CN104060615A - Construction method utilizing newly-built supporting structure of foundation pit to eliminate underground obstacle - Google Patents

Construction method utilizing newly-built supporting structure of foundation pit to eliminate underground obstacle Download PDF

Info

Publication number
CN104060615A
CN104060615A CN201410247776.3A CN201410247776A CN104060615A CN 104060615 A CN104060615 A CN 104060615A CN 201410247776 A CN201410247776 A CN 201410247776A CN 104060615 A CN104060615 A CN 104060615A
Authority
CN
China
Prior art keywords
construction
underground obstacle
foundation pit
concrete support
remove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410247776.3A
Other languages
Chinese (zh)
Other versions
CN104060615B (en
Inventor
魏春明
梁华杰
王青辉
王立群
刘剑
王烨
陆靖
才华
刘柳
杨鹏飞
管盈铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huajian Construction Co Ltd
Original Assignee
Jiangsu Huajian Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huajian Construction Co Ltd filed Critical Jiangsu Huajian Construction Co Ltd
Priority to CN201410247776.3A priority Critical patent/CN104060615B/en
Publication of CN104060615A publication Critical patent/CN104060615A/en
Application granted granted Critical
Publication of CN104060615B publication Critical patent/CN104060615B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a construction method utilizing a newly-built supporting structure of foundation pit to eliminate an underground obstacle. The method comprises the following steps: step one, confirming the particular position of an underground obstacle and the positions of a plurality of upright post poles to be constructed; leveling ground in an obstacle clearing area; placing concrete floor; step two, conducting construction on the upright post poles; step three, conducting construction on a first concrete support of the foundation pit; step four, removing the underground obstacle until undisturbed soil is exposed; backfilling soil to the level that 100 mm under the project level of the bottom of second concrete support; step five, conducting construction on the second concrete support; step six, adopting a high pressure rotary jet pile machine to conduct construction on reinforcement of pit bottom; step seven, digging a precipitation well to conduct precipitation of the foundation pit; step eight, continuously conducting excavating construction on the foundation pit. The construction method enables the obstacle clearing in the pit and excavation of the foundation pit to conduct synchronously, and not only shortens the construction period, but also reduces the construction cost.

Description

Utilize newly-built foundation pit supporting construction to remove the construction method of underground obstacle
Technical field
The present invention relates to remove in a kind of construction work the construction method of underground obstacle, be particularly related to a kind of in architectural engineering pit excavation construction process, utilize the supporting and protection structure of newly-built design of foundation pit as support system, remove the construction method of the original underground large obstacle in hole.
Background technology
Along with the development of urban construction; the exploitation of Reforming Center Urban Area and the underground space; often be faced with surrounding enviroment complexity, protection and require the difficult problems such as high, narrow field, underground obstacle are many, original building is retained in underground foundation becomes the obstacle before new building construction.Conventionally need first the underground obstacle in place to be removed obstacles.
Owing to being in area, down town, need to carry out construction pit for the removing of underground large obstacle goes along with sb. to guard him, prevent slope failure, backfill again after obstruction removing, dismounting construction pit is gone along with sb. to guard him, smooth location, the engineering pile of the new building of then constructing and bracing of foundation pit stake, finally ability excavation pit, construction underground structure.In this process, can need to do bracing of foundation pit twice, after removing obstacles, backfilling of earthwork excavates again, makes time duration long, forms the waste on definite meaning.
Summary of the invention
For addressing the above problem, the invention provides a kind of construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle, remove obstacles and excavate one-time-reach-place, avoid conventional construction method backfill after removing obstacles, go along with sb. to guard him again, excavate caused waste, reduce the duration, reduce cost.
For achieving the above object, the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle of the present invention, comprises the following steps:
Step 1, determines the particular location of underground obstacle and the position of the some root post stakes that need to construct, at the region smooth location of removing obstacles, builds at least thick concrete floor of 150mm;
Step 2, construction stand column pile;
Step 3, adopts pick machine to abolish concrete floor and underground obstacle more than design elevation at the bottom of first concrete support, the first concrete support of construction foundation pit;
Step 4, removes underground obstacle, until expose undisturbed soil, backfill is to 100mm under design elevation at the bottom of second concrete support;
Step 5, construction second concrete support;
Step 6, adopts jet grouting pile driving machine, and the construction end, hole reinforces;
Step 7, the construction end, hole, has reinforced rear complement dewatering well, carries out foundation pit dewatering.
Step 8, foundation ditch continues excavation construction.
In described step 1, the original engineering pile of underground obstacle position is avoided in the position of stand column pile 6, ensures at least 500mm of clear distance.
First concrete support in described step 3 wouldn't be constructed at the trestle plate in the region of removing obstacles, construction bridge plate again after the end, construction hole in step 6 has reinforced.
On first concrete support in described step 3, have at least a hole to reach 6m × 8m, can make pick machine pass through smoothly.
In described step 4, remove in the process of underground obstacle, if underground obstacle 2 has pile foundation, remove underground obstacle and to the operation in backfill process be: remove obstacles and expose old stake top → measure stake position → detection of pier foundation → backfill to 100mm under design elevation at the bottom of second concrete support.
In described step 4, remove in the process of underground obstacle, being divided into some sections along the order of removing obstacles constructs, every section width is not more than 15m, first remove the superstructure of underground obstacle, on first concrete support, lay again steel guidance tape, pick machine is removed underground obstacle on steel guidance tape, and the area of the underground space reaches after 200m2, and a pick machine enters the bottom removing underground obstacle of first concrete support.
The construction end, hole of second concrete support and the step 6 of constructing in described step 5, reinforces a point section and carries out, after the second concrete support of one of them section has been constructed, on first concrete support, jet grouting pile driving machine is set, the construction end, hole of carrying out this section, reinforces.
Effect of the present invention is: the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle of the present invention, make to remove obstacles and synchronize and carry out with excavation of foundation pit in hole, in the work progress of whole underground construction, do not take separately the duration, than conventional construction method few the operations such as region supporting, backfill, excavation of removing obstacles, reduce backfill, also the workload that has just reduced the reinforcing of the end, hole, has therefore not only reduced the duration, also reduces construction costs.And to have reduced the duration be exactly to have shortened the time that foundation ditch exposes, can control preferably bracing of foundation pit distortion, reduce to greatest extent the impact on environment.
Brief description of the drawings
Fig. 1 is the schematic diagram that adopts full circle swinging obstacle cleaning machine targeted elimination stand column pile position underground obstacle;
Fig. 2 is the schematic diagram that adopts bored concrete pile machine construction stand column pile;
Fig. 3 adopts pick machine to abolish more than first concrete support design end absolute altitude sclerosis terrace and the schematic diagram of obstruction;
Fig. 4 is the schematic diagram of construction first concrete support;
Fig. 5 is the top view of Fig. 4;
Fig. 6 is the schematic diagram that adopts pick crusher machine underground obstacle;
Fig. 7 is the schematic diagram of construction second concrete support;
Fig. 8 is the schematic diagram that adopts the end reinforcing of jet grouting pile driving machine construction hole;
Fig. 9 is the remove obstacles schematic diagram of trestle plate in region of construction;
Figure 10 is the top view after the construction of trestle plate in Fig. 9.
Detailed description of the invention
Referring to Fig. 1~10, the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle of the present invention, step is as follows:
Step 1, determines the particular location of underground obstacle and the position of the some root post stakes 6 that need to construct, at the region smooth location of removing obstacles, builds at least thick concrete floor 20 of 150mm.By measuring unwrapping wire, determine the particular location and the position that needs some root post stakes 6 of constructing of underground obstacle, stand column pile 6 tops are lattice steel column, insert in castinplace pile at the end, hole.The underground obstacle here refers to original building basement.And the original engineering pile of underground obstacle (claiming again old pile foundation) position is avoided, at least 500mm of guarantee clear distance in the position that makes stand column pile 6.Construction stand column pile 6 need to be passed underground obstacle 2 top boards and base plate, and inner building waste.Stand column pile 6 positions adopt RTP-350E full circle swinging obstacle cleaning machines 21 to remove to 500mm under underground obstacle 2 bottoms, aperture 1000mm, more than the large 100mm of aperture ratio castinplace pile diameter, adopt full circle swinging obstacle cleaning machine 21 targeted elimination stand column pile 6 position underground obstacles 2 as shown in Figure 1.Construction process: stand column pile location → obstacle cleaning machine is in place → hanging device is in place → sleeve pipe convolution is pressed into → circle round in eccentric cutting → groove and draws water, clear soil → full section circles round cut-out → handling obstruction → hole in backfill cement-soil → densification → telephone-moving carry out next hole removing.
Step 2, adopts bored concrete pile machine 22 stand column pile 6 of constructing, as shown in Figure 2, and castinplace pile diameter 850mm.The position of removing obstacles arranges the steel sleeve of full circle swinging obstacle cleaning machine 21, prevents from that underground water from entering in bored pile hole to cause that slurry coat method denseness declines, and causes hole wall collapse.
Step 3, adopts PC220 type to excavate pick machine 8 and abolishes more than 1 end of first concrete support absolute altitude concrete floor 20 and indoor wall 3, the exterior wall 4 of underground obstacle 2, and the first concrete support 1 of construction foundation pit, as shown in Fig. 3, Fig. 4 and Fig. 5.The trestle plate 12 in the non-region of removing obstacles on first concrete support 1 can first be constructed, and the trestle plate 13 in the region of removing obstacles wouldn't be constructed, and joint (reserved constuction joint) is located reserved straight screw sleeve, for the remove obstacles connection of trestle plate 13 in region of construction in later period.The hole of removing obstacles between the support of region needs to optimize, and ensureing has a hole to reach 6m × 8m on first concrete support 1, can make pick machine 10 pass through smoothly, sails the end, hole into.
Step 4, removes underground obstacle, as shown in Figure 6.Adopt 8 fragmentations of pick machine since a vertex angle part.In underground obstacle reset procedure, preferably, observe excavation based on space, take reasonable partitioned mode, be conducive to accelerate the speed of removing obstacles, as shown in Figure 5, the region of removing obstacles can be divided into some sections, shown in figure, be 3 sections, as 1st district in Fig. 5,2nd district, 3rd district, every section width is not more than 15m.First remove the superstructure of underground obstacle 2, on first concrete support 1, lay again steel guidance tape 9, pick machine 8 is removed underground obstacle 2 on steel guidance tape 9, the area of the underground space reaches after 200 ㎡, a pick machine 10 enters the hole end (being the bottom of first concrete support 1) and removes underground obstacle 2, until expose undisturbed soil.If underground obstacle 2 has pile foundation, can cut the earth afterwards time, remove with pick machine again.For the construct impact of the old pile foundation of not removed of the high-pressure rotary jet grouting pile after ensureing to remove obstacles and piling, or need to utilize the old pile foundation under underground obstacle 2, the operation of removing obstacles in backfilling process is: remove obstacles and expose old stake top → measure stake position → detection of pier foundation → backfill to 100mm under design elevation at the bottom of second concrete support.
Step 5, construction second concrete support 7.In step 4, will remove obstacles region when being divided into some sections and constructing, until a region wherein complete can be in backfill after removing obstacles formwork, the second concrete support 7 in this region of constructing, as shown in Figure 7.When part second concrete support 7 completes, the pick machine 8 on first concrete support 1 continues broken underground obstacle 2, and in hole, pick machine 10 is broken below, and so closely broken effect is than large in effect of pick machine 8.
Step 6, adopts jet grouting pile driving machine 11, and the construction end, hole reinforces.After the second concrete support 7 in this region has been constructed, jet grouting pile driving machine 11 is set on first concrete support 1, the construction end, hole, reinforces, as shown in Figure 8.The construction end, hole, reinforces and can carry out with removing obstacles of other regions simultaneously.After second concrete support 7 has all been constructed, in the backfill 23 of compacting in foundation ditch, the plank 24 of laying depth 50mm is set up framed bent 24 on plank 24, the constructed residual remaining trestle plate 13 in region of removing obstacles, as shown in Figures 9 and 10.Because trestle plate 13 is shelved on the beam of first concrete support 1, bottom framed bent 24 can be removed after concrete strength reaches C20.But the trestle plate 13 newly watering, can not load-bearing not reaching before design strength.
Step 7, the construction end, hole, has reinforced rear complement dewatering well, carries out foundation pit dewatering.
Step 8, foundation ditch continues excavation construction.Foundation ditch continues excavation construction, carries out follow-up construction according to conventional construction method.
Those skilled in the art will recognize that; above-mentioned detailed description of the invention is exemplary; in order to make those skilled in the art can better understand this patent content; should not be understood as the restriction to this patent protection domain; change or modify as long as disclose spiritual any being equal to of doing according to this patent, all fall into this patent protection domain.

Claims (7)

1. utilize newly-built foundation pit supporting construction to remove a construction method for underground obstacle, it is characterized in that, comprise the following steps:
Step 1, determines the particular location of underground obstacle and the position of the some root post stakes that need to construct, at the region smooth location of removing obstacles, builds at least thick concrete floor of 150mm;
Step 2, construction stand column pile;
Step 3, adopts pick machine to abolish concrete floor and underground obstacle more than design elevation at the bottom of first concrete support, the first concrete support of construction foundation pit;
Step 4, removes underground obstacle, until expose undisturbed soil, backfill is to 100mm under design elevation at the bottom of second concrete support;
Step 5, construction second concrete support;
Step 6, adopts jet grouting pile driving machine, and the construction end, hole reinforces;
Step 7, the construction end, hole, has reinforced rear complement dewatering well, carries out foundation pit dewatering.
Step 8, foundation ditch continues excavation construction.
2. the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle according to claim 1, is characterized in that, in described step 1, the original engineering pile of underground obstacle position is avoided in the position of stand column pile 6, ensures at least 500mm of clear distance.
3. the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle according to claim 1, it is characterized in that, first concrete support in described step 3 wouldn't be constructed at the trestle plate in the region of removing obstacles, construction bridge plate again after the end, construction hole in step 6 has reinforced.
4. the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle according to claim 1, is characterized in that on the first concrete support in described step 3, having at least a hole to reach 6m × 8m, can make pick machine pass through smoothly.
5. the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle according to claim 1, it is characterized in that, in described step 4, remove in the process of underground obstacle, if underground obstacle 2 has pile foundation, remove underground obstacle and to the operation in backfill process be: remove obstacles and expose old stake top → measure stake position → detection of pier foundation → backfill to 100mm under design elevation at the bottom of second concrete support.
6. the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle according to claim 1, it is characterized in that, in described step 4, remove in the process of underground obstacle, being divided into some sections along the order of removing obstacles constructs, every section width is not more than 15m, first remove the superstructure of underground obstacle, on first concrete support, lay again steel guidance tape, pick machine is removed underground obstacle on steel guidance tape, the area of the underground space reaches after 200m2, and a pick machine enters the bottom removing underground obstacle of first concrete support.
7. the construction method of utilizing newly-built foundation pit supporting construction to remove underground obstacle according to claim 6, it is characterized in that, the construction end, hole of second concrete support and the step 6 of constructing in described step 5, reinforces a point section and carries out, after the second concrete support of one of them section has been constructed, on first concrete support, jet grouting pile driving machine is set, the construction end, hole of carrying out this section, reinforces.
CN201410247776.3A 2014-06-05 2014-06-05 Newly-built foundation pit supporting construction is utilized to remove the construction method of underground obstacle Active CN104060615B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410247776.3A CN104060615B (en) 2014-06-05 2014-06-05 Newly-built foundation pit supporting construction is utilized to remove the construction method of underground obstacle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410247776.3A CN104060615B (en) 2014-06-05 2014-06-05 Newly-built foundation pit supporting construction is utilized to remove the construction method of underground obstacle

Publications (2)

Publication Number Publication Date
CN104060615A true CN104060615A (en) 2014-09-24
CN104060615B CN104060615B (en) 2016-06-15

Family

ID=51548529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410247776.3A Active CN104060615B (en) 2014-06-05 2014-06-05 Newly-built foundation pit supporting construction is utilized to remove the construction method of underground obstacle

Country Status (1)

Country Link
CN (1) CN104060615B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155516A (en) * 2015-08-14 2015-12-16 江苏省华建建设股份有限公司 Method for constructing cast-in-situ bored pile before comprehensively removing underground barriers
CN105735383A (en) * 2016-03-25 2016-07-06 上海建工四建集团有限公司 Partial underground obstacle removing construction method capable of reserving structural system
CN109914507A (en) * 2019-03-18 2019-06-21 上海市基础工程集团有限公司 Abolish the device of underground obstacle under the conditions of deep-cutting
CN110173274A (en) * 2019-05-31 2019-08-27 武汉市武昌市政建设(集团)有限公司 A kind of head is removed obstacles method
CN110952916A (en) * 2019-11-28 2020-04-03 武汉金瑞威基础工程有限公司 Construction method for crushing and dismantling deep part of old building pile foundation
CN112538981A (en) * 2020-11-26 2021-03-23 上海建工四建集团有限公司 Old building basement obstacle removing and new building pile foundation synchronous construction method
CN113322965A (en) * 2021-06-11 2021-08-31 中国建筑第八工程局有限公司 Deep foundation clearing construction method for near-subway deep foundation pit
CN114753381A (en) * 2022-05-23 2022-07-15 中铁七局集团郑州工程有限公司 Method for clearing underground obstacles in non-excavation construction path range in limited space

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1121894A (en) * 1997-06-27 1999-01-26 K Sutatsufu:Kk Mobile type sheathing device, and construction of method avoiding underground obstacle by sheathing device
CN101761083A (en) * 2008-12-24 2010-06-30 上海市基础工程公司 Underground continuous wall obstacle clearing construction method for traversing ultra-thick obstacle
CN103410153A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Adjacent deep foundation trench and shallow foundation trench synchronous construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1121894A (en) * 1997-06-27 1999-01-26 K Sutatsufu:Kk Mobile type sheathing device, and construction of method avoiding underground obstacle by sheathing device
CN101761083A (en) * 2008-12-24 2010-06-30 上海市基础工程公司 Underground continuous wall obstacle clearing construction method for traversing ultra-thick obstacle
CN103410153A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Adjacent deep foundation trench and shallow foundation trench synchronous construction method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
徐建伟: ""钻孔切割法清除地下障碍物的施工技术"", 《建筑施工》 *
汪前等: ""复杂环境下大型地下障碍物处理技术"", 《施工技术》 *
葛国华: ""上海外滩通道综合改造工程中的深层障碍物清除技术"", 《建筑施工》 *
顾亚囝等: ""大型地铁枢纽站施工中的地下障碍物拆除及车站结构逆作施工技术"", 《建筑施工》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155516A (en) * 2015-08-14 2015-12-16 江苏省华建建设股份有限公司 Method for constructing cast-in-situ bored pile before comprehensively removing underground barriers
CN105155516B (en) * 2015-08-14 2016-11-30 江苏省华建建设股份有限公司 The method of construction drill bored concrete pile before making an overall screening underground obstacle
CN105735383A (en) * 2016-03-25 2016-07-06 上海建工四建集团有限公司 Partial underground obstacle removing construction method capable of reserving structural system
CN109914507A (en) * 2019-03-18 2019-06-21 上海市基础工程集团有限公司 Abolish the device of underground obstacle under the conditions of deep-cutting
CN110173274A (en) * 2019-05-31 2019-08-27 武汉市武昌市政建设(集团)有限公司 A kind of head is removed obstacles method
CN110952916A (en) * 2019-11-28 2020-04-03 武汉金瑞威基础工程有限公司 Construction method for crushing and dismantling deep part of old building pile foundation
CN112538981A (en) * 2020-11-26 2021-03-23 上海建工四建集团有限公司 Old building basement obstacle removing and new building pile foundation synchronous construction method
CN113322965A (en) * 2021-06-11 2021-08-31 中国建筑第八工程局有限公司 Deep foundation clearing construction method for near-subway deep foundation pit
CN114753381A (en) * 2022-05-23 2022-07-15 中铁七局集团郑州工程有限公司 Method for clearing underground obstacles in non-excavation construction path range in limited space

Also Published As

Publication number Publication date
CN104060615B (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN104060615A (en) Construction method utilizing newly-built supporting structure of foundation pit to eliminate underground obstacle
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN101328712A (en) Construction method of interlocking pile for soft soil and soil layer with obstacle
CN102758458B (en) Underground continuous wall repairing method
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN104060617B (en) The prefabricated assembled inner support system of foundation pit support system and construction method
CN108842819A (en) A kind of urban track traffic cable run method for tunnel construction
CN103603508B (en) A kind of pile foundation closure reperfusion reinforcement construction method in buried shelter
CN107700474A (en) A kind of existing construction foundation reinforcement means and campshed formula diaphram wall
CN103015431A (en) Foundation pit supporting method for manual dig-hole cement-soil steel pile
CN101824825B (en) Deep foundation pit open cutting construction method
CN107700497A (en) A kind of building basement pattern foundation pit supporting structure and earth excavation construction method
CN101509258B (en) Method for precontrolling subsidence slant of sinking well
CN110424372A (en) Along road interval method in a row remove obstacles after construct diaphram wall construction method
CN111560964B (en) Construction method of rear anti-seepage system of foundation pit
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN105735383A (en) Partial underground obstacle removing construction method capable of reserving structural system
CN107313430A (en) The deep big foundation pit subregion construction method of three face Nearby Structures
CN108978709B (en) Urban comprehensive pipe gallery branch construction method in space-limited environment
CN208763446U (en) Increase the supporting construction for building the underground space under a kind of existing building group
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN103161469A (en) Method for excavating vertical shaft to underground repair pipe-jacking tool pipe
KR100701885B1 (en) Non-open cut pipe installation method
CN103510525A (en) Cascade support method of foundation trench of gravity type cement cob wall combined single-row piles
CN113958322A (en) Tunnel excavation method at lower layer of existing subway line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant