CN106403996A - Production method of forced centering observation mark stake for precision engineering measurement - Google Patents

Production method of forced centering observation mark stake for precision engineering measurement Download PDF

Info

Publication number
CN106403996A
CN106403996A CN201610763991.8A CN201610763991A CN106403996A CN 106403996 A CN106403996 A CN 106403996A CN 201610763991 A CN201610763991 A CN 201610763991A CN 106403996 A CN106403996 A CN 106403996A
Authority
CN
China
Prior art keywords
stake
concrete
forced centering
ground
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610763991.8A
Other languages
Chinese (zh)
Inventor
董玉启
高军
田永振
韩国东
闫永辉
强明明
何龙飞
曲海达
刘亚平
王海量
代言龙
王硕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Tianjin Corp Ltd
Original Assignee
MCC Tiangong Group Tianjin Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Tianjin Corp Ltd filed Critical MCC Tiangong Group Tianjin Corp Ltd
Priority to CN201610763991.8A priority Critical patent/CN106403996A/en
Publication of CN106403996A publication Critical patent/CN106403996A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C25/00Manufacturing, calibrating, cleaning, or repairing instruments or devices referred to in the other groups of this subclass

Abstract

The invention relates to a production method of a surveying control point mark stake, and discloses the production method of the force centering observation mark stake for precision engineering surveying. The method comprises the following steps: a stake hole is manually dug to a bedrock part; a steel reinforcement cage is hung in the stake hole, so that the bottom of the steel reinforcement cage is placed on the bedrock, and the a design height above the ground of the steel reinforcement cage is reserved; concrete is poured in the stake hole; after concrete below the ground is solidified, concrete is poured in a reserved steel reinforcement cage formwork above the ground; a forced centering bolt is embedded at a center position of the top of an overground part of the concrete stake, and the diameter of the bolt is matched with a bolt aperture at the bottom of a measuring instrument pedestal; a forced centering disc is embedded at the top of the overground part of the concrete stake, and the center of the disc passes through the forced centering bolt. Settlement and deviation are effectively avoided, damage is not easy, usage is convenient, observation errors are reduced, and observation precision is improved; during usage, a measuring instrument is directly screwed and connected to the forced centering bolt and leveled, interference factors are reduced and centering errors are reduced.

Description

The manufacture method observing stake for the forced centering of precise engineering survey
Technical field
The present invention relates to measurement control point marker peg manufacture method in precise engineering survey, specifically, it is to relate to The manufacture method that a kind of forced centering of precise engineering survey observes stake.
Background technology
In the face of currently country in engineering construction to environmental protection, energy-conservation, new material, new technique requirement, need to be phased out The high industry consuming of low yield energy, advocates and uses new material, new technique, new technology, new equipment, do not reach the little of energy-conserving and environment-protective requirement Type construction project no longer examines construction, the substitute is high-efficient energy-saving environment friendly mega project up to standard.With construction project rule Mould increases, and the requirement to e measurement technology precision also accordingly improves, and common survey can not meet the needs of engineering construction.Commonly The stake at measurement control point is simple due to making, pile foundation deficient in stability, easily causes stake sedimentation or offsets, makes control point Precision reduce and require it is impossible to meet engineering construction, this is accomplished by applying precise engineering survey meeting engineering construction precision side The requirement in face, provides a kind of manufacture method of accurate measurement stake for this.
Precise engineering survey is development and the extension of engineering survey, and it refers to that absolute measurement precision reaches millimeter or sub- milli Rice magnitude, with advanced measuring method, instrument and equipment, the measurement work carrying out under specific condition.Precise engineering survey needs Will special measuring apparatus, improve automaticity and the precision of measuring apparatus, analyse in depth in engineering survey various errors simultaneously Adopt various measures and overcome, precise engineering survey is to serve required precision " extra-high " in various engineering constructions, " special difficult " Part work.
Extensive application forced centering observation stake in precise engineering survey, stake according to the on-site geographical environment of engineering and Geological prospecting situation has many different manufacture methods, and common manufacture method is to dig 1.5 meters of the length of side, depth 1 on the ground The hole of rice, then formwork, casting concrete, on concrete, the embedded length of side is 100-150 millimeter, and thickness is 15 millimeters of steel Plate, carves, at steel plate center, the point position that a round dot to represent control point, and this manufacture method does not have reinforcing bar due to stake bottom, do not have Effectively support and stake ensures its stability, be very easy to cause to offset or settle, reduce accuracy of observation.
Content of the invention
The present invention is to solve the existing observation stake making technical problem that stability is poor, measurement error is big, there is provided The manufacture method that a kind of forced centering for precise engineering survey observes stake, easy to operation, from Measuring origin Reduce the human eye error of centralization, improve certainty of measurement, increase stake stability, reduce the probability of stake skew and sedimentation, meet The required precision of precision engineering.
In order to solve above-mentioned technical problem, the present invention is achieved by following technical scheme:
The manufacture method that a kind of forced centering for precise engineering survey observes stake, is carried out in accordance with the following steps:
(1) hand digging stake holes, until described stake holes is excavated to basement rock;
(2) into described stake holes, steel reinforcement cage is laid in lifting, and described steel reinforcement cage bottom is positioned on described basement rock, and described steel Design height reserved more than ground by muscle cage;
(3) casting concrete in described stake holes, forms concrete-pile under ground portion;
(4) after below ground concrete setting, the described steel reinforcement cage formwork of more than ground reserved design height is poured Concrete, forms concrete-pile aerial partss;
(5) before the above concrete setting in ground, embedding in the center on described concrete-pile aerial partss top Forced centering bolt, the bolt hole coupling of the diameter of described forced centering bolt and measuring instrument base bottom;
(6) in the top embedding forced centering disk of described concrete-pile aerial partss, and make described forced centering bolt Passed by the circle centre position of described forced centering disk;
(7) wait the above concrete setting in ground.
Preferably, the reserved design height more than ground of steel reinforcement cage described in step (2) is 1000-1500mm.
Preferably, concrete-pile aerial partss described in step (4) include directly being seated ground platform and with described The stake pile that platform formed by integrally casting shapes, described stake pile is located above described Platform center and perpendicular to described platform.
Preferably, the described platform-neutral in step (4) is provided with bench mark, and described bench mark is in the above coagulation in ground Insert concrete before soil initial set and reserve 1-2cm more than described platform.
Preferably, in step (6) during embedding described forced centering disk using circular bubble by described forced centering disk Upper surface horizontalization.
Preferably, after step (7), some fender posts are set around forced centering observation stake.
The invention has the beneficial effects as follows:
The forced centering of the present invention observes the manufacture method of stake it is adaptable to the geological condition of basement rock is arranged at bottom, will observe Stake is arranged on basement rock and irrigates pile, stake top embedding forced centering device using manually digging hole, making and can use During reduce sedimentation and the probability of skew, improve the stability of observation stake, have that making embedding method is easy, not rapid wear Feature bad, easy to use, without human eye centering observation monument, can reduce observation error, improve accuracy of observation, and use When directly instrument or prism are rotatably coupled on the forced centering bolt at observation mark stake top end and flatten, to greatest extent Reduce artificial interference factor, thus reducing the error of centralization, the accuracy of observation meeting precision engineering requires.
Brief description
Fig. 1 be forced centering provided by the present invention observe stake manufacture method schematic diagram;
Fig. 2 is the partial top view of Fig. 1.
Above-mentioned in figure:1- basement rock, 2- steel reinforcement cage, 3- concrete-pile under ground portion, 4- concrete-pile aerial partss, 5- stake Pile, 6- platform, 7- bench mark, 8- forced centering bolt, 9- forced centering disk, 10- fender post.
Specific embodiment
For content of the invention, feature and the effect of the present invention can be further appreciated that, hereby enumerate following examples, and coordinate accompanying drawing Describe in detail as follows:
As depicted in figs. 1 and 2, present embodiment discloses a kind of forced centering for precise engineering survey observes stake Manufacture method, is carried out in accordance with the following steps:
(1) manual type is adopted to excavate stake holes, until this stake holes is excavated to basement rock 1 at designed hole position;In stake holes It should be noted that controlling vertical degree of the peg hole, checking loosened soil, exclusion stake holes internal water accumulation in hole quality, cleaning stake holes in mining process.
(2), after the completion of stake holes is excavated, steel reinforcement cage 2 is laid in the lifting into stake holes, and steel reinforcement cage 2 bottom should be positioned on basement rock 1, And steel reinforcement cage 2 should reserve certain design height more than ground, this highly typically in the range of 1000-1500mm, with become After stake, survey crew facilitates operation to be defined.In the present embodiment, reserved height more than ground for the steel reinforcement cage 2 is 1200mm.
(3) hang after steel reinforcement cage 2 puts in place, casting concrete in stake holes, thus form concrete-pile ground in below ground Lower part 3;Concrete-pile under ground portion 3 is cross section is foursquare reinforced column, the length of side of this square cross section For 800mm.
(4) after below ground concrete setting (i.e. after concrete-pile under ground portion 3 solidification forming), then by ground with Upper reserved 1200mm steel reinforcement cage 2 formwork casting concrete, forms concrete-pile aerial partss 4.
Wherein concrete-pile aerial partss 4 include cross section is foursquare stake pile 6, the side of this square cross section A length of 300mm.In addition to stake pile 6, concrete-pile aerial partss 4 also include being arranged at stake pile 6 bottom and being directly located In the platform 5 on ground, platform 5 height is 300mm, and the length of side of its square cross section is 1200mm.Platform 5 and stake pile 6 The concrete-pile aerial partss 4 being constituted, its total height is 1200mm.
Because high process control is also a part for precise engineering survey work, in order to improve the use function of stake, permissible Erect bench mark 7 in platform 5, to control the elevation of engineering.Bench mark 7 is normally at stake pile 6 at a distance of 10- At the position of 20cm, insert concrete before the above concrete initial set in ground and reserve 1-2cm in platform more than 5.
(5) before the above concrete setting in ground (i.e. before concrete-pile aerial partss 4 solidification forming), in concrete The center embedding forced centering bolt 8 of stake aerial partss 4 top (namely stake pile 6 top), this forced centering bolt 8 Diameter and measuring instrument base bottom bolt hole coupling, with smooth, measuring instrument is installed.
(6) after embedding forced centering bolt 8, on the top (namely top of stake pile 6) of concrete-pile aerial partss 4 Embedding forced centering disk 9, and so that forced centering bolt 8 is passed by the circle centre position of forced centering disk 9, forced centering disk 9 A diameter of 140mm.It should be noted that should be using circular bubble by forced centering disk 9 during embedding forced centering disk 9 Upper surface horizontalization.
(7) the above concrete setting in ground, i.e. concrete-pile aerial partss 4 solidification forming are waited.
(8) last, in order to protect the forced centering completing to observe stake, arrange around forced centering observation stake Some concrete filled steel tube fender posts 10 red and white, to prevent it from being destroyed.A diameter of 200mm of fender post 10, totally It is highly 1100mm, wherein aerial partss are 500mm, and under ground portion is 600mm.
Although being described to the preferred embodiments of the present invention above in conjunction with accompanying drawing, the invention is not limited in The specific embodiment stated, above-mentioned specific embodiment is only schematically, is not restricted, this area common Technical staff, under the enlightenment of the present invention, in the case of without departing from present inventive concept and scope of the claimed protection, also may be used To make the concrete conversion of a lot of forms, these belong within protection scope of the present invention.

Claims (6)

1. a kind of forced centering for precise engineering survey observes the manufacture method of stake it is characterised in that walking according to following Suddenly carry out:
(1) hand digging stake holes, until described stake holes is excavated to basement rock;
(2) into described stake holes, steel reinforcement cage is laid in lifting, and described steel reinforcement cage bottom is positioned on described basement rock, and described steel reinforcement cage Design height is reserved more than ground;
(3) casting concrete in described stake holes, forms concrete-pile under ground portion;
(4) after below ground concrete setting, the described steel reinforcement cage formwork of more than ground reserved design height is poured coagulation Soil, forms concrete-pile aerial partss;
(5) before the above concrete setting in ground, in the embedding pressure in center on described concrete-pile aerial partss top GUIXIN bolt, the bolt hole coupling of the diameter of described forced centering bolt and measuring instrument base bottom;
(6) in the top embedding forced centering disk of described concrete-pile aerial partss, and make described forced centering bolt by institute The circle centre position stating forced centering disk passes;
(7) wait the above concrete setting in ground.
2. the manufacture method that a kind of forced centering for precise engineering survey according to claim 1 observes stake, its It is characterised by, the reserved design height more than ground of steel reinforcement cage described in step (2) is 1000-1500mm.
3. the manufacture method that a kind of forced centering for precise engineering survey according to claim 1 observes stake, its Be characterised by, concrete-pile aerial partss described in step (4) include directly being seated ground platform and with described platform one Body pours the stake pile of shaping, and described stake pile is located above described Platform center and perpendicular to described platform.
4. the manufacture method that a kind of forced centering for precise engineering survey according to claim 1 observes stake, its It is characterised by, the described platform-neutral in step (4) is provided with bench mark, described bench mark is in the above concrete initial set in ground Insert concrete before and reserve 1-2cm more than described platform.
5. the manufacture method that a kind of forced centering for precise engineering survey according to claim 1 observes stake, its Be characterised by, in step (6) during embedding described forced centering disk using circular bubble by the upper table of described forced centering disk Face horizontalization.
6. the manufacture method that a kind of forced centering for precise engineering survey according to claim 1 observes stake, its It is characterised by, after step (7), some fender posts are set around forced centering observation stake.
CN201610763991.8A 2016-08-29 2016-08-29 Production method of forced centering observation mark stake for precision engineering measurement Pending CN106403996A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610763991.8A CN106403996A (en) 2016-08-29 2016-08-29 Production method of forced centering observation mark stake for precision engineering measurement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610763991.8A CN106403996A (en) 2016-08-29 2016-08-29 Production method of forced centering observation mark stake for precision engineering measurement

Publications (1)

Publication Number Publication Date
CN106403996A true CN106403996A (en) 2017-02-15

Family

ID=58002249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610763991.8A Pending CN106403996A (en) 2016-08-29 2016-08-29 Production method of forced centering observation mark stake for precision engineering measurement

Country Status (1)

Country Link
CN (1) CN106403996A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109163716A (en) * 2018-10-25 2019-01-08 中国电力工程顾问集团西北电力设计院有限公司 A kind of engineering surveying control point structure and its construction method
CN111551156A (en) * 2020-06-10 2020-08-18 江苏安全技术职业学院 Forced centering device for precision engineering measurement
CN116481505A (en) * 2023-04-25 2023-07-25 上海勘测设计研究院有限公司 Prism and Beidou double-positioning observation pier

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103076010A (en) * 2013-01-25 2013-05-01 天津二十冶建设有限公司 Fabrication method of forced centering observation pillar for precision engineering measurement and observation pillar
CN104897143A (en) * 2014-03-05 2015-09-09 中国葛洲坝集团股份有限公司 Cylinder forced centering observation pillar and embedment method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103076010A (en) * 2013-01-25 2013-05-01 天津二十冶建设有限公司 Fabrication method of forced centering observation pillar for precision engineering measurement and observation pillar
CN104897143A (en) * 2014-03-05 2015-09-09 中国葛洲坝集团股份有限公司 Cylinder forced centering observation pillar and embedment method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109163716A (en) * 2018-10-25 2019-01-08 中国电力工程顾问集团西北电力设计院有限公司 A kind of engineering surveying control point structure and its construction method
CN111551156A (en) * 2020-06-10 2020-08-18 江苏安全技术职业学院 Forced centering device for precision engineering measurement
CN111551156B (en) * 2020-06-10 2022-02-18 江苏安全技术职业学院 Forced centering device for precision engineering measurement
CN116481505A (en) * 2023-04-25 2023-07-25 上海勘测设计研究院有限公司 Prism and Beidou double-positioning observation pier

Similar Documents

Publication Publication Date Title
CN101824919B (en) Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
CN105951747B (en) A kind of construction method of the pre-buried lattice column of contrary sequence method
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN113445498A (en) Construction process of karst hole pile foundation in complex geology
CN108149703B (en) Work transmission line basis precast construction method
CN112900450A (en) Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method
CN108149678A (en) A kind of loess retaining wall does the construction method of operation pore-creating filling pile
CN106836206A (en) Casing rotary digging bore forming method
CN109487822A (en) Reverse construction erection of steel pipe column method of adjustment and control device
CN106403996A (en) Production method of forced centering observation mark stake for precision engineering measurement
CN104897143A (en) Cylinder forced centering observation pillar and embedment method thereof
CN113293869A (en) Construction method for rear insertion of steel upright post
CN110644363A (en) Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway
CN113431039A (en) Construction method of bridge implanted pile
CN114673153A (en) Construction method of complex stratum overlength large-diameter pile foundation casing structure
CN102966254B (en) Arrangement method for measuring tower used for construction of stub matching method
CN109056808A (en) Stake and steel pipe column construction method in a kind of subway station
CN103016914A (en) Multifunctional forced centering leg bracket
CN103076010A (en) Fabrication method of forced centering observation pillar for precision engineering measurement and observation pillar
CN104895054A (en) Construction method of fiber rib concrete uplift pile
CN104088292A (en) Axis single-pile multi-tripod foundation and construction method thereof
CN206768822U (en) A kind of simple automatic positioning equipment of cast-in-place concrete pile interpolation steel pipe column
CN203310412U (en) GNSS (global navigation satellite system) observation pillar for reducing multipath effect
CN206289628U (en) Pile foundation casing set
CN211500533U (en) Hole guiding device for geological static pressure pile in rich thick sand layer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170215

WD01 Invention patent application deemed withdrawn after publication