CN104131635A - Method and platform for constructing peripheral shear wall of prefabricated staircase - Google Patents

Method and platform for constructing peripheral shear wall of prefabricated staircase Download PDF

Info

Publication number
CN104131635A
CN104131635A CN201410276140.1A CN201410276140A CN104131635A CN 104131635 A CN104131635 A CN 104131635A CN 201410276140 A CN201410276140 A CN 201410276140A CN 104131635 A CN104131635 A CN 104131635A
Authority
CN
China
Prior art keywords
shear wall
operation platform
rectangular frame
staircase
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410276140.1A
Other languages
Chinese (zh)
Other versions
CN104131635B (en
Inventor
李启涛
梁成佳
袁旭
石辉
尹川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201410276140.1A priority Critical patent/CN104131635B/en
Publication of CN104131635A publication Critical patent/CN104131635A/en
Application granted granted Critical
Publication of CN104131635B publication Critical patent/CN104131635B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

The invention discloses a method and platform for constructing a peripheral shear wall of a prefabricated staircase. The platform comprises a rectangular frame (5) and a steel plate (13), wherein the rectangular frame (5) is formed by welding channel bars, and the steel plate (13) is welded to the rectangular frame (5). A group of long supporting legs (6) and a group of short supporting legs (7) are arranged at the two ends of the rectangular frame (5) respectively and support the rectangular frame (5). A first diagonal bracing (8) and a second diagonal bracing (9) are welded between the rectangular frame (5) and each long supporting leg (6) and between the rectangular frame (5) and each short supporting leg (7) respectively. According to the method and platform for constructing the peripheral shear wall of the prefabricated staircase, the construction process is simple, operation is convenient and rapid, the construction progress of the shear wall is not influenced by the concrete strength of a bridging piece beam, the construction efficiency can be effectively improved, and the construction period can be shortened.

Description

Periphery shear wall construction method and operation platform between a kind of precast stair
Technical field
The present invention relates to periphery shear wall construction method and operation platform between a kind of precast stair, belong to architectural engineering construction technique field.
Background technology
The develop rapidly of modern architecture industry; and Green Architecture Conception is universal; construction party has proposed very high requirement to green construction, implements to concrete aspect, in " green building assessment standard ", propose exactly save land, the requirement of energy-conservation, material-saving, water saving and environmental protection and comfortable space.In building construction process, the normal precast stair that adopts improves construction speed, but because precast stair lifting must lift after bridging piece beam concrete reaches bearing capacity intensity, about about 7 days of time, but after being arranged on 1 day, can install the shear force wall reinforcing steel bar of staircase periphery, reinforcement installation is checked and accepted well rear horse back and is carried out template installation, it is also to complete in 3 days that template is installed consolidation time, therefore, it between the situation that there is no hoisting prefabricated stair is gone downstairs, is exactly a cavity, there is no the operating platform that can allow workman stand, therefore cannot complete the shear force wall reinforcing steel bar of staircase periphery, template is installed, have a strong impact on the construction speed of engineering.In order to address this problem, the construction method of traditional staircase periphery shear wall is: adopt fastener type steel pipe scaffold to set up an operating platform at staircase, reinforcing bar and the template of utilizing this platform to carry out staircase periphery shear wall are installed, complete after shear wall concreting form removal, also need this operating platform to remove, in the time carrying out between last layer stair periphery shear wall construction, need organize workman again to set up new operating platform, set up the required steel tube fastener of platform and also have the materials such as plank to adopt tower crane to hang operation layer.Therefore, not only operation is more loaded down with trivial details for existing staircase periphery shear wall construction method, waste of manpower and financial resources, and also the process of setting up platform can waste the precious time, and affects construction speed.
Summary of the invention
The object of the invention is to, provide a kind of working procedure simple, convenient to operation, and be not subject to bridging piece beam concrete strength to affect the construction speed of shear wall, can effectively improve periphery shear wall construction method and operation platform between the precast stair of efficiency of construction, to overcome prior art deficiency.
Technical scheme of the present invention: a kind of periphery shear wall construction method between precast stair, comprise existing shear wall formwork construction method, in the time that the bridging piece beam concrete of newly building floor does not reach the bearing capacity intensity that precast stair is installed, lift an operation platform with newly building in the staircase of floor building floor in advance, described operation platform can be by complete the staircase in original cavity capping, constructor can stand on this operation platform staircase periphery shear wall is carried out to reinforced-bar binding and template installation, after newly building the reinforced-bar binding and template installation of shear wall on floor, just can build the concrete of this story shear wall, after treating the concrete curing of shear wall, constructor may stand in equally on this operation platform staircase periphery shear wall formwork is removed, then adopt tower crane that operation platform is hung away, be used for the construction of the staircase periphery shear wall of upper strata floor,
The height of described operation platform is higher than newly building floor upper surface 10~20cm.
A kind of operation platform for periphery shear wall construction method between above-mentioned precast stair, comprise and adopt the rectangular frame of channel bar welding and be welded on the steel plate on rectangular frame, adopt respectively group leader's supporting leg and one group of short supporting leg to be supported at the two ends of rectangular frame, and between rectangular frame and long leg and between rectangular frame and short supporting leg, be welded with respectively the first diagonal brace and the second diagonal brace;
Described rectangular frame both sides are connected with one group of turnover panel symmetrically by hinge;
Described rectangular frame both sides of the edge are welded with two groups of suspension ring symmetrically;
Described turnover panel is provided with shape of a hoof breach in the position of welding hanging ring;
Between described long leg, be welded with a cross bar.
Compared with prior art, the invention has the advantages that: the present invention is not in the time that the bridging piece beam concrete of newly building floor reaches the bearing capacity intensity that precast stair is installed, reinforcing bar and template that constructor cannot utilize precast stair to carry out staircase periphery shear wall are installed, in order to speed up the work, the present invention lifts an operation platform with newly building in the staircase of floor building floor in advance, this operation platform is monolithic operation platform, utilize this operation platform by complete the staircase in original cavity capping, therefore, constructor may stand in reinforcing bar and the template installation of on this platform, carrying out staircase periphery shear wall, after this operation platform is finished using, hung away by tower crane, continue on for the construction of the staircase periphery shear wall of upper strata floor.Therefore, adopt the present invention to carry out periphery shear wall construction between precast stair, working procedure is simple, and does not repeat to set up scaffolding platform, convenient to operation, effectively improves construction speed., after disposable the completing of operation platform in the present invention, can reuse meanwhile, save material.
Brief description of the drawings
Fig. 1 is the front view that in the present invention, operation platform is implemented schematic diagram;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is the lateral view of operation platform in the present invention.
Description of reference numerals: 1-precast stair, 2-has built floor, and 3-newly builds floor, 4-shear wall, 5-rectangular frame, 6-long leg, the short supporting leg of 7-, 8-the first diagonal brace, 9-the second diagonal brace, 10-suspension ring, 11-turnover panel, 12-staircase, 13-steel plate, 14-hinge, 15-cross bar.
Detailed description of the invention
In order to make the object of the invention, technical scheme and advantage clearer, below in conjunction with drawings and Examples, the present invention is described in further detail.Should be appreciated that specific embodiment described herein, only for explaining the present invention, is not intended to limit the present invention.
While adopting the present invention to carry out between precast stair periphery shear wall construction, first the size between the precast stair of job site is measured, comprising the vertical height of length, width and the precast stair of staircase, and then determine the size of needed operation platform.The step of making operation platform of the present invention comprises a rectangular frame 5 of employing channel bar welding, then on rectangular frame 5, weld a steel plate 13 that 3mm is thick, by complete rectangular frame 5 capping, adopt respectively group leader's supporting leg 6 and one group short supporting leg 7 by its support at the two ends of rectangular frame 5 simultaneously, and between rectangular frame 5 and long leg 6 and between rectangular frame 5 and short supporting leg 7, be welded with respectively the first diagonal brace 8 and the second diagonal brace 9, and between long leg 6, weld a cross bar 15, in order to strengthen the rigidity of whole operation platform; Then connect symmetrically one group of turnover panel 11 in rectangular frame 5 both sides by hinge 14, and be welded with symmetrically two groups of suspension ring 10 in rectangular frame 5 both sides of the edge; For turnover panel 11 can freely be overturn on rectangular frame 5, described turnover panel 11 is provided with shape of a hoof breach in the position of welding hanging ring 10, thereby avoids suspension ring 10.
After operation platform of the present invention completes, for accelerating construction progress, can be in the time that the bridging piece beam concrete of newly building floor 3 reach the bearing capacity intensity that precast stair 1 is installed, building floor 2 and this operation platform of the interior lifting of staircase 12 of newly building floor 3 in advance, after operation platform lifts, the height of operation platform is now higher than newly building floor 3 upper surface 10cm, the lifting of constructability platform later stage, then open the turnover panel 11 on operation platform, make operation platform by complete the staircase in original cavity 12 capping, therefore, constructor can stand on this operation platform staircase 12 periphery shear walls 4 are carried out to reinforced-bar binding and template installation, easy construction safety.After the reinforced-bar binding and template installation of shear wall 4 on newly building floor 3, just can build the concrete of this story shear wall 4, after treating the concrete curing of shear wall 4, constructor may stand on this operation platform equally by staircase 12 periphery shear wall 4 form removables, then adopt tower crane that operation platform is hung away, continue on for the construction of the staircase periphery shear wall of upper strata floor; Finally, precast stair is lifted on and builds floor 2 and newly build in the staircase 12 of floor 3, complete whole staircase periphery shear wall construction process.

Claims (7)

1. periphery shear wall construction method between a precast stair, comprise existing shear wall formwork construction method, it is characterized in that: in the time that the bridging piece beam concrete of newly building floor (3) does not reach the bearing capacity intensity that precast stair (1) is installed, lift an operation platform with newly building in the staircase (12) of floor (3) building floor (2) in advance, described operation platform can be by the staircase in original cavity (12) capping completely, constructor stands on this operation platform staircase (12) periphery shear wall (4) is carried out to reinforced-bar binding and template installation, after newly building the reinforced-bar binding and template installation of the upper shear wall (4) of floor (3), just can build the concrete of this story shear wall (4), after treating the concrete curing of shear wall (4), constructor may stand on this operation platform equally by staircase (12) periphery shear wall (4) form removable, then adopt tower crane that operation platform is hung away, continue on for the construction of the staircase periphery shear wall of upper strata floor.
2. periphery shear wall construction method between precast stair according to claim 1, is characterized in that: the height of described operation platform is higher than newly building floor (3) upper surface 10~20cm.
3. the operation platform for periphery shear wall construction method between the precast stair described in claim 1 or 2, comprise and adopt the rectangular frame (5) of channel bar welding and be welded on the steel plate (13) on rectangular frame (5), it is characterized in that: adopt respectively group leader's supporting leg (6) and one group of short supporting leg (7) to be supported at the two ends of rectangular frame (5), and between rectangular frame (5) and long leg (6) and between rectangular frame (5) and short supporting leg (7), be welded with respectively the first diagonal brace (8) and the second diagonal brace (9).
4. operation platform according to claim 3, is characterized in that: described rectangular frame (5) both sides are connected with one group of turnover panel (11) symmetrically by hinge (14).
5. operation platform according to claim 3, is characterized in that: described rectangular frame (5) both sides of the edge are welded with two groups of suspension ring (10) symmetrically.
6. operation platform according to claim 4, is characterized in that: described turnover panel (11) is provided with shape of a hoof breach in the position of welding hanging ring (10).
7. operation platform according to claim 3, is characterized in that: between described long leg (6), be welded with a cross bar (15).
CN201410276140.1A 2014-06-20 2014-06-20 Method and platform for constructing peripheral shear wall of prefabricated staircase Active CN104131635B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410276140.1A CN104131635B (en) 2014-06-20 2014-06-20 Method and platform for constructing peripheral shear wall of prefabricated staircase

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410276140.1A CN104131635B (en) 2014-06-20 2014-06-20 Method and platform for constructing peripheral shear wall of prefabricated staircase

Publications (2)

Publication Number Publication Date
CN104131635A true CN104131635A (en) 2014-11-05
CN104131635B CN104131635B (en) 2017-05-17

Family

ID=51804473

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410276140.1A Active CN104131635B (en) 2014-06-20 2014-06-20 Method and platform for constructing peripheral shear wall of prefabricated staircase

Country Status (1)

Country Link
CN (1) CN104131635B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790564A (en) * 2014-12-01 2015-07-22 中国建筑股份有限公司 Assembly type concrete stairwell external wall structure and construction method thereof
CN110397267A (en) * 2019-07-15 2019-11-01 五冶集团上海有限公司 Staircase shear wall formwork installation method
CN113047548A (en) * 2021-03-10 2021-06-29 陕西华山建设集团有限公司 Hoisting construction method for steel stairs in irregular plate column shear wall structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102168483A (en) * 2011-03-23 2011-08-31 浙江南湖建设有限公司 Flexible construction platform of suspension cable
CN202170629U (en) * 2011-07-07 2012-03-21 中建三局第一建设工程有限责任公司 Stair hall operation platform
CN102839812A (en) * 2012-09-13 2012-12-26 中建三局建设工程股份有限公司 Intelligent construction platform for construction of super high-rise building
CN203924652U (en) * 2014-06-20 2014-11-05 中国建筑第四工程局有限公司 The operation platform of periphery shear wall between a kind of precast stair

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102168483A (en) * 2011-03-23 2011-08-31 浙江南湖建设有限公司 Flexible construction platform of suspension cable
CN202170629U (en) * 2011-07-07 2012-03-21 中建三局第一建设工程有限责任公司 Stair hall operation platform
CN102839812A (en) * 2012-09-13 2012-12-26 中建三局建设工程股份有限公司 Intelligent construction platform for construction of super high-rise building
CN203924652U (en) * 2014-06-20 2014-11-05 中国建筑第四工程局有限公司 The operation platform of periphery shear wall between a kind of precast stair

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790564A (en) * 2014-12-01 2015-07-22 中国建筑股份有限公司 Assembly type concrete stairwell external wall structure and construction method thereof
CN104790564B (en) * 2014-12-01 2017-03-22 中国建筑股份有限公司 Assembly type concrete stairwell external wall structure and construction method thereof
CN110397267A (en) * 2019-07-15 2019-11-01 五冶集团上海有限公司 Staircase shear wall formwork installation method
CN113047548A (en) * 2021-03-10 2021-06-29 陕西华山建设集团有限公司 Hoisting construction method for steel stairs in irregular plate column shear wall structure
CN113047548B (en) * 2021-03-10 2022-04-29 陕西华山建设集团有限公司 Hoisting construction method for steel stairs in irregular plate column shear wall structure

Also Published As

Publication number Publication date
CN104131635B (en) 2017-05-17

Similar Documents

Publication Publication Date Title
CN105863253B (en) Integral formwork support is asynchronous to pour staircase wall column formwork system and construction method
CN103790423B (en) Large-sized concrete silo construction method
CN103485574B (en) A kind of granulation tower tower top structure of reinforced concrete method
CN103276894A (en) Support system of large-cross-section girder transfer floor of hollow floor system and construction technology
CN210659200U (en) High-rise building elevator shaft operation platform
CN104131635B (en) Method and platform for constructing peripheral shear wall of prefabricated staircase
CN202064281U (en) Slip form frame
CN104675112A (en) Steel stair formwork and constructing method for once pouring forming of building staircase
CN106869479A (en) Bailey bracket sliding formwork system construction method
CN203924652U (en) The operation platform of periphery shear wall between a kind of precast stair
CN213836318U (en) Bridge floor wet joint hangs mould structure
CN110847113A (en) Cast-in-place deep arc type wave wall construction method based on sliding formwork
CN206829603U (en) A kind of device for quick and precisely installing flue arch top template
CN211714541U (en) Special handling frame for installing shear wall template in elevator shaft
CN105370027A (en) Construction method for integrally lifted and supported steel platform structure in high-rise suspended structure
CN106193578B (en) It is a kind of that modular system and construction technology are matched somebody with somebody based on groove type quarter bend
CN213806505U (en) Shaping operation platform in elevator shaft
CN214885471U (en) Operating platform jacking device used during construction of outer cylinder wall of square chimney
CN201339320Y (en) High-altitude overhanging hanging reinforced concrete hanging bracket
CN203320922U (en) Supporting device for forming of elevator shaft template
CN110883920B (en) Prefabricated T roof beam self-propelled hydraulic pressure template device and template system
CN204225503U (en) Large span steel truss high altitude bulk conversion beam moulding bed
CN204626965U (en) For the steel stair template of poured up at a time between architectural stair
CN110118014B (en) Exterior wall template system free of exterior scaffold and construction method thereof
CN206034950U (en) A early tear support open for building templates

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant