CN107527148A - The building site project management system of power network wisdom building site control platform - Google Patents
The building site project management system of power network wisdom building site control platform Download PDFInfo
- Publication number
- CN107527148A CN107527148A CN201710734103.4A CN201710734103A CN107527148A CN 107527148 A CN107527148 A CN 107527148A CN 201710734103 A CN201710734103 A CN 201710734103A CN 107527148 A CN107527148 A CN 107527148A
- Authority
- CN
- China
- Prior art keywords
- project
- cost
- module
- time
- building site
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 claims abstract description 88
- 238000007726 management method Methods 0.000 claims abstract description 58
- 230000002159 abnormal effect Effects 0.000 claims abstract description 19
- 238000005553 drilling Methods 0.000 claims abstract description 19
- 230000003111 delayed effect Effects 0.000 claims abstract description 17
- 230000005540 biological transmission Effects 0.000 claims description 15
- 238000010586 diagram Methods 0.000 claims description 13
- 238000012163 sequencing technique Methods 0.000 claims description 12
- 238000011156 evaluation Methods 0.000 claims description 8
- 230000008676 import Effects 0.000 claims description 4
- 238000004519 manufacturing process Methods 0.000 claims description 4
- 238000013461 design Methods 0.000 description 8
- 239000000463 material Substances 0.000 description 6
- 238000000034 method Methods 0.000 description 5
- 230000008569 process Effects 0.000 description 5
- 239000002699 waste material Substances 0.000 description 4
- 230000008901 benefit Effects 0.000 description 3
- 238000012544 monitoring process Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 230000006870 function Effects 0.000 description 2
- 230000008859 change Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 239000003550 marker Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06313—Resource planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Data Mining & Analysis (AREA)
- Public Health (AREA)
- Primary Health Care (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Biodiversity & Conservation Biology (AREA)
- Educational Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention provides a kind of building site project management system of power network wisdom building site control platform, module, Cost Accounting module, project abnormal alarm module and project trend prediction module are adjusted including PROJECT TIME, wherein, PROJECT TIME adjusts module and is used for the duration of expected sub-project and total lever factor automatically, the automatic Planning of construction periods for assessing user's input, and engineering project extension situation, and automatically generate plan time timetable;Cost Accounting module is used for the cost and totle drilling cost of expected sub-project automatically, the automatic product cost for assessing user's input, and over absorbed cost situation, and automatically generates cost statement;The project trend prediction module interlocking item time adjusts module, for calculating in real time and updating actual total lever factor and the actual construction time is delayed to send alarm signal, and automatically generates actual construction time timetable;Project abnormal alarm module sends corresponding warning message.The present invention can aid in layman to formulate the project plan, shorten the project cycle.
Description
Technical field
The present invention relates to control platform, more particularly to a kind of building site project management system.
Background technology
Project management system on the market only possesses simple construction speed record and search function at present.Need professional people
Member rule of thumb formulates the plan of project, the function of being made a plan without possessing auxiliary.Amateur management and control personnel are difficult from big
Pinpointed the problems in data.Also, hand inspection project wastes time and energy, and statistics is slow, often error, causes building site project
The degree of accuracy in the cycle of management and the actual propulsion data of project and planning data is difficult to meet the needs of current high-speed broadband network.
Therefore, there is an urgent need to a kind of building site project management system that can overcome above mentioned problem for this area.
The content of the invention
It is an object of the present invention to provide a kind of building site project management system of power network wisdom building site control platform, can aid in
Layman formulates the project plan, shortens the project cycle.
The present invention provides a kind of building site project management system of power network wisdom building site control platform, including PROJECT TIME is adjusted
Module, Cost Accounting module, project abnormal alarm module and project trend prediction module,
Wherein, PROJECT TIME adjusts duration and the total lever factor that module is used to be expected sub-project automatically according to big data, automatically
Assess the Planning of construction periods of user's input and engineering project is delayed to send alarm signal, and automatically generate the plan time time
Table;
Cost Accounting module is used for the cost and totle drilling cost for being expected sub-project automatically according to big data, and automatic assess is used
The product cost and human cost of family input, and alarm signal is sent to over absorbed cost, and automatically generate cost statement;
The project trend prediction module interlocking item time adjusts module, for according to actual sub-project duration, expected subitem
Mesh duration and expected total lever factor calculate and update actual total lever factor and the actual construction time is delayed to send alarm signal in real time, and
Automatically generate actual construction time timetable;
It is pre- that the project abnormal alarm module difference interlocking item time adjusts module, Cost Accounting module, project trend
Module and data renewal server are surveyed, for sending corresponding warning message to default terminal device according to alarm signal, with
And send sound and light alarm information.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, wherein, project
Time, which adjusts module, to be included:
Duration adjust module, for the history item data according to cloud platform from kinetonucleus calculate construction sub-project duration and
Total lever factor to generate expected project duration table, wherein, it is contemplated that project duration table includes expected total lever factor and expected sub-project duration;
Duration input module, for inputting Planning of construction periods table, wherein, Planning of construction periods table includes plan total lever factor and plan
Project duration;
Duration evaluation module, for receiving Planning of construction periods table, and by comparing Planning of construction periods table and expected project duration
Table sends alarm signal to generate plan time length assessment table to total lever factor extension, wherein, plan time length assesses table
Including the assessment result that sub-project is long in time limit, sub-project short time limit, sub-project duration are moderate and total lever factor is delayed;
Timetable generation module, for automatically generating plan time timetable according to Planning of construction periods table and exporting, wherein, meter
It is the block diagram generated according to the order auto-sequencing of time and planning item to draw duration timetable.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, wherein, project
Cost accounting module includes:
Cost accounting module, for the history item data according to cloud platform from kinetonucleus calculate construction sub-project cost and
Totle drilling cost to generate expected project cost table, wherein, it is contemplated that project cost table includes expected totle drilling cost and expected sub-project cost;
Cost input module, for inputting cost budget table, wherein, cost budgeting table include totle drilling cost and sub-project into
This;
Assessment of cost module, for receiving cost budgeting table, and by comparing cost budgeting table and expected project cost
Table carrys out manufacturing cost height assessment table, and sends alarm signal to totle drilling cost excess, wherein, cost height, which assesses table, includes subitem
Mesh cost is high, sub-project cost is low, the assessment result of sub-project moderate cost and totle drilling cost excess;
Cost statement generation module, for automatically generating project cost table according to cost budgeting table and exporting, wherein, project into
This table is the block diagram generated according to the cost of project and the order auto-sequencing of project.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, wherein, project
Trend prediction module includes:
Actual construction time input module, for inputting actual construction time table, wherein, actual construction time table includes actual sub-project work
Phase;
Actual construction time adjusts module, connects actual construction time input module, for according to actual sub-project duration, expected subitem
Mesh duration and expected total lever factor calculate in real time and update actual total lever factor, wherein, it is contemplated that project duration table includes expected chief engineer
Phase and expected sub-project duration;
Actual construction time evaluation module, delay to send out for comparing actual total lever factor and expected total lever factor, and to actual total lever factor
Go out alarm signal;
Actual construction time timetable generation module, for automatically generating reality according to actual sub-project duration and Planning of construction periods table
Duration timetable simultaneously exports, wherein, actual construction time timetable is to be given birth to according to the order auto-sequencing of actual construction time and actual items
Into block diagram.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, wherein, project
Abnormal alarm module includes:
Signal receiving/transmission device, corresponding warning message is sent to pre- for receiving alarm signal, and according to alarm signal
If terminal device;
Alarm, signal receiving/transmission device is connected, for sending sound and light alarm information according to alarm signal;
Module is retrieved, connects signal receiving/transmission device, for generating warning message inquiry request, Yi Jitong according to warning message
Signal receiving/transmission device is crossed to the module request of alert detailed plan time timetable, cost statement or actual construction time
Timetable;
Display screen, signal receiving/transmission device is connected, for display alarm information, plan time timetable, cost statement and reality
Duration timetable.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, in addition to:
Update module interface, difference interlocking item time adjust module, Cost Accounting module, project trend prediction mould
Block and data renewal server, update updating the data on server for receiving data by cable network or wireless network,
And send to update the data to PROJECT TIME and adjust module, Cost Accounting module, project trend prediction module and data more
New demand servicing device data.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, in addition to:
Big data import modul, interlocking item time adjust module, Cost Accounting module, project trend prediction module
Server is updated with data, for importing history item duration and project cost in batches and exporting.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, in addition to:
Cloud platform storage module, interlocking item time adjust module, Cost Accounting module, project trend prediction module
With item related information of the data renewal server for uploading and downloading in real time all modules.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, in addition to:
Cloud platform interface, cloud platform storage module is connected, for the real-time display in cloud platform and send all modules
Item related information.
It is preferred that, there is provided a kind of building site project management system of power network wisdom building site control platform, in addition to:
Adaptable interface, for accessing corresponding terminal device to show the item related information of all modules.
The building site project management system connection cloud platform and all kinds of terminal devices (smart machine) of the present invention, and pass through network
Transfer data to all kinds of terminal devices and cloud platform.
So, the building site project management system of one side power network wisdom building site control platform can aid in layman's system
Determine the project plan, shorten the project cycle, improve the degree of accuracy of the actual propulsion data of project and planning data, be greatly reduced manpower into
Originally it is and easy to use, to meet the needs of current high-speed broadband network.Layman is without project experiences, it becomes possible to passes through this
System to manage building site project automatically, formulates the project plan.Also, project duration, project cost and project trend are with form
Mode present, without manual sorting data, data are very clear, and it is convenient to search, easy to use.Project abnormal alarm module energy
Administrative staff are automatically reminded to when over absorbed cost and duration are delayed, facilitate administrative staff to pinpoint the problems.So, not only greatly save
Manpower and materials have been saved, and statistics is quick and precisely, and management means is flexible, disclosure satisfy that the need of current high-speed broadband network
Ask.
