CN104389348B - 一种带蒙皮拱结构的安装方法 - Google Patents

一种带蒙皮拱结构的安装方法 Download PDF

Info

Publication number
CN104389348B
CN104389348B CN201410530851.7A CN201410530851A CN104389348B CN 104389348 B CN104389348 B CN 104389348B CN 201410530851 A CN201410530851 A CN 201410530851A CN 104389348 B CN104389348 B CN 104389348B
Authority
CN
China
Prior art keywords
covering
arch
piecemeal
support
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410530851.7A
Other languages
English (en)
Other versions
CN104389348A (zh
Inventor
唐香君
吴文平
邵宝健
殷巧龙
巫明杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huning Steel Mechanism Co Ltd
Original Assignee
Jiangsu Huning Steel Mechanism Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huning Steel Mechanism Co Ltd filed Critical Jiangsu Huning Steel Mechanism Co Ltd
Priority to CN201410530851.7A priority Critical patent/CN104389348B/zh
Publication of CN104389348A publication Critical patent/CN104389348A/zh
Application granted granted Critical
Publication of CN104389348B publication Critical patent/CN104389348B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明公开了一种带蒙皮拱结构的安装方法,本发明中所述带蒙皮拱结构中蒙皮为弧形蒙皮,安装时依据已安装的结构作为可靠固定物进行拉接。本发明所述方法借助于计算机仿真技术,解决了带蒙皮拱结构空间安装定位难的问题,解决了无法直接使用临时支撑支承带蒙皮拱结构辅助安装的问题。

Description

一种带蒙皮拱结构的安装方法
技术领域
本发明涉及一种钢构件的施工方法,特别是一种带蒙皮拱结构安装的施工方法。
背景技术
对于各种场馆钢构工程而言,其中的典型结构较多,尤其带蒙皮拱结构的场馆是近年出现的新颖造型。运用临时支撑辅助高空安装的传统方法,由于场馆本身结构线型就限制了临时支撑的支承位置,根本无法支承。若采用满堂脚手架作为支承体系辅助安装,外部结构为拱曲结构,可能无法满足结构支承。安全风险非常大,且安装时间较长,安装精度无法得到保证。严重影响了工程质量和加工精度,制约了钢构建筑的发展趋势。
发明内容
发明目的:本发明的目的提供了一种更富有美感的带蒙皮拱结构钢架的结构及该结构的安装方法。
技术方案:本发明公开了一种带蒙皮拱结构钢架,该结构包括:蒙皮拱结构、楼层钢梁、独立支撑柱和砼结构;所述蒙皮拱结构包括:蒙皮支架和蒙皮;所述蒙皮为圆弧形;所述砼结构上安装所述楼层钢梁;所述楼层钢梁通过独立支撑柱固定支撑;所述蒙皮支架固定在楼层钢梁,通过楼层钢梁实现蒙皮支架的定位支撑;所述蒙皮固定在蒙皮支架上。本发明中公开了蒙皮为弧形的钢架结构,拓展了建筑设计的范围,使建筑设计更具有流线型,更富有流动的韵律;增加了建筑设计的多样性。
本发明中还公开了上述带蒙皮拱结构钢架的安装方法,该方法的具体步骤如下:
(1)将带蒙皮拱结构钢架构成部件运送到安装现场,先根据图纸按照常规方法先安装楼层钢梁、独立支撑柱和砼结构,使上述结构成为蒙皮支架安装基准和支撑;
(2)根据所述蒙皮拱结构的整体造型及现场配置的吊装机械的起重性能,对于蒙皮拱结构进行模拟分析后分块,将蒙皮拱结构整体转换成拱分块,所述拱分块重量设定根据安装现场吊装机械起重性能,设定时需含20%起吊余量;
(3)通过计算机采用仿真技术将拱分块的CAD三维模型通过旋转方法由空间位置调整到基本水平状态,以保证拱分块拼装最小的胎架高度符合安装要求,同时计算出所述拱分块的三维尺寸和各节点、端头对接接口中心的三维坐标值,作为拱分块拼装控制理论值;并根据其CAD三维模型,找出拱分块空间位置时的重心位置,从而确定安装拱分块的起吊吊点位置;
(4)将拱分块在地面进行拼装,安装拱分块的蒙皮支架和蒙皮;
(5)利用先前已安装完成的楼层钢梁、独立支撑柱和砼结构作为拱分块安装拉设固定物,按照“2下+1上” ,即先安装下部两块拱分块,再安装上部一块拱分块的安装原则,依次安装拱分块,直至全部安装完成;
(6)在安装过程中,测量人员随时跟踪测量定位,控制测量拱分块两侧及上下拱分块所有连接节点定位是否正确。
本发明中公开的方法采用“地面拼装分块再高空安装定位”+“利用既有钢结构作为可靠支承”的方法解决了带蒙皮拱结构安装定位难的问题;再则,采用先安装的楼层钢梁、独立支撑柱和砼结构作为拱分块安装拉设固定物,满足结构支承,降低了施工风险。
有益效果:
与现有技术相比,本发明具有以下优点:
1、本发明所述蒙皮为弧形的钢架结构,拓展了建筑设计的范围,使建筑设计更具有流线型,更富有流动的韵律;增加了建筑设计的多样性;
2、本发明所述方法借助于计算机仿真技术,采用“地面拼装分块再高空安装定位”+“利用既有钢结构作为可靠支承”的方法解决了带蒙皮拱结构安装定位难的问题,本发明所述方法可操作性强,高空安装效率高,同时提高了高空带蒙皮拱结构的安装定位精度,降低了误差率,提高了建筑钢结构的质量,降低了钢结构安装安全风险。。
附图说明
图1是本发明中带蒙皮拱结构钢架的结构示意图。
图2是本发明所述带蒙皮拱结构钢架的结构去掉蒙皮后的结构示意图。
图中:蒙皮支架1、蒙皮2、楼层钢梁3、独立支撑柱4、砼结构5。
具体实施方式
下面结合附图和具体实施例,进一步阐明本发明。
实施例
如图所示的一种带蒙皮拱结构钢架,包括:蒙皮拱结构、楼层钢梁3、独立支撑柱4和砼结构5;所述蒙皮拱结构包括:蒙皮支架1和蒙皮2;
所述蒙皮2为圆弧形;所述砼结构5上安装所述楼层钢梁3;所述楼层钢梁3通过独立支撑柱4固定支撑;所述蒙皮支架1固定在楼层钢梁3,通过楼层钢梁3实现蒙皮支架1的定位支撑;所述蒙皮2固定在蒙皮支架1上。
上述带蒙皮拱结构钢架的安装方法具体步骤如下:
(1)将带蒙皮拱结构钢架构成部件运送到安装现场,先根据图纸按照常规方法先安装楼层钢梁3、独立支撑柱4和砼结构5,使上述结构成为蒙皮支架安装基准和支撑;
(2)根据所述蒙皮拱结构的整体造型及现场配置的吊装机械的起重性能,对于蒙皮拱结构进行模拟分析后分块,将蒙皮拱结构整体转换成拱分块,所述拱分块重量设定根据安装现场吊装机械起重性能,设定时需含20%起吊余量;
(3)通过计算机采用仿真技术将拱分块的CAD三维模型通过旋转方法由空间位置调整到基本水平状态,同时计算出所述拱分块的三维尺寸和各节点、端头对接接口中心的三维坐标值,作为拱分块拼装控制理论值;并根据其CAD三维模型,找出拱分块空间位置时的重心位置,从而确定安装拱分块的起吊吊点位置;
(4)将拱分块在地面进行拼装,安装蒙皮结构;拱分块间铰接处为刚性固定连接;
(5)利用先前已安装完成的楼层钢梁3、独立支撑柱4和砼结构5作为拱分块安装拉设固定物,按照“2下+1上” ,即先安装下部两块拱分块,再安装上部一块拱分块的安装原则,依次安装拱分块,直至全部安装完成;
(6)在安装过程中,测量人员随时跟踪测量定位,控制测量拱分块两侧及上下拱分块所有连接节点定位是否正确。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以作出若干改进,这些改进也应视为本发明的保护范围。

Claims (1)

1.一种带蒙皮拱结构钢架的安装方法,其特征在于:包括:蒙皮拱结构、楼层钢梁(3)、独立支撑柱(4)和砼结构(5);所述蒙皮拱结构包括:蒙皮支架(1)和蒙皮(2);
所述蒙皮(2)为圆弧形;所述砼结构(5)上安装所述楼层钢梁(3);所述楼层钢梁(3)通过独立支撑柱(4)固定支撑;所述蒙皮支架(1)固定在楼层钢梁(3),通过楼层钢梁(3)实现蒙皮支架(1)的定位支撑;所述蒙皮(2)固定在蒙皮支架(1)上;该方法的具体步骤如下:
(1)将带蒙皮拱结构钢架构成部件运送到安装现场,先根据图纸按照常规方法先安装楼层钢梁(3)、独立支撑柱(4)和砼结构(5),使上述结构成为蒙皮支架安装基准和支撑;
(2)根据所述蒙皮拱结构的整体造型及现场配置的吊装机械的起重性能,对于蒙皮拱结构进行模拟分析后分块,将蒙皮拱结构整体转换成拱分块,所述拱分块重量设定根据安装现场吊装机械起重性能,设定时需含20%起吊余量;
(3)通过计算机采用仿真技术将拱分块的CAD三维模型通过旋转方法由空间位置调整到基本水平状态,同时计算出所述拱分块的三维尺寸和各节点、端头对接接口中心的三维坐标值,作为拱分块拼装控制理论值;并根据其CAD三维模型,找出拱分块空间位置时的重心位置,从而确定安装拱分块的起吊吊点位置;
(4)将拱分块在地面进行拼装,安装拱分块的蒙皮支架和蒙皮;
(5)利用先前已安装完成的楼层钢梁(3)、独立支撑柱(4)和砼结构(5)作为拱分块安装拉设固定物,按照“2下+1上” ,即先安装下部两块拱分块,再安装上部一块拱分块的安装原则,依次安装拱分块,直至全部安装完成;
(6)在安装过程中,测量人员随时跟踪测量定位,控制测量拱分块两侧及上下拱分块所有连接节点定位是否正确。
CN201410530851.7A 2014-10-11 2014-10-11 一种带蒙皮拱结构的安装方法 Active CN104389348B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410530851.7A CN104389348B (zh) 2014-10-11 2014-10-11 一种带蒙皮拱结构的安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410530851.7A CN104389348B (zh) 2014-10-11 2014-10-11 一种带蒙皮拱结构的安装方法

Publications (2)

Publication Number Publication Date
CN104389348A CN104389348A (zh) 2015-03-04
CN104389348B true CN104389348B (zh) 2017-08-01

Family

ID=52607301

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410530851.7A Active CN104389348B (zh) 2014-10-11 2014-10-11 一种带蒙皮拱结构的安装方法

Country Status (1)

Country Link
CN (1) CN104389348B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107413948B (zh) * 2017-03-16 2019-06-11 成都飞机工业(集团)有限责任公司 一种复合结构的拉形模及其制造方法
CN111894223B (zh) * 2020-06-24 2023-05-02 上海市建筑装饰工程集团有限公司 大面积多曲面艺术飘带的分件、外加工和安装方法
CN111890507A (zh) * 2020-06-24 2020-11-06 上海市建筑装饰工程集团有限公司 多曲复杂木饰面单元板块的塑形与精准定位加工装置及加工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20108513U1 (de) * 2001-05-21 2001-09-06 Gruber Flux Robert Tribünenüberdachung
DE102007052758A1 (de) * 2006-10-19 2008-04-30 Competents Gmbh Pavillon
CN101213945A (zh) * 2008-01-16 2008-07-09 戴网成 一种节能环保鸡舍
CN201119327Y (zh) * 2007-11-14 2008-09-24 三亚市南繁科学技术研究院 新型水泥镀锌管结构大棚
CN201850793U (zh) * 2010-11-05 2011-06-01 中国电力工程顾问集团西北电力设计院 拱形波纹钢屋盖结构的1000kVGIS室
CN103615118A (zh) * 2013-11-28 2014-03-05 湖北辉创重型工程有限公司 一种大型拱形结构的提升安装方法
CN203613839U (zh) * 2013-12-17 2014-05-28 铱格斯曼航空科技集团有限公司 一种汽车小型充气式车库
CN104032966A (zh) * 2014-06-27 2014-09-10 中国十九冶集团(防城港)设备结构有限公司 弧形双层网架分块吊装高空合拢安装方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20108513U1 (de) * 2001-05-21 2001-09-06 Gruber Flux Robert Tribünenüberdachung
DE102007052758A1 (de) * 2006-10-19 2008-04-30 Competents Gmbh Pavillon
CN201119327Y (zh) * 2007-11-14 2008-09-24 三亚市南繁科学技术研究院 新型水泥镀锌管结构大棚
CN101213945A (zh) * 2008-01-16 2008-07-09 戴网成 一种节能环保鸡舍
CN201850793U (zh) * 2010-11-05 2011-06-01 中国电力工程顾问集团西北电力设计院 拱形波纹钢屋盖结构的1000kVGIS室
CN103615118A (zh) * 2013-11-28 2014-03-05 湖北辉创重型工程有限公司 一种大型拱形结构的提升安装方法
CN203613839U (zh) * 2013-12-17 2014-05-28 铱格斯曼航空科技集团有限公司 一种汽车小型充气式车库
CN104032966A (zh) * 2014-06-27 2014-09-10 中国十九冶集团(防城港)设备结构有限公司 弧形双层网架分块吊装高空合拢安装方法

Also Published As

Publication number Publication date
CN104389348A (zh) 2015-03-04

Similar Documents

Publication Publication Date Title
CN104912340B (zh) 一种双曲面三角铝板单元式挂装吊顶施工工法
CN104389348B (zh) 一种带蒙皮拱结构的安装方法
CN104358410B (zh) 反弧墙模板空间定位控制方法
CN104631684A (zh) 基于混凝土建筑的单层网壳钢结构屋面系统及其组装方法
CN103057662A (zh) 钻井船锚台整体制作工艺及锚台结构
CN107491619A (zh) 一种基于bim技术的旧改项目钢结构定位吊装施工方法
CN204059794U (zh) 一种钢混组合装配式楼梯
CN204356970U (zh) 基于混凝土建筑的单层网壳钢结构屋面系统
CN106760559B (zh) 半球形球冠网壳的安装方法
CN103061514B (zh) 大跨度钢结构连廊施工方法
CN102953554A (zh) 一种大跨度蜂窝形双层网壳结构的安装方法
CN109440987A (zh) 一种超高层建筑的构件式幕墙的施工方法
CN203808281U (zh) 一种井道下挂式转换牛腿的隔震结构
CN105133774A (zh) 组合装配式吊顶反向支撑体系结构及设计安装一体化方法
CN205349372U (zh) 一种小净距盾构叠交隧道可控门型钢架
CN204199691U (zh) 一种螺旋楼梯的扶手浇筑模板结构
CN209323691U (zh) 一种超长超高巨型斜撑
CN203640291U (zh) 建筑主体和外装饰施工用高差可调双层操作平台
CN205742210U (zh) Z型钢牛腿
CN207249988U (zh) 装配式混凝土模拟吊装装置
CN202466902U (zh) 套芯连接的横向装饰线条幕墙系统
CN206581398U (zh) 一种3d模块建筑z型龙骨墙体与梁的连接结构
CN206205401U (zh) 一种不锈钢旋转楼梯施工用组合支架系统
CN205047100U (zh) 一种倾斜蜂窝结构承重通道门
CN205444489U (zh) 一种箱型幕墙柱与结构主桁架连接节点

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 214200 Baijia village, Zhangzhu Town, Yixing City, Wuxi City, Jiangsu Province

Patentee after: JIANGSU HUNING STEEL MECHANISM Co.,Ltd.

Address before: 214200 Baijia village, Zhangzhu Town, Yixing City, Suzhou City, Jiangsu Province

Patentee before: JIANGSU HUNING STEEL MECHANISM Co.,Ltd.