CN110397267A - Staircase shear wall formwork installation method - Google Patents
Staircase shear wall formwork installation method Download PDFInfo
- Publication number
- CN110397267A CN110397267A CN201910634579.XA CN201910634579A CN110397267A CN 110397267 A CN110397267 A CN 110397267A CN 201910634579 A CN201910634579 A CN 201910634579A CN 110397267 A CN110397267 A CN 110397267A
- Authority
- CN
- China
- Prior art keywords
- shear wall
- template
- staircase
- wall formwork
- installation method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/06—Tying means; Spacers ; Devices for extracting or inserting wall ties
- E04G17/065—Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
A kind of staircase shear wall formwork installation method, characterized by the following steps: a, unwrapping wire positioning, b, a side template in stair in place is installed, c, installation support, d, it is inserted into through-wall bolt and casing, e, the outer side template of stair in place and Screw arbor with nut at both-ends are installed, f, adjust template position, fasten through-wall bolt, g, fixed support, check calibration, h, check and accept and deliver next process construction: staircase shear wall formwork makes a report on associated acceptance solid data on the basis of self-test qualification after being installed, next process construction is carried out after each side's responsible party's acceptance(check).Staircase shear wall formwork installation method of the invention is simple with template-setup structure, facilitates operation, construction quality is safe and reliable, the advantages of shear wall lap-joint at stair rise mould, spillage and inconsistent phenomenon occurs, improves staircase shear wall surface concrete entity impression quality is prevented.
Description
Technical field
The present invention relates to a kind of concrete mould method of plate installation, specifically, being a kind of staircase shear wall formwork installation
Method.
Background technique
Staircase shear wall formwork conventional mounting technique, generallys use steel pipe support, and complicated for operation, Screw arbor with nut at both-ends is difficult to
Fastening causes to reinforce not in place there are gap, staircase shear wall upper and lower level lap-joint occurs and rises the quality such as mould, spillage, dislocation
Common fault.
Therefore known staircase shear wall formwork conventional mounting mode there are problems that it is above-mentioned various inconvenient and.
Summary of the invention
The purpose of the present invention is to propose a kind of improved staircase shear wall formwork installation method.
To achieve the above object, the technical solution of the invention is as follows:
A kind of staircase shear wall formwork installation method, be suitable for industry with the wide 200-400mm in civil buildings main structure section,
Staircase shear wall within high 4200mm, it is characterised in that the following steps are included:
A, unwrapping wire positions: releasing control line according to building axis line and staircase shear wall installs sideline;
B, a side template in stair in place is installed: ordering pressure foot by unwrapping wire position, then carries out the assembly of template, in installation
It is inserted into through-wall bolt and casing, the stupefied wood of template uses the edge-on vertical array of flitch, spacing 200mm, and flitch should cover in column on side
The vertical piece of template;
C, the pull rod or diagonal brace of installation staircase shear wall formwork, side form in staircase installation support: are required according to stencil design
Diagonal brace is arranged in plate, and corrects its flatness, verticality in installation;
D, through-wall bolt and casing are inserted into: to guarantee shear wall body construction quality, it is necessary to install cushion block of concrete bar protective layer, cushion block
For mortar block or plastic clasp, pad thickness is different because of engineering position difference, and cushion block is arranged to quincunx, and through-wall bolt should be by
It is arranged according to the designed spacing of special scheme, horizontal, smooth vertical and horizontal vertically at line, spacing is uniform;
E, the outer side template of stair in place and Screw arbor with nut at both-ends are installed: needed on the outside of stair with pre-buried nail fixation starting board flitch, then into
The assembly of row template, is inserted into through-wall bolt and casing in installation, forms table using Screw arbor with nut at both-ends drawknot double steel pipe;
F, adjust template position, fastening through-wall bolt: template, which installs, checks that whether securely a fastener, bolt, drawing shore,
Whether template splicing and bottom edge are tight, should reinforce rechecking template position and verticality, guarantee that perpendicularity deviation is allowing partially up and down
Poor range;
G, fixed support, check calibration: check the verticality of shear wall formwork, thickness of wall body, whether protective layer thickness meets sets
Meter and code requirement, after satisfaction can fixed form support, side fixed edge calibration;
H, check and accept and deliver next process construction: staircase shear wall formwork is made a report on the basis of self-test qualification after being installed
Associated acceptance solid data carries out next process construction after each side's responsible party's acceptance(check).
Staircase shear wall formwork installation method of the invention can also be further achieved by the following technical measures.
Method above-mentioned, wherein the template uses glued board.
Method above-mentioned, wherein the flitch specification is 40 × 90mm.
Method above-mentioned wherein the Screw arbor with nut at both-ends cooperates double steel pipe in wall, and separately increases φ 14mm again in column
Screw arbor with nut at both-ends, φ 20mmPVC pipe are reinforced;.
Method above-mentioned, wherein the road table Zhong Di table is preferably close to ground, the intermediate vertical spacing of tie is not more than
The setting of 500mm equity, upper track tie is from beam bottom 200mm.
After adopting the above technical scheme, staircase shear wall formwork installation method of the invention has the advantage that
1, template-setup structure is simple, facilitates operation;
2, construction quality is safe and reliable, has prevented shear wall lap-joint at stair and rise mould, spillage and inconsistent phenomenon has occurred, has improved building
Shear wall surface concrete entity impression quality between ladder.
Detailed description of the invention
Fig. 1 is the staircase shear wall formwork setting structure schematic diagram of the embodiment of the present invention;
Fig. 2 is the side view of Fig. 1.
In figure: 1 double steel pipe, 2 Screw arbor with nut at both-ends, 3 outboard templates, 4 flitches, 5 inner side templates, 6 staircase half spaces.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
Staircase shear wall formwork installation process of the invention:
Template places built-in fitting → installation inner side template in place → installation supports → and is inserted into through-wall bolt and casing etc. → installation just
Position outboard template and support → adjustment template position → fastening through-wall bolt → fixation support → inspection corrects → connect adjacent mould
Plate → do preliminary examination.
It is wide with civil buildings main structure section to be suitable for industry to staircase shear wall formwork installation method of the invention
Staircase shear wall within 200-400mm, high 4200mm, comprising the following steps:
A, unwrapping wire positions: releasing control line according to building axis line and staircase shear wall installs sideline.
B, a side template in stair in place is installed, template uses glued board.
It is the staircase shear wall formwork setting structure schematic diagram of the embodiment of the present invention, figure referring now to Fig. 1 and Fig. 2, Fig. 1
2 be the side view of Fig. 1.As shown, ordering pressure foot by unwrapping wire position, the assembly of template is then carried out, is inserted into installation
Through-wall bolt and casing, the specification and spacing of through-wall bolt should design consistent with template special scheme.
C, installation support: the pull rod or diagonal brace of installation staircase shear wall formwork are required according to stencil design, in staircase
Side template 5 can directly add diagonal brace, and correct its flatness, verticality in installation.The arrangement of diagonal brace should be by template special scheme
Design time is away from the installation such as technical requirements.It is staircase half space 6 between two inner side templates 5.
D, through-wall bolt and casing etc. are inserted into: to guarantee shear wall body construction quality, it is necessary to install cover to reinforcement pad
Block, cushion block are mortar block or plastic clasp.Pad thickness is different because of engineering position difference, cushion block be arranged to it is quincunx, it is through walls
Bolt should be arranged according to the designed spacing of special scheme, and horizontal, smooth vertical and horizontal vertically at line, spacing is uniform.
E, stair outboard template 3 in place and pull rod are installed: needed on the outside of stair with pre-buried nail fixation starting board flitch 4, then into
The assembly of row template is inserted into through-wall bolt and casing in installation, and the specification and spacing of through-wall bolt should be by template special schemes
Design time is away from the installation such as technical requirements.The flitch specification is 40 × 90mm.
F, adjust template position, fastening through-wall bolt: template install check a fastener, bolt, drawing shore whether
Securely, whether template splicing and bottom edge are tight.Preferably close to ground, the intermediate vertical spacing of tie is not more than the road table Zhong Di table
The setting of 500mm equity, upper track tie is from beam bottom 200mm.
G, fixed support, check calibration: check whether the verticality of shear wall formwork, thickness of wall body, protective layer thickness full
Foot design and code requirement, after satisfaction can fixed form support, side fixed edge calibration.The Screw arbor with nut at both-ends cooperates in wall
Double steel pipe 1, and separately increase φ 14mm Screw arbor with nut at both-ends 2, φ 20mmPVC pipe are reinforced again in column.
H, check and accept deliver next process construction: staircase shear wall formwork be installed after self-test qualification on the basis of
Associated acceptance solid data is made a report on, next process construction is carried out after each side's responsible party's acceptance(check).
Staircase form height is higher in staircase shear wall formwork installation of the invention, and floor is stretched out on inner side template top
Half floor height of face need to construct on scaffold when close to the shear wall concreting of scaffold side, should Strengthen Safety Management, foot
Constructing number in hand cradle should not be excessive.And vibrate comprehensively on concrete and have certain influence, should carefully vibrate staircase in construction
Shear wall concrete.Because construction technology needs, the side template of staircase cannot be with this story shear wall side form premature removal, should be to upper
Layer staircase shear wall concreting rear is dismountable.
The present invention has substantive distinguishing features and significant technological progress, staircase shear wall formwork installation method of the invention
Efficiently solving occur rising in industry and the construction of Civil structure staircase shear wall conventional template mould, spillage leads to concrete
The advantages that bad influence of body structure surface perception has consolidation effect good, facilitates operation, and processing and fabricating is simple, overcomes staircase
The disadvantages of reinforcing of shear wall conventional template is cumbersome, influences quality and slow speed of application.It is improved and is imitated according to practice of construction process template
Fruit has prevented shear wall lap-joint at stair and rise mould, spillage and inconsistent phenomenon has occurred, improves staircase shear wall surface coagulation
Native entity impression quality.
Staircase shear wall formwork installation method of the invention is in Shangli County urbanization infrastructure construction PPP project Kingsoft
It is used in town Kingsoft placement cellular engineering, significant effect has obtained construction authorities, construction unit and supervisor and sufficiently agreed
It is fixed.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field
Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent
Technical solution also should belong to scope of the invention, should be limited by each claim.
Claims (5)
1. a kind of staircase shear wall formwork installation method is suitable for industry and the wide 200- in civil buildings main structure section
Staircase shear wall within 400mm, high 4200mm, it is characterised in that the following steps are included:
A, unwrapping wire positions: releasing control line according to building axis line and staircase shear wall installs sideline;
B, a side template in stair in place is installed: ordering pressure foot by unwrapping wire position, then carries out the assembly of template, in installation
It is inserted into through-wall bolt and casing, the stupefied wood of template uses the edge-on vertical array of flitch, spacing 200mm, and flitch should cover in column on side
The vertical piece of template;
C, the pull rod or diagonal brace of installation staircase shear wall formwork, side form in staircase installation support: are required according to stencil design
Diagonal brace is arranged in plate, and corrects its flatness, verticality in installation;
D, through-wall bolt and casing are inserted into: to guarantee shear wall body construction quality, it is necessary to install cushion block of concrete bar protective layer, cushion block
For mortar block or plastic clasp, pad thickness is different because of engineering position difference, and cushion block is arranged to quincunx, and through-wall bolt should be by
It is arranged according to the designed spacing of special scheme, horizontal, smooth vertical and horizontal vertically at line, spacing is uniform;
E, the outer side template of stair in place and Screw arbor with nut at both-ends are installed: needed on the outside of stair with pre-buried nail fixation starting board flitch, then into
The assembly of row template, is inserted into through-wall bolt and casing in installation, forms table using Screw arbor with nut at both-ends drawknot double steel pipe;
F, adjust template position, fastening through-wall bolt: template, which installs, checks that whether securely a fastener, bolt, drawing shore,
Whether template splicing and bottom edge are tight, should reinforce rechecking template position and verticality, guarantee that perpendicularity deviation is allowing partially up and down
Poor range;
G, fixed support, check calibration: check the verticality of shear wall formwork, thickness of wall body, whether protective layer thickness meets sets
Meter and code requirement, after satisfaction can fixed form support, side fixed edge calibration;
H, check and accept and deliver next process construction: staircase shear wall formwork is made a report on the basis of self-test qualification after being installed
Associated acceptance solid data carries out next process construction after each side's responsible party's acceptance(check).
2. staircase shear wall formwork installation method as described in claim 1, which is characterized in that the template is using glued
Plate.
3. staircase shear wall formwork installation method as described in claim 1, which is characterized in that the flitch specification be 40 ×
90mm。
4. staircase shear wall formwork installation method as described in claim 1, which is characterized in that the Screw arbor with nut at both-ends is in wall
Middle cooperation double steel pipe, and separately increase φ 14mm Screw arbor with nut at both-ends, φ 20mmPVC pipe are reinforced again in column;.
5. staircase shear wall formwork installation method as described in claim 1, which is characterized in that the road table Zhong Di wall
Hoop is preferably close to ground, and the intermediate vertical spacing of tie is arranged no more than 500mm equity, and upper track tie is from beam bottom 200mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910634579.XA CN110397267A (en) | 2019-07-15 | 2019-07-15 | Staircase shear wall formwork installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910634579.XA CN110397267A (en) | 2019-07-15 | 2019-07-15 | Staircase shear wall formwork installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110397267A true CN110397267A (en) | 2019-11-01 |
Family
ID=68325438
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910634579.XA Pending CN110397267A (en) | 2019-07-15 | 2019-07-15 | Staircase shear wall formwork installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110397267A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114703986A (en) * | 2022-04-02 | 2022-07-05 | 东莞职业技术学院 | High-rise staircase shear wall pouring method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103821361A (en) * | 2014-03-03 | 2014-05-28 | 永升建设集团有限公司 | Improved construction method for casting staircase studding formwork by grading |
CN103967271A (en) * | 2014-05-27 | 2014-08-06 | 安徽华力建设集团有限公司 | Formwork combination reinforcing and supporting structure used in short-leg shear wall construction and construction method thereof |
CN104131635A (en) * | 2014-06-20 | 2014-11-05 | 中国建筑第四工程局有限公司 | Method and platform for constructing peripheral shear wall of prefabricated staircase |
-
2019
- 2019-07-15 CN CN201910634579.XA patent/CN110397267A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103821361A (en) * | 2014-03-03 | 2014-05-28 | 永升建设集团有限公司 | Improved construction method for casting staircase studding formwork by grading |
CN103967271A (en) * | 2014-05-27 | 2014-08-06 | 安徽华力建设集团有限公司 | Formwork combination reinforcing and supporting structure used in short-leg shear wall construction and construction method thereof |
CN104131635A (en) * | 2014-06-20 | 2014-11-05 | 中国建筑第四工程局有限公司 | Method and platform for constructing peripheral shear wall of prefabricated staircase |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114703986A (en) * | 2022-04-02 | 2022-07-05 | 东莞职业技术学院 | High-rise staircase shear wall pouring method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109208790B (en) | Single-side formwork erecting construction method for arc shear wall | |
CN108385980A (en) | Deformation joint shear wall set shaped steel formwork installs unidirectional fastening screw construction method | |
CN103821364A (en) | Method for constructing reinforced concrete pond | |
US20060185293A1 (en) | Wall form support apparatus and method | |
CN108894488A (en) | A kind of construction method of Novel section steel keel steel and wood composite template | |
CN103061505A (en) | Multifunctional split bolt and application thereof | |
CN105178604A (en) | Construction method of assembly type superimposed floor slab | |
CN110700570A (en) | Construction method of cast-in-place concrete curved surface inclined cylinder structure | |
CN103821361B (en) | Stair studding formwork construction method is built in the gradation improved | |
CN108457469A (en) | A kind of concrete structure construction method with assembled masonry filler wall | |
CN101614039B (en) | Inverted construction method for template engineering of cast-in-place shear wall structure system | |
CN110397267A (en) | Staircase shear wall formwork installation method | |
CN103590420A (en) | Top-formwork-erection-free construction method of coke oven base smoke dividing flue | |
CN102444275A (en) | Silo flexible slip form torsion resistance construction device | |
CN101967884B (en) | Method for controlling concrete planeness of large-area steel bar truss template | |
CN110777635A (en) | Side arch rib construction method and side arch rib | |
CN103174155A (en) | Reverse construction method for erecting steel column and pouring concrete foundation later and steel support for construction | |
CN110905202A (en) | Wall formwork perpendicularity adjusting assembly and construction method thereof | |
CN111236632A (en) | Construction method of heavy bracket and profile steel combined supporting system for super-thick top plate | |
CN103243731B (en) | Mould supporting method for trapezoid cross section base of shear wall | |
CN108979137A (en) | The assembling and disassembling construction method of Round Concrete column composite wooden template | |
CN111379337B (en) | Secondary structure anti-seepage and anti-leakage construction method | |
KR101728161B1 (en) | Flatness pad for installation truss girder type deck panels and ceiling mold structure using there of | |
CN105002926B (en) | Parabasal plate alignment method for mounting large equipment | |
CN210396122U (en) | Stair inclined plate type stadium stand template reinforcing system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191101 |