CN114673153A - Construction method of super long diameter pile foundation casing structure in complex stratum - Google Patents

Construction method of super long diameter pile foundation casing structure in complex stratum Download PDF

Info

Publication number
CN114673153A
CN114673153A CN202210251917.3A CN202210251917A CN114673153A CN 114673153 A CN114673153 A CN 114673153A CN 202210251917 A CN202210251917 A CN 202210251917A CN 114673153 A CN114673153 A CN 114673153A
Authority
CN
China
Prior art keywords
steel
casing
steel casing
guide frame
working platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210251917.3A
Other languages
Chinese (zh)
Inventor
王新泉
王康宇
刁红国
崔允亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou City University
Original Assignee
Hangzhou City University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou City University filed Critical Hangzhou City University
Priority to CN202210251917.3A priority Critical patent/CN114673153A/en
Publication of CN114673153A publication Critical patent/CN114673153A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/18Placing by vibrating
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B11/00Measuring arrangements characterised by the use of optical techniques
    • G01B11/26Measuring arrangements characterised by the use of optical techniques for measuring angles or tapers; for testing the alignment of axes
    • G01B11/27Measuring arrangements characterised by the use of optical techniques for measuring angles or tapers; for testing the alignment of axes for testing the alignment of axes
    • G01B11/272Measuring arrangements characterised by the use of optical techniques for measuring angles or tapers; for testing the alignment of axes for testing the alignment of axes using photoelectric detection means

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention relates to a construction method of a complex stratum overlong large-diameter pile foundation casing structure, which comprises the following steps: preparing a technology; sinking the steel pipe pile on the initial working platform; and (5) sinking the steel casing on the initial working platform. The beneficial effects of the invention are: the initial working platform adopts the steel pipe piles as the bearing structures, and the pile casing area working platform adopts the steel casing as the bearing structures to be erected, so that the construction period is greatly shortened, and meanwhile, the platform erection materials are saved. The steel protects a sunken leading truck of section of thick bamboo as the steel and protects a point contact formula leading truck, protects a central point with the help of the leading truck location steel simultaneously and puts, is convenient for be under construction and guarantees that protecting a section of thick bamboo sinks smoothly and the development of follow-up work. Detecting the horizontal position of the steel casing by adopting a casing center positioning line, and detecting the verticality of the steel casing by using a laser pen and a laser receiving surface; and correcting the horizontal position and the verticality by using hydraulic screw jacks at different positions. The construction precision of hoisting the steel casing is greatly improved, disturbance is reduced, and the construction quality is improved.

Description

复杂地层超长大直径桩基护筒结构的施工方法Construction method of super-long diameter pile foundation casing structure in complex stratum

技术领域technical field

本发明属于建筑施工技术领域,具体涉及一种复杂地层超长大直径桩基护筒结构的施工方法。The invention belongs to the technical field of building construction, and in particular relates to a construction method of a super-long diameter pile foundation casing structure in complex strata.

背景技术Background technique

钻孔灌注桩是大型建筑和桥梁建设上常用的一种深基础形式。近年来我国在建设领域高速发展,桥梁跨径不断增大,建筑高度越来越高。钻孔灌注桩的长度也越来越长,直径增大。Bored piles are a form of deep foundation commonly used in large buildings and bridge construction. In recent years, my country has developed rapidly in the field of construction, the span of bridges has continued to increase, and the height of buildings has become higher and higher. Bored piles are also getting longer in length and larger in diameter.

受我国复杂地质情况的影响,在进行桩基础施工时,常常遇见地下水较为丰富,钻孔处地质多为粉沙、细沙、中粗沙及沙砾层等易坍孔地层的情况;易坍孔地层的渗透系数较大,施工中存在大量涌水、涌砂的可能,这给桩基施工带来了诸多困难。Affected by the complex geological conditions in my country, during the construction of pile foundations, it is often encountered that the groundwater is relatively abundant, and the geology of the boreholes is mostly silt, fine sand, medium-coarse sand and gravel layers and other strata that are prone to collapse; The permeability coefficient of the stratum is relatively large, and there is a possibility of a large amount of water and sand gushing during the construction, which brings many difficulties to the pile foundation construction.

施工中遇到类似易坍孔地层的地质条件时,可设置钢护筒,减少对交互粉细砂层的扰动。但传统钢护筒施工平台搭设耗钢材量大,焊接量大,面对交互粉细砂层较厚的,易造成浪费。When encountering geological conditions similar to slump-prone formations during construction, steel casings can be installed to reduce disturbance to the alternating silty and fine sand layers. However, the construction of the traditional steel casing construction platform consumes a large amount of steel, and the amount of welding is large, and it is easy to cause waste in the face of the thick interactive fine sand layer.

因此,目前亟需寻求一种结构合理,安装稳固且施工便捷,经济环保的复杂地层超长大直径桩基护筒结构的施工方法。Therefore, there is an urgent need to find a construction method for a super-long diameter pile foundation casing structure in complex strata, which is reasonable in structure, stable in installation, convenient in construction, economical and environmentally friendly.

发明内容SUMMARY OF THE INVENTION

本发明的目的是克服现有技术中的不足,提供一种复杂地层超长大直径桩基护筒结构的施工方法。The purpose of the present invention is to overcome the deficiencies in the prior art, and to provide a construction method for a super-long diameter pile foundation casing structure in a complex stratum.

这种复杂地层超长大直径桩基护筒结构的施工方法,包括以下步骤:The construction method of the super-long diameter pile foundation casing structure in the complex stratum includes the following steps:

S1、技术准备:在工厂预制钢护筒、钢护筒点接触式导向架、钢管桩导向架和钢桁架,以上预制部件出厂检验合格后,用驳船运输至施工现场;S1. Technical preparation: Prefabricated steel casing, steel casing point-contact guide frame, steel pipe pile guide frame and steel truss in the factory. After the above prefabricated components are qualified after factory inspection, they will be transported to the construction site by barge;

S2、沉放起始工作平台上的钢管桩;S2, sink the steel pipe pile on the starting working platform;

S3、沉放起始工作平台上的钢护筒;S3, sink the steel casing on the starting working platform;

S4、护筒区工作平台搭设;S4. Setting up of the working platform in the protective tube area;

S5、起始工作平台上的钢护筒下沉;S5. The steel casing on the starting working platform sinks;

S6、钢护筒点接触式导向架移动;S6. The point-contact guide frame of the steel casing moves;

S7、后续钢护筒沉放;S7. Subsequent steel casing sinks;

S8、钢管桩施工:下沉所有钢护筒后,开展后续钢管桩的施工。S8. Steel pipe pile construction: After sinking all steel casings, follow-up steel pipe pile construction is carried out.

作为优选,步骤S2具体为:起始工作平台位于钻孔平台上游侧;利用安装在打桩船上的钢管桩导向架进行定位,用打桩船吊起振动锤振动下沉;当钢管桩起吊竖直后,将钢管桩送进钢管桩导向架内,测量调整钢管桩的平面位置及倾斜度,当钢管桩的平面位置及倾斜度合乎施工要求后,将振动锤振动下沉到设定位置。Preferably, step S2 is specifically as follows: the initial working platform is located on the upstream side of the drilling platform; the steel pipe pile guide frame installed on the piling ship is used for positioning, and the piling ship is used to hoist the vibrating hammer to vibrate and sink; After straightening, send the steel pipe pile into the guide frame of the steel pipe pile, measure and adjust the plane position and inclination of the steel pipe pile. Set the location.

作为优选,步骤S3具体为:在指定位置安设钢护筒点接触式导向架,用打桩船吊起钢护筒,钢护筒保持垂直,在平潮或流速较小时将钢护筒缓慢下滑,直至钢护筒入泥稳定,打桩船脱钩。Preferably, step S3 is specifically as follows: installing a point-contact guide frame for the steel casing at a designated position, hoisting the steel casing with a piling ship, keeping the steel casing vertical, and slowly sliding the steel casing when the tide is flat or the flow rate is small , until the steel casing is stable in the mud, and the piling ship is decoupled.

作为优选,步骤S4具体为:打桩船吊装钢桁架,将钢桁架安装于已完成的起始工作平台或钢护筒顶部;在钢桁架前端设置悬臂式护筒导向架平台;在钢桁架表面铺设护筒区工作平台面层。Preferably, step S4 is specifically as follows: the piling ship hoists the steel truss, and the steel truss is installed on the completed starting work platform or the top of the steel casing; the cantilever type casing guide platform is arranged at the front end of the steel truss; the surface of the steel truss is laid Surface layer of working platform in casing area.

作为优选,步骤S5具体为:用打桩船吊起钢护筒,调整钢护筒的平面位置及垂直度直至到达设定的平面位置及垂直度;打桩船落钩,钢护筒沿钢护筒点接触式导向架下至河底并插入土中,打桩船脱钩。Preferably, step S5 is specifically as follows: lifting the steel casing with a piling boat, adjusting the plane position and verticality of the steel casing until reaching the set plane position and verticality; the piling boat is hooked, and the steel casing follows the steel casing. The point-contact guide frame is lowered to the bottom of the river and inserted into the soil, and the piling boat is decoupled.

作为优选,步骤S6具体为:钢护筒下沉完成后,吊走振动锤,拆除钢护筒点接触式导向架与锚固梁间的连接;将钢护筒点接触式导向架移至另一钢护筒位定位,重复步骤S5,下沉钢护筒,将钢护筒点接触式导向架与起始工作平台及相邻钢护筒连接。Preferably, step S6 is specifically as follows: after the sinking of the steel casing is completed, the vibrating hammer is lifted away, and the connection between the point-contact guide frame of the steel casing and the anchor beam is removed; the point-contact guide frame of the steel casing is moved to another Position the steel casing, repeat step S5, sink the steel casing, and connect the point-contact guide frame of the steel casing to the starting working platform and the adjacent steel casing.

作为优选,步骤S7具体为:测量第一排钢护筒的位置,对焊接在钢护筒上的牛腿进行找平;将支撑梁、次梁和锚固梁搁置至第一排钢护筒上,并与钢护筒上的牛腿焊接,将钢护筒点接触式导向架吊装并锚固在前后锚固梁上;重复上述步骤直至下沉完所有钢护筒。Preferably, step S7 is specifically as follows: measuring the position of the first row of steel casings, leveling the corbels welded on the steel casings; placing the support beam, secondary beam and anchor beam on the first row of steel casings, And weld with the corbel on the steel casing, hoist and anchor the steel casing point-contact guide frame on the front and rear anchor beams; repeat the above steps until all the steel casings are sunk.

复杂地层超长大直径桩基护筒结构,根据上述方法得到的。The super-long diameter pile foundation casing structure in complex stratum is obtained according to the above method.

本发明的有益效果是:The beneficial effects of the present invention are:

本发明起始工作平台采用钢管桩作为承重结构,护筒区工作平台采用钢护筒作为承重结构的搭设,大大节约工期,同时节省了平台搭设材料。本发明采用钢护筒点接触式导向架作为钢护筒下沉的导向架,同时借助导向架定位钢护筒中心位置;导向架分上下两部分,便于施工且保证护筒顺利下沉和后续工作的开展。本发明采用护筒中心定位线检测钢护筒水平位置,通过激光笔及激光接收面检测钢护筒垂直度;借助不同位置的液压螺旋千斤顶进行水平位置和垂直度纠偏。大大提高了钢护筒吊装的施工精度,减少扰动,提高施工质量。The initial working platform of the present invention adopts steel pipe piles as the load-bearing structure, and the working platform in the casing area adopts the steel casing as the load-bearing structure for erection, which greatly saves the construction period and saves the platform erection materials. The invention adopts the point-contact guide frame of the steel casing as the guide frame for the sinking of the steel casing, and simultaneously locates the center position of the steel casing by means of the guide frame; the guide frame is divided into upper and lower parts, which is convenient for construction and ensures the smooth sinking of the casing and subsequent development of work. The invention adopts the protective tube center positioning line to detect the horizontal position of the steel protective tube, and detects the verticality of the steel protective tube through a laser pointer and a laser receiving surface; It greatly improves the construction accuracy of steel casing hoisting, reduces disturbance and improves construction quality.

本发明的复杂地层超长大直径桩基护筒结构设计合理,能够有效的提高施工速度,减少施工过程中交互细粉砂层扰动,且经济环保,减少资源浪费。The super-long diameter pile foundation casing structure of the invention is reasonable in design, can effectively improve the construction speed, reduce the disturbance of the interactive fine silt layer during the construction process, is economical and environmentally friendly, and reduces the waste of resources.

附图说明Description of drawings

图1是复杂地层超长大直径桩基护筒结构的整体结构示意图;Fig. 1 is the overall structural schematic diagram of the super-long diameter pile foundation casing structure in complex strata;

图2是起始工作平台正视图;Fig. 2 is the front view of the starting working platform;

图3是起始工作平台俯视图;Figure 3 is a top view of the initial working platform;

图4是钢管桩打桩船示意图;Figure 4 is a schematic diagram of a steel pipe pile piling ship;

图5是钢管桩导向架示意图;Fig. 5 is the schematic diagram of the guide frame of the steel pipe pile;

图6是护筒区工作平台正视图;Figure 6 is a front view of the working platform in the protective tube area;

图7是护筒区工作平台俯视图;Figure 7 is a top view of the working platform in the protective tube area;

图8是护筒导向架平台俯视图;Fig. 8 is the top view of the protective tube guide frame platform;

图9是钢护筒点接触式导向架示意图,其中图9(a)为正视图,图9(b)为俯视图;Fig. 9 is a schematic diagram of a point-contact guide frame of a steel casing, wherein Fig. 9(a) is a front view, and Fig. 9(b) is a top view;

图10是垂直度动态调整系统示意图;Figure 10 is a schematic diagram of the verticality dynamic adjustment system;

图11是便携水平器示意图。Figure 11 is a schematic diagram of a portable level.

附图标记说明:1-钢护筒点接触式导向架、2-钢护筒定位与吊装装置、3-钢护筒位置与垂直度动态调整系统、4-起始工作平台、5-护筒区工作平台、6-钢护筒、7-牛腿、8-连接梁、9-钢管桩、10-上层平联、11-下层平联、12-钻孔平台、13-支撑梁、14-次梁、15-锚固梁、16-刚面板、17-栏杆、18-打桩船、19-振动锤、20-钢管桩导向架、21-船头、22-槽钢骨架、23-千斤顶、24-钢桁架、25-面层、26-悬臂式护筒导向架平台、27-吊耳、28-螺栓、29-悬臂梁、30-支座、31-护筒中心定位线、32-连接杆、33-型钢拉杆、34-型钢骨架、35-锁扣拉杆、36-上层导向架、37-下层导向架、38-液压螺旋千斤顶、39-下层液压螺旋千斤顶、40-便携水平器、41-激光笔、42-激光笔导向管、43-激光接收面、44-水准泡、45-垂直度允许区间、46-上层液压螺旋千斤顶。Explanation of reference numerals: 1-point-contact guide frame for steel casing, 2-steel casing positioning and hoisting device, 3-dynamic adjustment system for the position and verticality of steel casing, 4-starting working platform, 5- casing Area working platform, 6-steel casing, 7-corbel, 8-connecting beam, 9-steel pipe pile, 10-upper level connection, 11-lower level connection, 12-drilling platform, 13-support beam, 14 - Secondary beam, 15- Anchor beam, 16- Rigid panel, 17- Railing, 18- Piling boat, 19- Vibrating hammer, 20- Steel pipe pile guide frame, 21- Bow, 22- Channel steel frame, 23- Jack , 24-steel truss, 25-surface layer, 26-cantilever guard guide frame platform, 27-lifting lug, 28-bolt, 29-cantilever beam, 30-support, 31-guard cylinder center positioning line, 32- Connecting rod, 33-section steel rod, 34-section steel frame, 35-lock rod, 36-upper guide frame, 37-lower guide frame, 38-hydraulic screw jack, 39-lower hydraulic screw jack, 40-portable level, 41-laser pointer, 42-laser pointer guide tube, 43-laser receiving surface, 44-level bubble, 45-permissible interval of verticality, 46-upper hydraulic screw jack.

具体实施方式Detailed ways

下面结合实施例对本发明做进一步描述。下述实施例的说明只是用于帮助理解本发明。应当指出,对于本技术领域的普通人员来说,在不脱离本发明原理的前提下,还可以对本发明进行若干修饰,这些改进和修饰也落入本发明权利要求的保护范围内。The present invention will be further described below in conjunction with the embodiments. The following examples are illustrative only to aid in the understanding of the present invention. It should be pointed out that for those of ordinary skill in the art, without departing from the principle of the present invention, the present invention can also be modified several times, and these improvements and modifications also fall within the protection scope of the claims of the present invention.

作为一种实施例,如图1至图11所示,复杂地层超长大直径桩基护筒结构的施工方法,包括以下步骤:As an embodiment, as shown in Figure 1 to Figure 11, the construction method of the super long diameter pile foundation casing structure in complex strata includes the following steps:

S1、技术准备:在工厂预制钢护筒6、钢护筒点接触式导向架1、钢管桩导向架20和钢桁架24,以上预制部件出厂检验合格后,用驳船运输至施工现场;S1. Technical preparation: Prefabricated steel casing 6, steel casing point-contact guide frame 1, steel pipe pile guide frame 20 and steel truss 24 in the factory. After the above prefabricated components have passed the factory inspection, they will be transported to the construction site by barge;

S2、沉放起始工作平台4上的钢管桩9:起始工作平台4位于钻孔平台12上游侧;利用安装在打桩船18上的钢管桩导向架20进行定位,用打桩船18吊起振动锤19振动下沉;当钢管桩9起吊竖直后,将钢管桩9送进钢管桩导向架20内,测量调整钢管桩9的平面位置及倾斜度,当钢管桩9的平面位置及倾斜度合乎施工要求后,将振动锤19振动下沉到设定位置;S2, laying down the steel pipe pile 9 on the starting working platform 4: the starting working platform 4 is located on the upstream side of the drilling platform 12; Lift the vibrating hammer 19 to vibrate and sink; when the steel pipe pile 9 is lifted upright, the steel pipe pile 9 is sent into the steel pipe pile guide frame 20, and the plane position and inclination of the steel pipe pile 9 are measured and adjusted. After the plane position and inclination of the pile 9 meet the construction requirements, the vibrating hammer 19 is vibrated and sunk to the set position;

S3、沉放起始工作平台4上的钢护筒6:在指定位置安设钢护筒点接触式导向架1,用打桩船18吊起钢护筒6,钢护筒6保持垂直,在平潮或流速较小时将钢护筒6缓慢下滑,直至钢护筒6入泥稳定,打桩船18脱钩;S3, sink the steel casing 6 on the starting working platform 4: install the steel casing point-contact guide frame 1 at the designated position, lift the steel casing 6 with the piling ship 18, and keep the steel casing 6 vertical. When the tide is flat or the flow rate is small, slowly slide the steel casing 6 down until the steel casing 6 is stably immersed in the mud, and the piling ship 18 is decoupled;

S4、护筒区工作平台5搭设:打桩船18吊装钢桁架24,将钢桁架24安装于已完成的起始工作平台4或钢护筒6顶部;在钢桁架24前端设置悬臂式护筒导向架平台26;在钢桁架24表面铺设护筒区工作平台5面层;S4. Setting up of the working platform 5 in the protective tube area: the steel truss 24 is hoisted by the piling ship 18, and the steel truss 24 is installed on the top of the completed initial working platform 4 or the steel protective tube 6; The platform 26 is laid; the surface layer of the working platform 5 in the casing area is laid on the surface of the steel truss 24;

S5、起始工作平台4上的钢护筒6下沉:用打桩船18吊起钢护筒6,调整钢护筒6的平面位置及垂直度直至到达设定的平面位置及垂直度;打桩船18落钩,钢护筒6沿钢护筒点接触式导向架1下至河底并插入土中,打桩船18脱钩;S5. The steel casing 6 on the initial working platform 4 sinks: lift the steel casing 6 with the piling boat 18, adjust the plane position and verticality of the steel casing 6 until the set plane position and verticality are reached; The boat 18 is hooked, the steel casing 6 is lowered to the bottom of the river along the point-contact guide frame 1 of the steel casing and inserted into the soil, and the piling boat 18 is decoupled;

S6、钢护筒点接触式导向架1移动:钢护筒6下沉完成后,吊走振动锤19,拆除钢护筒点接触式导向架1与锚固梁15间的连接;将钢护筒点接触式导向架1移至另一钢护筒位定位,重复步骤S5,下沉钢护筒6,将钢护筒点接触式导向架1与起始工作平台4及相邻钢护筒6连接;S6. The steel casing point-contact guide frame 1 moves: after the steel casing 6 sinks, the vibrating hammer 19 is lifted away, and the connection between the steel casing point-contact guide frame 1 and the anchor beam 15 is removed; The point-contact guide frame 1 is moved to another steel casing for positioning, and step S5 is repeated, the steel casing 6 is lowered, and the point-contact guide frame 1 of the steel casing is connected to the starting working platform 4 and the adjacent steel casing 6 connect;

S7、后续钢护筒沉放:测量第一排钢护筒6的位置,对焊接在钢护筒6上的牛腿7进行找平;将支撑梁13、次梁14和锚固梁15搁置至第一排钢护筒6上,并与钢护筒6上的牛腿7焊接,将钢护筒点接触式导向架1吊装并锚固在前后锚固梁15上;重复上述步骤直至下沉完所有钢护筒6;S7. Subsequent steel casings are placed: measure the position of the first row of steel casings 6, and level the corbels 7 welded on the steel casings 6; place the support beam 13, the secondary beam 14 and the anchor beam 15 to the first row A row of steel casings 6 is welded to the corbels 7 on the steel casings 6, and the point-contact guide frame 1 of the steel casings is hoisted and anchored on the front and rear anchor beams 15; the above steps are repeated until all the steel casings are sunk. Guard 6;

S8、钢管桩9施工:下沉所有钢护筒6后,开展后续钢管桩9的施工。S8. Construction of steel pipe piles 9: After sinking all the steel casings 6, the subsequent construction of steel pipe piles 9 is carried out.

根据上述方法得到的复杂地层超长大直径桩基护筒结构,包括钢护筒工作平台、钢护筒点接触式导向架1、钢护筒定位与吊装装置2、钢护筒位置与垂直度动态调整系统3;钢护筒工作平台为钢护筒6下沉的施工平台,包括位于钻孔平台12上游侧的起始工作平台4和护筒区工作平台5;钢护筒定位与吊装装置2包括打桩船18和振动锤19;钢护筒位置与垂直度动态调整系统3包括平面位置测量纠偏装置和垂直度测量纠偏装置;The super-long diameter pile foundation casing structure obtained according to the above method includes a steel casing working platform, a steel casing point-contact guide frame 1, a steel casing positioning and hoisting device 2, a steel casing position and verticality Dynamic adjustment system 3; the steel casing working platform is the construction platform where the steel casing 6 sinks, including the initial working platform 4 and the casing working platform 5 located on the upstream side of the drilling platform 12; the steel casing positioning and hoisting device 2 includes a piling ship 18 and a vibratory hammer 19; a dynamic adjustment system for the position and verticality of the steel casing 3 includes a plane position measurement rectification device and a verticality measurement rectification device;

起始工作平台4以钢管桩9为支撑,多根钢管桩9之间上下平行焊接有型钢作为上层平联10和下层平联11;钢管桩9上搭设钻孔平台12;钻孔平台12包括支撑梁13、次梁14、锚固梁15、钢面板16和栏杆17;支撑梁13搭设于钢管桩9上,钢管桩9上方的两根支撑梁13之间平行布置数道次梁14和锚固梁15;The starting working platform 4 is supported by steel pipe piles 9, and the steel pipe piles 9 are welded with profiled steel up and down in parallel as the upper level parallel connection 10 and the lower level parallel connection 11; a drilling platform 12 is set up on the steel pipe pile 9; The platform 12 includes a support beam 13, a secondary beam 14, an anchor beam 15, a steel panel 16 and a railing 17; Secondary beam 14 and anchor beam 15;

护筒导向架平台26包括悬臂梁29、锚固梁15、支座30和护筒中心定位线31;护筒导向架平台26后端焊接于连接杆32上,护筒导向架平台26前端设置支座30,支座30通过型钢拉杆33与连接杆32的上端支座30相连;悬臂梁29平行布置,与锚固梁15构成护筒导向架平台26的主体结构;悬臂梁29前端均布置支座30;钢护筒点接触式导向架1锚固于锚固梁15上端;The protective tube guide frame platform 26 includes a cantilever beam 29, an anchor beam 15, a support 30 and a protective tube center positioning line 31; the rear end of the protective tube guide frame platform 26 is welded on the connecting rod 32, and the front end of the protective tube guide frame platform 26 is provided with support The seat 30, the support 30 is connected with the upper end support 30 of the connecting rod 32 through the section steel tie rod 33; the cantilever beam 29 is arranged in parallel, and the anchor beam 15 constitutes the main structure of the shield guide frame platform 26; the front end of the cantilever beam 29 is arranged with supports 30; the point-contact guide frame 1 of the steel casing is anchored on the upper end of the anchor beam 15;

打桩船18的船头21处设有钢管桩导向架20,钢管桩9放置于钢管桩导向架20内;打桩船18通过吊勾吊接振动锤19;钢管桩导向架20包括槽钢骨架22和千斤顶23;槽钢骨架22设置于船头21前端,槽钢骨架22上布置相互垂直的四个方向的千斤顶23。A steel pipe pile guide frame 20 is provided at the bow 21 of the piling ship 18, and the steel pipe pile 9 is placed in the steel pipe pile guide frame 20; Channel steel frame 22 and jack 23;

护筒区工作平台5包括钢护筒6、牛腿7、连接梁8、钢桁架24、面层25和护筒导向架平台26;钢护筒6外侧焊有牛腿7,牛腿7上搭设连接梁8;钢桁架24搭设在钢护筒6和连接梁8上;钢桁架24上铺设面层25,面层25上搭设有栏杆17;钢桁架24上设有吊耳27;钢桁架24前端采用螺栓28与护筒导向架平台26横向栓接。护筒区工作平台5上设置的钢护筒6作为钻孔平台12的承重结构。The working platform 5 in the protective tube area includes a steel protective tube 6, a corbel 7, a connecting beam 8, a steel truss 24, a surface layer 25 and a protective tube guide frame platform 26; The connecting beam 8 is erected; the steel truss 24 is erected on the steel casing 6 and the connecting beam 8; the surface layer 25 is laid on the steel truss 24, and the railing 17 is erected on the surface layer 25; the steel truss 24 is provided with lifting ears 27; The front end of 24 is bolted with bolts 28 laterally to the platform 26 of the shield guide frame. The steel casing 6 set on the working platform 5 in the casing area serves as the load-bearing structure of the drilling platform 12 .

钢护筒点接触式导向架1平面为向一侧开口的正方状环形,钢护筒点接触式导向架1上下两层之间用螺栓28连接,钢护筒点接触式导向架1的上下两层分别设置于钻孔平台12的上下两层;钢护筒点接触式导向架1主体由型钢骨架34组成,钢护筒点接触式导向架1的开口端设有锁扣拉杆35;上层导向架36架设于钻孔平台12上方,上层导向架36顶端和底端及下层导向架37底端均布置有相互垂直的四个液压螺旋千斤顶38。The plane of the point-contact guide frame 1 of the steel casing is a square ring that opens to one side. The upper and lower layers of the point-contact guide frame 1 are connected by bolts 28. The upper and lower layers of the point-contact guide frame 1 are connected by bolts 28. The two layers are respectively arranged on the upper and lower layers of the drilling platform 12; the main body of the point-contact guide frame 1 of the steel casing is composed of a steel frame 34, and the open end of the point-contact guide frame 1 of the steel casing is provided with a locking rod 35; the upper layer The guide frame 36 is erected above the drilling platform 12 , and the top and bottom ends of the upper guide frame 36 and the bottom end of the lower guide frame 37 are arranged with four hydraulic screw jacks 38 that are perpendicular to each other.

钢护筒6顶端安装有振动锤19,振动锤19连接于打桩船18吊钩上。A vibrating hammer 19 is installed on the top of the steel casing 6 , and the vibrating hammer 19 is connected to the hook of the piling ship 18 .

垂直度动态调整系统3内:平面位置测量纠偏装置包括钢护筒点接触式导向架1和下层液压螺旋千斤顶39;钢护筒点接触式导向架1中心和护筒中心定位线31重合;下层液压螺旋千斤顶39安装于上层导向架36的底部;在钢护筒6和点接触式导向架1内边设定距离处设置钢护筒6;垂直度测量纠偏装置包括便携水平器40、激光笔41和激光笔导向管42;便携水平器40包括激光接收面43和水准泡44;激光接收面43上划分有垂直度允许区间45;激光笔41和激光笔导向管42设置于钢护筒6顶部外侧;钢护筒点接触式导向架1顶部安装有上层液压螺旋千斤顶46。In the verticality dynamic adjustment system 3: the plane position measurement and correction device includes the steel casing point contact guide frame 1 and the lower hydraulic screw jack 39; the center of the steel casing point contact guide frame 1 and the casing center positioning line 31 coincide; the lower layer The hydraulic screw jack 39 is installed on the bottom of the upper guide frame 36; the steel protective tube 6 is set at the set distance between the steel protective tube 6 and the inner edge of the point-contact guide frame 1; the verticality measurement and deviation correction device includes a portable level 40, a laser pointer 41 and a laser pointer guide tube 42; the portable level 40 includes a laser receiving surface 43 and a level bubble 44; the laser receiving surface 43 is divided into a verticality allowable section 45; Outside the top; the top of the steel casing point-contact guide frame 1 is provided with an upper hydraulic screw jack 46 .

钢护筒6穿过钢护筒点接触式导向架1延伸至河底土层中;钢护筒点接触式导向架1与锚固梁15可拆卸连接。The steel casing 6 extends through the steel casing point-contact guide frame 1 into the river bottom soil layer; the steel casing point-contact guide frame 1 and the anchor beam 15 are detachably connected.

Claims (8)

1.一种复杂地层超长大直径桩基护筒结构的施工方法,其特征在于,包括以下步骤:1. the construction method of a complex stratum super long diameter pile foundation casing structure, is characterized in that, comprises the following steps: S1、技术准备:在工厂预制钢护筒(6)、钢护筒点接触式导向架(1)、钢管桩导向架(20)和钢桁架(24),以上预制部件出厂检验合格后,用驳船运输至施工现场;S1. Technical preparation: After the factory prefabricated steel casing (6), steel casing point-contact guide frame (1), steel pipe pile guide frame (20) and steel truss (24), the above prefabricated components have passed the factory inspection. Transported by barge to the construction site; S2、沉放起始工作平台(4)上的钢管桩(9);S2, sink the steel pipe pile (9) on the starting working platform (4); S3、沉放起始工作平台(4)上的钢护筒(6);S3, sink the steel casing (6) on the starting working platform (4); S4、护筒区工作平台(5)搭设;S4. The working platform (5) in the protection tube area is set up; S5、起始工作平台(4)上的钢护筒(6)下沉;S5. The steel casing (6) on the starting working platform (4) sinks; S6、钢护筒点接触式导向架(1)移动;S6. The point-contact guide frame (1) of the steel casing moves; S7、后续钢护筒沉放;S7. Subsequent steel casing sinks; S8、钢管桩(9)施工:下沉所有钢护筒(6)后,开展后续钢管桩(9)的施工。S8. Construction of steel pipe piles (9): After sinking all the steel casings (6), follow-up construction of the steel pipe piles (9) is carried out. 2.根据权利要求1所述复杂地层超长大直径桩基护筒结构的施工方法,其特征在于,步骤S2具体为:起始工作平台(4)位于钻孔平台(12)上游侧;利用安装在打桩船(18)上的钢管桩导向架(20)进行定位,用打桩船(18)吊起振动锤(19)振动下沉;当钢管桩(9)起吊竖直后,将钢管桩(9)送进钢管桩导向架(20)内,测量调整钢管桩(9)的平面位置及倾斜度,当钢管桩(9)的平面位置及倾斜度合乎施工要求后,将振动锤(19)振动下沉到设定位置。2. according to the construction method of the complex stratum super long diameter pile foundation casing structure according to claim 1, it is characterized in that, step S2 is specifically: starting working platform (4) is positioned on the upstream side of drilling platform (12); The steel pipe pile guide frame (20) installed on the piling ship (18) is positioned, and the vibrating hammer (19) is hoisted by the piling ship (18) to vibrate and sink; when the steel pipe pile (9) is lifted upright, the The steel pipe pile (9) is sent into the steel pipe pile guide frame (20), and the plane position and inclination of the steel pipe pile (9) are measured and adjusted. When the plane position and inclination of the steel pipe pile (9) meet the construction requirements , and vibrate the vibrating hammer (19) down to the set position. 3.根据权利要求2所述复杂地层超长大直径桩基护筒结构的施工方法,其特征在于,步骤S3具体为:在指定位置安设钢护筒点接触式导向架(1),用打桩船(18)吊起钢护筒(6),钢护筒(6)保持垂直,在平潮或流速较小时将钢护筒(6)缓慢下滑,直至钢护筒(6)入泥稳定,打桩船(18)脱钩。3. according to the construction method of the complex stratum super long diameter pile foundation casing structure according to claim 2, it is characterized in that, step S3 is specifically: install the steel casing point-contact guide frame (1) at the designated position, use The piling ship (18) lifts the steel casing (6), the steel casing (6) is kept vertical, and the steel casing (6) is slowly lowered when the tide is flat or the flow velocity is small, until the steel casing (6) is stably immersed in the mud , the piling boat (18) is decoupled. 4.根据权利要求3所述复杂地层超长大直径桩基护筒结构的施工方法,其特征在于,步骤S4具体为:打桩船(18)吊装钢桁架(24),将钢桁架(24)安装于已完成的起始工作平台(4)或钢护筒(6)顶部;在钢桁架(24)前端设置悬臂式护筒导向架平台(26);在钢桁架(24)表面铺设护筒区工作平台(5)面层。4. according to the construction method of the complex stratum super long diameter pile foundation casing structure according to claim 3, it is characterized in that, step S4 is specifically: piling ship (18) hoists steel truss (24), and steel truss (24) Install on the top of the completed starting work platform (4) or the steel casing (6); set the cantilever casing guide platform (26) at the front end of the steel truss (24); lay the casing on the surface of the steel truss (24) Area working platform (5) surface layer. 5.根据权利要求4所述复杂地层超长大直径桩基护筒结构的施工方法,其特征在于,步骤S5具体为:用打桩船(18)吊起钢护筒(6),调整钢护筒(6)的平面位置及垂直度直至到达设定的平面位置及垂直度;打桩船(18)落钩,钢护筒(6)沿钢护筒点接触式导向架(1)下至河底并插入土中,打桩船(18)脱钩。5. according to the construction method of the complex stratum super long diameter pile foundation casing structure according to claim 4, it is characterized in that, step S5 is specifically: lift the steel casing (6) with the piling ship (18), adjust the steel casing The plane position and verticality of the cylinder (6) until it reaches the set plane position and verticality; the piling boat (18) is hooked, and the steel casing (6) goes down to the river along the point-contact guide frame (1) of the steel casing bottom and insert into the soil, and the piling boat (18) is unhooked. 6.根据权利要求5所述复杂地层超长大直径桩基护筒结构的施工方法,其特征在于,步骤S6具体为:钢护筒(6)下沉完成后,吊走振动锤(19),拆除钢护筒点接触式导向架(1)与锚固梁(15)间的连接;将钢护筒点接触式导向架(1)移至另一钢护筒位定位,重复步骤S5,下沉钢护筒(6),将钢护筒点接触式导向架(1)与起始工作平台(4)及相邻钢护筒(6)连接。6. according to the construction method of the complex stratum super long diameter pile foundation casing structure according to claim 5, it is characterized in that, step S6 is specifically: after the steel casing (6) sinking is completed, suspend the vibrating hammer (19) , remove the connection between the point-contact guide frame (1) of the steel casing and the anchor beam (15); move the point-contact guide frame (1) of the steel casing to another steel casing for positioning, repeat step S5, go down The steel protective tube (6) is submerged, and the point-contact guide frame (1) of the steel protective tube is connected with the starting working platform (4) and the adjacent steel protective tube (6). 7.根据权利要求6所述复杂地层超长大直径桩基护筒结构的施工方法,其特征在于,步骤S7具体为:测量第一排钢护筒(6)的位置,对焊接在钢护筒(6)上的牛腿(7)进行找平;将支撑梁(13)、次梁(14)和锚固梁(15)搁置至第一排钢护筒(6)上,并与钢护筒(6)上的牛腿(7)焊接,将钢护筒点接触式导向架(1)吊装并锚固在前后锚固梁(15)上;重复上述步骤直至下沉完所有钢护筒(6)。7. according to the construction method of the complex formation super long diameter pile foundation casing structure of claim 6, it is characterized in that, step S7 is specifically: measure the position of the first row of steel casing (6), butt welding on the steel casing The corbel (7) on the barrel (6) is leveled; the supporting beam (13), the secondary beam (14) and the anchor beam (15) are placed on the first row of the steel casing (6), and are connected with the steel casing. Weld the corbels (7) on the (6), hoist and anchor the steel casing point-contact guide frame (1) on the front and rear anchor beams (15); repeat the above steps until all the steel casings (6) are sunk. . 8.复杂地层超长大直径桩基护筒结构,其特征在于,根据权利要求1至7任一所述的方法得到的。8 . The super-long-diameter pile foundation casing structure in complex strata, characterized in that it is obtained by the method of any one of claims 1 to 7 .
CN202210251917.3A 2022-03-15 2022-03-15 Construction method of super long diameter pile foundation casing structure in complex stratum Pending CN114673153A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210251917.3A CN114673153A (en) 2022-03-15 2022-03-15 Construction method of super long diameter pile foundation casing structure in complex stratum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210251917.3A CN114673153A (en) 2022-03-15 2022-03-15 Construction method of super long diameter pile foundation casing structure in complex stratum

Publications (1)

Publication Number Publication Date
CN114673153A true CN114673153A (en) 2022-06-28

Family

ID=82074424

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210251917.3A Pending CN114673153A (en) 2022-03-15 2022-03-15 Construction method of super long diameter pile foundation casing structure in complex stratum

Country Status (1)

Country Link
CN (1) CN114673153A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115434527A (en) * 2022-09-28 2022-12-06 中建科工集团有限公司 A steel column guide frame and its construction method
CN115573333A (en) * 2022-09-02 2023-01-06 中铁一局集团有限公司 Calibration pile casing for micro steel pipe mixing pile of soft sea-land interactive deposition silt layer and construction method of mixing pile
CN116837806A (en) * 2023-06-12 2023-10-03 中国铁建港航局集团有限公司 Method for erecting anti-collision pier water platform
CN118481148A (en) * 2024-05-15 2024-08-13 中国铁建港航局集团有限公司 Quick construction method for steel casing of underwater inclined rock face or exposed bedrock
WO2025081614A1 (en) * 2023-10-16 2025-04-24 中国港湾工程有限责任公司 Cast-in-place pile construction device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102433880A (en) * 2011-12-30 2012-05-02 广东省长大公路工程有限公司 Simply-support guide frame of sinking steel protecting barrel and construction method for sinking steel protecting barrel
CN202298623U (en) * 2011-10-27 2012-07-04 中交四航局第一工程有限公司 Light adjustable positioning device for steel protection barrel on sea
CN203403418U (en) * 2013-06-18 2014-01-22 重庆建工第一市政工程有限责任公司 Steel casing double-layer guide frame structure
CN107034884A (en) * 2017-05-27 2017-08-11 中交二航局第四工程有限公司 The steel pile casting constructing device and method of the big oblique rock surface of shallow overburden profundal zone flow velocity
WO2021179466A1 (en) * 2020-03-13 2021-09-16 中交武汉港湾工程设计研究院有限公司 Movable land construction platform and method for wharf reconstruction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202298623U (en) * 2011-10-27 2012-07-04 中交四航局第一工程有限公司 Light adjustable positioning device for steel protection barrel on sea
CN102433880A (en) * 2011-12-30 2012-05-02 广东省长大公路工程有限公司 Simply-support guide frame of sinking steel protecting barrel and construction method for sinking steel protecting barrel
CN203403418U (en) * 2013-06-18 2014-01-22 重庆建工第一市政工程有限责任公司 Steel casing double-layer guide frame structure
CN107034884A (en) * 2017-05-27 2017-08-11 中交二航局第四工程有限公司 The steel pile casting constructing device and method of the big oblique rock surface of shallow overburden profundal zone flow velocity
WO2021179466A1 (en) * 2020-03-13 2021-09-16 中交武汉港湾工程设计研究院有限公司 Movable land construction platform and method for wharf reconstruction

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115573333A (en) * 2022-09-02 2023-01-06 中铁一局集团有限公司 Calibration pile casing for micro steel pipe mixing pile of soft sea-land interactive deposition silt layer and construction method of mixing pile
CN115573333B (en) * 2022-09-02 2024-05-03 中铁一局集团有限公司 Calibration pile casing of mini-type steel pipe mixing pile for soft sea Liu Jiaohu phase sediment silt layer and construction method of mixing pile
CN115434527A (en) * 2022-09-28 2022-12-06 中建科工集团有限公司 A steel column guide frame and its construction method
CN116837806A (en) * 2023-06-12 2023-10-03 中国铁建港航局集团有限公司 Method for erecting anti-collision pier water platform
WO2025081614A1 (en) * 2023-10-16 2025-04-24 中国港湾工程有限责任公司 Cast-in-place pile construction device
CN118481148A (en) * 2024-05-15 2024-08-13 中国铁建港航局集团有限公司 Quick construction method for steel casing of underwater inclined rock face or exposed bedrock

Similar Documents

Publication Publication Date Title
CN114673153A (en) Construction method of super long diameter pile foundation casing structure in complex stratum
CN111945767B (en) Construction process of pile-first outer jacket type jacket of offshore wind power booster station
CN105386408B (en) Deep-water bridge pile foundation construction method
CN101824919B (en) Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
WO2019128155A1 (en) Open caisson construction structure and method
CN103741657B (en) The construction method of large-sized multifunction waterborne traffic accident
CN103243747B (en) Deviation rectifying method of prestressed concrete pipe pile foundation
CN105951747B (en) A kind of construction method of the pre-buried lattice column of contrary sequence method
CN104532813A (en) Overwater building construction platform and erecting method and use method thereof
CN111962504A (en) Construction method for covering and digging top-down permanent steel pipe column
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN113550340A (en) A construction method for deep water foundation of double-wall steel cofferdam without back cover under the condition of deep water entering into rock
CN108505529A (en) A kind of construction method of the bearing platform construction steel cofferdam of Through Steel case arch bridge
CN110644363A (en) Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway
CN107700479A (en) A kind of construction method of large diameter drill hole pile
CN109853531A (en) A kind of pile foundation construction process of cast-in-situ bored pile
CN203654196U (en) Guide apparatus for large and multifunctional over-water construction platform
CN110206071B (en) Method and device for reinforcing joints of underground continuous wall
CN215562604U (en) Pile connecting and pouring structure
CN114396063A (en) A steel cofferdam positioning adjustment system and positioning method
CN202969333U (en) Steel truss rock-socketed wharf structure
CN118292429A (en) Construction method of impact-rotary digging combined pore-forming filling pile
CN111663456A (en) Ultra-long pile casing construction system and method for integrated process of pier and pile in water
CN212561551U (en) Steel stand hoist and mount and transfer positioner
CN114541438A (en) A steel cofferdam with positioning function and positioning method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination