: in described step 1, schedule establishment comprises following steps:
Step 11, formulates WBS and task: project work is down decomposed into WBS element and task;
Step 12, the responsible party of definition WBS element and task or person liable: these responsible partys (i.e. responsible department) or person liable are fed back determining the progress worked by whom;
Step 13, defines each WBS element and the weight of task shared by father's item: weight embodies the proportion of task shared by father's project, when subitem WBS or task all complete, just represents in father's item and complete corresponding proportion;
Step 14, formulate PROJECT TIME (progress) plan: according to the activity command of project task, duration, resource requirement and progress constraint etc., the process of establishment project schedule plan, the result of process is a schedule diagram, wherein for each WBS and task specify start time and end time, plan time;
Step 15, determine feedback cycle: after PROJECT TIME (progress) has been formulated, need according to project reality, determine within the whole project cycle, the frequency of progress statistics and variance analysis and the time interval, i.e. feedback cycle, generally can week, two week, the moon, ten days etc. as the feedback cycle of project; After determining feedback cycle, namely can carry out repeatedly making a report on of task progress according to feedback cycle.
In the present invention: described step 2 is in progress feedback packet containing following steps:
Step 21, selects feedback cycle: system selects the cycle current period by default comprising current time automatically, and user also can select the cycle before current period to carry out supplementary making a report on;
Step 22, feedback task progress: in plan implementation, the person liable of task feeds back Percent Complete and the progress explanation of task, and feed back problem and the risk of task as required, project manager audits rear feedback information and comes into force;
Step 23, gathers and forms WBS progress: according to execution progress and its weight of all direct sub-level tasks of some WBS elements, gather the actual development generating parent WBS.
In the present invention: described step 3 variance analysis and displaying comprise following steps:
Step 31, generates the working percentage that current period plan completes, and for ongoing task, need to calculate the working percentage that current period plan completes, computing method are as follows:
For WBS, the working percentage computing method that its current period plan completes are as follows:
Step 32, generates tasks carrying deviation, with the contrast of the current period plan Percent Complete of the actual development of feeding back in project implementation process of task progress number percent and task, generates tasks carrying deviation; Its computing method are as follows:
The current period plan Percent Complete of the actual development number percent-task of tasks carrying deviation=task ;
Step 33, generates WBS implementation deviation, with the contrast of the current period plan Percent Complete of the WBS actual development and WBS element that gather formation, generates WBS implementation deviation; Its computing method are as follows:
The current period plan Percent Complete of the actual development number percent-WBS of WBS implementation deviation=WBS;
Step 34, diagram is shown, to illustrate the implementation deviation of display task, WBS, project simply and intuitively in project Gantt chart.
In the present invention: described variance analysis and show in, step 34 illustrate show in comprise following steps:
Step 341, the display of 0 deviation: do not start, completed and deviation be 0 task, WBS, the position of deviation point in Gantt chart, the task of itself that ordinate is positioned, on WBS lateral road, horizontal ordinate with current time on Gantt chart for basic point, without skew;
Step 342, the display of minus deviation: ongoing task, WBS, its deviation is negative, the position of deviation point in Gantt chart, and on the task of itself that ordinate is positioned, WBS lateral road, horizontal ordinate, offsets left for basic point with current time on Gantt chart; Side-play amount is:
Task deviation point ordinate side-play amount=| the tasks carrying deviation * task scheduling duration |
WBS deviation point ordinate side-play amount=| WBS implementation deviation * WBS plan time |
Step 343, the display of overgauge: ongoing task, WBS, its deviation is positive, the position of deviation point in Gantt chart, and on the task of itself that ordinate is positioned, WBS lateral road, horizontal ordinate, offsets to the right for basic point with current time on Gantt chart; Side-play amount is:
Task deviation point ordinate side-play amount=| the tasks carrying deviation * task scheduling duration |
WBS deviation point ordinate side-play amount=| WBS implementation deviation * WBS plan time |
Step 344, draws deviation line: connect in not starting, carrying out, the deviation point of completed WBS, task, forms deviation line; Deviation line indicate each task, WBS to proceed to the end be in advance or fallen behind, in advance or fall behind how many.
In the present invention: the system of a kind of project management progress feedback and variance analysis, comprises and connect schedule scheduling apparatus, progress feedback assembly and variance analysis and exhibiting device successively.
Adopt after said structure, beneficial effect of the present invention is: quantitatively and the qualitative progress feedback combined, and illustrates support progress number percent that is digitized, rationalization by progress that is detailed, perception; Combine the problem produced, current actual development, future risk project be comprehensively in progress feedback, can feed back and understand detailed solution progress and the state of problem in time, the probability of risk, impact and preparedness plan, alleviation state of progress; Consider progress and the weight of all subordinates task, gather and form the WBS of high-level and the actual development of project, obviously have workload little, succinct, save time, maneuverable advantage; Contrast with the actual development of task, WBS, project and period planning, form respective deviation, and show intuitively in Gantt chart, showing current schedules is intuitively shift to an earlier date or fall behind, the degree fallen behind in advance, improve the visual of management data, with more convenient project administrator, management and control, improvement, optimization are carried out to project, and finally reach project objective.
[accompanying drawing explanation]
Accompanying drawing described herein is used to provide a further understanding of the present invention, forms a application's part, but does not form inappropriate limitation of the present invention, in the accompanying drawings:
Fig. 1 is system architecture schematic diagram of the present invention;
Fig. 2 is schedule Planning procedure figure of the present invention;
Fig. 3 is Project decomposition schematic diagram of the present invention;
Fig. 4 is progress process of feedback figure of the present invention;
Fig. 5 is variance analysis of the present invention and shows process flow diagram;
Fig. 6 is the schematic diagram of variance analysis of the present invention and displaying.
[embodiment]
Describe the present invention in detail below in conjunction with accompanying drawing and specific embodiment, illustrative examples wherein and explanation are only used for explaining the present invention, but not as a limitation of the invention.
As shown in Figure 1, the system of a kind of project management progress feedback and variance analysis, comprise connect successively planning device, be in progress feedback assembly and variance analysis and exhibiting device.
A method for project management progress feedback and variance analysis, comprises the following steps:
Step 1, schedule is worked out: first project manager formulates WBS and task, the responsible party of definition WBS element and task or person liable, defines each WBS element and the weight of task shared by father's item, and forms PROJECT TIME (progress) plan;
Step 2, progress feedback: in plan implementation, the person liable of task feeds back Percent Complete and the progress explanation of task, feed back problem and the risk of task as required, and be in progress and its weight according to the execution of all direct sub-level tasks of some WBS elements, gather the actual development generating parent WBS;
Step 3, variance analysis and displaying: contrast with the period planning of the actual development fed back in tasks carrying and task, generate tasks carrying deviation; Contrast with the period planning of the WBS actual development and WBS that gather formation, generate WBS implementation deviation; By deviation line in project Gantt chart to illustrate the implementation deviation of display task, WBS simply and intuitively.
As shown in Figure 2, in development of projects feedback and Deviation Analysis Method and system, step 1 schedule is worked out and is comprised following steps:
Step 11, formulates WBS and task: project work is down decomposed into WBS element and task;
Step 12, the responsible party of definition WBS element and task or person liable: these responsible partys (i.e. responsible department) or person liable are fed back determining the progress worked by whom;
Step 13, defines each WBS element and the weight of task shared by father's item: weight embodies the proportion of task shared by father's project, when subitem WBS or task all complete, just represents in father's item and complete corresponding proportion;
Step 14, formulate PROJECT TIME (progress) plan: according to the activity command of project task, duration, resource requirement and progress constraint etc., the process of establishment project schedule plan, the result of process is a schedule diagram, wherein for each WBS and task specify start time and end time, plan time;
Step 15, determine feedback cycle: after PROJECT TIME (progress) has been formulated, need according to project reality, determine within the whole project cycle, the frequency of progress statistics and variance analysis and the time interval, i.e. feedback cycle, generally can week, two week, the moon, ten days etc. as the feedback cycle of project; After determining feedback cycle, namely can carry out repeatedly making a report on of task progress according to feedback cycle.
As shown in Figure 4, in development of projects feedback and Deviation Analysis Method and system, step 2 is in progress feedback packet and contains following steps:
Step 21, selects feedback cycle: system selects the cycle current period by default comprising current time automatically, and user also can select the cycle before current period to carry out supplementary making a report on;
Step 22, feedback task progress: in plan implementation, the person liable of task feeds back Percent Complete and the progress explanation of task, and feed back problem and the risk of task as required, project manager audits rear feedback information and comes into force;
Step 23, gathers and forms WBS progress: according to execution progress and its weight of all direct sub-level tasks of some WBS elements, gather the actual development generating parent WBS.
As shown in Figure 5, in development of projects feedback and Deviation Analysis Method and system, step 3 variance analysis and displaying comprise following steps:
Step 31, generates the working percentage that current period plan completes, and for ongoing task, need to calculate the working percentage that current period plan completes, computing method are as follows:
For WBS, the working percentage computing method that its current period plan completes are as follows:
Step 32, generates tasks carrying deviation, with the contrast of the current period plan Percent Complete of the actual development of feeding back in project implementation process of task progress number percent and task, generates tasks carrying deviation; Its computing method are as follows:
The current period plan Percent Complete of the actual development number percent-task of tasks carrying deviation=task ;
Step 33, generates WBS implementation deviation, with the contrast of the current period plan Percent Complete of the WBS actual development and WBS element that gather formation, generates WBS implementation deviation; Its computing method are as follows:
The current period plan Percent Complete of the actual development number percent-WBS of WBS implementation deviation=WBS;
Step 34, diagram is shown, to illustrate the implementation deviation of display task, WBS, project simply and intuitively in project Gantt chart.
As shown in Figure 6, variance analysis and show in, step 34 illustrate show in comprise following steps:
Step 341, the display of 0 deviation: do not start, completed and deviation be 0 task, WBS, the position of deviation point in Gantt chart, the task of itself that ordinate is positioned, on WBS lateral road, horizontal ordinate with current time on Gantt chart for basic point, without skew;
Step 342, the display of minus deviation: ongoing task, WBS, its deviation is negative, the position of deviation point in Gantt chart, and on the task of itself that ordinate is positioned, WBS lateral road, horizontal ordinate, offsets left for basic point with current time on Gantt chart; Side-play amount is:
Task deviation point ordinate side-play amount=| the tasks carrying deviation * task scheduling duration |
WBS deviation point ordinate side-play amount=| WBS implementation deviation * WBS plan time |
Step 343, the display of overgauge: ongoing task, WBS, its deviation is positive, the position of deviation point in Gantt chart, and on the task of itself that ordinate is positioned, WBS lateral road, horizontal ordinate, offsets to the right for basic point with current time on Gantt chart; Side-play amount is:
Task deviation point ordinate side-play amount=| the tasks carrying deviation * task scheduling duration |
WBS deviation point ordinate side-play amount=| WBS implementation deviation * WBS plan time |
Step 344, draws deviation line: connect in not starting, carrying out, the deviation point of completed WBS, task, forms deviation line; Deviation line indicate each task, WBS to proceed to the end be in advance or fallen behind, in advance or fall behind how many.
The above is only better embodiment of the present invention, therefore all equivalences done according to structure, feature and the principle described in patent claim of the present invention change or modify, and are included in patent claim of the present invention.

Claims (6)

1. a method for project management progress feedback and variance analysis, is characterized in that: comprise the following steps:
Step 1, schedule is worked out: first project manager formulates WBS and task, the responsible party of definition WBS element and task or person liable, defines each WBS element and the weight of task shared by father's item, and forms PROJECT TIME (progress) plan;
Step 2, progress feedback: in plan implementation, the person liable of task feeds back Percent Complete and the progress explanation of task, feed back problem and the risk of task as required, and be in progress and its weight according to the execution of all direct sub-level tasks of some WBS elements, gather the actual development generating parent WBS;
Step 3, variance analysis and displaying: contrast with the period planning of the actual development fed back in tasks carrying and task, generate tasks carrying deviation; Contrast with the period planning of the WBS actual development and WBS that gather formation, generate WBS implementation deviation; By deviation line in project Gantt chart to illustrate the implementation deviation of display task, WBS simply and intuitively.
2. the method for a kind of project management progress feedback according to claim 1 and variance analysis, is characterized in that: in described step 1, schedule establishment comprises following steps:
Step 11, formulates WBS and task: project work is down decomposed into WBS element and task;
Step 12, the responsible party of definition WBS element and task or person liable: these responsible partys (i.e. responsible department) or person liable are fed back determining the progress worked by whom;
Step 13, defines each WBS element and the weight of task shared by father's item: weight embodies the proportion of task shared by father's project, when subitem WBS or task all complete, just represents in father's item and complete corresponding proportion;
Step 14, formulate PROJECT TIME (progress) plan: according to the activity command of project task, duration, resource requirement and progress constraint etc., the process of establishment project schedule plan, the result of process is a schedule diagram, wherein for each WBS and task specify start time and end time, plan time;
Step 15, determine feedback cycle: after PROJECT TIME (progress) has been formulated, need according to project reality, determine within the whole project cycle, the frequency of progress statistics and variance analysis and the time interval, i.e. feedback cycle, generally can week, two week, the moon, ten days etc. as the feedback cycle of project; After determining feedback cycle, namely can carry out repeatedly making a report on of task progress according to feedback cycle.
3. the method for a kind of project management progress feedback according to claim 1 and variance analysis, is characterized in that: described step 2 is in progress feedback packet containing following steps:
Step 21, selects feedback cycle: system selects the cycle current period by default comprising current time automatically, and user also can select the cycle before current period to carry out supplementary making a report on;
Step 22, feedback task progress: in plan implementation, the person liable of task feeds back Percent Complete and the progress explanation of task, and feed back problem and the risk of task as required, project manager audits rear feedback information and comes into force;
Step 23, gathers and forms WBS progress: according to execution progress and its weight of all direct sub-level tasks of some WBS elements, gather the actual development generating parent WBS.
4. the method for a kind of project management progress feedback according to claim 1 and variance analysis, is characterized in that: described step 3 variance analysis and displaying comprise following steps:
Step 31, generates the working percentage that current period plan completes, and for ongoing task, need to calculate the working percentage that current period plan completes, computing method are as follows:
For WBS, the working percentage computing method that its current period plan completes are as follows:
Step 32, generates tasks carrying deviation, with the contrast of the current period plan Percent Complete of the actual development of feeding back in project implementation process of task progress number percent and task, generates tasks carrying deviation; Its computing method are as follows:
The current period plan Percent Complete of the actual development number percent-task of tasks carrying deviation=task;
Step 33, generates WBS implementation deviation, with the contrast of the current period plan Percent Complete of the WBS actual development and WBS element that gather formation, generates WBS implementation deviation; Its computing method are as follows:
The current period plan Percent Complete of the actual development number percent-WBS of WBS implementation deviation=WBS;
Step 34, diagram is shown, to illustrate the implementation deviation of display task, WBS, project simply and intuitively in project Gantt chart.
5. the method for a kind of project management progress feedback according to claim 4 and variance analysis, is characterized in that: described variance analysis and in showing, step 34 illustrates in displaying and comprises following steps:
Step 341, the display of 0 deviation: do not start, completed and deviation be 0 task, WBS, the position of deviation point in Gantt chart, the task of itself that ordinate is positioned, on WBS lateral road, horizontal ordinate with current time on Gantt chart for basic point, without skew;
Step 342, the display of minus deviation: ongoing task, WBS, its deviation is negative, the position of deviation point in Gantt chart, and on the task of itself that ordinate is positioned, WBS lateral road, horizontal ordinate, offsets left for basic point with current time on Gantt chart; Side-play amount is:
Task deviation point ordinate side-play amount=| the tasks carrying deviation * task scheduling duration |
WBS deviation point ordinate side-play amount=| WBS implementation deviation * WBS plan time |
Step 343, the display of overgauge: ongoing task, WBS, its deviation is positive, the position of deviation point in Gantt chart, and on the task of itself that ordinate is positioned, WBS lateral road, horizontal ordinate, offsets to the right for basic point with current time on Gantt chart; Side-play amount is:
Task deviation point ordinate side-play amount=| the tasks carrying deviation * task scheduling duration |
WBS deviation point ordinate side-play amount=| WBS implementation deviation * WBS plan time |
Step 344, draws deviation line: connect in not starting, carrying out, the deviation point of completed WBS, task, forms deviation line; Deviation line indicate each task, WBS to proceed to the end be in advance or fallen behind, in advance or fall behind how many.
6. a system for project management progress feedback and variance analysis, is characterized in that: comprise and connect schedule scheduling apparatus, progress feedback assembly and variance analysis and exhibiting device successively.
CN201510094390.8A 2015-03-03 2015-03-03 A kind of project management progress feedback and the method and system of variance analysis Active CN104636880B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510094390.8A CN104636880B (en) 2015-03-03 2015-03-03 A kind of project management progress feedback and the method and system of variance analysis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510094390.8A CN104636880B (en) 2015-03-03 2015-03-03 A kind of project management progress feedback and the method and system of variance analysis

Publications (2)

Publication Number Publication Date
CN104636880A true CN104636880A (en) 2015-05-20
CN104636880B CN104636880B (en) 2018-03-23

Family

ID=53215599

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510094390.8A Active CN104636880B (en) 2015-03-03 2015-03-03 A kind of project management progress feedback and the method and system of variance analysis

Country Status (1)

Country Link
CN (1) CN104636880B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107392425A (en) * 2017-06-15 2017-11-24 中国烟草总公司 A kind of the tobacco business project implementation SOP management method and system
CN108122089A (en) * 2016-11-30 2018-06-05 中国航空工业集团公司成都飞机设计研究所 A kind of task feedback based on delivery object
CN108170406A (en) * 2017-12-29 2018-06-15 中国银行股份有限公司 A kind of analysis method and device of required by task stock number
CN108960779A (en) * 2018-07-04 2018-12-07 广东电网有限责任公司 Electricity power engineering management method
CN110704441A (en) * 2019-09-27 2020-01-17 杭州时光坐标影视传媒股份有限公司 Method, system, equipment and readable storage medium for scheduling movie and television tasks
CN111612428A (en) * 2020-05-25 2020-09-01 国家电网有限公司技术学院分公司 Project progress visualization method and system based on work structure decomposition
CN112526952A (en) * 2020-12-14 2021-03-19 安徽巨一科技股份有限公司 Method and system for acquiring and analyzing rhythm based on linear body
CN112818182A (en) * 2021-01-27 2021-05-18 意潜建筑科技(上海)有限公司 Gantt chart-based working density calculation display method
CN113051748A (en) * 2021-03-19 2021-06-29 北京圣涛平试验工程技术研究院有限责任公司 Method and device for constructing asset risk full elements of aircraft reliability data
CN113283851A (en) * 2020-02-20 2021-08-20 长城汽车股份有限公司 Project progress control method and system
CN113780860A (en) * 2021-09-17 2021-12-10 上海易立德信息技术股份有限公司 Progress display method and system for milestone and storage medium
CN114003831A (en) * 2021-10-21 2022-02-01 易协云(杭州)科技有限公司 Method and system for graphically displaying project progress by utilizing webpage

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101599013A (en) * 2009-06-26 2009-12-09 中国科学院软件研究所 A kind of iteration project quantification monitoring method and system thereof based on defect driven
CN102799771A (en) * 2012-06-29 2012-11-28 厦门易用软件技术有限公司 Execution quality analysis system
CN103136636A (en) * 2013-03-15 2013-06-05 中广核工程有限公司 Nuclear power project progress measuring method and system
CN104112174A (en) * 2013-04-17 2014-10-22 中广核工程有限公司 Project regulating and controlling method and system of nuclear power plant

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101599013A (en) * 2009-06-26 2009-12-09 中国科学院软件研究所 A kind of iteration project quantification monitoring method and system thereof based on defect driven
CN102799771A (en) * 2012-06-29 2012-11-28 厦门易用软件技术有限公司 Execution quality analysis system
CN103136636A (en) * 2013-03-15 2013-06-05 中广核工程有限公司 Nuclear power project progress measuring method and system
CN104112174A (en) * 2013-04-17 2014-10-22 中广核工程有限公司 Project regulating and controlling method and system of nuclear power plant

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈锐: ""哈平汽零部件产业基地工程项目进度控制研究"", 《中国优秀硕士学位论文全文数据库经济与管理科学辑》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108122089A (en) * 2016-11-30 2018-06-05 中国航空工业集团公司成都飞机设计研究所 A kind of task feedback based on delivery object
CN107392425A (en) * 2017-06-15 2017-11-24 中国烟草总公司 A kind of the tobacco business project implementation SOP management method and system
CN108170406A (en) * 2017-12-29 2018-06-15 中国银行股份有限公司 A kind of analysis method and device of required by task stock number
CN108960779A (en) * 2018-07-04 2018-12-07 广东电网有限责任公司 Electricity power engineering management method
CN110704441B (en) * 2019-09-27 2020-09-08 杭州时光坐标影视传媒股份有限公司 Method, system, equipment and readable storage medium for scheduling movie and television tasks
CN110704441A (en) * 2019-09-27 2020-01-17 杭州时光坐标影视传媒股份有限公司 Method, system, equipment and readable storage medium for scheduling movie and television tasks
CN113283851A (en) * 2020-02-20 2021-08-20 长城汽车股份有限公司 Project progress control method and system
CN111612428A (en) * 2020-05-25 2020-09-01 国家电网有限公司技术学院分公司 Project progress visualization method and system based on work structure decomposition
CN112526952A (en) * 2020-12-14 2021-03-19 安徽巨一科技股份有限公司 Method and system for acquiring and analyzing rhythm based on linear body
CN112818182A (en) * 2021-01-27 2021-05-18 意潜建筑科技(上海)有限公司 Gantt chart-based working density calculation display method
CN113051748A (en) * 2021-03-19 2021-06-29 北京圣涛平试验工程技术研究院有限责任公司 Method and device for constructing asset risk full elements of aircraft reliability data
CN113780860A (en) * 2021-09-17 2021-12-10 上海易立德信息技术股份有限公司 Progress display method and system for milestone and storage medium
CN114003831A (en) * 2021-10-21 2022-02-01 易协云(杭州)科技有限公司 Method and system for graphically displaying project progress by utilizing webpage
CN114003831B (en) * 2021-10-21 2024-04-30 易协云(杭州)科技有限公司 Method and system for graphically displaying project progress by using webpage

Also Published As

Publication number Publication date
CN104636880B (en) 2018-03-23

Similar Documents

Publication Publication Date Title
CN104636880A (en) Method and system for project management process feedback and deviation analysis
von Wangenheim et al. Experiences on establishing software processes in small companies
US7168045B2 (en) Modeling business objects
Farid et al. NORMATIC: A visual tool for modeling non-functional requirements in agile processes
US20070143169A1 (en) Real-time workload information scheduling and tracking system and related methods
CN107341643A (en) Visual flow methods of exhibiting and system
Wesz et al. Planning and controlling design in engineered-to-order prefabricated building systems
CN110704441B (en) Method, system, equipment and readable storage medium for scheduling movie and television tasks
US10776759B2 (en) Workplace movement visualizations
CN104599031A (en) Resume model matching system and method
CN111445218A (en) BIM-based project progress management method, device, equipment and storage medium
CN106777106A (en) The method for exhibiting data of the financial statement based on excel
CN111861418A (en) Task generation method and device and electronic equipment
Roderick et al. Accelerator fault tracking at CERN
CN103761604A (en) Method and device for conforming completion of report data compilation
Alarcón et al. A production planning support system for construction projects
KR20150096191A (en) Project management system
CN102799971A (en) Tobacco supply-by-order process control system
CN114003831B (en) Method and system for graphically displaying project progress by using webpage
CA2832806C (en) Method for optimizing schedule compression in projects using accelerating and overlapping of activities
CN113723900A (en) Product life cycle management platform, and system and method for executing and managing changed data
CN107315579B (en) Automatic generation method and system of software development plan
CN110796353A (en) Scheduling processing method and device
CN111311037A (en) Method for compiling custom construction plan, progress summarizing and data analysis
Ganah et al. Innovative Integration of Modern Technologies for Health and Safety Decision Making in the Construction Industry

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20180214

Address after: 210003 old school A2, No. 350, Zhongshan North Road, Nanjing, Jiangsu

Applicant after: Nanjing high beam Guang'an Mdt InfoTech Ltd

Address before: 210003 old school A2, No. 350, Zhongshan North Road, Nanjing, Jiangsu

Applicant before: NANJING GUANGAN TECHNOLOGY CO., LTD.

TA01 Transfer of patent application right
GR01 Patent grant