CN104631459B - Pile body perpendicularity and the high control method of stake top mark in static press piling construction - Google Patents

Pile body perpendicularity and the high control method of stake top mark in static press piling construction Download PDF

Info

Publication number
CN104631459B
CN104631459B CN201510014925.6A CN201510014925A CN104631459B CN 104631459 B CN104631459 B CN 104631459B CN 201510014925 A CN201510014925 A CN 201510014925A CN 104631459 B CN104631459 B CN 104631459B
Authority
CN
China
Prior art keywords
pile
line
control
piling
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510014925.6A
Other languages
Chinese (zh)
Other versions
CN104631459A (en
Inventor
王新新
吴小建
陈峰军
程子聪
朱小军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Group Co Ltd
Original Assignee
Shanghai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Group Co Ltd filed Critical Shanghai Construction Group Co Ltd
Priority to CN201510014925.6A priority Critical patent/CN104631459B/en
Publication of CN104631459A publication Critical patent/CN104631459A/en
Application granted granted Critical
Publication of CN104631459B publication Critical patent/CN104631459B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Pile body perpendicularity and the high control method of stake top mark in the static press piling construction of the present invention, relate to technical field of building construction, and for existing pressing pile construction, pile body perpendicularity does not takes control measure and easily deflection, the problem that stake top mark high measurement anthropic factor impact is big.Control method: one, before pressing pile construction, true fixed pile control axis also makes concrete buttress;Two, labelling pile head elevation control line on concrete buttress, labelling piling severity control line on pile press machine;Three, setting up two laser levelers, the thick tangent line putting down and making its horizontal line and static pressure pipe pile stake position is 90 ° of angles;Four, smart flat laser leveler, adjusts horizontal line concordant with pile head elevation control line;Five, hanging straight static pressure pipe pile piling, utilize the vertical line correction pile body perpendicularity of laser leveler laser cross-line, the horizontal line of laser cross-line controls the pile follower degree of depth, until piling severity control line is concordant with pile head elevation control line, stops piling.

Description

Pile body perpendicularity and the high control method of stake top mark in static press piling construction
Technical field
The present invention relates to technical field of building construction, hang down particularly to pile body in a kind of static press piling work progress Straight degree and the high measurement control method of stake top mark.
Background technology
Static pressure construction is to make counter-force by prefabricated by static pile press with the counterweight in pile press machine deadweight and pile frame A kind of process for sinking in stake press-in soil.Construction of Static Pressure Pile technique low noise, friction, pollution-free, permissible Construction continuously in 24 hours, shortens the completion time of project, creates Saving in time costs, thus reduce construction costs;Owing to sending The contact surface of stake device and engineering pile pile crown coincide preferably, Pile feeder will not roll during pile follower and on Under beat, thus can be relatively deep with pile follower, the intercepting amount after foundation excavation is few;Construction causes due to piling Stress is less, and pile body does not haves tension in work progress, and pile crown is the most excellent, multiple pressure It is relatively easy to.Owing to static pressed pile has, vibration is little, noise is low, mud-less pollution, bearing capacity of single pile easily determine Etc. advantage, it is widely used in the engineerings such as shallow foundation, basement, equipment deep foundation, harbour.
But, during static pressed pile piling due to bearing capacity of foundation slab uneven and influence on groundwater so that During static pressed pile pile follower, the control difficulty to pile body perpendicularity and absolute altitude strengthens, and to take in time during pile follower Satisfactory after correcting, therefore, during measurement pile follower, pile body perpendicularity is exactly the most important thing.
Traditional pile body squareness measurement is after pile foundation is in place, is hung down in the adjacent both sides of stake by theodolite Directly spend observation, set up in pile body perpendicular quadrature side two hang stone roller vertical line carry out observe correction, piling machine is still A strip levelling rod need to be equipped with, to measure the perpendicularity of pile body at any time, and vertical to pile body during piling Degree does not takes control measure, is thus likely to result in pile body deflection during piling, and, pile head elevation control It is when piling is close to pile body top mark height, survey crew uninterruptedly measures, anthropic factor during controlling Impact is relatively big, and accuracy is poor.
Summary of the invention
During existing static pressure pipe pile pressing pile construction, pile body perpendicularity does not takes control measure, Yi Zao Becoming pile body deflection, and pile head elevation control uninterruptedly need to be measured by survey crew, anthropic factor impact is big, The problem of poor accuracy, it is an object of the invention to provide pile body perpendicularity and stake top in a kind of static press piling construction The control method of absolute altitude, it is possible to observe that the change of pile body perpendicularity and pile follower are deep during piling intuitively and accurately Degree, it is simple to construction technical staff takes counter-measure of rectifying a deviation in time, is conducive to on-the-spot Construction control, thus Improve the quality control that pile body perpendicularity and stake top mark during piling are high, simplify measuring process, improve Work efficiency.
It is high that the present invention solves pile body perpendicularity and stake top mark in the static press piling construction that its technical problem is used Control method, step is as follows:
One, before described static press piling is constructed, true fixed pile control axis, and outside the control axis of stake position The concrete buttress for controlling static pressure pipe pile absolute altitude is made on the extended line of side;
Two, go between as pile head elevation control line from chopped-off head absolute altitude control point to described concrete buttress, and Labelling piling severity control line on pile press machine;
Three, in the control axis of described stake position, two laser levelers are set up, thick flat described laser leveler, Making the horizontal line of two described laser levelers and the tangent line of described static pressure pipe pile stake position is 90 ° of angles;
Four, the flat described laser leveler of essence, the horizontal line adjusting described laser leveler props up with described concrete On pier, the described pile head elevation control line of labelling is concordant;
Five, hang straight described static pressure pipe pile and utilize described presser-into-rod to carry out pressing pile construction, utilizing described laser water Vertical line correction pile body perpendicularity in the laser cross-line of level, and utilize horizontal line to control the pile follower degree of depth, Until the piling severity control line on described presser-into-rod is put down with the pile head elevation control line on described concrete buttress Together, piling is stopped.
Preferably, in described step 2, alert at the pile head elevation control line overlay mark of described concrete buttress Timberline, vertical dimension D2 between described pile head elevation control line and described warning line is 10cm~50cm.
Preferably, vertical dimension D2 between described pile head elevation control line and described warning line is 10cm.
Preferably, in described step 4, adjust the horizontal line of a described laser leveler and described concrete On buttress, the described pile head elevation control line of labelling is concordant, the horizontal line of another described laser leveler and institute State the described warning line of labelling on concrete buttress concordant.
Preferably, in described step 5, when piling severity control line described on described pile press machine is close to described police During the horizontal line at timberline place, slow down described pile press machine pile follower speed, carry out pile follower severity control.
Preferably, in described step one, described concrete buttress apart from described stake position control axis level away from It is 3m~5m from D1.
Preferably, described concrete buttress is 3m apart from horizontal range D1 of described stake position control axis.
Preferably, after described laser leveler is slightly put down, close the horizontal line of described laser leveler, open institute State the laser cross-line of laser leveler and sight the central axis of described static pressure pipe pile stake position, rotating described sharp Light level meter makes it be turned to a side by the central axis of described static pressure pipe pile stake position, on the basis of stake side bottom, The vertical line making described laser cross-line is tangent with stake side.
Preferably, the buried degree of depth of described concrete buttress is 500mm, and each described concrete buttress top Absolute altitude keeps consistent.
Effect of the invention is that:
One, pile body perpendicularity and the high control method of stake top mark in the static press piling construction of the present invention, first, Outside the control axis of static pressure pipe pile stake position, concrete buttress, and peg top mark on concrete buttress are set High control line, labelling piling severity control line on pile press machine, then, set up two laser levelers, make The horizontal line of two laser levelers is tangent with the stake position of static pressure pipe pile respectively and is mutually perpendicular to, horizontal line and stake Top mark height control line is concordant, during piling, observes respectively in two laser leveler laser cross-lines The relative position of vertical line and static pressure pipe pile stake lateral edges, it is possible to determine the perpendicularity of pile body during piling Real-time change, and can adjust accordingly in time;Observe respectively in two laser leveler laser cross-lines The position relationship of the piling severity control line on horizontal line and pile press machine, it is possible to intuitively determine the pile follower degree of depth. In sum, the control method of the present invention can observe pile body during piling the very first time intuitively and accurately The concrete condition of perpendicularity change, when there is skew in pile body, it is possible to stop piling in good time, it is simple to construction skill Art personnel take counter-measure of rectifying a deviation in time, are conducive to on-the-spot Construction control, thus improve piling process The quality control of middle pile body perpendicularity, also simplify measuring process simultaneously, improves work efficiency.
Two, pile body perpendicularity and the high control method of stake top mark in the static press piling construction of the present invention, adjust one The horizontal line of platform laser leveler flushes with the pile head elevation control line on concrete buttress, another laser water The horizontal line of level flushes with the warning line on concrete buttress, when on pile press machine, piling severity control line is close During the horizontal line at warning line place, slow down pile press machine pile follower speed, carry out pile follower severity control, it is simple in time Stop pile follower.Visible, by arranging the observation discrepancy in elevation, it is possible to reflect pile body mark during piling simple and clearly High change, it is simple to construction technical staff controls design of pile top absolute altitude, prevents pile body overvoltage or under-voltage, it is to avoid Pile extension or cut the drawback of stake in subsequent construction.By above-mentioned control method, the most permissible during piling Observe perpendicularity and the absolute altitude change of pile body intuitively, and do not affected by light day and night, it is simple to execute Work technical staff quickly makes corresponding counter-measure, it is simple to construction of Static Pressure Pile quality control.
Accompanying drawing explanation
Fig. 1 is the top view of one embodiment of the invention;
Fig. 2 is the side view of one embodiment of the invention.
Detailed description of the invention
In the static press piling construction present invention proposed below in conjunction with the drawings and specific embodiments pile body perpendicularity and The control method that stake top mark is high is described in further detail.According to description below and claims, this Bright advantage and feature will be apparent from.Hereinafter will be combined accompanying drawing by cited embodiment, describe this in detail Bright technology contents and feature.Need to additionally illustrate, accompanying drawing all uses the form simplified very much and all uses Non-ratio accurately, only in order to facilitate, to aid in illustrating lucidly the purpose of the embodiment of the present invention.For narration side Just, described below " on ", the upper and lower direction of D score and accompanying drawing consistent, but this can not become this The restriction of inventive technique scheme.
Pile body perpendicularity and the high control of stake top mark in the static press piling construction of the present invention is described in conjunction with Fig. 1 and Fig. 2 Method processed, specifically comprises the following steps that
S101: before construction equipment is marched into the arena, removes and hinders the ground of construction, underground obstacle, carry out place Finishing operations, as it is shown in figure 1, before pressing pile construction, use method of polar coordinates to carry out the setting-out of stake position, determine Stake position control axis 2 also encloses rectangle, and the extended line outside stake position control axis 2 makes four use In the concrete buttress 3 controlling static pressure pipe pile 1 absolute altitude;
S102: as in figure 2 it is shown, from chopped-off head absolute altitude control point (being provided by Surveying And Mapping Institute, not shown in figure) to Concrete buttress 3 goes between, and labelling pile head elevation control line a on concrete buttress 3, and, in piling Labelling piling severity control line (not shown) outside machine;
S103: please continue to refer to Fig. 1, sets up two in the rectangular area that stake position control axis 2 is enclosed and swashs Light level meter 4,5, adjusts the spider supporting leg of laser leveler 4,5, keeps instrument slightly to put down, and makes two to swash The horizontal line of light level meter 4,5 is 90 ° of angles with the tangent line of 1 position of static pressure pipe pile;
S104: please continue to refer to Fig. 2, smart flat laser leveler 4,5, adjust two laser levelers 4,5 Horizontal line concordant with the pile head elevation control line a of labelling on concrete buttress 3;
S105: hang straight static pressure pipe pile 1, hangs in static pressure pipe pile 1 in the holding chamber of pile press machine, manually buttresses quiet Pressure pipe stake 1 lower end is with align piles position, and by static pressure pipe pile 1 pile top (boots) press-in soil 0.5~1.0m, closes Close the horizontal line of two laser levelers 4,5, open laser cross-line, observe laser cross from stake side, bottom The vertical line of line and the relative position relation of stake side, by regulation pile press machine adjustment pile body to vertically, treat pile body Formal piling when perpendicularity deviation is less than 0.5%, then pine is pressed from both sides, rises, presss from both sides, presses, the most repeatedly enters OK;When static pressure pipe pile 1 is pressed onto distance ground 80~100cm, pile extension can be carried out, continue piling, until When the piling severity control line of pile press machine is concordant with the horizontal line of laser cross-line, i.e. piling severity control line with When the pile head elevation control line a of labelling is concordant on concrete buttress 3, stopping piling, pressing pile construction reaches in good time To designed elevation.It is to say, during Kong Zhiing, utilize the vertical line correction static pressure pipe pile 1 of laser cross-line Pile body perpendicularity, utilizes the horizontal line of laser cross-line to control the pile follower degree of depth.
Pile body perpendicularity and the high control method of stake top mark in the static press piling construction of the present invention, first, quiet Concrete buttress 3, and peg top on concrete buttress 3 are set outside 1 position control axis 2 of pressure pipe stake Absolute altitude control line a, labelling piling severity control line on pile press machine, then, set up two laser levelers 4, 5, make the horizontal line of two laser levelers 4,5 tangent with the stake position of static pressure pipe pile 1 respectively and be mutually perpendicular to, Horizontal line is concordant with pile head elevation control line a, during piling, observe respectively two laser levelers 4, The relative position of 1 lateral edges of the vertical line in 5 laser cross-lines and static pressure pipe pile, it is possible to determine piling The perpendicularity real-time change of pile body in journey, and can adjust accordingly in time;Observe two laser levels respectively Horizontal line in instrument 4,5 laser cross-line and the position relationship of the piling severity control line on pile press machine, so that it may Intuitively to determine the pile follower degree of depth.In sum, the control method of the present invention can the very first time intuitively and accurately Observe the concrete condition of pile body perpendicularity change during piling, when pile body occurs skew, it is possible in good time Stop piling, it is simple to construction technical staff takes counter-measure of rectifying a deviation in time, is conducive to on-the-spot Construction control, Thus the quality control of pile body perpendicularity during improving piling, also simplify measuring process simultaneously, improve Work efficiency.
More preferably, as in figure 2 it is shown, above-mentioned steps S102 is additionally included in the stake top mark height control of concrete buttress 3 Line a processed is provided above warning line b, distance D2 between pile head elevation control line a and warning line b be 5~ 15cm, the preferred 10cm of the present embodiment.The setting of warning line b, it is possible in piling close to pile head elevation control line Workmen is pointed out, it is simple to construction technical staff makes counter-measure in time, to ensure pressing pile construction matter before a Amount.
With continued reference to Fig. 1 and Fig. 2, in above-mentioned steps S104, adjust the horizontal line of laser leveler 4 with mixed Pile head elevation control line a on solidifying soil buttress 3 flushes, the horizontal line of laser leveler 5 and concrete buttress 3 On warning line b flush, when on pile press machine, piling severity control line is close to the horizontal line at warning line b place, Slow down pile press machine pile follower speed, carry out pile follower severity control, it is simple to stop pile follower in time.Visible, by setting Put the observation discrepancy in elevation, it is possible to reflect the change of pile body absolute altitude during piling, it is simple to construction technology simple and clearly Personnel control design of pile top absolute altitude, prevent pile body overvoltage or under-voltage, it is to avoid pile extension or cut stake in subsequent construction Drawback.By above-mentioned control method, during piling, just can observe the perpendicularity of pile body intuitively And absolute altitude change, and do not affected by light day and night, it is simple to construction technical staff is quickly made accordingly Counter-measure, it is simple to construction of Static Pressure Pile quality control.
Preferably, concrete buttress 3 is 3m~5m apart from horizontal range D1 of stake position control axis 2.This In embodiment, distance D1 is 3m, had not both interfered with the pressing pile construction of static pressure pipe pile, and ensure that again observation Accuracy.
In above-mentioned steps S103, after laser leveler 4,5 is the most flat, close the level of laser leveler 4,5 Line, opens laser cross-line and sights the central axis ax of 1 position of static pressure pipe pile, rotating laser level gently Instrument 4,5 makes it be turned to a side by the central axis ax of 1 position of static pressure pipe pile, on the basis of stake side bottom, The vertical line making laser cross-line is tangent with stake side, returns back to when bottom stake lateral edges about 2mm (several afterwards The most tangent) stop.Aforesaid operations can be accurately positioned laser cross-line, make the vertical line of laser cross-line with Stake side is tangent, prepares for the observation of pile body perpendicularity during follow-up piling.
Preferably, above-mentioned concrete buttress 3 is the cube of size 500mm × 500mm × 1200mm, The buried degree of depth of concrete buttress 3 is 500mm, and each concrete buttress 3 top absolute altitude keeps consistent.
Foregoing description is only the description to present pre-ferred embodiments, not any restriction to the scope of the invention, Any change that the those of ordinary skill in field of the present invention does according to the disclosure above content, modification, belong to power The protection domain of profit claim.

Claims (8)

1. pile body perpendicularity and the high control method of stake top mark in static press piling construction, step is as follows:
One, before described static press piling is constructed, true fixed pile control axis, and outside the control axis of stake position The concrete buttress for controlling static pressure pipe pile absolute altitude is made on the extended line of side;
Two, go between as pile head elevation control line from chopped-off head absolute altitude control point to described concrete buttress, in institute State pile head elevation control line overlay mark warning line, and labelling piling severity control line on pile press machine;
Three, in the control axis of described stake position, two laser levelers are set up, thick flat described laser leveler, Making the horizontal line of two described laser levelers and the tangent line of described static pressure pipe pile stake position is 90 ° of angles;
Four, the flat described laser leveler of essence, the horizontal line adjusting described laser leveler props up with described concrete On pier, the described pile head elevation control line of labelling is concordant;Or, adjust the level of a described laser leveler Line is concordant with the described pile head elevation control line of labelling on described concrete buttress, another described laser level The horizontal line of instrument is concordant with the described warning line of labelling on described concrete buttress;
Five, hang straight described static pressure pipe pile and utilize described pile press machine to carry out pressing pile construction, utilizing described laser water Vertical line correction pile body perpendicularity in the laser cross-line of level, and utilize horizontal line to control the pile follower degree of depth, Until the piling severity control line on described pile press machine is put down with the pile head elevation control line on described concrete buttress Together, piling is stopped.
Control method the most according to claim 1, it is characterised in that: in described step 2, described stake top mark Vertical dimension D2 between high control line and described warning line is 10cm~50cm.
Control method the most according to claim 2, it is characterised in that: described pile head elevation control line is with described Vertical dimension D2 between warning line is 10cm.
Control method the most according to claim 1, it is characterised in that: in described step 5, when described piling When described piling severity control line is close to the horizontal line at described warning line place on machine, slows down described pile press machine and send Stake speed, carries out pile follower severity control.
5. according to the control method described in any one of claims 1 to 3, it is characterised in that: in described step one, Described concrete buttress is 3m~5m apart from horizontal range D1 of described stake position control axis.
Control method the most according to claim 5, it is characterised in that: described concrete buttress is apart from described stake Horizontal range D1 of position control axis is 3m.
7. according to the control method described in any one of claims 1 to 3, it is characterised in that: described laser leveler After the most flat, close the horizontal line of described laser leveler, open the laser cross-line of described laser leveler also Sight the central axis of described static pressure pipe pile stake position, rotate described laser leveler and make it by described static pressure pipe pile The central axis of stake position turns to a side, on the basis of stake side bottom, make the vertical line of described laser cross-line with Stake side is tangent.
8. according to the control method described in any one of claims 1 to 3, it is characterised in that: described concrete buttress The buried degree of depth be 500mm, and each described concrete buttress top absolute altitude keeps consistent.
CN201510014925.6A 2015-01-13 2015-01-13 Pile body perpendicularity and the high control method of stake top mark in static press piling construction Active CN104631459B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510014925.6A CN104631459B (en) 2015-01-13 2015-01-13 Pile body perpendicularity and the high control method of stake top mark in static press piling construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510014925.6A CN104631459B (en) 2015-01-13 2015-01-13 Pile body perpendicularity and the high control method of stake top mark in static press piling construction

Publications (2)

Publication Number Publication Date
CN104631459A CN104631459A (en) 2015-05-20
CN104631459B true CN104631459B (en) 2017-01-04

Family

ID=53210657

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510014925.6A Active CN104631459B (en) 2015-01-13 2015-01-13 Pile body perpendicularity and the high control method of stake top mark in static press piling construction

Country Status (1)

Country Link
CN (1) CN104631459B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108343064A (en) * 2018-04-24 2018-07-31 中铁十九局集团第七工程有限公司 Steel sheet pile construction alignment control guider and pile-driving method
CN109736574A (en) * 2019-03-01 2019-05-10 中国二十二冶集团有限公司 Control the construction method of concrete casting elevation
CN109914492B (en) * 2019-03-26 2023-12-12 中交上海三航科学研究院有限公司 System and method for monitoring verticality of single-pipe pile axis in real time
CN111910635A (en) * 2019-05-10 2020-11-10 深圳市北斗云信息技术有限公司 Precise pile feeding method and system for pile driver
CN111264242B (en) * 2020-03-12 2022-09-13 新疆科创天达农业工程有限公司 High parallel and level device of modern agricultural automation support frame for greenhouse construction
CN111576417B (en) * 2020-06-11 2021-06-08 湖北鄂东桩基工程有限公司 Static pressure pile machine
CN112030971B (en) * 2020-09-01 2021-08-24 中国十七冶集团有限公司 Device for detecting and adjusting perpendicularity of pile body of static pressure pile and construction method
CN112551395B (en) * 2020-11-30 2023-03-31 中天建设集团有限公司 Method for correcting installation inclination of tower crane installation structure caused by foundation inclination
CN114622556B (en) * 2022-03-24 2023-08-08 中国电建市政建设集团有限公司 Intelligent correction method and correction device for CFG pile based on AI image recognition

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2603587B2 (en) * 1992-10-20 1997-04-23 株式会社 技研製作所 Pile automatic feeding press-in method and pile automatic pull-out method
CN102587374B (en) * 2012-03-26 2014-07-30 江苏龙源振华海洋工程有限公司 Perpendicularity control process for single-tubular-pile foundation of offshore intertidal wind farm
CN203096779U (en) * 2013-03-05 2013-07-31 天津市洛睿甫科技有限公司 Static pressure pile incline measurement recording device
CN203891025U (en) * 2014-06-16 2014-10-22 杨林 Hydraulic static pile driver
CN104153353B (en) * 2014-08-22 2016-03-30 中铁六局集团天津铁路建设有限公司 A kind of method utilizing laser level determination bored pile absolute altitude
CN104251688B (en) * 2014-09-25 2016-08-24 陕西华山路桥工程有限公司 Pipe-jacking project utilizes laser straight line orientation survey engineering method

Also Published As

Publication number Publication date
CN104631459A (en) 2015-05-20

Similar Documents

Publication Publication Date Title
CN104631459B (en) Pile body perpendicularity and the high control method of stake top mark in static press piling construction
CN103352455A (en) Monitoring method of bottom soil heave of excavation foundation pit
CN202562406U (en) Mining fissure monitoring device
CN206191060U (en) Gas pipeline push pipe construction structures
CN104594334B (en) A kind of erecting device of structure improved deal pile
CN108625302A (en) A kind of adjusting apparatus and its monitoring and control method of box culvert advancing head fall
CN105798067A (en) Accurate measurement method for installation of rolling mill base
CN207017267U (en) Engineering pile guider in piling construction
CN206457858U (en) High-pressure rotary jet grouting pile verticality control device
CN105804041A (en) Large-area ultra-soft foundation settlement monitoring device and method
CN105220689B (en) A kind of photovoltaic piling machine
CN103741726B (en) A kind of open caisson settlement measurement metering method
CN104727320A (en) Deal pile installation device with controller
CN203270585U (en) Riprap leveling device
CN108560369A (en) Lofting construction method for high-speed loop curved surface paving
CN106403996A (en) Production method of forced centering observation mark stake for precision engineering measurement
CN205664836U (en) Civil engineering construction laying -out guide pile
CN103572769B (en) Well sinking medium dip degree method for supervising
CN105649086A (en) Shallow-to-deep reverse construction method for underground concrete structure
CN204059326U (en) A kind of pit retaining monitoring device
CN209230632U (en) A kind of measurement and positioning and the fixed control stake of elevation
CN208567732U (en) A kind of measuring device for cooling tower tower radius
CN208564865U (en) A kind of constructing structure of concrete tower alignment
CN102494579A (en) Box body state measurement method in one-dimensional jacking construction process of large box body
CN203514319U (en) Perpendicular positioning mechanism of pine pile mounting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant