CN115186977A - Method and system for monitoring task abnormity of automobile part research and development project - Google Patents

Method and system for monitoring task abnormity of automobile part research and development project Download PDF

Info

Publication number
CN115186977A
CN115186977A CN202210605857.0A CN202210605857A CN115186977A CN 115186977 A CN115186977 A CN 115186977A CN 202210605857 A CN202210605857 A CN 202210605857A CN 115186977 A CN115186977 A CN 115186977A
Authority
CN
China
Prior art keywords
project
user
information
weight
determining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210605857.0A
Other languages
Chinese (zh)
Inventor
刘辉
胡冰
欧瑜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Weizhi Intelligent Technology Co ltd
Original Assignee
Zhejiang Kangle Industrial Software Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Kangle Industrial Software Co ltd filed Critical Zhejiang Kangle Industrial Software Co ltd
Priority to CN202210605857.0A priority Critical patent/CN115186977A/en
Publication of CN115186977A publication Critical patent/CN115186977A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/904Browsing; Visualisation therefor
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/018Certifying business or products
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B31/00Predictive alarm systems characterised by extrapolation or other computation using updated historic data

Abstract

The invention provides a method and a system for monitoring task abnormity of an automobile part research and development project; the establishment of a monitoring network is realized by constructing a uniform monitoring platform, a uniform template is set, the standardized management of projects is realized, and a personalized self-management scheme is customized for a user; user weight is introduced, and abnormity monitoring is carried out based on information of users, projects and the like, so that automatic early warning of the projects is realized, and the automation degree of project management is improved; through the authority control mechanism of the user, the confidentiality of the core project management information of the enterprise can be ensured, abnormal operation can be found timely, problems and risks can be guaranteed to be responsible for people, the standardization of project management is greatly improved, and the efficiency of project management is improved.

Description

Method and system for monitoring task abnormity of automobile part research and development project
Technical Field
The invention relates to a method and a system for monitoring task abnormity of an automobile part research and development project.
Background
In the manufacturing industry and internet enterprises, the time efficiency requirement of innovation is transited from the traditional year and month unit to week and day unit, and the enterprises are challenged by factors such as planning, resources, risks, problems, cost and the like in the innovation. In particular, in the automobile part project, because the number of parts is large, the number of projects is large, the time, resources and cost required by innovation are different, the problems and risks faced are different, and therefore a new challenge is provided for the management of the project.
At present, project management is more overall by means of project managers, and various kinds of project information are regularly collected according to project nodes, so that the project information is not updated timely, the collected information is not uniform in standard and different in format, and uniform management is not facilitated; various risks and problem information of the project cannot be visually seen; furthermore, there is no way to blame a person when a problem arises. Therefore, how to solve the mutual exclusion contradiction in the innovation process by adopting the technology + the tool + the management, help the innovator to improve the visibility of the data, help the innovator and the manager to find the problem in time, and solve the problem is a problem which needs to be solved urgently at present, so that a data sharing system for coordinating innovation is needed to be provided.
Disclosure of Invention
In order to solve the problems in the prior art, the invention provides a method for monitoring task abnormity of an automobile part research and development project, which comprises the following steps:
network monitoring: the method comprises the steps that login information and operation information of a user are obtained in real time through distributed nodes, and the user uploads project updating information through a specified template on the distributed nodes;
a data processing step: determining the personnel weight W of the user according to the login information of the user User' s (ii) a Determining a project risk assessment value Q according to the project updating information;
and an abnormal alarming step: determining a project abnormal weight W according to the personnel weight and the project risk assessment value, and performing early warning according to the project abnormal weight;
visualization management: and the method is used for performing visual data management according to the abnormal weight.
Wherein the network monitoring step further comprises: after obtaining login information and operation information of a user, determining operation authority of the user according to the login information of the user, and verifying the operation information of the user according to the operation authority;
and when the verification is passed, acquiring project updating information through the operation information.
Wherein, determining the personnel weight of the user according to the login information of the user specifically comprises:
acquiring historical item information of the user from a historical database;
acquiring project data information of a user from the historical project information, wherein the project data information comprises: the method comprises the following steps of (1) obtaining a project average question amount N, a project average delay time T, a user evaluation value P, a project delivered quality M and a project average risk value F;
determining the personnel weight W according to the project data information of the user User' s
Wherein, determining the item risk assessment value according to the item update information specifically includes: updating the project state according to the project updating information, and calculating a project risk assessment value Q according to the project state;
wherein, the item risk assessment value Q is based on the item problem quantity N now Predicted delay period T delay The number of problems processed N old Determining the project progress S and the project coefficient A.
Wherein determining the project anomaly weight according to the personnel weight and the project risk assessment value further comprises:
acquiring integral information of a project, wherein the integral information of the project comprises a project progress S of the project and a total problem quantity N found by the project total Number of problems processed N old The execution condition of the delivered object comprises the number K of the finished delivered objects and the mass M of the finished delivered objects i ,M i Representing the mass of the ith delivery;
determining an abnormal weight W of the project according to the overall information, the personnel weight and the risk assessment value of the project;
wherein, the first and the second end of the pipe are connected with each other,
Figure BDA0003671259410000031
wherein, K total The total number of deliveries to be submitted; n is a radical of User' s Is the total number of people participating in the project; w is a group of j user Representing a personal weight of a jth user;
and early warning of the project abnormity is carried out according to the project abnormity weight.
The invention also provides a system for monitoring the task abnormity of the automobile part research and development project, which comprises:
a network monitoring module: the login information and the operation information of the user are obtained in real time through the distributed nodes, and the user uploads the project updating information through a specified template on the distributed nodes;
a data processing module: determining the personnel weight W of the user according to the login information of the user User' s (ii) a Determining a project risk assessment value Q according to the project updating information;
an abnormality alarm module: determining a project abnormal weight W according to the personnel weight and the project risk assessment value, and performing early warning according to the project abnormal weight;
a visualization management module: and the method is used for performing visual data management according to the abnormal weight.
The invention has the beneficial effects that the invention provides a method and a system for monitoring the task abnormity of the automobile part research and development project; by constructing a uniform monitoring platform and setting a uniform template, the standardized management of projects and a customized and personalized self-management scheme for users are realized; user weight is introduced, and abnormity monitoring is carried out based on information of users, projects and the like, so that automatic early warning of the projects is realized, and the automation degree of project management is improved; through the authority control mechanism of the user, the confidentiality of the enterprise core project management information can be ensured, abnormal operation can be found timely, problems and risks can be guaranteed to be responsible for people, the standardization of project management is greatly improved, and the project management efficiency is improved.
Drawings
The invention is further illustrated by the following examples in conjunction with the drawings.
FIG. 1 is a flow chart of a method of a preferred embodiment of the present invention;
FIG. 2 is a network architecture diagram of the preferred embodiment of the present invention;
fig. 3 is a system block diagram of a preferred embodiment of the present invention.
Detailed Description
The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic views illustrating only the basic structure of the present invention in a schematic manner, and thus show only the constitution related to the present invention.
A method for monitoring task abnormity of an automobile part research and development project is disclosed, as shown in FIG. 1, and the method comprises the following steps:
network monitoring: the login information and the operation information of the user are obtained in real time through the distributed nodes, and the user uploads the project updating information through a specified template on the distributed nodes; users related to the project, such as research personnel, log in the project background through the personal terminal to upload project update information, and therefore the update of project data is achieved; and the specified template is selected and set by a project manager and/or a project responsible person in a unified way according to the characteristics of the project.
A data processing step: determining the personnel weight W of the user according to the login information of the user User' s (ii) a Determining a project risk assessment value Q according to the project updating information; and acquiring information of a target user according to the login information of the user, acquiring information related to the user and the project from a historical database, and calculating the personnel weight.
An abnormity alarming step: determining a project abnormal weight W according to the personnel weight and the project risk assessment value, and performing early warning according to the project abnormal weight;
visualization management: and the method is used for performing visual data management according to the abnormal weight. And when the abnormal weight of the item is obtained, setting a display and/or reminding scheme aiming at the abnormal weight.
Users such as research personnel update project progress in real time through the distributed nodes, and abnormity confirmation is carried out through risk assessment of the research personnel and risk assessment of project indexes, so that projects with abnormal information can be found in time and follow up in time.
In the invention, as shown in fig. 2, a monitoring network is established by a server and distributed nodes, and project management is realized by cooperation of the server and the distributed nodes; the server and the distributed nodes form an internal network of the enterprise, and the internal network is preferably an internal local area network in the enterprise. The server can be a server in an enterprise; the distributed nodes may be end devices of individual users within the enterprise. Nodes at all levels are customized according to projects, different users have own node attributes, the users log in the nodes through equipment configured by enterprises, then project information is updated, and problems are presented in time. The templates used by the same project are the same, and users related to the project update data based on the same template, so that the standardization of project management is greatly improved.
According to the invention, by establishing a uniform monitoring system, each user, such as research personnel, can access the project system in time through personal computers, mobile phones and other terminal devices, and update the project according to the specified template, so that the standardized management of project files is realized. Meanwhile, a personnel monitoring and project risk evaluation mechanism is introduced, so that personalized early warning can be effectively carried out on users and projects, the project responsibility is realized, the supervision of each link is effectively realized, and the project management efficiency is improved.
Wherein the network monitoring step further comprises: after obtaining login information and operation information of a user, determining the operation authority of the user according to the login information of the user, and verifying the operation information of the user according to the operation authority;
and when the verification is passed, acquiring item updating information through the operation information.
In the prior art, a project manager needs to set a template by itself, inform users related to a project and inform users of submitting project data on time. In the process, the workload is large, and due to different habits of each user at ordinary times and different understandings on the templates, the formats of the project data submitted at the time are different; the timeliness of submitting data cannot be guaranteed, and tasks cannot be blamed to people; through the scheme of the invention, each user is distributed with different operation authorities, preferably, the operation authorities are distributed based on project tasks, each task is different, and the operation content/object is different, so that each task and each data are definitely completed by a specific user; moreover, through the scheme of the invention, the user can only submit the data according to the specific template, so that the unification of the data format is ensured, the responsibility to people is really realized, and the management efficiency of the project is greatly improved.
Wherein, determining the personal weight of the user according to the login information of the user specifically comprises:
acquiring historical item information of the user from a historical database; in order to facilitate the tracing of the project, a historical database is established in the enterprise server, and the historical database stores historical project information, so that research and development personnel can conveniently use for reference.
Acquiring project data information of a user from the historical project information, wherein the project data information comprises: the method comprises the following steps of (1) obtaining a project average question amount N, a project average delay time T, a user evaluation value P, a project delivered quality M and a project average risk value F; the project data information is counted or scored by a project manager, a project leader or related responsible persons, quality management personnel and the like; preferably, the average project problem amount N, the average project delay time length T and the project delivered quality M are obtained by a project manager through statistics, and the evaluation value P of the user is evaluated by a leader or a leader in charge of the project; the risk value F is obtained by comprehensively scoring by a project manager, and a quality manager, and the preferred risk value F may be an evaluation value of an infringement risk and the like. If the user is a newly added user, a history item similar to an item responsible for the user can be selected from a history database to serve as a history item set, and then the item data information of the history item set is obtained from the history item set to serve as the item data information of the user.
Determining the person weight W according to the project data information of the user User' s
Figure BDA0003671259410000061
Wherein, N max For the most number of questions in the history, N min The minimum number of questions in the history item; t is max Is the longest delay time, T, in the history min The time length is the shortest delay time length in the historical project, wherein, the value is a positive value when the project is delayed, if the project is complete in advance, the value is a negative value, and if the project is completed on time according to a plan, the value is 0; m max For the highest value of delivered substance in the history, T min The minimum value of the quality of the delivered goods in the historical item; the historical items can be a set of items completed in a past period of time or a set of a certain number of items completed in the past, and the selection of the historical item set can be selected by a project manager according to actual properties of the items.
The invention creatively provides a concrete evaluation mode of project personnel for the first time, and research personnel and other users can be effectively managed through risk evaluation, so that the time awareness of the research personnel and the development personnel is enhanced, the ordered progress of projects is ensured, and the completion efficiency of the projects is effectively improved; the working state and the working quality of personnel related to each project can be effectively known through the setting of the personnel weight, the larger the personnel weight is, the worse the project completion level of the user is, more attention needs to be added to project tasks responsible for the user, and possible problems, risks and the like can be timely discovered. By means of the method, more reasonable personnel management strategies can be formulated, project task responsibility to people is further promoted, and project management efficiency is promoted.
Wherein, determining the item risk assessment value according to the item update information specifically includes: updating the project state according to the project updating information, and calculating a project risk assessment value Q according to the project state;
item Risk assessment value Q based on item quantity N now Predicted delay time T delay The number of problems processed N old Determining project progress S and project coefficient A (reflecting the importance degree of the project, and setting by a project manager and a responsible person when the project is started); wherein the data is provided by the user associated with the project.
Figure BDA0003671259410000071
The larger the risk value Q is, the more problem risks in the explanation project are, the early warning needs to be improved, and related responsible persons are reminded to increase attention.
According to the method for assessing the project risk, which is creatively determined for the first time, the problem of how to assess the project risk can be effectively solved, and the server can automatically complete processing according to the collected data in the mode, so that the risk state of the project is directly presented to related personnel of the project; therefore, more reasonable project management strategies can be formulated, and the quality and the efficiency of the project are improved.
Wherein determining the project anomaly weight according to the personnel weight and the project risk assessment value further comprises:
acquiring the whole information of the project, wherein the whole information of the project comprises the project progress S of the project and the total problem quantity N found by the project total Number of problems processed N old The execution condition of the delivered object comprises the number K of the finished delivered objects and the mass M of the finished delivered objects i
Determining an abnormal weight W of the project according to the overall information, the personnel weight and the risk assessment value of the project;
and early warning of the project abnormity is carried out according to the project abnormity weight.
Figure BDA0003671259410000081
Wherein the content of the first and second substances,K total the total number of deliveries that need to be submitted; n is a radical of hydrogen User The total number of persons participating in the project, preferably the number of developers; w j user Representing the personal weight of the jth user.
The invention creatively uses the project information and the information of the project related members for comprehensive consideration for the first time, thereby realizing the abnormal early warning scheme of the project, and the current state and the abnormal degree of the project can be more reasonably determined by the scheme. By means of the method, more reasonable personnel management strategies can be formulated, project task accountability is further promoted, project time management efficiency is improved, and project management efficiency is promoted.
In order to help innovators to improve data visibility, help innovators and managers to find problems in time and solve problems, the invention provides visual data management, preferably, the visual data management comprises: customizing data display and information reminding;
wherein the customizing data displaying step comprises: a user customizes a display interface according to the demand of the user; the method comprises the steps of establishing a personal portal, a personal calendar, chart management setting, a task board, a message reminding mode and the like.
The information reminding step comprises the following steps: the user customizes information and a reminding mode to be reminded according to the project state; and the project manager sets the contents to be displayed at the user terminal according to the personnel weights of different users.
And establishing a personal portal, and presenting information such as progress, tasks, resources, abnormal prompts and the like of various projects concerned by the user, such as the execution state of the project, the execution condition of the problem, the execution condition of the risk, the execution condition of the project change, the execution condition of the delivered object, the recent work arrangement and the like.
And establishing a personal calendar, and realizing the checking, management and supervision of project progress by integrating the outlook calendar and sharing the log with external related personnel.
Chart management: personalized management of the displayed chart is supported, such as comparing the project schedule with the plan by using a Gantt chart, and no details are missed; constructing a self-defined task view, such as a task board and a form; including but not limited to the following functions: various screening modes are realized, such as according to labels, priorities, states and the like; the user-defined sequencing mode simultaneously provides tags to help members to quickly classify, and simultaneously supports task comments so as to provide easy project social experience, support task reminding setting, avoid missing important time and the like. And task management, problem management, risk management, cost management, delivery management and the like of the project are realized through the task boards and the tables.
The system can realize project evaluation, discussion and monitoring mechanisms through personalized visual management, preferably also has a user assessment mechanism, timely knows the personnel weight of the user and promotes the improvement of the self-ability of the individual.
Through visual management, the system can help the executive users, project managers and project managers of project tasks to know the states, problems, risks and the like of projects in time, does not need to inform data collection every time like the prior art, and then spends a great deal of time and energy to arrange; the visual management scheme of the invention not only greatly reduces a lot of manpower and material resources, but also improves the processing efficiency of project information and reduces the maintenance cost of project schedule.
In order to implement the method, the present invention further provides a system for monitoring task abnormity of an automobile part development project, as shown in fig. 3, wherein the system may be disposed in a server and/or distributed nodes, and the system includes:
a network monitoring module: the method comprises the steps that login information and operation information of a user are obtained in real time through distributed nodes, and project updating information uploaded by the user through a specified template on the distributed nodes is obtained;
a data processing module: determining the personnel weight W of the user according to the login information of the user User' s (ii) a Determining a project risk assessment value Q according to the project updating information;
an abnormality alarm module: determining a project abnormity weight W according to the personnel weight and the project risk assessment value, and carrying out early warning according to the project abnormity weight;
a visualization management module: and the method is used for performing visual data management according to the abnormal weight.
In the invention, project management is realized through cooperation of the server and the distributed nodes; the servers and distributed nodes form an internal network of the enterprise. The server can be a server in an enterprise; the distributed nodes may be end devices of individual users within the enterprise. And customizing nodes at all levels according to the project, wherein different users have own node attributes, and updating project information through the home node to present problems in time. The templates used by the same project are the same, and users related to the project update data based on the same template, so that the standardization of project management is greatly improved.
Wherein the network monitoring module is further configured to: after obtaining login information and operation information of a user, determining the operation authority of the user according to the login information of the user, and verifying the operation information of the user according to the operation authority;
and when the verification is passed, acquiring item updating information through the operation information.
Wherein, determining the personal weight of the user according to the login information of the user specifically comprises:
acquiring historical item information of the user from a historical database;
acquiring project data information of a user from the historical project information, wherein the project data information comprises: the method comprises the following steps of (1) calculating an average project problem quantity N, an average project delay time length T, an evaluation value P of a user, a project delivered quality M and an average project risk value F;
determining the personnel weight W according to the project data information of the user User' s
Wherein, determining the item risk assessment value according to the item update information specifically includes: updating the project state according to the project updating information, and calculating a project risk assessment value Q according to the project state;
wherein, the item risk assessment value Q is based on the problem quantity N of the item now Predicted delay period T delay The number of problems processed N old Determining the project progress S and the project coefficient A.
Wherein determining the project anomaly weight according to the personnel weight and the project risk assessment value further comprises:
acquiring integral information of a project, wherein the integral information of the project comprises a project progress S of the project and a total problem quantity N found by the project total Number of problems processed N old The execution condition of the delivered object comprises the number K of the finished delivered objects and the mass M of the finished delivered objects i ,M i Representing the mass of the ith delivery;
determining an abnormal weight W of the project according to the overall information, the personnel weight and the risk assessment value of the project;
wherein the content of the first and second substances,
Figure BDA0003671259410000111
wherein, K total The total number of deliveries to be submitted; n is a radical of hydrogen User' s Is the total number of people participating in the project; w j user Representing a personal weight of a jth user;
and early warning of the project abnormity is carried out according to the project abnormity weight.
The invention creatively uses the project information and the information of the project related members for comprehensive consideration for the first time, thereby realizing the abnormal early warning scheme of the project, and the current state and the abnormal degree of the project can be more reasonably determined by the scheme. By means of the method, more reasonable personnel management strategies can be formulated, project task responsibility to people is further promoted, and project management efficiency is promoted.
In order to help the innovator to improve the visibility of the data, help the innovator and the manager to find the problem and solve the problem in time, the invention provides visualized data management, preferably, the visualized data management comprises: customizing data display and information reminding;
wherein, the customized data display step comprises: a user customizes a display interface according to the demand; the method comprises the steps of establishing a personal portal, a personal calendar, chart management setting, a task board, a message reminding mode and the like.
The information reminding step comprises the following steps: the user customizes information and a reminding mode to be reminded according to the project state; and the project management personnel set the contents to be displayed by the user side according to the personnel weights of different users.
And establishing a personal portal, and presenting information such as progress, tasks, resources, abnormal prompts and the like of various projects concerned by the user, such as the execution state of the project, the execution condition of the problem, the execution condition of the risk, the execution condition of the project change, the execution condition of the delivered object, the recent work arrangement and the like.
And establishing a personal calendar, and realizing the viewing, management and supervision of project schedules by integrating the outlook calendar and sharing the log with external related personnel.
Chart management: personalized management of the displayed chart is supported, such as comparing the project schedule with the plan by using a Gantt chart, and no details are missed; constructing a self-defined task view, such as a task board and a form; including but not limited to the following functions: various screening modes are realized, such as according to labels, priorities, states and the like; the user-defined sequencing mode simultaneously provides tags to help members to quickly classify, and simultaneously supports task comments so as to provide easy project social experience, support task reminding setting, avoid missing important time and the like. And task management, problem management, risk management, cost management, delivery management and the like of the project are realized through the task boards and the tables.
The system can realize project evaluation, discussion and monitoring mechanisms through personalized visual management, preferably has a user assessment mechanism, timely knows the personnel weight of the user and promotes the improvement of the self-ability of the user.
Through visual management, the system can help the executive users, project managers and project managers of project tasks to know the states, problems, risks and the like of projects in time, does not need to inform data collection every time like the prior art, and then spends a great deal of time and energy to arrange; the visual management scheme of the invention not only greatly reduces a lot of manpower and material resources, but also improves the processing efficiency of project information and reduces the maintenance cost of project schedule. .
The invention realizes the standardized management of projects and the customized personalized self-management scheme for users by constructing a unified monitoring platform and setting a unified template; user weight is introduced, and exception monitoring is performed based on information such as users and projects, so that automatic early warning of the projects is realized, and the automation degree of project management is improved; through the authority control mechanism of the user, the confidentiality of the enterprise core project management information can be ensured, abnormal operation can be found timely, problems and risks can be guaranteed to be responsible for people, the standardization of project management is greatly improved, and the project management efficiency is improved.
In light of the foregoing description of the preferred embodiment of the present invention, many modifications and variations will be apparent to those skilled in the art without departing from the spirit and scope of the invention. The technical scope of the present invention is not limited to the content of the specification, and must be determined according to the scope of the claims.

Claims (10)

1. A method for monitoring task abnormity of an automobile part research and development project is characterized by comprising the following steps:
network monitoring: the method comprises the steps that login information and operation information of a user are obtained in real time through distributed nodes, and the user uploads project updating information through a specified template on the distributed nodes;
and (3) data processing: determining the personnel weight W of the user according to the login information of the user User (ii) a Determining a project risk assessment value Q according to the project updating information;
and an abnormal alarming step: determining a project abnormity weight W according to the personnel weight and the project risk assessment value, and carrying out early warning according to the project abnormity weight;
visualization management: and the method is used for performing visual data management according to the abnormal weight.
2. The monitoring method of claim 1, wherein the network monitoring step further comprises: after obtaining login information and operation information of a user, determining operation authority of the user according to the login information of the user, and verifying the operation information of the user according to the operation authority;
and when the verification is passed, acquiring item updating information through the operation information.
3. The monitoring method of claim 1, wherein determining the personal weight of the user based on the login information of the user specifically comprises:
acquiring historical item information of the user from a historical database;
acquiring project data information of a user from the historical project information, wherein the project data information comprises: the method comprises the following steps of (1) calculating an average project problem quantity N, an average project delay time length T, an evaluation value P of a user, a project delivered quality M and an average project risk value F;
determining the personnel weight W according to the project data information of the user User
4. The monitoring method of claim 1, wherein determining an item risk assessment value based on the item update information specifically comprises: updating the project state according to the project updating information, and calculating a project risk assessment value Q according to the project state;
wherein, the item risk assessment value Q is based on the problem quantity N of the item now Predicted delay period T delay The number of problems processed N old Determining the project progress S and the project coefficient A.
5. A monitoring method according to claim 4,
determining the abnormal weight of the project according to the personnel weight and the risk assessment value of the project further comprises:
acquiring integral information of a project, wherein the integral information of the project comprises a project progress S of the project and a question of project discoveryTotal number of questions N total Number of problems processed N old The execution condition of the delivered object comprises the number K of the finished delivered objects and the mass M of the finished delivered objects i ,M i Representing the mass of the ith delivery;
determining an abnormal weight W of the project according to the overall information, the personnel weight and the risk assessment value of the project;
Figure FDA0003671259400000021
wherein, K total The total number of deliveries to be submitted; n is a radical of User Is the total number of people participating in the project; w is a group of j user Representing a personal weight of a jth user;
and early warning of the project abnormity is carried out according to the project abnormity weight.
6. A system for monitoring task abnormity of automobile part research and development projects, which is characterized by comprising:
a network monitoring module: the method comprises the steps that login information and operation information of a user are obtained in real time through distributed nodes, and the user uploads project updating information through a specified template on the distributed nodes;
a data processing module: determining the personnel weight W of the user according to the login information of the user User (ii) a Determining a project risk assessment value Q according to the project updating information;
an abnormality alarm module: determining a project abnormity weight W according to the personnel weight and the project risk assessment value, and carrying out early warning according to the project abnormity weight;
a visualization management module: and the method is used for performing visual data management according to the abnormal weight.
7. The monitoring system of claim 6, wherein the network monitoring module is further configured to: after obtaining login information and operation information of a user, determining operation authority of the user according to the login information of the user, and verifying the operation information of the user according to the operation authority;
and when the verification is passed, acquiring project updating information through the operation information.
8. The monitoring system of claim 6, wherein determining the personal weight of the user based on the login information of the user specifically comprises:
acquiring historical item information of the user from a historical database;
acquiring project data information of a user from the historical project information, wherein the project data information comprises: the method comprises the following steps of (1) calculating an average project problem quantity N, an average project delay time length T, an evaluation value P of a user, a project delivered quality M and an average project risk value F;
determining the personnel weight W according to the project data information of the user User' s
9. The monitoring system of claim 6, wherein determining an item risk assessment value based on the item update information specifically includes: updating the project state according to the project updating information, and calculating a project risk assessment value Q according to the project state;
wherein, the item risk assessment value Q is based on the problem quantity N of the item now Predicted delay period T delay The amount of processed problem N old Determining the project progress S and the project coefficient A.
10. The monitoring system of claim 9, wherein determining a project anomaly weight based on the personnel weight and a project risk assessment value further comprises:
acquiring the whole information of the project, wherein the whole information of the project comprises the project progress S of the project and the total problem quantity N found by the project total Number of problems processed N old The execution condition of the delivered object comprises the number K of the finished delivered objects and the mass M of the finished delivered objects i ,M i Represents the ithThe mass of the deliverable;
determining an abnormal weight W of the project according to the overall information, the personnel weight and the risk assessment value of the project;
wherein the content of the first and second substances,
Figure FDA0003671259400000041
wherein, K total The total number of deliveries to be submitted; n is a radical of User' s Is the total number of people participating in the project; w is a group of j user Representing a personal weight of a jth user;
and early warning of the project abnormity is carried out according to the project abnormity weight.
CN202210605857.0A 2022-05-31 2022-05-31 Method and system for monitoring task abnormity of automobile part research and development project Pending CN115186977A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210605857.0A CN115186977A (en) 2022-05-31 2022-05-31 Method and system for monitoring task abnormity of automobile part research and development project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210605857.0A CN115186977A (en) 2022-05-31 2022-05-31 Method and system for monitoring task abnormity of automobile part research and development project

Publications (1)

Publication Number Publication Date
CN115186977A true CN115186977A (en) 2022-10-14

Family

ID=83514368

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210605857.0A Pending CN115186977A (en) 2022-05-31 2022-05-31 Method and system for monitoring task abnormity of automobile part research and development project

Country Status (1)

Country Link
CN (1) CN115186977A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116109116A (en) * 2023-04-13 2023-05-12 中建安装集团有限公司 Cloud computing-based comprehensive application program supervision control system and method
CN116629774A (en) * 2023-04-19 2023-08-22 合芯科技有限公司 Chip process data processing method, device and storage medium
CN117455419A (en) * 2023-12-22 2024-01-26 江西五十铃汽车有限公司 Whole vehicle project management method and system
CN117575335A (en) * 2024-01-17 2024-02-20 成都赛力斯科技有限公司 Vehicle development project risk monitoring method, device, system, equipment and medium

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116109116A (en) * 2023-04-13 2023-05-12 中建安装集团有限公司 Cloud computing-based comprehensive application program supervision control system and method
CN116629774A (en) * 2023-04-19 2023-08-22 合芯科技有限公司 Chip process data processing method, device and storage medium
CN117455419A (en) * 2023-12-22 2024-01-26 江西五十铃汽车有限公司 Whole vehicle project management method and system
CN117575335A (en) * 2024-01-17 2024-02-20 成都赛力斯科技有限公司 Vehicle development project risk monitoring method, device, system, equipment and medium

Similar Documents

Publication Publication Date Title
CN115186977A (en) Method and system for monitoring task abnormity of automobile part research and development project
US7640165B2 (en) Web based methods and systems for managing compliance assurance information
Tribelsky et al. An empirical study of information flows in multidisciplinary civil engineering design teams using lean measures
US7957990B2 (en) System and method for managing asset installation and evaluation
US20050144022A1 (en) Web-based system, method, apparatus and software to manage performance securely across an extended enterprise and between entities
US20130006408A1 (en) Automated system for digitized product management
US20090089154A1 (en) System, method and computer product for implementing a 360 degree critical evaluator
US7398187B2 (en) Method of batching and analyzing of data from computerized process and control systems
JP2002092156A (en) Centralized multiple biomedical information sources
US20140350985A1 (en) Systems, methods, and computer programs for providing integrated critical path method schedule management & data analytics
US20080294505A1 (en) Methods and systems for task assessment management
CN113626914A (en) Engineering project management method, device and system based on digital twins
CN101770612A (en) Device defect management module of EAM (Enterprise Asset Management) system in power plant
CN113673858B (en) Maintenance method, device and system for factory equipment and storage medium
CN101763580A (en) Equipment state overhaul management module for EAM system of power plant
CN111523812A (en) Model life cycle management method and system, equipment and storage medium
CN112070450A (en) TCM system
CN111523810A (en) Enterprise-level model management method, system, device and storage medium
CN110555676A (en) Dynamic supervision platform system implementation method
US20130282419A1 (en) Goal-oriented planning system
AU2009233598B2 (en) System and method for managing implementations
US20210357841A1 (en) Method and System for Monitoring Accountability and Fairness for An Enterprises
JP2008527500A (en) Automated project office and system and method for automated risk assessment and reporting
US20190266544A1 (en) Techniques for managing process-flows across an enterprise
CN115587720A (en) Configuration management system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20230920

Address after: 310000, No.128 Shuangxi Road, Shuangxi Village, Jingshan Town, Yuhang District, Hangzhou City, Zhejiang Province - A0053

Applicant after: Hangzhou Weizhi Intelligent Technology Co.,Ltd.

Address before: 311100 Room 301, Building 6, No. 1818-2, Wenyi West Road, Yuhang Street, Hangzhou, Zhejiang

Applicant before: Zhejiang Kangle Industrial Software Co.,Ltd.

TA01 Transfer of patent application right