CN108960779A - Power Grid Engineering Management Method - Google Patents
Power Grid Engineering Management Method Download PDFInfo
- Publication number
- CN108960779A CN108960779A CN201810726318.6A CN201810726318A CN108960779A CN 108960779 A CN108960779 A CN 108960779A CN 201810726318 A CN201810726318 A CN 201810726318A CN 108960779 A CN108960779 A CN 108960779A
- Authority
- CN
- China
- Prior art keywords
- task
- engineering management
- engineering
- node
- time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007726 management method Methods 0.000 title claims abstract description 207
- 238000010276 construction Methods 0.000 claims abstract description 107
- 230000005611 electricity Effects 0.000 claims description 40
- 238000012935 Averaging Methods 0.000 claims description 5
- 238000000034 method Methods 0.000 abstract description 16
- 238000010586 diagram Methods 0.000 abstract description 10
- 238000012550 audit Methods 0.000 description 9
- 238000013461 design Methods 0.000 description 7
- 238000011156 evaluation Methods 0.000 description 7
- 230000006870 function Effects 0.000 description 7
- 238000004590 computer program Methods 0.000 description 6
- 239000000463 material Substances 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 3
- 238000004458 analytical method Methods 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 2
- 238000004891 communication Methods 0.000 description 2
- 230000003111 delayed effect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000012790 confirmation Methods 0.000 description 1
- 238000000354 decomposition reaction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000008030 elimination Effects 0.000 description 1
- 238000003379 elimination reaction Methods 0.000 description 1
- 238000009472 formulation Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 238000012549 training Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Tourism & Hospitality (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- Entrepreneurship & Innovation (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a power grid engineering management method, which comprises the following steps: acquiring an engineering management task, and the category and the grade of the engineering management task; determining a multi-stage task implementation node of the engineering management task according to the category; evaluating a planning period corresponding to the multi-stage task implementation node according to the historical project with the same category and level as the engineering management task; acquiring an actual construction period corresponding to a multi-stage task implementation node; storing the multi-stage task implementation nodes, the planning construction period and the actual construction period in a data structure with a preset format; reading a data structure in a preset format, and generating a crosswalk graph for describing the implementation condition of the engineering management task by using the data structure; and calculating engineering parameters of the engineering management task according to the crosswalk diagram. The invention enables non-professional personnel to be familiar with the flow nodes, the project plan progress, the actual progress and the like of the project construction, avoids the conditions of item shortage and item leakage in the project management process, reduces the labor cost and enables the statistical data to be fast and accurate.
Description
Technical field
The present invention relates to electricity power engineering technical fields, in particular to a kind of electricity power engineering management method.
Background technique
In existing project management system, project Items in order manager, undertaker and multiple executors it is common
Cooperation could be completed, and create project by project manager, and Project decomposition is multiple tasks by undertaker, is then given each executor and is paid
All implementation.This is a very complicated process, needs to formulate the detailed project plan in advance just and can guarantee going on smoothly for project.Work
Thread management personnel have generally required specialty background, could grasp pipe comprehensively by prolonged engineering management training, practical experience
Manage process, progress implement needed for reasonable time limit for construction, and engineering management in practice, because of artificial careless omission, often generate engineering pipe
The case where managing key node missing, certain influence is generated to engineering actual management;Meanwhile in engineering progress, the work is completed
The actual construction time of journey task often exceeds the plan time of formulation, in the case of this kind, non-professional supervisor of construction be difficult from
It finds the problem in big data, manual inspection project is time-consuming and laborious, and statistical data is slower, is easy error, causes a large amount of people
The waste of power physics.
Summary of the invention
In view of the above problems, the embodiment of the present invention has been designed to provide a kind of electricity power engineering management method, to solve
The deficiencies in the prior art.
According to embodiment of the present invention, a kind of electricity power engineering management method is provided, comprising:
Obtain engineering management task, the classification and grade of the engineering management task;
The multistage task-cycle node of the engineering management task is determined according to the classification;
According to history item identical with the classification of the engineering management task and grade assessment multistage task-cycle
The corresponding plan time of node;
Obtain the multistage task-cycle node corresponding actual construction time;
By the multistage task-cycle node, the data structure of the plan time and the actual construction time in a predetermined format
It is stored;
The data structure of the predetermined format is read, and the data structure building is used to describe the engineering management and is appointed
The gunter drawing for performance of being engaged in;
The engineering parameter of the engineering management task is calculated according to the gunter drawing.
In above-mentioned electricity power engineering management method, the multistage that the engineering management task is determined according to the classification
Task-cycle node includes:
Determine that the multistage of the corresponding engineering management task of the classification is appointed according to preset engineering management task template
It is pragmatic to apply node, wherein each level-one task-cycle node includes that multiple second tasks implement node.
In above-mentioned electricity power engineering management method, the basis is identical as the classification of the engineering management task and grade
The corresponding plan time of the history item assessment multistage task-cycle node include:
According to each task-cycle section of all history items identical with the classification of the engineering management task and grade
The actual construction time of point obtains the corresponding duration threshold value of each task-cycle node with default operation;
The corresponding plan time of the multistage task-cycle node is determined according to the duration threshold value.
In above-mentioned electricity power engineering management method, the default operation is operation of averaging.
In above-mentioned electricity power engineering management method, the data structure of the predetermined format is excel tableau format.
In above-mentioned electricity power engineering management method, the gunter drawing includes the perpendicular column being made of multistage task-cycle node
Information, the row information being made of the time series of duration and plan time and the actual construction time for indicating task-cycle nodes at different levels
The lines figure of progress.
In above-mentioned electricity power engineering management method, the work that the engineering management task is calculated according to the gunter drawing
Journey parameter includes:
Obtain initial time and end time that task-cycle node at different levels in the gunter drawing corresponds to lines figure;
The engineering management task is calculated according to the initial time of all task-cycle nodes and the end time
Engineering parameter.
In above-mentioned electricity power engineering management method, the engineering parameter includes the plan chief engineer of the engineering management task
Phase, the practical total construction period of the engineering management task, the corresponding plan time of task-cycle node at different levels, task-cycle section at different levels
Point corresponding actual construction time, delay time at stop total construction period and task-cycle node at different levels correspond to the construction delay time.
In above-mentioned electricity power engineering management method, when the task-cycle nodes at different levels correspond to construction delay, issue
The warning message of construction delay time is corresponded to containing each task-cycle node.
In above-mentioned electricity power engineering management method, joined according to the engineering that the gunter drawing calculates the engineering management task
After number further include:
The engineering management task is stored as relevant history item and records the described more of the engineering management task
The actual construction time of grade task-cycle node.
Another embodiment of the present invention provides a kind of electricity power engineering management system, comprising:
Task acquisition module, for obtaining the classification and grade of engineering management task, the engineering management task;
Task-cycle node determining module, the multistage task for determining the engineering management task according to the classification are real
Apply node;
Plan time duration evaluation module, for according to history identical with the classification of the engineering management task and grade
The corresponding plan time of multistage task-cycle node described in the project evaluation;
Actual construction time obtains module, for obtaining the multistage task-cycle node corresponding actual construction time;
Memory module is used for the multistage task-cycle node, the plan time and the actual construction time with predetermined
The data structure of format is stored;
Generation module is read, is used for for reading the data structure of the predetermined format, and by the data structure building
The gunter drawing of the engineering management task-cycle situation is described;
Computing module, for calculating the engineering parameter of the engineering management task according to the gunter drawing.
A further embodiment of the invention provides a kind of terminal, which includes memory and place
Device is managed, the memory runs the computer program so that the computer for storing computer program, the processor
Terminal executes above-mentioned electricity power engineering management method.
A further embodiment of the invention provides a kind of computer readable storage medium, the computer readable storage medium
In be stored with above-mentioned electricity power engineering management method.
The electricity power engineering management method that embodiment disclosed by the invention provides at least provides following technical effect: helping engineering
Administrative staff quickly understand the main flow for grasping engineering management;For the careless omission problem of administrative staff in existing engineering management,
Management node is clearly recorded in gunter drawing item by item, avoids slipping, statistical data is quick and precisely;Not for Management of engineering schedule
Deterministic problem, using gunter drawing be intended to progress and it is practical only need to compare, show constructing aims, duration short slab, bright
True engineering striving direction, reduces the cost of manpower and material resources.
Detailed description of the invention
In order to illustrate more clearly of technical solution of the present invention, letter will be made to attached drawing needed in the embodiment below
It singly introduces, it should be understood that the following drawings illustrates only certain embodiments of the present invention, therefore is not construed as to the present invention
The restriction of protection scope.
Fig. 1 shows a kind of flow diagram of electricity power engineering management method of first embodiment of the invention offer.
Fig. 2 shows a kind of schematic diagrames of gunter drawing provided in an embodiment of the present invention.
Fig. 3 shows a kind of flow diagram of electricity power engineering management method of second embodiment of the invention offer.
Fig. 4 shows a kind of structural schematic diagram of electricity power engineering management system provided in an embodiment of the present invention.
Main element symbol description:
300- electricity power engineering management system;310- task acquisition module;320- task-cycle node determining module;330- meter
Draw duration evaluation module;The 340- actual construction time obtains module;350- memory module;360- reads generation module;370- calculates mould
Block.
Specific embodiment
Below in conjunction with attached drawing in the embodiment of the present invention, technical solution in the embodiment of the present invention carries out clear, complete
Ground description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Usually exist
The component of the embodiment of the present invention described and illustrated in attached drawing can be arranged and be designed with a variety of different configurations herein.Cause
This, is not intended to limit claimed invention to the detailed description of the embodiment of the present invention provided in the accompanying drawings below
Range, but it is merely representative of selected embodiment of the invention.Based on the embodiment of the present invention, those skilled in the art are not doing
Every other embodiment obtained under the premise of creative work out, shall fall within the protection scope of the present invention.
In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance
Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or
Implicitly include one or more of the features.In the description of the present invention, the meaning of " plurality " is two or more,
Unless otherwise specifically defined.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention
The normally understood meaning of technical staff is identical.It is intended merely to herein in the term used in the description of multiple dimensioned scaling board
The purpose of specific embodiment is described, it is not intended that the limitation present invention.Term " and or " used herein includes one or more
Any and all combinations of a relevant listed item.
With reference to the accompanying drawing, it elaborates to a specific embodiment of the invention.
Embodiment 1
Fig. 1 shows a kind of flow diagram of electricity power engineering management method of first embodiment of the invention offer.
The method flow that the implementation exemplifies includes the following steps:
Step S110 obtains engineering management task, the classification and grade of the engineering management task.
In the present embodiment, the input operation for responding user obtains engineering management task and according to the user's choice operation acquisition
The corresponding task category of engineering management task and grade.
Wherein, the classification of the engineering management task can be divided into moving according to the attribute of engineering management task and changes engineering, base
Build engineering, technology innovation project etc..
The grade of the engineering management task can be divided into level-one task, two in charge of a grade according to the scale of engineering management task
Business, three-level task dispatching, the more big corresponding higher grade of scale.
The corresponding grade of scale of engineering management task can be preset.For example, " certain province " corresponding grade is that " four is in charge of a grade
Business ", " certain city " corresponding grade are " three-level task ", and " certain county " corresponding grade is " second task ", and " certain township/town " is corresponding
Grade is " level-one task " etc..
For example, the engineering management task names obtained are " certain city's urban distribution network, which moves, changes 110 kilovolts of certain lines of engineering ", the engineering
The corresponding classification of management role " certain city's urban distribution network, which moves, changes 110 kilovolts of certain lines of engineering " is " move and change engineering " classification, the engineering pipe
The corresponding grade of reason task " certain city's urban distribution network, which moves, changes 110 kilovolts of certain lines of engineering " is " three-level task ".
In some other embodiments, the input operation that can also respond user obtains the title of engineering management task,
And the title of the engineering management task is analyzed, determine the corresponding classification of engineering management task based on the analysis results and is waited
Grade.
For example, being that " certain city's urban distribution network, which moves, changes engineering according to the engineering management task names that the input operation of user obtains
110 kilovolts of certain lines " analyze the title " certain city's urban distribution network, which moves, changes 110 kilovolts of certain lines of engineering " of the engineering management task,
It was found that including " move and change " printed words in the title, it can assert that the engineering management task belongs to " move and change engineering " classification;To the engineering pipe
The title " certain city's urban distribution network, which moves, changes 110 kilovolts of certain lines of engineering " of reason task is analyzed, and finds to include " certain city " in the title
Printed words can assert that the engineering management task belongs to " three-level task " grade.
After determining the corresponding classification of engineering management task, it may also be used for show the engineering management task, the engineering pipe
The classification and grade of reason task are checked for user, and receive the confirmation message of user.
For example, determining that the engineering management task of entitled " certain city's urban distribution network, which moves, changes 110 kilovolts of certain lines of engineering " is corresponding
Classification is " move and change engineering ", and corresponding grade is " three-level task ", and by the title, " certain city's urban distribution network, which moves, changes 110 kilovolts of engineering
Certain line ", classification " move and change engineering " and grade " three-level task " carry out being displayed for user checking, user appoints the engineering management
Business and the corresponding classification of engineering management task and grade are confirmed.
The corresponding classification of engineering management task cannot be clearly determined according to the analysis result to engineering management task names
And when grade, the input operation that can respond user obtains the corresponding classification of engineering management task and grade.
For example, be " urban network reconstruction engineering " according to the engineering management task names that the input operation of user obtains, it is right
The title " urban network reconstruction engineering " of the engineering management task is analyzed, and does not find to include " move and change " " skill in the title
Change " etc. clear printed words, can determine that the corresponding classification of engineering management task be " move and change engineering " or " technology innovation project ", use can be passed through
The selection operation at family obtains the corresponding classification of engineering management task, and e.g., operation selects the engineering management according to the user's choice
The corresponding classification of task is " move and change engineering ".In addition, can also lead to when not can determine that the corresponding classification of the engineering management task
It crosses user's input operation and directly acquires the corresponding classification of engineering management task, for example, user can take in the engineering management manually
The classification " move and change engineering " of task.
It is " urban network reconstruction engineering " according to the engineering management task names that the input operation of user obtains, to the engineering
The title " urban network reconstruction engineering " of management role is analyzed, and does not find to include that " certain city " " certain province " etc. is bright in the title
True printed words can determine that the corresponding classification of engineering management task is " three-level task " or " second task ", can pass through the choosing of user
It selects operation and obtains the corresponding grade of engineering management task, e.g., operation selects the engineering management task pair according to the user's choice
The classification answered is " three-level task ".In addition, user can also be passed through when not can determine that the corresponding grade of the engineering management task
Input operation directly acquires the corresponding grade of engineering management task, for example, user can take in the engineering management task manually
Classification " three-level task ".
Step S120 determines the multistage task-cycle node of the engineering management task according to the classification.
In the present embodiment, the corresponding engineering management task of the category is determined according to preset engineering management task template
Multistage task-cycle node.
In this implementation, the multistage task-cycle node is two-stage task-cycle node, and each engineering management task is corresponding
Multiple level-one task-cycle nodes, each level-one task-cycle node include that multiple second tasks implement node.
For example, in the engineering management task of entitled " certain city's urban distribution network, which moves, changes 110 kilovolts of certain lines of engineering ", the engineering
The corresponding classification of management role is " move and change engineering ", and it is as follows to be somebody's turn to do " move and change engineering " corresponding multistage task-cycle node:
The engineering management task " certain city's urban distribution network, which moves, changes 110 kilovolts of certain lines of engineering " includes previous work, engineering design
And it bid, purchase of goods and materials, goes into operation and process is checked and accepted, have a power failure application, power cut construction and final acceptance of construction and engineering startup and assets are moved
Hand over 7 level-one task-cycle nodes;Level-one task-cycle node " former work " includes moving to change to apply for that letter, tissue scene are surveyed
Examine, move change intention write a letter in reply, receive application for developing, tissue feasibility study examine, ask for instructions above provincial company, provincial company reply, move and change feasibility study
It writes a letter in reply and negotiates to sign 9 second tasks implementation nodes of indemnity agreement;Level-one task-cycle node " engineering design and bid " packet
Include that design and bid Note Auditing is affixed one's seal, construction bid Note Auditing is affixed one's seal, supervising tender Note Auditing is affixed one's seal, designing unit's qualification
(industry that audit is put on record (owner's letters report), unit in charge of construction's aptitude checking is put on record (owner's letters report), supervisor's aptitude checking is put on record
Main letters report), preliminary design review (3,000,000 or more project cost) and construction drawing design examine that 8 second tasks implement nodes;
Level-one task-cycle node " purchase of goods and materials " include determine goods and materials supplier, audit and sign after purchase of goods and materials technical conditions book and
It sends someone to participate in 3 second tasks implementation nodes of factory inspection and acceptance;Level-one task-cycle node " go into operation and process is checked and accepted " includes receiving
Commencement of works report, organize safe practice tell somebody what one's real intentions are, audit and conutersign in protection of electric power facility area arrangement and method for construction examine, audit
Receive land occupation, crop compensation data, receive money handle asset retirement formality, audit and conutersign design alteration, reception Acceptance application and
It organizes 9 second tasks of engineering intermediate acceptance and implements node;Level-one task-cycle node " have a power failure application " includes auditing simultaneously
It reports line parameter circuit value, audit and conutersigns starting scheme, tissue audit power cut construction scheme, communication disruption application and audit and conutersign
Communication disruption arrangement and method for construction, declare power failure plan, audit and conutersign power supply bureau's material object move change engineering power failure report table, ground connection, group to a higher authorities for approval
Tower conducting wire, replacement, optical cable, is replaced, tears tower open, sag adjustment, attachment installation, checks and accepts defect elimination and the 17 second tasks implementations that put into operation
Node;Level-one task-cycle node " power cut construction and final acceptance of construction " includes that construction, owner's unit is supervised to submit construction plan, test
Receipts plan, tissue supervise construction, management, owner's unit to carry out safe practice and tell somebody what one's real intentions are, supervise and handle formality (if any) of entering the station, countersign
Work ticket is handled, final acceptance of construction is organized, supervises design, construction and management to carry out the typing of system account and transfer 12 second levels
Task-cycle node;Level-one task-cycle node " engineering startup and asset handover " include organize acceptance of work summing-up meeting,
Starting meeting organizes engineering startup, dismounting, receives the waste and old assets of engineering and supervise and handle engineering asset handover work 6 two
Grade task-cycle node.
In some other embodiments, according to the grade or level of materiality of engineering management task, the multistage task is real
Applying node can also include three-level and the above task-cycle node.
In this implementation, corresponding work is arranged in the identical history item of classification and grade previously according to the engineering management task
Thread management task template.
In some other embodiments, supervisor of construction determines different classes of engineering pipe according to project management experience
The corresponding multistage task-cycle node of reason task.
Step S130 assesses the multistage according to history item identical with the classification of the engineering management task and grade
The corresponding plan time of task-cycle node.
The duration is the difference between the end time and initial time of the task-cycle node.
In the present embodiment, according to each of all history items identical with the classification of the engineering management task and grade
The actual construction time of task-cycle node obtains the corresponding duration threshold value of each task-cycle node with default operation;According to the work
Phase threshold value determines the corresponding plan time of the multistage task-cycle node.
Preferably, the default operation is operation of averaging.In yet other embodiment, the default operation is also
It can be the other kinds of arithmetic operation for seeking duration threshold value.
The actual construction time of task-cycle node each in all history items is subjected to default operation, it is real to obtain each task
Apply the corresponding duration threshold value of node.
For example, classification corresponding with the engineering management task and grade history item all the same share 5,5 history
Level-one task-cycle node " previous work " the corresponding duration is respectively 51 days, 49 days, 62 days, 56 days and 46 days in project, is led to
Crossing operation of averaging and obtaining the corresponding duration threshold value of level-one task-cycle node " previous work " is 52.8 days.5 history phases
The corresponding second task implementation node of level-one task-cycle node " move and change application letter " the corresponding duration is respectively 8 in the project of pass
It, 9 days, 7 days, 6 days and 10 days, second task is obtained by operation of averaging and implements the corresponding work of node " move change application letter "
Phase threshold value is 8 days.
It is real according to each task after the duration threshold calculations of task-cycle nodes all in the engineering management task are obtained
Apply the corresponding duration threshold value of node, the inclusion relation that level-one implements node and second task is implemented between node determines multistage task
Implement the corresponding plan time of node.
For example, according to the corresponding plan work of 52.8 days determination task-cycle nodes of duration threshold value of level-one task-cycle node
Phase is 52 days, and implementing the corresponding duration threshold value assessment of node according to all second tasks that the level-one task-cycle node includes should
All second tasks implement the plan time of node, and, the plan time of the level-one task-cycle node is equal to the level-one task
Implement the sum of the plan time that all second tasks that node includes implement node.
In some other embodiments, it can also be operated according to the input of user and obtain the multistage task-cycle node pair
The plan time answered.
In yet other embodiment, it can also pass through the pre- of the related plan time that reading supervisory engineering department provides
The data of setting formula obtain the corresponding plan time of multistage task-cycle node.
Wherein, the predetermined form can be common form form, excel table etc..
Step S140 obtains the multistage task-cycle node corresponding actual construction time.
In the present embodiment, it can be operated according to the input of user and obtain the corresponding practical work of the multistage task-cycle node
Phase.In some other embodiments, the preboarding for the related actual construction time that reading supervisory engineering department provides can also be passed through
The data acquisition multistage task-cycle node corresponding actual construction time of formula.
Wherein, the predetermined form can be common form form, excel table etc..
In the present embodiment, the progress of the current actual construction time of the engineering management task is obtained every prefixed time interval
Information.In some other embodiments, when the progress msg in the actual construction time changes, the engineering is obtained automatically
The progress msg of the current actual construction time of management role.
Step S150, in a predetermined format by the multistage task-cycle node, the plan time and the actual construction time
Data structure stored.
In the present embodiment, the data structure of the predetermined format is excel table.In some other embodiments, institute
The data structure for stating predetermined format can also be all data formats that can be converted into gunter drawing.
In the present embodiment, according to including a title bar, multiple level-one task-cycle nodes, each level-one task-cycle
All second tasks that node includes implement the data such as plan time and the actual construction time of node and all task-cycle nodes
Form is stored as the data of excel file format.
For example, row is time series in the excel table, the perpendicular task-cycle sections at different levels for being classified as engineering management task
Point, wherein level-one task-cycle node second task corresponding with its is implemented node and listed respectively in different perpendicular column.
For example, in excel table, first it is perpendicular be classified as the corresponding serial number of task-cycle nodes at different levels, second perpendicular is classified as level-one
Task-cycle node, third is perpendicular to be classified as second task and implements node, the 4th it is perpendicular be classified as task-cycle nodes at different levels correspond to the duration into
Degree etc., wherein each level-one task-cycle node of the second perpendicular column is arranged in multiple cells, the level-one in the perpendicular column of third
The summation for the number that the corresponding all second tasks of task-cycle node implement the corresponding cell of node is should in the second perpendicular column
The occupied cell number of level-one task-cycle node, e.g., level-one task-cycle node " prerequisite task " is in the second perpendicular column
The height for occupying 8 cells, corresponding 8 second tasks of the level-one task-cycle node implement node point in the perpendicular column of third
8 cells are not occupied.
Step S160, reads the data structure of the predetermined format, and the data structure building is used to describe described
The gunter drawing of engineering management task-cycle situation.
The data of the excel form of storage are generated to the cross for being used to describe the engineering management task-cycle situation
Road figure.
Gunter drawing is called Gantt chart (Gantt chart), it is diagrammatically by effort scale and time scale
Visually represent activity command and the duration of any specific project.
The gunter drawing includes the perpendicular column information being made of multistage task-cycle node, is made of the time series of duration
The lines figure of the plan time and actual construction time progress of row information and expression task-cycle nodes at different levels.It is illustrated in figure 2 this
A kind of schematic diagram for gunter drawing that inventive embodiments provide.
In the present embodiment, the plan time and the actual construction time corresponding bar chart can be the item of same pixel value
Shape figure, in some other embodiments, the bar chart can also for different pixel values bar chart just, be convenient for engineering management people
Member more intuitively checks the progress msg of the engineering management task.
In the present embodiment, the bar chart can be the color block of predetermined pixel value, described in some other embodiments
Bar chart can also be the color bar of predetermined color value.
When often getting the progress msg of the current actual construction time of the engineering management task, by corresponding task-cycle section
The lines figure of point duration progress msg is updated.
For example, the duration progress msg of the task-cycle node increases, the corresponding bar chart of the task-cycle node increases.
Step S170 calculates the engineering parameter of the engineering management task according to the gunter drawing.
According to the corresponding serial number information of task nodes at different levels and level-one task-cycle node and second task implement node it
Between Relation acquisition described in gunter drawing task-cycle node at different levels correspond to initial time and the end time of lines figure, according to institute
There are the initial time of task-cycle node and the end time to calculate the engineering parameter of the engineering management task.
The engineering parameter include the plan total construction period of the engineering management task, the engineering management task it is practical total
Duration, the corresponding plan time of task-cycle node at different levels, task-cycle node at different levels corresponding actual construction time, total construction period delay
Time and task-cycle node at different levels correspond to construction delay time etc..
The plan total construction period is the corresponding plan time phase of all level-one task-cycle nodes of the engineering management task
What is added implements the sum that the corresponding plan time of node is added with or for all second tasks of the engineering management task.
The practical total construction period is the corresponding actual construction time phase of all level-one task-cycle nodes of the engineering management task
What is added implements the sum that node corresponding actual construction time is added with or for all second tasks of the engineering management task.
The plan time of the level-one task-cycle node is all second tasks that the level-one task-cycle node includes
Implement the sum that the plan time of node is added.
The actual construction time of the level-one task-cycle node is all second tasks that the level-one task-cycle node includes
Implement the sum of the actual construction time addition of node.
The time range that the engineering management task is crossed over is the engineering management task earliest start time at the end of the latest
Between between the time value crossed over.
Delay time at stop total construction period is the difference between the practical total construction period of the engineering management task and plan total construction period.
The task-cycle node at different levels corresponding construction delay time is actual construction time and the plan work of each task-cycle node
Difference between phase.
Embodiment 2
Fig. 3 shows a kind of flow diagram of electricity power engineering management method of second embodiment of the invention offer.
The method flow that the implementation exemplifies includes the following steps:
Step S210 obtains engineering management task, the classification and grade of the engineering management task.
Step S220 determines the corresponding engineering management task of the classification according to preset engineering management task template
Multistage task-cycle node.
Step S230, according to each of all history items identical with the classification of the engineering management task and grade
The pragmatic actual construction time for applying node obtains the corresponding duration threshold value of each task-cycle node with default operation.
Step S240 determines the corresponding plan time of the multistage task-cycle node according to the duration threshold value.
Step S250 obtains the multistage task-cycle node corresponding actual construction time.
Step S260, in a predetermined format by the multistage task-cycle node, the plan time and the actual construction time
Data structure stored.
Step S270, reads the data structure of the predetermined format, and the data structure building is used to describe described
The gunter drawing of engineering management task-cycle situation.
Step S280, obtain task-cycle node at different levels in the gunter drawing correspond to lines figure initial time and at the end of
Between.
Line is corresponded to according to task-cycle nodes at different levels in each task-cycle node corresponding ranks value acquisition gunter drawing
The initial time of item figure and end time.
For example, as shown in Fig. 2, it is the 4/5th row C that second task, which implements the corresponding ranks value of node " move and change application letter ",
Column, the corresponding lines figure of the 4/5th row are the 4/5th row F column, and the initial time of the lines figure is 2018/01/01, at the end of
Between be 2018/01/08, should duration of " move change application letter " be 8 days, i.e. the second task plan time of implementing node
Being with the actual construction time is 8 days.
In some other task-cycle nodes, the corresponding plan time of task-cycle node and actual construction time can not also
Together.When there is construction delay, the actual construction time is greater than the plan time;The engineering management is checked and accepted in advance when appearance to appoint
When business, the actual construction time is less than the plan time.
Step S290 calculates the engineering according to the initial time of all task-cycle nodes and the end time
The engineering parameter of management role.
The engineering parameter include the plan total construction period of the engineering management task, the engineering management task it is practical total
Duration, the corresponding plan time of task-cycle node at different levels, task-cycle node at different levels corresponding actual construction time, total construction period delay
Time and task-cycle node at different levels correspond to the construction delay time.
Step S300, judges whether the duration is delayed.
Whether the value for delay time at stop total construction period that judgment step S290 is obtained is 0, if the value of delay time at stop total construction period
It is not 0, then the construction delay of the engineering management task, advances to step S310;If the value of delay time at stop total construction period is 0,
Then the duration of the engineering management task is not delayed, advances to step S320.
Step S310 issues the warning message that the construction delay time is corresponded to containing each task-cycle node.
In the case where the construction delay of the engineering management task, issue include construction delay task-cycle node and
Terminal where the warning message of the data such as the task-cycle node corresponding construction delay time to corresponding supervisor of construction,
The progress msg of the engineering management task is grasped convenient for supervisor of construction.
The engineering management task is stored as relevant history item and records the engineering management task by step S320
The multistage task-cycle node actual construction time.
After the engineering management task is checked and accepted, the engineering management task is also stored as history relevant item, and will
The actual construction time of the engineering management task and the actual construction time of task-cycle node at different levels are stored, and successive projects management is used for
Task calculates duration threshold value when assessing plan time, increases the resonable degree of plan time assessment, not the engineering of project experiences
Administrative staff again may be by the plan time of this kind of mode evaluation item.
Embodiment 3
Fig. 4 shows a kind of structural schematic diagram of electricity power engineering management system provided in an embodiment of the present invention.The power grid work
Thread management system 300 corresponds to electricity power engineering management method in embodiment 1.
The electricity power engineering management system 300 includes: task acquisition module 310, task-cycle node determining module 320, meter
Draw duration evaluation module 330, the actual construction time obtains module 340, memory module 350, reads generation module 360 and computing module
370。
Task acquisition module 310, for obtaining the classification and grade of engineering management task, the engineering management task.
Task-cycle node determining module 320, for determining that the multistage of the engineering management task is appointed according to the classification
It is pragmatic to apply node.
Plan time evaluation module 330, for according to history identical with the classification of the engineering management task and grade
The corresponding plan time of multistage task-cycle node described in the project evaluation.
Actual construction time obtains module 340, for obtaining the multistage task-cycle node corresponding actual construction time.
Memory module 350 is used for the multistage task-cycle node, the plan time and the actual construction time with pre-
The data structure for the formula that fixes is stored.
Generation module 360 is read, is used for reading the data structure of the predetermined format, and by the data structure building
In the gunter drawing for describing the engineering management task-cycle situation.
Computing module 370, for calculating the engineering parameter of the engineering management task according to the gunter drawing.
Another embodiment of the present invention also proposed a kind of terminal, which includes memory and place
Device is managed, the memory runs the computer program so that the computer for storing computer program, the processor
Terminal executes above-mentioned electricity power engineering management method.
The terminal includes PC, tablet computer, server etc..
A kind of computer program product of electricity power engineering management method provided by another embodiment of the present invention, including storage
The computer readable storage medium of program code, the instruction that said program code includes can be used for executing previous methods embodiment
Described in method, specific implementation can be found in embodiment of the method, details are not described herein.
With this, a kind of electricity power engineering management method in the present invention helps supervisor of construction to quickly understand and grasps engineering pipe
The main flow of reason;For the careless omission problem of administrative staff in existing engineering management, management node is clearly recorded in cross item by item
It in road figure, avoids slipping, statistical data is quick and precisely;It, will using gunter drawing for the problem of Management of engineering schedule uncertainty
Target advance and reality only need to compare, and show constructing aims, duration short slab, clear engineering striving direction, reduce manpower object
The cost of power.
In several embodiments provided herein, it should be understood that disclosed system and method can also pass through
Other modes are realized.System embodiment described above is only schematical, for example, flow chart and structure in attached drawing
Figure shows the system frame in the cards of the system of multiple embodiments according to the present invention, method and computer program product
Structure, function and operation.In this regard, each box in flowchart or block diagram can represent a module, section or code
A part, a part of the module, section or code includes one or more for implementing the specified logical function
Executable instruction.It should also be noted that function marked in the box can also be to be different from the implementation as replacement
The sequence marked in attached drawing occurs.For example, two continuous boxes can actually be basically executed in parallel, they are sometimes
It can execute in the opposite order, this depends on the function involved.It is also noted that in structure chart and/or flow chart
The combination of each box and the box in structure chart and/or flow chart, can function or movement as defined in executing it is dedicated
Hardware based system realize, or can realize using a combination of dedicated hardware and computer instructions.
In addition, each functional module or unit in each embodiment of the present invention can integrate one independence of formation together
Part, be also possible to modules individualism, an independent part can also be integrated to form with two or more modules.
It, can be with if the function is realized and when sold or used as an independent product in the form of software function module
It is stored in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially in other words
The part of the part that contributes to existing technology or the technical solution can be embodied in the form of software products, the meter
Calculation machine software product is stored in a storage medium, including some instructions are used so that a computer equipment (can be intelligence
Can mobile phone, personal computer, server or network equipment etc.) execute each embodiment the method for the present invention whole or
Part steps.And storage medium above-mentioned include: USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory),
Random access memory (RAM, Random Access Memory), magnetic or disk etc. be various to can store program code
Medium.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any
Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain
Lid is within protection scope of the present invention.
Claims (10)
1. a kind of electricity power engineering management method characterized by comprising
Obtain engineering management task, the classification and grade of the engineering management task;
The multistage task-cycle node of the engineering management task is determined according to the classification;
According to history item identical with the classification of the engineering management task and grade assessment multistage task-cycle node
Corresponding plan time;
Obtain the multistage task-cycle node corresponding actual construction time;
The multistage task-cycle node, the data structure of the plan time and the actual construction time in a predetermined format are carried out
Storage;
The data structure of the predetermined format is read, and the data structure building is used to describe the engineering management task reality
Apply the gunter drawing of situation;
The engineering parameter of the engineering management task is calculated according to the gunter drawing.
2. electricity power engineering management method according to claim 1, which is characterized in that described according to classification determination
The multistage task-cycle node of engineering management task includes:
Determine that the multistage task of the corresponding engineering management task of the classification is real according to preset engineering management task template
Apply node, wherein each level-one task-cycle node includes that multiple second tasks implement node.
3. electricity power engineering management method according to claim 1, which is characterized in that the basis is appointed with the engineering management
The identical history item of the classification and grade of business assesses the corresponding plan time of the multistage task-cycle node
According to each task-cycle node of all history items identical with the classification of the engineering management task and grade
Actual construction time obtains the corresponding duration threshold value of each task-cycle node with default operation;
The corresponding plan time of the multistage task-cycle node is determined according to the duration threshold value.
4. electricity power engineering management method according to claim 3, which is characterized in that the default operation is fortune of averaging
It calculates.
5. electricity power engineering management method according to claim 1, which is characterized in that the data structure of the predetermined format is
Excel tableau format.
6. electricity power engineering management method according to claim 1, which is characterized in that the gunter drawing includes by multistage task
Implement the node perpendicular column information constituted, the row information that is made of the time series of duration and indicates task-cycle nodes at different levels
The lines figure of plan time and actual construction time progress.
7. electricity power engineering management method according to claim 1, which is characterized in that described to calculate institute according to the gunter drawing
The engineering parameter for stating engineering management task includes:
Obtain initial time and end time that task-cycle node at different levels in the gunter drawing corresponds to lines figure;
The work of the engineering management task is calculated according to the initial time of all task-cycle nodes and the end time
Journey parameter.
8. electricity power engineering management method according to claim 7, which is characterized in that the engineering parameter includes the engineering
Plan total construction period, the practical total construction period of the engineering management task, the corresponding plan of task-cycle node at different levels of management role
Duration, task-cycle node at different levels corresponding actual construction time, delay time at stop total construction period and task-cycle node at different levels correspond to the duration
Delay time at stop.
9. electricity power engineering management method according to claim 8, which is characterized in that in the task-cycle nodes pair at different levels
When answering construction delay, the warning message that the construction delay time is corresponded to containing each task-cycle node is issued.
10. electricity power engineering management method according to claim 1, which is characterized in that according to gunter drawing calculating
After the engineering parameter of engineering management task further include:
The multistage that the engineering management task is stored as relevant history item and records the engineering management task is appointed
The pragmatic actual construction time for applying node.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810726318.6A CN108960779A (en) | 2018-07-04 | 2018-07-04 | Power Grid Engineering Management Method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810726318.6A CN108960779A (en) | 2018-07-04 | 2018-07-04 | Power Grid Engineering Management Method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108960779A true CN108960779A (en) | 2018-12-07 |
Family
ID=64485734
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810726318.6A Pending CN108960779A (en) | 2018-07-04 | 2018-07-04 | Power Grid Engineering Management Method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108960779A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109872126A (en) * | 2019-01-31 | 2019-06-11 | 北京博望华科科技有限公司 | Project implementation condition managing method and system based on power grid |
CN112862366A (en) * | 2021-03-17 | 2021-05-28 | 深圳海智创科技有限公司 | Differential building time scale evaluation method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110302090A1 (en) * | 2010-06-03 | 2011-12-08 | Richard Newpol | Determining a Critical Path in Statistical Project Management |
CN102945516A (en) * | 2012-10-19 | 2013-02-27 | 北京神舟航天软件技术有限公司 | Multistage network planned schedule analysis method |
CN103136636A (en) * | 2013-03-15 | 2013-06-05 | 中广核工程有限公司 | Nuclear power project progress measuring method and system |
CN104636880A (en) * | 2015-03-03 | 2015-05-20 | 南京广安科技有限公司 | Method and system for project management process feedback and deviation analysis |
CN107527148A (en) * | 2017-08-24 | 2017-12-29 | 北京融通智慧科技有限公司 | The building site project management system of power network wisdom building site control platform |
-
2018
- 2018-07-04 CN CN201810726318.6A patent/CN108960779A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110302090A1 (en) * | 2010-06-03 | 2011-12-08 | Richard Newpol | Determining a Critical Path in Statistical Project Management |
CN102945516A (en) * | 2012-10-19 | 2013-02-27 | 北京神舟航天软件技术有限公司 | Multistage network planned schedule analysis method |
CN103136636A (en) * | 2013-03-15 | 2013-06-05 | 中广核工程有限公司 | Nuclear power project progress measuring method and system |
CN104636880A (en) * | 2015-03-03 | 2015-05-20 | 南京广安科技有限公司 | Method and system for project management process feedback and deviation analysis |
CN107527148A (en) * | 2017-08-24 | 2017-12-29 | 北京融通智慧科技有限公司 | The building site project management system of power network wisdom building site control platform |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109872126A (en) * | 2019-01-31 | 2019-06-11 | 北京博望华科科技有限公司 | Project implementation condition managing method and system based on power grid |
CN112862366A (en) * | 2021-03-17 | 2021-05-28 | 深圳海智创科技有限公司 | Differential building time scale evaluation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Shou et al. | Lean management framework for improving maintenance operation: Development and application in the oil and gas industry | |
Tummala et al. | Applying a risk management process (RMP) to manage cost risk for an EHV transmission line project | |
Wesz et al. | Planning and controlling design in engineered-to-order prefabricated building systems | |
CN112446649A (en) | Method and device for examining material purchasing plan | |
Cavone et al. | Intermodal terminal planning by petri nets and data envelopment analysis | |
Sing et al. | Multiplier model for forecasting manpower demand | |
CN108960779A (en) | Power Grid Engineering Management Method | |
Dotoli et al. | An integrated technique for the internal logistics analysis and management in discrete manufacturing systems | |
Rudwan et al. | Quality Assurance of Construction Design and Contractual Phases in Syria Within BIM Environment: A Case study | |
Behrouzi et al. | A fuzzy-based model to measure supplier performance with lean attributes | |
Luyster et al. | Creating your lean future state | |
Saad et al. | Fundamentals of construction project management | |
Shou | Enhanced value stream mapping for improving turnaround process efficiency in oil and gas industry | |
Chatzistelios et al. | From scientific research to industrial application: a Lean Six Sigma system for improving the bill of materials of the packaging process | |
Sahin et al. | The first function of engineering management: Planning | |
Leal | A business intelligence approach for operational performance monitoring and improvement in a Logistics Operator | |
Liu | Research on the Status Quo and Countermeasures of HR Company's Inventory Management | |
De Leon | Adapting Lean Six Sigma for a Non-Profit Organization | |
Azevedo | Continuous Improvement in the Construction of Solar Parks | |
Kulkova et al. | Digital transformation of energy in the Russian Federation: project approach, realities and prospects | |
Bradul et al. | Budgeting development under conditions of digital economy | |
Damarapurapu et al. | Automation of Input Data Management for Discrete Event Simulation | |
Ayebazibwe | Investigating impact of contractor related re-works on construction projects in Kampala. | |
Goodwin et al. | Improving a production flow using Value Stream Mapping and Discrete Event Simulation | |
Kivikko | Process mapping for project execution from the perspective of the purchasing function: Case ABB Power Grids Finland Oy |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181207 |
|
RJ01 | Rejection of invention patent application after publication |