On the other hand, module, Cost Accounting module, project abnormal alarm module, project are adjusted by PROJECT TIME
Trend prediction module and all kinds of terminal devices (smart machine) composition Internet of Things, are integrated with " internet ", by the various projects in building site
Information uploads to cloud platform and terminal device by network, and realizing job site can perceive, visualize.So it is truly realized
Build authorities, owner, design, management comprehensive to engineering construction, overall process, round-the-clock and multiple views, multi-angle, multilayer
The real-time monitoring in face, make all departments manager that the various problems occurred in engineering construction are accomplished with " very first time finds, when first
Between dispose, the very first time solves ", promote green, intensive, lean management.It so can effectively reduce cost, reduce waste, it is real
Existing Project Benefit maximizes, and finally realizes the wisdom, green, the construction object of collaboration of building-site.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing
There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are only used for solving
Release the design of the present invention.
Fig. 1 is a kind of block schematic illustration of the building site project management system of power network wisdom building site control platform of the present invention.
Reference collects:
1st, Cost Accounting module 2, PROJECT TIME adjust module 3, project trend prediction module
4th, project abnormal alarm module 5, terminal device 6, cloud platform
Embodiment
Hereinafter, a kind of building site project management of power network wisdom building site control platform of the present invention is described with reference to the accompanying drawings
The embodiment of system.
The embodiment recorded herein is specific embodiment of the invention, for illustrating the design of the present invention,
It is explanatory and exemplary, should not be construed as the limitation to embodiment of the present invention and the scope of the invention.Except what is recorded herein
Outside embodiment, those skilled in the art can also be based on the application claims and specification disclosure of that using aobvious and
The other technical schemes being clear to, these technical schemes include making the embodiment recorded herein it is any it is obvious replace and
The technical scheme of modification.
The accompanying drawing of this specification is schematic diagram, aid in illustrating the present invention design, it is schematically indicated each several part it is mutual
Relation.Same or analogous reference marker is used to represent same or analogous part.
Referring to Fig. 1, a kind of building site project management system of power network wisdom building site control platform of the invention, including during project
Between adjust module 2, Cost Accounting module 1, project abnormal alarm module 4 and project trend prediction module 3,
Wherein, PROJECT TIME adjusts duration and the total lever factor that module 2 is used to be expected sub-project automatically according to big data, automatically
Assess the Planning of construction periods of user's input and engineering project is delayed to send alarm signal, and automatically generate the plan time time
Table;
Cost Accounting module 1 is used for the cost and totle drilling cost for being expected sub-project automatically according to big data, automatic to assess
The product cost and human cost of user's input, and alarm signal is sent to over absorbed cost, and automatically generate cost statement;
The interlocking item time of project trend prediction module 3 adjusts module 2, for according to actual sub-project duration, expected son
Project duration and expected total lever factor calculate and update actual total lever factor and the actual construction time is delayed to send alarm signal in real time, with
And automatically generate actual construction time timetable;
Interlocking item time accounting module 2, Cost Accounting module 1 and project become project abnormal alarm module 4 respectively
Gesture prediction module 3, for sending corresponding warning message to default terminal device 5 according to alarm signal, and send acousto-optic
Warning message.
In the present embodiment, building site project management system connection cloud platform 6 of the invention and all kinds of terminal devices 5, and it is logical
Transmitted data on network is crossed to all kinds of terminal devices 5 (smart machine) and cloud platform 6.
The groundwork step of the building site project management system of power network wisdom building site control platform is as follows:
User inputs Planning of construction periods to PROJECT TIME and adjusts module 2.PROJECT TIME adjusts the statistics network of module 2 and cloud platform
The time of the history relevant item (sub-project and whole project) of 6 servers, draw corresponding time threshold.PROJECT TIME is adjusted
Module 2 selects the moderate duration according to time threshold, to generate expected project duration table.PROJECT TIME accounting module 2 compares pre-
Data on phase project duration table and the Planning of construction periods of user's input, to generate plan time length assessment table, and to total lever factor
Extension sends alarm signal.For example, when the data on Planning of construction periods are more than the data on expected project duration table, it is believed that meter
It is long to draw the duration;It is on the contrary, then it is assumed that plan time is shorter.PROJECT TIME adjusts module 2 according to Planning of construction periods table to planning item
Auto-sequencing is carried out according to its execution sequence and duration length, to generate plan time timetable (block diagram).
User inputs cost budget table to Cost Accounting module 1.The statistics network of Cost Accounting module 1 and Yun Ping
The cost of the history relevant item (sub-project and whole project) of the server of platform 6, draws corresponding cost threshold value.Project cost core
Calculate module 1 and moderate cost is selected according to cost threshold value, to generate expected project cost table.Cost Accounting module 1 compares
It is expected that the data on project cost table and the cost budgeting table of user's input, table is assessed with manufacturing cost height, and to totle drilling cost
Excess sends alarm signal.For example, when the data on cost budgeting table are more than the data on expected project cost table, it is believed that
Cost is too high;It is on the contrary, then it is assumed that cost is relatively low.Cost Accounting module 1 according to cost budgeting table to its cost data according to
Execution sequence and the cost height of project carry out auto-sequencing, to generate project cost statement (block diagram).
User inputs actual construction time table to project trend prediction module 3.Project trend prediction module 3 receives PROJECT TIME core
Calculate the data in module 2.Project trend prediction module 3 is according to actual sub-project duration, expected sub-project duration and expected chief engineer
Phase is calculated in real time and updates actual total lever factor, and actual total lever factor is delayed to send alarm signal.Project trend prediction module 3
According to actual sub-project duration and Planning of construction periods table, the actual construction time is replaced with by being intended to the duration, and according to each project
Execution sequence and duration length carry out auto-sequencing, to generate actual construction time timetable (block diagram).
It is pre- that project abnormal alarm module 4 receives PROJECT TIME accounting module 2, Cost Accounting module 1 and project trend
Survey the alarm signal of module 3.Also, project abnormal alarm module 4 sends corresponding warning message to default according to alarm signal
Terminal device 5, and carry out sound and light alarm.
Data (such as project duration, project cost, project warning message) in all modules of the real-time reception of cloud platform 6,
And real-time update is shown.
So, the building site project management system of one side power network wisdom building site control platform can aid in layman's system
Determine the project plan, shorten the project cycle, improve the degree of accuracy of the actual propulsion data of project and planning data, be greatly reduced manpower into
Originally it is and easy to use, to meet the needs of current high-speed broadband network.Layman is without project experiences, it becomes possible to passes through this
System to manage building site project automatically, formulates the project plan.Also, project duration, project cost and project trend are with form
Mode present, without manual sorting data, data are very clear, and it is convenient to search, easy to use.Project abnormal alarm module 4
Administrative staff can be automatically reminded to when over absorbed cost and duration are delayed, facilitate administrative staff to pinpoint the problems.So, not only greatly
Manpower and materials are saved, and statistics is quick and precisely, and management means is flexible, disclosure satisfy that the need of current high-speed broadband network
Ask.
On the other hand, module 2, Cost Accounting module 1, project abnormal alarm module 4, item are adjusted by PROJECT TIME
Mesh trend prediction module 3 and all kinds of terminal devices 5 (smart machine) composition Internet of Things, are integrated with " internet ", and building site is various
Project information uploads to cloud platform 6 and terminal device 5 by network, and realizing job site can perceive, visualize.It is so real
Realize and build authorities, owner, design, management comprehensive to engineering construction, overall process, round-the-clock and multiple views, polygonal
Degree, multifaceted monitoring in real time, make all departments manager that the various problems occurred in engineering construction are accomplished with " very first time is sent out
Existing, very first time disposal, the very first time solves ", promote green, intensive, lean management.It so can effectively reduce cost, subtract
Little waste, realize that Project Benefit maximizes, finally realize the wisdom, green, the construction object of collaboration of building-site.
The present embodiment it is further preferred that provide a kind of building site project management system of power network wisdom building site control platform,
Wherein, PROJECT TIME is adjusted module 2 and included:
Duration adjusts module, calculates the duration of construction sub-project from kinetonucleus for the history item data according to cloud platform 6
With total lever factor to generate expected project duration table, wherein, it is contemplated that project duration table includes expected total lever factor and expected sub-project work
Phase;
Duration input module, for inputting Planning of construction periods table, wherein, Planning of construction periods table includes plan total lever factor and plan
Project duration;
Duration evaluation module, for receiving Planning of construction periods table, and by comparing Planning of construction periods table and expected project duration
Table sends alarm signal to generate plan time length assessment table to total lever factor extension, wherein, plan time length assesses table
Including the assessment result that sub-project is long in time limit, sub-project short time limit, sub-project duration are moderate and total lever factor is delayed;
Timetable generation module, for automatically generating plan time timetable according to Planning of construction periods table and exporting, wherein, meter
It is the block diagram generated according to the order auto-sequencing of time and planning item to draw duration timetable.
So, it is easy to the accurate evaluation item Planning of construction periods of project manager, assessment result automatically generates, not only greatly
Manpower and materials are saved, and statistics is quick and precisely, and management means is flexible, disclosure satisfy that the need of current high-speed broadband network
Ask.Also, once total lever factor is delayed, project manager can just receive warning message in time.
The present embodiment is it is further preferred that the embodiment provides a kind of work of power network wisdom building site control platform
Ground project management system, wherein, Cost Accounting module 1 includes:
Cost accounting module, the cost of construction sub-project is calculated from kinetonucleus for the history item data according to cloud platform 6
With totle drilling cost to generate expected project cost table, wherein, it is contemplated that project cost table include expected totle drilling cost and expection sub-project into
This;
Cost input module, for inputting cost budget table, wherein, cost budgeting table include totle drilling cost and sub-project into
This;
Assessment of cost module, for receiving cost budgeting table, and by comparing cost budgeting table and expected project cost
Table carrys out manufacturing cost height assessment table, and sends alarm signal to totle drilling cost excess, wherein, cost height, which assesses table, includes subitem
Mesh cost is high, sub-project cost is low, the assessment result of sub-project moderate cost and totle drilling cost excess;
Cost statement generation module, for automatically generating project cost table according to cost budgeting table and exporting, wherein, project into
This table is the block diagram generated according to the cost of project and the order auto-sequencing of project.
So, it is easy to the accurate evaluation item cost of project manager, assessment result automatically generates, and not only greatly saves
Manpower and materials, and statistics is quick and precisely, and management means is flexible, disclosure satisfy that the demand of current high-speed broadband network.
Also, once over absorbed cost, project manager can just receive warning message in time.
The present embodiment is it is further preferred that the embodiment provides a kind of work of power network wisdom building site control platform
Ground project management system, wherein, project trend prediction module 3 includes:
Actual construction time input module, for inputting actual construction time table, wherein, actual construction time table includes actual sub-project work
Phase;
Actual construction time adjusts module, connects actual construction time input module, for according to actual sub-project duration, expected subitem
Mesh duration and expected total lever factor calculate in real time and update actual total lever factor, wherein, it is contemplated that project duration table includes expected chief engineer
Phase and expected sub-project duration;
Actual construction time evaluation module, delay to send out for comparing actual total lever factor and expected total lever factor, and to actual total lever factor
Go out alarm signal;
Actual construction time timetable generation module, for automatically generating reality according to actual sub-project duration and Planning of construction periods table
Duration timetable simultaneously exports, wherein, actual construction time timetable is to be given birth to according to the order auto-sequencing of actual construction time and actual items
Into block diagram.
So, it is easy to project manager to contrast actual construction time and plan time, problem is found out according to duration difference, it is actual
Duration timetable real-time update and generation, manpower and materials are not only greatly saved, and statistics is quick and precisely, manages hand
Section flexibly, disclosure satisfy that the demand of current high-speed broadband network.Also, once actual total lever factor is delayed, and project manager is just
Warning message can be received in time.
The present embodiment is it is further preferred that the embodiment provides a kind of work of power network wisdom building site control platform
Ground project management system, wherein, project abnormal alarm module 4 includes:
Signal receiving/transmission device, corresponding warning message is sent to pre- for receiving alarm signal, and according to alarm signal
If terminal device 5;
Alarm, signal receiving/transmission device is connected, for sending sound and light alarm information according to alarm signal;
Module is retrieved, connects signal receiving/transmission device, for generating warning message inquiry request, Yi Jitong according to warning message
Signal receiving/transmission device is crossed to the module request of alert detailed plan time timetable, cost statement or actual construction time
Timetable;
Display screen, signal receiving/transmission device is connected, for display alarm information, plan time timetable, cost statement and reality
Duration timetable.
So, layman also can intuitively and quickly obtain warning message, monitor all project construction progresses,
It is greatly saved the mankind and material resources.
The present embodiment is it is further preferred that the embodiment provides a kind of work of power network wisdom building site control platform
Ground project management system, in addition to:
Update module interface, interlocking item time accounting module 2, Cost Accounting module 1 and project trend are pre- respectively
Module 3 is surveyed, updates updating the data on server for receiving data by cable network or wireless network, and send renewal
Data to PROJECT TIME adjusts module 2, Cost Accounting module 1 and the data of project trend prediction module 3.
So, when PROJECT TIME and cost change, the system also can real-time update data, in time eliminate legacy data,
So that the project plan is more accurately and reliably.
The present embodiment is it is further preferred that the embodiment provides a kind of work of power network wisdom building site control platform
Ground project management system, in addition to:
Big data import modul, interlocking item time adjust module 2, Cost Accounting module 1 and project trend prediction
Module 3, for importing history item duration and project cost in batches and exporting.
So, on the one hand input simple easily operated.On the other hand, the time is saved, project management can import history in batches
Project duration and project cost are into system, without inputting related data in turn.
The present embodiment is it is further preferred that the embodiment provides a kind of work of power network wisdom building site control platform
Ground project management system, in addition to:
The memory module of cloud platform 6, interlocking item time adjust module 2, Cost Accounting module 1 and project trend prediction
Module 3 is used for the item related information for uploading and downloading in real time all modules.
So project manager can be downloaded above the memory module of cloud platform 6 newest in real time by any smart machine
Data, it is easy to grasp the first-hand data of project process.
The present embodiment is it is further preferred that the embodiment provides a kind of work of power network wisdom building site control platform
Ground project management system, in addition to:
The interface of cloud platform 6, the memory module of cloud platform 6 is connected, for the real-time display in cloud platform 6 and send all modules
Item related information.
So module 2, Cost Accounting module 1, project abnormal alarm module 4, project is adjusted by PROJECT TIME to become
Gesture prediction module 3 and all kinds of terminal devices 5 form Internet of Things, are integrated with " internet ", the various project information in building site are passed through into net
Network uploads to cloud platform 6 and terminal device 5, and realizing job site can perceive, visualize.So it is truly realized construction supervisor
Department, owner, design, management are comprehensive to engineering construction, overall process, round-the-clock and multiple views, multi-angle, it is multifaceted in real time
Monitoring, make all departments manager the various problems occurred in engineering construction are accomplished " very first time find, the very first time disposal,
The very first time solves ", promote green, intensive, lean management.It so can effectively reduce cost, reduce waste, realize that project is imitated
Benefit maximizes, and finally realizes the wisdom, green, the construction object of collaboration of building-site.
The present embodiment is it is further preferred that the embodiment provides a kind of work of power network wisdom building site control platform
Ground project management system, in addition to:
Adaptable interface, for accessing corresponding terminal device 5 to show the item related information of all modules.
So project manager can show the item related information of all modules by any terminal device 5, be easy to
Grasp the first-hand data of project process.
A kind of embodiment of the building site project management system of power network wisdom building site control platform of the present invention is entered above
Explanation is gone.Can basis for the specific features of the building site project management system of the power network wisdom building site control platform of the present invention
The effect of the feature of above-mentioned disclosure carries out specific design, and these designs are that those skilled in the art can realize.On moreover,
Each technical characteristic for stating disclosure is not limited to disclosed and further feature combination, and those skilled in the art can also be according to this hair
Bright purpose carries out other combinations between each technical characteristic, is defined by the purpose for realizing the present invention.
Claims (10)
1. a kind of building site project management system of power network wisdom building site control platform, including PROJECT TIME adjust module, project into
This accounting module, project abnormal alarm module and project trend prediction module,
Wherein, the PROJECT TIME adjusts duration and the total lever factor that module is used to be expected sub-project automatically according to big data, automatically
Assess the Planning of construction periods of user's input and engineering project is delayed to send alarm signal, and automatically generate the plan time time
Table;
The Cost Accounting module is used for the cost and totle drilling cost for being expected sub-project automatically according to big data, and automatic assess is used
The product cost and human cost of family input, and alarm signal is sent to over absorbed cost, and automatically generate cost statement;
The project trend prediction module connects the PROJECT TIME and adjusts module, for according to actual sub-project duration, expection
Sub-project duration and expected total lever factor calculate and update actual total lever factor and the actual construction time is delayed to send alarm signal in real time,
And automatically generate actual construction time timetable;
The project abnormal alarm module connects the PROJECT TIME and adjusts module, Cost Accounting module and the item respectively
Mesh trend prediction module, for sending corresponding warning message to default terminal device according to alarm signal, and send sound
Light alarm information.
2. a kind of building site project management system of power network wisdom building site control platform according to claim 1, wherein, it is described
PROJECT TIME, which adjusts module, to be included:
Duration adjusts module, calculates duration and the chief engineer of construction sub-project from kinetonucleus for the history item data according to cloud platform
Phase to generate expected project duration table, wherein, it is contemplated that project duration table includes expected total lever factor and expected sub-project duration;
Duration input module, for inputting Planning of construction periods table, wherein, Planning of construction periods table includes plan total lever factor and plan sub-project
Duration;
Duration evaluation module, for receiving Planning of construction periods table, and by compare Planning of construction periods table and expected project duration table come
Generate plan time length and assess table, and total lever factor is delayed to send alarm signal, wherein, plan time length assessment table includes
The assessment result that sub-project is long in time limit, sub-project short time limit, sub-project duration are moderate and total lever factor is delayed;
Timetable generation module, for automatically generating plan time timetable according to Planning of construction periods table and exporting, wherein, plan work
Phase timetable is the block diagram generated according to the order auto-sequencing of time and planning item.
3. a kind of building site project management system of power network wisdom building site control platform according to claim 1, wherein, it is described
Cost Accounting module includes:
Cost accounting module, the cost and assembly of construction sub-project are calculated from kinetonucleus for the history item data according to cloud platform
Originally to generate expected project cost table, wherein, it is contemplated that project cost table includes expected totle drilling cost and expected sub-project cost;
Cost input module, for inputting cost budget table, wherein, cost budgeting table includes totle drilling cost and sub-project cost;
Assessment of cost module, for receiving cost budgeting table, and by compare cost budgeting table and expected project cost table come
Manufacturing cost height assesses table, and sends alarm signal to totle drilling cost excess, wherein, cost height assess table include sub-project into
This height, sub-project cost are low, the assessment result of sub-project moderate cost and totle drilling cost excess;
Cost statement generation module, for automatically generating project cost table according to cost budgeting table and exporting, wherein, project cost table
For the block diagram of the order auto-sequencing of the cost according to project and project generation.
4. a kind of building site project management system of power network wisdom building site control platform according to claim 1, wherein, it is described
Project trend prediction module includes:
Actual construction time input module, for inputting actual construction time table, wherein, actual construction time table includes the actual sub-project duration;
Actual construction time adjusts module, connects the actual construction time input module, for according to actual sub-project duration, expected subitem
Mesh duration and expected total lever factor calculate in real time and update actual total lever factor, wherein, it is contemplated that project duration table includes expected chief engineer
Phase and expected sub-project duration;
Actual construction time evaluation module, for comparing actual total lever factor and expected total lever factor, and actual total lever factor is delayed to send report
Alert signal;
Actual construction time timetable generation module, for automatically generating the actual construction time according to actual sub-project duration and Planning of construction periods table
Timetable simultaneously exports, wherein, actual construction time timetable is to be generated according to the order auto-sequencing of actual construction time and actual items
Block diagram.
5. a kind of building site project management system of power network wisdom building site control platform according to claim 1, wherein, it is described
Project abnormal alarm module includes:
Signal receiving/transmission device, corresponding warning message is sent to default for receiving alarm signal, and according to alarm signal
Terminal device;
Alarm, the signal receiving/transmission device is connected, for sending sound and light alarm information according to alarm signal;
Module is retrieved, connects the signal receiving/transmission device, for generating warning message inquiry request, Yi Jitong according to warning message
The signal receiving/transmission device is crossed to come to the module request of alert detailed plan time timetable, cost statement or reality
Duration timetable;
Display screen, the signal receiving/transmission device is connected, for display alarm information, plan time timetable, cost statement and reality
Duration timetable.
6. a kind of building site project management system of power network wisdom building site control platform according to claim 1, in addition to:
Update module interface, the PROJECT TIME is connected respectively and adjusts module, Cost Accounting module, project trend prediction mould
Block and data renewal server, for receiving the renewal number on the data renewal server by cable network or wireless network
According to, and send update the data to the PROJECT TIME adjust module, Cost Accounting module, project trend prediction module and
Data update server data.
7. a kind of building site project management system of power network wisdom building site control platform according to claim 1, in addition to:
Big data import modul, connect the PROJECT TIME and adjust module, Cost Accounting module, project trend prediction module
Server is updated with data, for importing history item duration and project cost in batches and exporting.
8. a kind of building site project management system of power network wisdom building site control platform according to claim 1, in addition to:
Cloud platform storage module, connect the PROJECT TIME and adjust module, Cost Accounting module, project trend prediction module
With item related information of the data renewal server for uploading and downloading in real time all modules.
9. a kind of building site project management system of power network wisdom building site control platform according to claim 8, in addition to:
Cloud platform interface, the cloud platform storage module is connected, for the real-time display in cloud platform and send all modules
Item related information.
10. a kind of building site project management system of power network wisdom building site control platform according to claim 9, in addition to:
Adaptable interface, for accessing corresponding terminal device to show the item related information of all modules.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710734103.4A CN107527148B (en) | 2017-08-24 | 2017-08-24 | Building site project management system of power grid smart building site management and control platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710734103.4A CN107527148B (en) | 2017-08-24 | 2017-08-24 | Building site project management system of power grid smart building site management and control platform |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107527148A true CN107527148A (en) | 2017-12-29 |
CN107527148B CN107527148B (en) | 2021-04-02 |
Family
ID=60681914
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710734103.4A Active CN107527148B (en) | 2017-08-24 | 2017-08-24 | Building site project management system of power grid smart building site management and control platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107527148B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108960779A (en) * | 2018-07-04 | 2018-12-07 | 广东电网有限责任公司 | Power Grid Engineering Management Method |
CN111598419A (en) * | 2020-04-30 | 2020-08-28 | 国网浙江省电力有限公司台州供电公司 | Power grid construction management and control method based on Internet and intelligent infrastructure platform system |
CN114282827A (en) * | 2021-12-27 | 2022-04-05 | 中铁建工集团有限公司 | Method and system for scheduling construction period progress |
CN115204851A (en) * | 2022-09-19 | 2022-10-18 | 北京中创碳投科技有限公司 | Method and system for evaluating and optimizing effect of intelligent accounting model |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103325024A (en) * | 2013-07-18 | 2013-09-25 | 北京影合众新媒体技术服务有限公司 | Intelligent scheduling system |
CN104636479A (en) * | 2015-02-15 | 2015-05-20 | 西安电子科技大学 | Industrial big data driven total completion time prediction method |
CN105574673A (en) * | 2015-12-22 | 2016-05-11 | 中煤科工集团武汉设计研究院有限公司 | System and method for man-hour management of design company |
CN105608524A (en) * | 2015-12-15 | 2016-05-25 | 国网北京市电力公司 | Method and apparatus for predicting engineering data |
CN106096905A (en) * | 2016-05-31 | 2016-11-09 | 北京诚公通信工程监理股份有限公司 | A kind of project management method and system |
CN106920068A (en) * | 2017-01-19 | 2017-07-04 | 国家电网公司 | Electricity power engineering pricing management of the one kind based on big data and " internet+" |
-
2017
- 2017-08-24 CN CN201710734103.4A patent/CN107527148B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103325024A (en) * | 2013-07-18 | 2013-09-25 | 北京影合众新媒体技术服务有限公司 | Intelligent scheduling system |
CN104636479A (en) * | 2015-02-15 | 2015-05-20 | 西安电子科技大学 | Industrial big data driven total completion time prediction method |
CN105608524A (en) * | 2015-12-15 | 2016-05-25 | 国网北京市电力公司 | Method and apparatus for predicting engineering data |
CN105574673A (en) * | 2015-12-22 | 2016-05-11 | 中煤科工集团武汉设计研究院有限公司 | System and method for man-hour management of design company |
CN106096905A (en) * | 2016-05-31 | 2016-11-09 | 北京诚公通信工程监理股份有限公司 | A kind of project management method and system |
CN106920068A (en) * | 2017-01-19 | 2017-07-04 | 国家电网公司 | Electricity power engineering pricing management of the one kind based on big data and " internet+" |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108960779A (en) * | 2018-07-04 | 2018-12-07 | 广东电网有限责任公司 | Power Grid Engineering Management Method |
CN111598419A (en) * | 2020-04-30 | 2020-08-28 | 国网浙江省电力有限公司台州供电公司 | Power grid construction management and control method based on Internet and intelligent infrastructure platform system |
CN114282827A (en) * | 2021-12-27 | 2022-04-05 | 中铁建工集团有限公司 | Method and system for scheduling construction period progress |
CN115204851A (en) * | 2022-09-19 | 2022-10-18 | 北京中创碳投科技有限公司 | Method and system for evaluating and optimizing effect of intelligent accounting model |
Also Published As
Publication number | Publication date |
---|---|
CN107527148B (en) | 2021-04-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107527148A (en) | The building site project management system of power network wisdom building site control platform | |
CN110070343A (en) | A kind of prospecting project management system and method | |
CN105155599B (en) | Remote information monitoring and analyzing device and method for cement soil mixing pile | |
CN103279831B (en) | For the management system implementation method of evaluation software test mass and development ability | |
CN109800250B (en) | System architecture for no longer configuring enterprise central server | |
CN105447681B (en) | Physical and chemical detection control and information management system | |
CN109190962A (en) | Project process supervision control system | |
CN109543992A (en) | Intelligent polling method, device, intelligent terminal and server | |
CN109857080B (en) | Intelligent ship lock operation and maintenance system based on BIM | |
KR100606861B1 (en) | Infrastructure maintenance and management business support system, the method using the same | |
CN104809933B (en) | A kind of power grid is without script emergency drilling system, drilling method and equipment | |
CN113626914A (en) | Engineering project management method, device and system based on digital twins | |
CN116720752A (en) | Assembled building quality information supervision system based on big data | |
CN104899143B (en) | The software peer review system implementation device of data mining is provided | |
CN101656020A (en) | System and method for evaluating urban road traffic zone servings levels based on actual measurements | |
CN208888869U (en) | It is a kind of based on internet+external coordination construction team safety control platform | |
CN109359900A (en) | A kind of inspection management platform | |
CN117371952B (en) | Multi-project collaborative management system | |
CN109117526A (en) | One kind being suitable for mechanical system maintenance of equipment and guides data record and analysis system | |
CN115186977A (en) | Method and system for monitoring task abnormity of automobile part research and development project | |
CN110956444A (en) | Infrastructure distribution network engineering data management mobile system | |
CN107844102A (en) | Production plan management method and system | |
KR100584903B1 (en) | System for real time controlling driving data of power plant | |
US10981586B2 (en) | Railway diagnostic systems and methods | |
CN207070219U (en) | Projects supervision system based on video monitoring |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |