CN104005370B - The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof - Google Patents

The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof Download PDF

Info

Publication number
CN104005370B
CN104005370B CN201310183482.4A CN201310183482A CN104005370B CN 104005370 B CN104005370 B CN 104005370B CN 201310183482 A CN201310183482 A CN 201310183482A CN 104005370 B CN104005370 B CN 104005370B
Authority
CN
China
Prior art keywords
revetment
building
mask
barricade
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310183482.4A
Other languages
Chinese (zh)
Other versions
CN104005370A (en
Inventor
张桂荣
周成
何宁
朱红亮
饶志刚
肖红玲
张明
赵波
曾子
刘焦
关春曼
何建村
李登华
周彦章
钱亚俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU CHANGZHOU SEA-ROUTE MANAGEMENT BUREAU
Sichuan University
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Original Assignee
JIANGSU CHANGZHOU SEA-ROUTE MANAGEMENT BUREAU
Sichuan University
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU CHANGZHOU SEA-ROUTE MANAGEMENT BUREAU, Sichuan University, Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources filed Critical JIANGSU CHANGZHOU SEA-ROUTE MANAGEMENT BUREAU
Priority to CN201310183482.4A priority Critical patent/CN104005370B/en
Publication of CN104005370A publication Critical patent/CN104005370A/en
Application granted granted Critical
Publication of CN104005370B publication Critical patent/CN104005370B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof: be provided with from bottom to top on ground: bottom geo-grid, hardcore bed, some layers roll " the geogrids reinforced earth layer " that fill stratum and top layer geo-grid or layering geo-grid are alternately formed; Top layer geo-grid tiling stretch-draw is connected with form anchor; Stone-laying barricade mask is filled with in being comprehensively coated with lateral surface above of reinforcement soil layer, extends to inside revetment barricade and makes spats; The surface covering lateral surface part is provided with building-block layer; In the building block hole of building-block layer, be filled with excavation spoir, and plant herbaceous plant, form ecological revetment mask.The present invention is reasonable in design, technique is simple, be easy to construction, easy to operate, cost is low, be easy to popularization, is specially adapted to the ecological protection on riverbank, navigation channel, soft clay area.

Description

The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof
Technical field
The present invention relates in the revetment barricade engineering of a kind of navigation channel the reinforced earth lightweight revetment barricade applying the ecological mask of building-block, be applicable to that collapse on the bank is serious, the navigation channel of soft clay area or riverbank.This invention overcomes the drawback of conventional rigid shore protection Gravity Retaining Wall from the process of great desirably base, substantially solve collapse on the bank, current and ship wave to bank slope wash away and vessel to the problem that may clash into of bank protection structure, achieve the combination of bank protection structure durability and ecological property.The invention still further relates to the construction method of this lightweight revetment barricade.
This patent is by the special project " western middle and small river and bank slope bionomic control complete set technology research (No:201301022) thereof " of Ministry of Water Resources's public welfare industry scientific research, Jiangsu Province's traffic and transportation science research program project " red golden Li river for transporting grain to the capital informer times waterway regulation (red golden ship lock) engineering navigation channel soil bank slope Ecological recovery technology research (2011Z01-1) ", and the subsidy of Nsfc Major research program integrated project (No:91215301).
Background technology
Navigation channel Slope Failure, landslide, avalanche are of common occurrence at home and abroad.At present, navigation channel bank slope generally adopts the form of structure of rigidity revetment to protect, but because Gravity Retaining Wall is from great, soft foundation needs process, cause costly and can cause the degeneration of river ecological environment, therefore bank slope ecological protection has become the new trend that bank protection work is built.How under the prerequisite meeting cruiseway navigation function, realizing the combination of bank protection structure durability and ecological property, is the difficult point and hot issue that face in ecological revetment Technique Popularizing.
Summary of the invention
In order to overcome the deficiency of existing traditional bank slope protection engineering, the invention provides a kind of reinforced earth lightweight revetment barricade utilizing the ecological mask of building-block, not only effectively can solve the collapse on the bank on riverbank, navigation channel, cave in and Gravity Retaining Wall from the great problem needing soft soil foundation etc., and improving in the Riparian Zone ecological functions reduction that conventional rigid shore protection causes and will play positive role.The present invention also will provide the construction method of this lightweight revetment barricade.
The technical solution adopted for the present invention to solve the technical problems is, the reinforced earth lightweight revetment barricade of the ecological mask of a kind of building-block, and its structure is:
On ground, be provided with successively from bottom to up: bottom geo-grid, hardcore bed, some layers roll " the geogrids reinforced earth layer " that fill stratum and top layer geo-grid or layering geo-grid are alternately formed;
With lateral surface (one side towards navigation channel) on described geogrids reinforced earth layer, be coated with comprehensively and fill with stone-laying barricade mask;
Described filling stone-laying barricade mask covers the part above geogrids reinforced earth layer, extends to the inner side spats (leaving the side in navigation channel) of this revetment barricade; Top layer geo-grid tiling stretch-draw in described geo-grid, is connected with this form anchor;
Described filling stone-laying barricade mask covers the part of geogrids reinforced earth layer lateral surface, extends downwardly into spats in ground;
Described filling stone-laying barricade mask covers the surface of geogrids reinforced earth layer lateral surface part, is provided with building-block layer;
In the building block hole of described building-block layer, be filled with excavation spoir, and plant herbaceous plant, form ecological revetment mask.
One of prioritization scheme is: the bottom surface kind outside revetment barricade is implanted with pilotage and the reed of wave that disappears, and forms vertical ecological mask, and opposing current scour, ship wave are corroded and prevent accidental ship collision etc.
Prioritization scheme of the present invention also has:
1, described " geogrids reinforced earth " refers to: the bottom in revetment barricade, top layer geo-grid or layering geogrids reinforced earth, the soil pressure that revetment barricade is suffered when low water stage can be balanced, with enhanced level to resistance to overturning, adjustment uneven settlement of foundation; The domatic geo-grid of revetment barricade can, as the flexible support face of filling with stone-laying, prevent its changing of the relative positions from ftractureing;
2, described " form anchor " refers to: for top layer geo-grid provides the concrete breast boards with reinforcing bar crotch of anchored force;
3, described " filling stone-laying " refers to: from levee toe up stone-laying perfusion mortar on the geo-grid as flexible support face, to make soil property revetment and the barricade mask thereof of design grade, prevent wave cut or water logging soil property revetment; Banket after building soil property revetment end face by laying bricks or stones, geo-grid is tiled stretch-draw, bankets and roll and fill with stone-laying, carry out soil property revetment end face clad;
4, described " building-block layer " refers to: filling with the mode according to fissure of displacement bond on stone-laying revetment barricade mask, from soil property revetment levee toe up staged build aperture building-block vertically upward by laying bricks or stones, or building-block aperture is against slope masonry;
5, described " ecological revetment mask " refers to: in building block hole, insert excavation spoir and be mixed into composite long-acting nutrient material, the herbaceous plant such as plantation vetiver, form ecological revetment mask, the vegetation planted can not give maintenance and can survive by natural rainfall.
In other words, the formation of the reinforced earth lightweight revetment barricade of the ecological mask of building-block of the present invention is: directly utilize original position to excavate the soil body, geo-grid and filling stone-laying clad, make reinforced earth revetment barricade; The flexible bearing surface of geo-grid makes filling stone-laying domatic, form the revetment barricade of face predetermined slope near water; Again filling stone pitching on from soil property revetment levee toe up staged build aperture building-block vertically upward by laying bricks or stones, or building-block aperture is against slope masonry, in building block hole, insert excavation spoir and be mixed into composite long-acting nutrient material, the herbaceous plant such as plantation vetiver.
Like this, reinforced earth lightweight revetment barricade is utilized to reduce sedimentation and the disposal cost of soft foundation, the lateral deformation of opposing bank slope; Rely on the ecological mask of building-block that reinforced earth lightweight revetment barricade is made, opposing collapse on the bank, current scour and ship wave erosion etc.; In the plantation pilotage of revetment barricade bottom surface and the unrestrained reed that disappears, form vertical ecological mask, opposing current scour, ship wave are corroded and prevent accidental ship collision etc.
The technical scheme completing the present application task is, the construction method of the reinforced earth lightweight revetment barricade of the ecological mask of above-mentioned building-block, and it is characterized in that, step is as follows,
(1). after excavating the design basis degree of depth along the design longitudinal axis of navigation channel revetment barricade, lay one deck geo-grid and reserve certain length in side, navigation channel, fill hardcore bed, rolling bankets forms reinforced earth with enhanced level to resistance to overturning, adjustment uneven settlement of foundation;
(2). according to the gradient of design revetment barricade, geo-grid reserved for side, navigation channel is spread out to slope top stretch-draw along domatic, and placement in layers rolls the soil body and makes soil property revetment;
(3). up fill with stone-laying in geo-grid from levee toe, to make soil property revetment and the barricade mask thereof of design grade.Geo-grid can, as the flexible support face of filling with stone-laying, prevent its changing of the relative positions from ftractureing;
(4). after layered backfill builds soil property revetment end face by laying bricks or stones, geo-grid is tiled stretch-draw, is connected with form anchor, bankets and roll and fill with stone-laying;
. on filling stone-laying revetment barricade mask, according to the mode of fissure of displacement bond, from soil property revetment levee toe up staged build aperture building-block vertically upward by laying bricks or stones, or building-block aperture is against slope masonry;
(6). in building block hole, insert excavation spoir and be mixed into composite long-acting nutrient material, the herbaceous plant such as plantation vetiver, form ecological revetment mask;
(7). in the plantation pilotage of revetment barricade bottom surface and the unrestrained reed that disappears, form vertical ecological mask, opposing current scour, ship wave are corroded and prevent accidental ship collision etc.
The invention has the beneficial effects as follows: the present invention is reasonable in design, technique is simple, be easy to construction, easy to operate, cost is low, be easy to popularization, is specially adapted to the ecological protection on riverbank, navigation channel, soft clay area.
Accompanying drawing explanation
Fig. 1 is the mechanical model figure of the embodiment of the present invention; Wherein Fig. 1-a be domatic on geo-grid cant beam; Fig. 1-(b) is the geo-grid footing beam on ground;
Fig. 2 is the side arrangement figure of the embodiment of the present invention;
Fig. 3 is the front arrangement diagram of the embodiment of the present invention.
In figure, 1 navigation channel ground, 2 geo-grid, 3 hardcore beds, 4 roll and banket, 5 fill with stone-laying, 6 form anchors, 7 building-blocks, 8 vetivers etc., 9 reeds.
Detailed description of the invention
Embodiment 1, in the embodiment shown in fig. 1, using the horizontal foundation beam that horizontal for geo-grid 2-1 composite foundation supports as Vertical Spring navigation channel ground 1, lightweight reinforced earth revetment barricade is comprised hardcore bed 3, roll banket 4, domatic on the deadweight of filling stone-laying 5 and building-block 7 etc. as external load, vertically act on this horizontal foundation beam; Geo-grid 2-1 reinforced earth domatic for revetment barricade is rolled the tip ground beam of 3 supports of banketing as Vertical Spring, the geo-grid 2-1 of twice up and down of the horizontal pull provided is supported as horizontal spring, using the filling stone-laying 5 and building-block 7 etc. on domatic for revetment barricade as external load, act on this tip ground beam.
In the embodiment depicted in figure 2, after the design longitudinal axis excavation ground 1 to the design basis degree of depth of navigation channel revetment barricade, lay one deck geo-grid 2-1 and reserve certain length in side, navigation channel, filling hardcore bed 3, roll the 4 formation reinforced earths that banket; According to the gradient of design revetment barricade, geo-grid 2-1 reserved for side, navigation channel is spread out to slope top stretch-draw along revetment is domatic, placement in layers rolls to banket 4 makes soil property revetment; Then up construct in the geo-grid 2 as flexible support face from levee toe and fill with stone-laying 5; Banket 4 and after building by laying bricks or stones and filling with stone-laying 5 to soil property revetment end face, geo-grid 2-1 is tiled stretch-draw, and is connected with form anchor 6, geo-grid 2-1 or 2 roll and bankets 4 and stone-layings 5 are filled with in construction; Filling with the mode according to fissure of displacement bond on stone-laying 5 revetment barricade mask, from soil property revetment levee toe up staged build aperture building-block 7 vertically upward by laying bricks or stones, or building-block 7 aperture is against slope masonry; In building block 7 hole, insert excavation spoir and be mixed into composite long-acting nutrient material, the herbaceous plant 8 such as plantation vetiver, form ecological revetment mask; In the plantation pilotage of revetment barricade bottom surface and the unrestrained reed 9 that disappears, form vertical ecological mask.
In the embodiment shown in fig. 3, building-block 7 is put by the mode of fissure of displacement bond, from soil property revetment levee toe up staged build aperture building-block 7 vertically upward by laying bricks or stones, or building-block 7 aperture is against slope masonry, in the hole of building-block 7, insert excavation spoir and be mixed into composite long-acting nutrient material, plantation vetiver 8, form vegetation cover, in the plantation pilotage of revetment barricade bottom surface and the unrestrained reed 9 that disappears, form vertical ecological mask, opposing current scour, ship wave are corroded and prevent accidental ship collision etc.

Claims (5)

1. a reinforced earth lightweight revetment barricade for the ecological mask of building-block, is characterized in that, the structure of the reinforced earth lightweight revetment barricade of the ecological mask of this building-block is:
On ground, be provided with successively from bottom to up: bottom geo-grid, hardcore bed, some layers roll " the geogrids reinforced earth layer " that fill stratum and top layer geo-grid or layering geo-grid are alternately formed;
On described geogrids reinforced earth layer and lateral surface, be coated with comprehensively and fill with stone-laying barricade mask;
Described filling stone-laying barricade mask covers the part above geogrids reinforced earth layer, extends to the inner side spats of this revetment barricade; Described top layer geo-grid tiling stretch-draw, is connected with form anchor;
Described filling stone-laying barricade mask covers the part of geogrids reinforced earth layer lateral surface, extends downwardly into spats in ground;
Described filling stone-laying barricade mask covers the surface of geogrids reinforced earth layer lateral surface part, is provided with building-block layer;
In the building block hole of described building-block layer, be filled with excavation spoir, and plant herbaceous plant, form ecological revetment mask;
Described " form anchor " refers to: for top layer geo-grid provides the concrete breast boards with reinforcing bar crotch of anchored force;
Described " filling stone-laying " refers to: from levee toe up stone-laying perfusion mortar on the geo-grid as flexible support face, to make soil property revetment and the barricade mask thereof of design grade, prevent wave cut or water logging soil property revetment; Banket after building soil property revetment end face by laying bricks or stones, geo-grid is tiled stretch-draw, bankets and roll and fill with stone-laying, carry out soil property revetment end face clad.
2. the reinforced earth lightweight revetment barricade of the ecological mask of building-block according to claim 1, it is characterized in that, described " building-block layer " refers to: filling with the mode according to fissure of displacement bond on stone-laying revetment barricade mask, from soil property revetment levee toe up staged build aperture building-block vertically upward by laying bricks or stones, or building-block aperture is against slope masonry.
3. the reinforced earth lightweight revetment barricade of the ecological mask of building-block according to claim 1, it is characterized in that, described " ecological revetment mask " refers to: in building block hole, insert excavation spoir and be mixed into composite long-acting nutrient material, and plantation herbaceous plant vetiver, forms ecological revetment mask.
4. according to the reinforced earth lightweight revetment barricade of the ecological mask of the building-block one of claim 1-3 Suo Shu, it is characterized in that, the bottom surface kind outside described revetment barricade is implanted with pilotage and the reed of wave that disappears, and forms vertical ecological mask.
5. the construction method of the reinforced earth lightweight revetment barricade of the ecological mask of building-block according to claim 1, it is characterized in that, step is as follows,
(1). after excavating the design basis degree of depth along the design longitudinal axis of navigation channel revetment barricade, lay one deck geo-grid and reserve certain length in side, navigation channel, fill hardcore bed, rolling bankets forms reinforced earth with enhanced level to resistance to overturning, adjustment uneven settlement of foundation;
(2). according to the gradient of design revetment barricade, geo-grid reserved for side, navigation channel is spread out to slope top stretch-draw along domatic, and placement in layers rolls the soil body and makes soil property revetment;
(3). up fill with stone-laying in geo-grid from levee toe, to make soil property revetment and the barricade mask thereof of design grade; Geo-grid, as the flexible support face of filling with stone-laying, prevents its changing of the relative positions from ftractureing;
(4). after layered backfill builds soil property revetment end face by laying bricks or stones, top layer geo-grid tiling stretch-draw, be connected with form anchor, banket and roll and fill with stone-laying;
. on filling stone-laying revetment barricade mask, according to the mode of fissure of displacement bond, from soil property revetment levee toe up staged build aperture building-block vertically upward by laying bricks or stones, or building-block aperture is against slope masonry;
(6). in building block hole, insert excavation spoir and be mixed into composite long-acting nutrient material, plantation herbaceous plant vetiver, forms ecological revetment mask;
(7). in the plantation pilotage of revetment barricade bottom surface and the unrestrained reed that disappears, form vertical ecological mask, opposing current scour, ship wave are corroded and prevent accidental ship collision.
CN201310183482.4A 2013-05-16 2013-05-16 The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof Active CN104005370B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310183482.4A CN104005370B (en) 2013-05-16 2013-05-16 The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310183482.4A CN104005370B (en) 2013-05-16 2013-05-16 The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof

Publications (2)

Publication Number Publication Date
CN104005370A CN104005370A (en) 2014-08-27
CN104005370B true CN104005370B (en) 2015-12-23

Family

ID=51366259

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310183482.4A Active CN104005370B (en) 2013-05-16 2013-05-16 The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof

Country Status (1)

Country Link
CN (1) CN104005370B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059790A (en) * 2017-05-14 2017-08-18 海宁市利益建材有限公司 Barricade
CN107724422A (en) * 2017-10-17 2018-02-23 浙江八比实业有限公司 A kind of staged Ecological Retaining Wall
CN108086250B (en) * 2017-12-22 2024-08-16 上海市政工程设计研究总院(集团)有限公司 Self-embedded ecological hydraulic retaining wall brick with plant growth groove
CN114703875B (en) * 2022-04-20 2024-02-23 长沙理工大学 High-steep artificial side slope wavy reinforced soil retaining structure and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0819330A (en) * 1994-05-02 1996-01-23 Saikou:Kk Reinforced soil and vegetation construction using soil fiber, soil-reinforcing material and vegetation base material consisting of soil fiber
KR20040017387A (en) * 2002-08-21 2004-02-27 김영섭 Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device
CN2851347Y (en) * 2005-12-27 2006-12-27 四平市水利勘测设计研究院 Reinforced earth structured revetment retaining wall
CN201158826Y (en) * 2008-02-25 2008-12-03 山东玮丰达建筑工程有限公司 Earth work grille reinforced retaining wall
CN202148531U (en) * 2011-07-23 2012-02-22 中铁二院工程集团有限责任公司 Sand layer cut slope ecological protection structure
CN102953353A (en) * 2012-11-14 2013-03-06 河海大学 Microbial river embankment reinforcement ecological slope protection technology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0819330A (en) * 1994-05-02 1996-01-23 Saikou:Kk Reinforced soil and vegetation construction using soil fiber, soil-reinforcing material and vegetation base material consisting of soil fiber
KR20040017387A (en) * 2002-08-21 2004-02-27 김영섭 Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device
CN2851347Y (en) * 2005-12-27 2006-12-27 四平市水利勘测设计研究院 Reinforced earth structured revetment retaining wall
CN201158826Y (en) * 2008-02-25 2008-12-03 山东玮丰达建筑工程有限公司 Earth work grille reinforced retaining wall
CN202148531U (en) * 2011-07-23 2012-02-22 中铁二院工程集团有限责任公司 Sand layer cut slope ecological protection structure
CN102953353A (en) * 2012-11-14 2013-03-06 河海大学 Microbial river embankment reinforcement ecological slope protection technology

Also Published As

Publication number Publication date
CN104005370A (en) 2014-08-27

Similar Documents

Publication Publication Date Title
CN202718138U (en) Self-locking type ecological retaining wall structure
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN202298556U (en) Novel prevention structure for landslide converting-type debris flow
CN207760804U (en) A kind of Multi-functional economy dike structure
CN109183809B (en) Construction method for replacing support of composite support of muddy clay deep foundation pit engineering
CN105887757A (en) Ecological slope protection composite retaining wall structure and construction method
CN104234061A (en) Reinforced ecological concrete revetment and construction method thereof
CN104005370B (en) The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN202430681U (en) Bank protection structure
CN107059882A (en) Arch anchor net and Anchor-Pile Retaining Structure structure
CN102966072A (en) Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN107012871A (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation ditch fabricated construction
CN206693140U (en) A kind of protection slope
CN205502063U (en) Combined type retaining structure
CN107503323B (en) A kind of method of construction of ecological slope protection
CN201981551U (en) Supporting and retaining structure by combining iron-rib ecological retaining wall with concrete retaining wall
CN207032212U (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN205776070U (en) Ecological revetment is combined retaining wall structure
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN210482339U (en) Embankment side slope protection system
CN102425179B (en) Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile
CN107178088A (en) A kind of basement waterproofing foundation pit structure and its construction method
CN107299646A (en) Ecological Retaining Wall structure and its method of construction
CN215441846U (en) Foundation anti-settling structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant