CN104631459B - Pile body perpendicularity and the high control method of stake top mark in static press piling construction - Google Patents
Pile body perpendicularity and the high control method of stake top mark in static press piling construction Download PDFInfo
- Publication number
- CN104631459B CN104631459B CN201510014925.6A CN201510014925A CN104631459B CN 104631459 B CN104631459 B CN 104631459B CN 201510014925 A CN201510014925 A CN 201510014925A CN 104631459 B CN104631459 B CN 104631459B
- Authority
- CN
- China
- Prior art keywords
- pile
- line
- control
- piling
- stake
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/20—Placing by pressure or pulling power
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D33/00—Testing foundations or foundation structures
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Pile body perpendicularity and the high control method of stake top mark in the static press piling construction of the present invention, relate to technical field of building construction, and for existing pressing pile construction, pile body perpendicularity does not takes control measure and easily deflection, the problem that stake top mark high measurement anthropic factor impact is big.Control method: one, before pressing pile construction, true fixed pile control axis also makes concrete buttress;Two, labelling pile head elevation control line on concrete buttress, labelling piling severity control line on pile press machine;Three, setting up two laser levelers, the thick tangent line putting down and making its horizontal line and static pressure pipe pile stake position is 90 ° of angles;Four, smart flat laser leveler, adjusts horizontal line concordant with pile head elevation control line;Five, hanging straight static pressure pipe pile piling, utilize the vertical line correction pile body perpendicularity of laser leveler laser cross-line, the horizontal line of laser cross-line controls the pile follower degree of depth, until piling severity control line is concordant with pile head elevation control line, stops piling.
Description
Technical field
The present invention relates to technical field of building construction, hang down particularly to pile body in a kind of static press piling work progress
Straight degree and the high measurement control method of stake top mark.
Background technology
Static pressure construction is to make counter-force by prefabricated by static pile press with the counterweight in pile press machine deadweight and pile frame
A kind of process for sinking in stake press-in soil.Construction of Static Pressure Pile technique low noise, friction, pollution-free, permissible
Construction continuously in 24 hours, shortens the completion time of project, creates Saving in time costs, thus reduce construction costs;Owing to sending
The contact surface of stake device and engineering pile pile crown coincide preferably, Pile feeder will not roll during pile follower and on
Under beat, thus can be relatively deep with pile follower, the intercepting amount after foundation excavation is few;Construction causes due to piling
Stress is less, and pile body does not haves tension in work progress, and pile crown is the most excellent, multiple pressure
It is relatively easy to.Owing to static pressed pile has, vibration is little, noise is low, mud-less pollution, bearing capacity of single pile easily determine
Etc. advantage, it is widely used in the engineerings such as shallow foundation, basement, equipment deep foundation, harbour.
But, during static pressed pile piling due to bearing capacity of foundation slab uneven and influence on groundwater so that
During static pressed pile pile follower, the control difficulty to pile body perpendicularity and absolute altitude strengthens, and to take in time during pile follower
Satisfactory after correcting, therefore, during measurement pile follower, pile body perpendicularity is exactly the most important thing.
Traditional pile body squareness measurement is after pile foundation is in place, is hung down in the adjacent both sides of stake by theodolite
Directly spend observation, set up in pile body perpendicular quadrature side two hang stone roller vertical line carry out observe correction, piling machine is still
A strip levelling rod need to be equipped with, to measure the perpendicularity of pile body at any time, and vertical to pile body during piling
Degree does not takes control measure, is thus likely to result in pile body deflection during piling, and, pile head elevation control
It is when piling is close to pile body top mark height, survey crew uninterruptedly measures, anthropic factor during controlling
Impact is relatively big, and accuracy is poor.
Summary of the invention
During existing static pressure pipe pile pressing pile construction, pile body perpendicularity does not takes control measure, Yi Zao
Becoming pile body deflection, and pile head elevation control uninterruptedly need to be measured by survey crew, anthropic factor impact is big,
The problem of poor accuracy, it is an object of the invention to provide pile body perpendicularity and stake top in a kind of static press piling construction
The control method of absolute altitude, it is possible to observe that the change of pile body perpendicularity and pile follower are deep during piling intuitively and accurately
Degree, it is simple to construction technical staff takes counter-measure of rectifying a deviation in time, is conducive to on-the-spot Construction control, thus
Improve the quality control that pile body perpendicularity and stake top mark during piling are high, simplify measuring process, improve
Work efficiency.
It is high that the present invention solves pile body perpendicularity and stake top mark in the static press piling construction that its technical problem is used
Control method, step is as follows:
One, before described static press piling is constructed, true fixed pile control axis, and outside the control axis of stake position
The concrete buttress for controlling static pressure pipe pile absolute altitude is made on the extended line of side;
Two, go between as pile head elevation control line from chopped-off head absolute altitude control point to described concrete buttress, and
Labelling piling severity control line on pile press machine;
Three, in the control axis of described stake position, two laser levelers are set up, thick flat described laser leveler,
Making the horizontal line of two described laser levelers and the tangent line of described static pressure pipe pile stake position is 90 ° of angles;
Four, the flat described laser leveler of essence, the horizontal line adjusting described laser leveler props up with described concrete
On pier, the described pile head elevation control line of labelling is concordant;
Five, hang straight described static pressure pipe pile and utilize described presser-into-rod to carry out pressing pile construction, utilizing described laser water
Vertical line correction pile body perpendicularity in the laser cross-line of level, and utilize horizontal line to control the pile follower degree of depth,
Until the piling severity control line on described presser-into-rod is put down with the pile head elevation control line on described concrete buttress
Together, piling is stopped.
Preferably, in described step 2, alert at the pile head elevation control line overlay mark of described concrete buttress
Timberline, vertical dimension D2 between described pile head elevation control line and described warning line is 10cm~50cm.
Preferably, vertical dimension D2 between described pile head elevation control line and described warning line is 10cm.
Preferably, in described step 4, adjust the horizontal line of a described laser leveler and described concrete
On buttress, the described pile head elevation control line of labelling is concordant, the horizontal line of another described laser leveler and institute
State the described warning line of labelling on concrete buttress concordant.
Preferably, in described step 5, when piling severity control line described on described pile press machine is close to described police
During the horizontal line at timberline place, slow down described pile press machine pile follower speed, carry out pile follower severity control.
Preferably, in described step one, described concrete buttress apart from described stake position control axis level away from
It is 3m~5m from D1.
Preferably, described concrete buttress is 3m apart from horizontal range D1 of described stake position control axis.
Preferably, after described laser leveler is slightly put down, close the horizontal line of described laser leveler, open institute
State the laser cross-line of laser leveler and sight the central axis of described static pressure pipe pile stake position, rotating described sharp
Light level meter makes it be turned to a side by the central axis of described static pressure pipe pile stake position, on the basis of stake side bottom,
The vertical line making described laser cross-line is tangent with stake side.
Preferably, the buried degree of depth of described concrete buttress is 500mm, and each described concrete buttress top
Absolute altitude keeps consistent.
Effect of the invention is that:
One, pile body perpendicularity and the high control method of stake top mark in the static press piling construction of the present invention, first,
Outside the control axis of static pressure pipe pile stake position, concrete buttress, and peg top mark on concrete buttress are set
High control line, labelling piling severity control line on pile press machine, then, set up two laser levelers, make
The horizontal line of two laser levelers is tangent with the stake position of static pressure pipe pile respectively and is mutually perpendicular to, horizontal line and stake
Top mark height control line is concordant, during piling, observes respectively in two laser leveler laser cross-lines
The relative position of vertical line and static pressure pipe pile stake lateral edges, it is possible to determine the perpendicularity of pile body during piling
Real-time change, and can adjust accordingly in time;Observe respectively in two laser leveler laser cross-lines
The position relationship of the piling severity control line on horizontal line and pile press machine, it is possible to intuitively determine the pile follower degree of depth.
In sum, the control method of the present invention can observe pile body during piling the very first time intuitively and accurately
The concrete condition of perpendicularity change, when there is skew in pile body, it is possible to stop piling in good time, it is simple to construction skill
Art personnel take counter-measure of rectifying a deviation in time, are conducive to on-the-spot Construction control, thus improve piling process
The quality control of middle pile body perpendicularity, also simplify measuring process simultaneously, improves work efficiency.
Two, pile body perpendicularity and the high control method of stake top mark in the static press piling construction of the present invention, adjust one
The horizontal line of platform laser leveler flushes with the pile head elevation control line on concrete buttress, another laser water
The horizontal line of level flushes with the warning line on concrete buttress, when on pile press machine, piling severity control line is close
During the horizontal line at warning line place, slow down pile press machine pile follower speed, carry out pile follower severity control, it is simple in time
Stop pile follower.Visible, by arranging the observation discrepancy in elevation, it is possible to reflect pile body mark during piling simple and clearly
High change, it is simple to construction technical staff controls design of pile top absolute altitude, prevents pile body overvoltage or under-voltage, it is to avoid
Pile extension or cut the drawback of stake in subsequent construction.By above-mentioned control method, the most permissible during piling
Observe perpendicularity and the absolute altitude change of pile body intuitively, and do not affected by light day and night, it is simple to execute
Work technical staff quickly makes corresponding counter-measure, it is simple to construction of Static Pressure Pile quality control.
Accompanying drawing explanation
Fig. 1 is the top view of one embodiment of the invention;
Fig. 2 is the side view of one embodiment of the invention.
Detailed description of the invention
In the static press piling construction present invention proposed below in conjunction with the drawings and specific embodiments pile body perpendicularity and
The control method that stake top mark is high is described in further detail.According to description below and claims, this
Bright advantage and feature will be apparent from.Hereinafter will be combined accompanying drawing by cited embodiment, describe this in detail
Bright technology contents and feature.Need to additionally illustrate, accompanying drawing all uses the form simplified very much and all uses
Non-ratio accurately, only in order to facilitate, to aid in illustrating lucidly the purpose of the embodiment of the present invention.For narration side
Just, described below " on ", the upper and lower direction of D score and accompanying drawing consistent, but this can not become this
The restriction of inventive technique scheme.
Pile body perpendicularity and the high control of stake top mark in the static press piling construction of the present invention is described in conjunction with Fig. 1 and Fig. 2
Method processed, specifically comprises the following steps that
S101: before construction equipment is marched into the arena, removes and hinders the ground of construction, underground obstacle, carry out place
Finishing operations, as it is shown in figure 1, before pressing pile construction, use method of polar coordinates to carry out the setting-out of stake position, determine
Stake position control axis 2 also encloses rectangle, and the extended line outside stake position control axis 2 makes four use
In the concrete buttress 3 controlling static pressure pipe pile 1 absolute altitude;
S102: as in figure 2 it is shown, from chopped-off head absolute altitude control point (being provided by Surveying And Mapping Institute, not shown in figure) to
Concrete buttress 3 goes between, and labelling pile head elevation control line a on concrete buttress 3, and, in piling
Labelling piling severity control line (not shown) outside machine;
S103: please continue to refer to Fig. 1, sets up two in the rectangular area that stake position control axis 2 is enclosed and swashs
Light level meter 4,5, adjusts the spider supporting leg of laser leveler 4,5, keeps instrument slightly to put down, and makes two to swash
The horizontal line of light level meter 4,5 is 90 ° of angles with the tangent line of 1 position of static pressure pipe pile;
S104: please continue to refer to Fig. 2, smart flat laser leveler 4,5, adjust two laser levelers 4,5
Horizontal line concordant with the pile head elevation control line a of labelling on concrete buttress 3;
S105: hang straight static pressure pipe pile 1, hangs in static pressure pipe pile 1 in the holding chamber of pile press machine, manually buttresses quiet
Pressure pipe stake 1 lower end is with align piles position, and by static pressure pipe pile 1 pile top (boots) press-in soil 0.5~1.0m, closes
Close the horizontal line of two laser levelers 4,5, open laser cross-line, observe laser cross from stake side, bottom
The vertical line of line and the relative position relation of stake side, by regulation pile press machine adjustment pile body to vertically, treat pile body
Formal piling when perpendicularity deviation is less than 0.5%, then pine is pressed from both sides, rises, presss from both sides, presses, the most repeatedly enters
OK;When static pressure pipe pile 1 is pressed onto distance ground 80~100cm, pile extension can be carried out, continue piling, until
When the piling severity control line of pile press machine is concordant with the horizontal line of laser cross-line, i.e. piling severity control line with
When the pile head elevation control line a of labelling is concordant on concrete buttress 3, stopping piling, pressing pile construction reaches in good time
To designed elevation.It is to say, during Kong Zhiing, utilize the vertical line correction static pressure pipe pile 1 of laser cross-line
Pile body perpendicularity, utilizes the horizontal line of laser cross-line to control the pile follower degree of depth.
Pile body perpendicularity and the high control method of stake top mark in the static press piling construction of the present invention, first, quiet
Concrete buttress 3, and peg top on concrete buttress 3 are set outside 1 position control axis 2 of pressure pipe stake
Absolute altitude control line a, labelling piling severity control line on pile press machine, then, set up two laser levelers 4,
5, make the horizontal line of two laser levelers 4,5 tangent with the stake position of static pressure pipe pile 1 respectively and be mutually perpendicular to,
Horizontal line is concordant with pile head elevation control line a, during piling, observe respectively two laser levelers 4,
The relative position of 1 lateral edges of the vertical line in 5 laser cross-lines and static pressure pipe pile, it is possible to determine piling
The perpendicularity real-time change of pile body in journey, and can adjust accordingly in time;Observe two laser levels respectively
Horizontal line in instrument 4,5 laser cross-line and the position relationship of the piling severity control line on pile press machine, so that it may
Intuitively to determine the pile follower degree of depth.In sum, the control method of the present invention can the very first time intuitively and accurately
Observe the concrete condition of pile body perpendicularity change during piling, when pile body occurs skew, it is possible in good time
Stop piling, it is simple to construction technical staff takes counter-measure of rectifying a deviation in time, is conducive to on-the-spot Construction control,
Thus the quality control of pile body perpendicularity during improving piling, also simplify measuring process simultaneously, improve
Work efficiency.
More preferably, as in figure 2 it is shown, above-mentioned steps S102 is additionally included in the stake top mark height control of concrete buttress 3
Line a processed is provided above warning line b, distance D2 between pile head elevation control line a and warning line b be 5~
15cm, the preferred 10cm of the present embodiment.The setting of warning line b, it is possible in piling close to pile head elevation control line
Workmen is pointed out, it is simple to construction technical staff makes counter-measure in time, to ensure pressing pile construction matter before a
Amount.
With continued reference to Fig. 1 and Fig. 2, in above-mentioned steps S104, adjust the horizontal line of laser leveler 4 with mixed
Pile head elevation control line a on solidifying soil buttress 3 flushes, the horizontal line of laser leveler 5 and concrete buttress 3
On warning line b flush, when on pile press machine, piling severity control line is close to the horizontal line at warning line b place,
Slow down pile press machine pile follower speed, carry out pile follower severity control, it is simple to stop pile follower in time.Visible, by setting
Put the observation discrepancy in elevation, it is possible to reflect the change of pile body absolute altitude during piling, it is simple to construction technology simple and clearly
Personnel control design of pile top absolute altitude, prevent pile body overvoltage or under-voltage, it is to avoid pile extension or cut stake in subsequent construction
Drawback.By above-mentioned control method, during piling, just can observe the perpendicularity of pile body intuitively
And absolute altitude change, and do not affected by light day and night, it is simple to construction technical staff is quickly made accordingly
Counter-measure, it is simple to construction of Static Pressure Pile quality control.
Preferably, concrete buttress 3 is 3m~5m apart from horizontal range D1 of stake position control axis 2.This
In embodiment, distance D1 is 3m, had not both interfered with the pressing pile construction of static pressure pipe pile, and ensure that again observation
Accuracy.
In above-mentioned steps S103, after laser leveler 4,5 is the most flat, close the level of laser leveler 4,5
Line, opens laser cross-line and sights the central axis ax of 1 position of static pressure pipe pile, rotating laser level gently
Instrument 4,5 makes it be turned to a side by the central axis ax of 1 position of static pressure pipe pile, on the basis of stake side bottom,
The vertical line making laser cross-line is tangent with stake side, returns back to when bottom stake lateral edges about 2mm (several afterwards
The most tangent) stop.Aforesaid operations can be accurately positioned laser cross-line, make the vertical line of laser cross-line with
Stake side is tangent, prepares for the observation of pile body perpendicularity during follow-up piling.
Preferably, above-mentioned concrete buttress 3 is the cube of size 500mm × 500mm × 1200mm,
The buried degree of depth of concrete buttress 3 is 500mm, and each concrete buttress 3 top absolute altitude keeps consistent.
Foregoing description is only the description to present pre-ferred embodiments, not any restriction to the scope of the invention,
Any change that the those of ordinary skill in field of the present invention does according to the disclosure above content, modification, belong to power
The protection domain of profit claim.
Claims (8)
1. pile body perpendicularity and the high control method of stake top mark in static press piling construction, step is as follows:
One, before described static press piling is constructed, true fixed pile control axis, and outside the control axis of stake position
The concrete buttress for controlling static pressure pipe pile absolute altitude is made on the extended line of side;
Two, go between as pile head elevation control line from chopped-off head absolute altitude control point to described concrete buttress, in institute
State pile head elevation control line overlay mark warning line, and labelling piling severity control line on pile press machine;
Three, in the control axis of described stake position, two laser levelers are set up, thick flat described laser leveler,
Making the horizontal line of two described laser levelers and the tangent line of described static pressure pipe pile stake position is 90 ° of angles;
Four, the flat described laser leveler of essence, the horizontal line adjusting described laser leveler props up with described concrete
On pier, the described pile head elevation control line of labelling is concordant;Or, adjust the level of a described laser leveler
Line is concordant with the described pile head elevation control line of labelling on described concrete buttress, another described laser level
The horizontal line of instrument is concordant with the described warning line of labelling on described concrete buttress;
Five, hang straight described static pressure pipe pile and utilize described pile press machine to carry out pressing pile construction, utilizing described laser water
Vertical line correction pile body perpendicularity in the laser cross-line of level, and utilize horizontal line to control the pile follower degree of depth,
Until the piling severity control line on described pile press machine is put down with the pile head elevation control line on described concrete buttress
Together, piling is stopped.
Control method the most according to claim 1, it is characterised in that: in described step 2, described stake top mark
Vertical dimension D2 between high control line and described warning line is 10cm~50cm.
Control method the most according to claim 2, it is characterised in that: described pile head elevation control line is with described
Vertical dimension D2 between warning line is 10cm.
Control method the most according to claim 1, it is characterised in that: in described step 5, when described piling
When described piling severity control line is close to the horizontal line at described warning line place on machine, slows down described pile press machine and send
Stake speed, carries out pile follower severity control.
5. according to the control method described in any one of claims 1 to 3, it is characterised in that: in described step one,
Described concrete buttress is 3m~5m apart from horizontal range D1 of described stake position control axis.
Control method the most according to claim 5, it is characterised in that: described concrete buttress is apart from described stake
Horizontal range D1 of position control axis is 3m.
7. according to the control method described in any one of claims 1 to 3, it is characterised in that: described laser leveler
After the most flat, close the horizontal line of described laser leveler, open the laser cross-line of described laser leveler also
Sight the central axis of described static pressure pipe pile stake position, rotate described laser leveler and make it by described static pressure pipe pile
The central axis of stake position turns to a side, on the basis of stake side bottom, make the vertical line of described laser cross-line with
Stake side is tangent.
8. according to the control method described in any one of claims 1 to 3, it is characterised in that: described concrete buttress
The buried degree of depth be 500mm, and each described concrete buttress top absolute altitude keeps consistent.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510014925.6A CN104631459B (en) | 2015-01-13 | 2015-01-13 | Pile body perpendicularity and the high control method of stake top mark in static press piling construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510014925.6A CN104631459B (en) | 2015-01-13 | 2015-01-13 | Pile body perpendicularity and the high control method of stake top mark in static press piling construction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104631459A CN104631459A (en) | 2015-05-20 |
CN104631459B true CN104631459B (en) | 2017-01-04 |
Family
ID=53210657
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510014925.6A Active CN104631459B (en) | 2015-01-13 | 2015-01-13 | Pile body perpendicularity and the high control method of stake top mark in static press piling construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104631459B (en) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108343064A (en) * | 2018-04-24 | 2018-07-31 | 中铁十九局集团第七工程有限公司 | Steel sheet pile construction alignment control guider and pile-driving method |
CN109736574A (en) * | 2019-03-01 | 2019-05-10 | 中国二十二冶集团有限公司 | Control the construction method of concrete casting elevation |
CN109914492B (en) * | 2019-03-26 | 2023-12-12 | 中交上海三航科学研究院有限公司 | System and method for monitoring verticality of single-pipe pile axis in real time |
CN111910635A (en) * | 2019-05-10 | 2020-11-10 | 深圳市北斗云信息技术有限公司 | Precise pile feeding method and system for pile driver |
CN111264242B (en) * | 2020-03-12 | 2022-09-13 | 新疆科创天达农业工程有限公司 | High parallel and level device of modern agricultural automation support frame for greenhouse construction |
CN111576417B (en) * | 2020-06-11 | 2021-06-08 | 湖北鄂东桩基工程有限公司 | Static pressure pile machine |
CN112030971B (en) * | 2020-09-01 | 2021-08-24 | 中国十七冶集团有限公司 | Device for detecting and adjusting perpendicularity of pile body of static pressure pile and construction method |
CN112551395B (en) * | 2020-11-30 | 2023-03-31 | 中天建设集团有限公司 | Method for correcting installation inclination of tower crane installation structure caused by foundation inclination |
CN114622556B (en) * | 2022-03-24 | 2023-08-08 | 中国电建市政建设集团有限公司 | Intelligent correction method and correction device for CFG pile based on AI image recognition |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2603587B2 (en) * | 1992-10-20 | 1997-04-23 | 株式会社 技研製作所 | Pile automatic feeding press-in method and pile automatic pull-out method |
CN102587374B (en) * | 2012-03-26 | 2014-07-30 | 江苏龙源振华海洋工程有限公司 | Perpendicularity control process for single-tubular-pile foundation of offshore intertidal wind farm |
CN203096779U (en) * | 2013-03-05 | 2013-07-31 | 天津市洛睿甫科技有限公司 | Static pressure pile incline measurement recording device |
CN203891025U (en) * | 2014-06-16 | 2014-10-22 | 杨林 | Hydraulic static pile driver |
CN104153353B (en) * | 2014-08-22 | 2016-03-30 | 中铁六局集团天津铁路建设有限公司 | A kind of method utilizing laser level determination bored pile absolute altitude |
CN104251688B (en) * | 2014-09-25 | 2016-08-24 | 陕西华山路桥工程有限公司 | Pipe-jacking project utilizes laser straight line orientation survey engineering method |
-
2015
- 2015-01-13 CN CN201510014925.6A patent/CN104631459B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104631459A (en) | 2015-05-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631459B (en) | Pile body perpendicularity and the high control method of stake top mark in static press piling construction | |
CN103352455A (en) | Monitoring method of bottom soil heave of excavation foundation pit | |
CN202562406U (en) | Mining fissure monitoring device | |
CN206191060U (en) | Gas pipeline push pipe construction structures | |
CN104594334B (en) | A kind of erecting device of structure improved deal pile | |
CN108625302A (en) | A kind of adjusting apparatus and its monitoring and control method of box culvert advancing head fall | |
CN105798067A (en) | Accurate measurement method for installation of rolling mill base | |
CN207017267U (en) | Engineering pile guider in piling construction | |
CN206457858U (en) | High-pressure rotary jet grouting pile verticality control device | |
CN105804041A (en) | Large-area ultra-soft foundation settlement monitoring device and method | |
CN105220689B (en) | A kind of photovoltaic piling machine | |
CN103741726B (en) | A kind of open caisson settlement measurement metering method | |
CN104727320A (en) | Deal pile installation device with controller | |
CN203270585U (en) | Riprap leveling device | |
CN108560369A (en) | Lofting construction method for high-speed loop curved surface paving | |
CN106403996A (en) | Production method of forced centering observation mark stake for precision engineering measurement | |
CN205664836U (en) | Civil engineering construction laying -out guide pile | |
CN103572769B (en) | Well sinking medium dip degree method for supervising | |
CN105649086A (en) | Shallow-to-deep reverse construction method for underground concrete structure | |
CN204059326U (en) | A kind of pit retaining monitoring device | |
CN209230632U (en) | A kind of measurement and positioning and the fixed control stake of elevation | |
CN208567732U (en) | A kind of measuring device for cooling tower tower radius | |
CN208564865U (en) | A kind of constructing structure of concrete tower alignment | |
CN102494579A (en) | Box body state measurement method in one-dimensional jacking construction process of large box body | |
CN203514319U (en) | Perpendicular positioning mechanism of pine pile mounting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |