CN104074195A - Method for controlling sedimentation of ground outside foundation pit through horizontal grouting - Google Patents

Method for controlling sedimentation of ground outside foundation pit through horizontal grouting Download PDF

Info

Publication number
CN104074195A
CN104074195A CN201410344924.3A CN201410344924A CN104074195A CN 104074195 A CN104074195 A CN 104074195A CN 201410344924 A CN201410344924 A CN 201410344924A CN 104074195 A CN104074195 A CN 104074195A
Authority
CN
China
Prior art keywords
foundation pit
grouting
horizontal
ground
surface settlement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410344924.3A
Other languages
Chinese (zh)
Other versions
CN104074195B (en
Inventor
吴才德
沈俊杰
王洁栋
方宝民
安然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Huazhan Research And Design Institute Co ltd
Original Assignee
Zhejiang Huazhan Engineering Research & Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Huazhan Engineering Research & Design Institute Co Ltd filed Critical Zhejiang Huazhan Engineering Research & Design Institute Co Ltd
Priority to CN201410344924.3A priority Critical patent/CN104074195B/en
Publication of CN104074195A publication Critical patent/CN104074195A/en
Application granted granted Critical
Publication of CN104074195B publication Critical patent/CN104074195B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention provides a method for controlling the sedimentation of ground outside a foundation pit through horizontal grouting. According to the method, horizontal sealed tubes are embedded in a diaphragm wall in advance when the diaphragm wall is constructed; during the foundation pit excavation process, when the ground sediments greatly, in the positions, where the sealed tubes are embedded in advance or in the preset grouting positions of support pile seams, a grouting pipe is horizontally embedded in soil in an active region, and then horizontal grouting is performed from the interior of the foundation pit to the soil in the active region outside the foundation pit. According to the invention, horizontal grouting is performed from inside to outside of the foundation pit, so that ground loss of the active region can be compensated, and the sedimentation of soil outside the foundation pit can be reduced; in addition, the horizontal pipes are embedded in advance, and real-time and layered horizontal grouting can be performed according to the conditions of sedimentation of the soil outside the foundation pit and the foundation pit excavation working condition, so that the sedimentation of ground outside the foundation pit can be effectively controlled in real time.

Description

A kind of method of controlling the outer surface settlement of foundation ditch by horizontal grouting
Technical field
The present invention relates to a kind of method of controlling the outer surface settlement of foundation ditch, specifically during a kind of excavation of foundation pit by soldier pile within the walls side direction foundation ditch implement layering horizontal grouting outward to control the method for surface settlement.
Background technology
In Soft Deep Foundation Pit digging process, due to the displacement of supporting piling wall, hole end uplift of soil, foundation pit dewatering etc., foundation ditch there will be Stratum Loss outward, produces surface settlement.In base pit engineering, generally take to strengthen supporting piling wall building-in depth, increase support stiffness, reinforce the method control surface settlement such as the passive area soil body, subregion piecemeal excavation.But said method is all " controlling in advance " to surface settlement, once monitored data shows the outer soil body rate of settling in hole, has enlarged markedly or produced larger sedimentation, and said method is all difficult to control timely and effectively surface settlement again.
Slip casting method is mainly used in stratum consolidation, surrounding enviroment protection tracking grouting, the aspects such as leak stopping of speedily carrying out rescue work in base pit engineering.Aspect surrounding enviroment protection tracking grouting; tracking grouting can be compensated Stratum Loss slip casting, passive area slip casting or be corrected the distortion that foundation ditch Adjacent Buildings, pipeline etc. are controlled in distortion slip casting effectively by active region; no matter but any tracking grouting mode, existing tracking grouting is all vertical slip casting or oblique slip casting.While controlling surface settlement, settlement Control scope is larger, if adopt vertical or oblique slip casting, the row of injected hole can increase a lot, and slip casting operates outward at foundation ditch, needs enough foundation ditches construction space outward.
Summary of the invention
In order to overcome the deficiency of the outer ground of existing control foundation ditch sedimentation method, the invention provides a kind of method of controlling surface settlement by horizontal grouting, the method when surface settlement is larger outside hole, can promptly be brought into play the effect of control surface settlement.
In Excavation Process, deep soil is realized existing Stratum Loss, in the larger region of Stratum Loss, carries out horizontal grouting, and slurries can play the effect of filling, compensation active region Stratum Loss; The grouting pressure producing during slip casting can make the injected hole top soil body have on certain to lift, and then reduces ground settlement; In addition, injecting cement paste is equivalent to the effect of reinforced earth to a certain extent, can improve the outer soil deformation characteristic in hole.
The technical solution adopted in the present invention is: during ground-connecting-wall fabrication of reinforcing cage, in the default slip casting of ground-connecting-wall position, horizontal seal pipe is installed; During ground-connecting-wall construction, horizontal seal pipe is followed reinforcing cage and is together transferred; Concreting subsequently, completes the pre-buried process of sealed tube.In soil excavation process, when surface settlement is larger, on ground-connecting-wall, pre-buried sealed tube position is inserted Grouting Pipe level in the active region soil body, carries out subsequently horizontal grouting; According to excavation of foundation pit operating mode, respectively in soldier pile diverse location carrying out horizontal slip casting within the walls.When foundation ditch adopts soldier pile supporting, horizontal grouting position is arranged on soldier pile stake seam place, when surface settlement is larger, can directly in default slip casting position, carry out horizontal grouting.
Compared with prior art, the invention has the beneficial effects as follows, can realize layering horizontal grouting according to excavation of foundation pit operating mode, and in foundation ditch, the horizontal grouting execution conditions outside foundation ditch are desirable, without the outer construction space of foundation ditch, workable.
Accompanying drawing explanation
Below in conjunction with accompanying drawing and example, the present invention is further described.
Fig. 1 controls the drawing in side sectional elevation of the surface settlement that excavation of foundation pit causes by horizontal grouting.
Fig. 2 controls the longitudinal plan of the surface settlement that excavation of foundation pit causes by horizontal grouting.
1. roads in figure, 2. ground-connecting-wall, 3. horizontal seal pipe, 4. injecting cement paste, 5. grit, 6. support, 7. base plate.
The specific embodiment
According to the protection of foundation ditch surrounding enviroment (1), require to determine pre-range of grouting, according to the excavation of foundation pit degree of depth, support arrangement situation, construction convenience etc., the position of horizontal grouting point is arranged on to each layer of support (6) top.At ground-connecting-wall (2) predeterminated position, pre-buried horizontal seal pipe (3) and ground-connecting-wall reinforcing cage are connected and fixed, horizontal tube two ends should seal reliably, when preventing ground-connecting-wall disturbing concrete, concrete enters steel pipe, after treating ground-connecting-wall grooving, transfer reinforcing cage and embedded steel tube, subsequently concrete perfusion.
In soil excavation process, need ground-connecting-wall distortion, surface settlement etc. tightly to monitor, once monitored data demonstration supporting piling wall distortion or surface settlement, advance the speed greatly or increase to certain value, the pre-buried sealed tube position that is engraved in excavation face top is inserted Grouting Pipe level in the active region soil body, carry out subsequently horizontal grouting, below ground, form horizontal grouting body (4).After slip casting finishes the last time, must adopt an effective measure, horizontal seal pipe is sealed.

Claims (3)

1. control a method for the outer surface settlement of foundation ditch, it is characterized in that by by foundation ditch outside foundation ditch the layering horizontal grouting of the active region soil body control surface settlement.
2. the method for the outer surface settlement of control foundation ditch according to claim 1, is characterized in that: according to default slip casting position, bury horizontal seal pipe in ground-connecting-wall underground, sealed tube and ground-connecting-wall reinforcing cage are connected and fixed; When surface settlement is larger, in ground-connecting-wall pre-buried sealed tube position or the default slip casting of soldier pile seam position, Grouting Pipe level is inserted in the active region soil body, carry out subsequently horizontal grouting.
3. the method for the outer surface settlement of control foundation ditch according to claim 1, is characterized in that: the position of horizontal grouting point is arranged on each layer of support top, according to excavation of foundation pit operating mode, respectively in soldier pile diverse location carrying out horizontal slip casting within the walls.
CN201410344924.3A 2014-07-21 2014-07-21 A kind of method controlling the outer surface subsidence of foundation ditch by horizontal grouting Active CN104074195B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410344924.3A CN104074195B (en) 2014-07-21 2014-07-21 A kind of method controlling the outer surface subsidence of foundation ditch by horizontal grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410344924.3A CN104074195B (en) 2014-07-21 2014-07-21 A kind of method controlling the outer surface subsidence of foundation ditch by horizontal grouting

Publications (2)

Publication Number Publication Date
CN104074195A true CN104074195A (en) 2014-10-01
CN104074195B CN104074195B (en) 2016-08-17

Family

ID=51595771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410344924.3A Active CN104074195B (en) 2014-07-21 2014-07-21 A kind of method controlling the outer surface subsidence of foundation ditch by horizontal grouting

Country Status (1)

Country Link
CN (1) CN104074195B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120811A (en) * 2016-08-24 2016-11-16 中天建设集团有限公司天津分公司 A kind of foundation ditch periphery distortion preventing and deviation rectification construction method
CN108316283A (en) * 2018-01-25 2018-07-24 天津大学 The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall
CN113699998A (en) * 2021-05-07 2021-11-26 金华职业技术学院 Method for controlling foundation pit settlement deviation
CN114687345A (en) * 2022-04-28 2022-07-01 浙江华展工程研究设计院有限公司 Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3215153A1 (en) * 1982-04-23 1983-11-03 Beratende Ingenieure VBI Frank-Kauer-Raffelt GmbH, 8012 Ottobrunn Retaining structure and method of producing a retaining structure
CN1131221A (en) * 1995-12-29 1996-09-18 曾宪明 Supporting and protecting method for base pit, side slope, flat anchor and spray net
RU2371547C1 (en) * 2008-03-25 2009-10-27 Общество с ограниченной ответственностью Проектно-строительная компания "Фундамент" Method for strengthening of slopes and slot maker for its realisation
CN101718099A (en) * 2009-11-14 2010-06-02 欧阳甘霖 Automatic wall-forming device and method of static pressure continuous concrete wall
CN103334371A (en) * 2013-07-05 2013-10-02 中南大学 Roadbed subsidence grouting treatment structure and construction method thereof
CN203583493U (en) * 2013-09-29 2014-05-07 中国一冶集团有限公司 Combined lattice steel frame spray anchoring foundation pit supporting structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3215153A1 (en) * 1982-04-23 1983-11-03 Beratende Ingenieure VBI Frank-Kauer-Raffelt GmbH, 8012 Ottobrunn Retaining structure and method of producing a retaining structure
CN1131221A (en) * 1995-12-29 1996-09-18 曾宪明 Supporting and protecting method for base pit, side slope, flat anchor and spray net
RU2371547C1 (en) * 2008-03-25 2009-10-27 Общество с ограниченной ответственностью Проектно-строительная компания "Фундамент" Method for strengthening of slopes and slot maker for its realisation
CN101718099A (en) * 2009-11-14 2010-06-02 欧阳甘霖 Automatic wall-forming device and method of static pressure continuous concrete wall
CN103334371A (en) * 2013-07-05 2013-10-02 中南大学 Roadbed subsidence grouting treatment structure and construction method thereof
CN203583493U (en) * 2013-09-29 2014-05-07 中国一冶集团有限公司 Combined lattice steel frame spray anchoring foundation pit supporting structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙剑平等: "《深厚杂填土基坑位移控制设计与施工技术》", 《岩土工程学报》, vol. 34, 30 November 2012 (2012-11-30), pages 576 - 580 *
陈兴年等: "《关于软土基坑加固的一点看法》", 《地下空间》, vol. 22, no. 1, 31 March 2003 (2003-03-31) *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120811A (en) * 2016-08-24 2016-11-16 中天建设集团有限公司天津分公司 A kind of foundation ditch periphery distortion preventing and deviation rectification construction method
CN108316283A (en) * 2018-01-25 2018-07-24 天津大学 The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall
CN113699998A (en) * 2021-05-07 2021-11-26 金华职业技术学院 Method for controlling foundation pit settlement deviation
CN114687345A (en) * 2022-04-28 2022-07-01 浙江华展工程研究设计院有限公司 Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall

Also Published As

Publication number Publication date
CN104074195B (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN104805854B (en) A kind of Deep Water Ultra-long steel sheet pile cofferdam construction method under tide environment
CN205742213U (en) Foundation pit supporting construction
CN103114599B (en) Deep basal pit sealing dewatering device and construction method thereof
CN101949153B (en) Foundation drainage control method
CN107268688B (en) Construction method for reinforcing and sealing I-shaped steel joint of underground continuous wall
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN106801417A (en) Tunnel Passing structures steel pipe isolation pile stratum consolidation system and its construction method
CN106368219B (en) A kind of the support reinforcement structure and construction method of deep basal pit
CN202194149U (en) Water-proof curtain
CN104074195A (en) Method for controlling sedimentation of ground outside foundation pit through horizontal grouting
CN206616565U (en) Door font double-row pile and double high-pressed spin-spewing water-stopping curtain combined retaining structure
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN201424658Y (en) Water leakage detection of underground continuous wall groove seams and block repair device
CN113373962B (en) Combined leakage stoppage construction method for deep foundation pit
CN207862925U (en) A kind of slip casting casing device
CN104099946A (en) Novel jacking pipe intersegment overhaul well
CN213508493U (en) Steel open caisson counter pressure sinking support system for soft soil area
CN213328983U (en) Soft soil foundation prepressing drainage consolidation field peripheral building/structure protection structure
CN113216215A (en) Deep groove support reverse construction method in complex environment
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN105350575A (en) Reverse construction method for underground continuous wall
CN206220101U (en) A kind of support reinforcement structure of deep basal pit
CN203113361U (en) Deep foundation pit sealing precipitation device
CN206298896U (en) A kind of Tunnel Passing structures steel pipe isolation pile stratum consolidation system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 315010 496 Xin Dian Road, Haishu District, Zhejiang, Ningbo

Applicant after: ZHEJIANG HUAZHAN INSTITUTE OF ENGINEERING RESEARCH AND DESIGN

Address before: 315010 Zhejiang Province, Ningbo city Haishu District Baoshan Road No. 166

Applicant before: ZHEJIANG HUAZHAN INSTITUTE OF ENGINEERING RESEARCH AND DESIGN

C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 315000 No.496, Xindian Road, Haishu District, Ningbo City, Zhejiang Province

Patentee after: Zhejiang Huazhan Research and Design Institute Co.,Ltd.

Address before: No. 496, Xindian Road, Haishu District, Ningbo City, Zhejiang Province, 315010