CN107178088A - A kind of basement waterproofing foundation pit structure and its construction method - Google Patents

A kind of basement waterproofing foundation pit structure and its construction method Download PDF

Info

Publication number
CN107178088A
CN107178088A CN201710253029.4A CN201710253029A CN107178088A CN 107178088 A CN107178088 A CN 107178088A CN 201710253029 A CN201710253029 A CN 201710253029A CN 107178088 A CN107178088 A CN 107178088A
Authority
CN
China
Prior art keywords
basement
foundation pit
pile
stand column
reinforcing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710253029.4A
Other languages
Chinese (zh)
Other versions
CN107178088B (en
Inventor
胡涛
彭道艳
袁国新
李冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Zhengyuan Geotechnical Technology Co., Ltd.
Original Assignee
Wuhan Chi And Geotechnical Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Chi And Geotechnical Engineering Co Ltd filed Critical Wuhan Chi And Geotechnical Engineering Co Ltd
Priority to CN201710253029.4A priority Critical patent/CN107178088B/en
Publication of CN107178088A publication Critical patent/CN107178088A/en
Application granted granted Critical
Publication of CN107178088B publication Critical patent/CN107178088B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • E02D19/185Joints between sheets constituting the sealing aprons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The present invention relates to building underground engineering field, and in particular to a kind of basement waterproofing foundation pit structure and its construction method, a kind of basement waterproofing foundation pit structure, including:The stake of many root posts and engineering pile in basement main body, foundation pit enclosure wall, basement reinforcing anti-seepage layer and foundation ditch, a piece stand column pile connects into a stanchion with an engineering pile, engineering pile is arranged on below stand column pile in the stanchion, it is concordant with foundation ditch elevation of top at the top of the engineering pile bottom insertion water barrier or rock stratum, the stand column pile;The foundation pit enclosure wall is arranged on basement body side, and the basement bottom part body is provided with basement bottom board;The foundation pit enclosure wall is to form diaphram wall by the way of the spliced prefabricated panel of polylith mutually splices;The basement reinforcing anti-seepage layer is arranged on the lower section of the basement bottom board, and its side is connected with the foundation pit enclosure wall, and Formation cross-section is the structure of " H " shape.

Description

A kind of basement waterproofing foundation pit structure and its construction method
Technical field
The present invention relates to building underground engineering field, and in particular to a kind of basement waterproofing foundation pit structure and its construction party Method.
Background technology
At present, similar Wuhan I grades of terraces diadactic structure geologic feature, the fine-grained sediment layer of top overbank phase, bottom is river The coarse grain sedimentary of bed phase, bottom is the geologic structure of rock stratum, to reach the effect of sealing, prevents periphery soil layer from drawing water sedimentation often In the following ways:1st, lithosphere or other clay water barriers are arrived in seepage proof curtain construction, are set according to design requirement before curtain Other retaining structures such as bored concrete pile;2nd, the cast-in-place diaphram wall that antiseepage and retaining structure are integrated, wall depth equally reaches Lithosphere or water barrier, while as water proof antiseepage and retaining structure, leakage preventing structure runs through the diaphram wall of whole Soft Soil Layer Underground water can effectively be completely cut off and pour in basement.This form of construction work has the following disadvantages:1st, diaphragm wall depth is big, construction cost Height, on the basis of hole bottom Resistant heave and stability requirement is met, usual diaphram wall, which will typically surpass, beats depth more than 2 to 4 times; 2nd, cast-in-situ wall is deeper, because degree control is more difficult, is difficult to ensure that into the big pouring quality of groove depth, so with causing adjacent width Weak part is easily formed at lower continuous wall connector;Cause percolating water hidden danger, cause surrounding ground to collapse and threaten foundation ditch stabilization.
The content of the invention
The problem of purpose of the present invention is to solve in background technology there is provided a kind of basement waterproofing foundation pit structure and Its construction method.
The present invention above-mentioned technical purpose technical scheme is that:
A kind of basement waterproofing foundation pit structure, including:Basement main body, foundation pit enclosure wall, basement reinforcing anti-seepage layer and foundation ditch Interior many root posts stake and engineering pile, a stand column pile connect into a stanchion, the stanchion with an engineering pile Middle engineering pile is arranged on below stand column pile, the engineering pile bottom insertion water barrier or rock stratum, the stand column pile top and foundation ditch Elevation of top is concordant;The foundation pit enclosure wall is arranged on basement body side, and the basement bottom part body is provided with underground Room bottom plate;The foundation pit enclosure wall is to form diaphram wall by the way of the spliced prefabricated panel of polylith mutually splices;Institute The lower section that basement reinforcing anti-seepage layer is arranged on the basement bottom board is stated, its side is connected with the foundation pit enclosure wall, shape Into the structure that section is " H " shape.
Preferably, the both sides of the spliced prefabricated panel are provided between assembled portion, the spliced prefabricated panel It is connected by assembled portion, half mouthful of grouting, the grouting of adjacent two pieces of spliced prefabricated panels is provided with the assembled portion Half mouthful after splicing, forms grouting chamber.
Preferably, being provided with the splicing bar being mutually matched and splicing groove in the assembled portion.
Preferably, the grouting intracavitary is provided with reinforcing bar and concrete.
Preferably, being provided with perforate on the length direction of the spliced prefabricated panel.
Preferably, being provided with reinforcing bar and concrete in the perforate.
Preferably, being set between the stand column pile stake bottom and engineering pile stake top and having grouting layer.
Assembled structure diaphram wall is carried out using spliced prefabricated panel, scene is greatly reduced pours the time, carries High efficiency of construction, also, be not in because scene for pouring continuous wall compared to tradition because wallboard is prefabricated The problems such as bubbling that pours and produce, crack, the water resistance of prefabricated panel is very reliable.Meanwhile, enter further through to grouting chamber Row is poured, and thoroughly solves the hidden danger of stitching portion infiltration.
Preferably, being provided with the armored concrete Guan Liang of closing at the top of the foundation pit enclosure wall.
A kind of construction method of basement waterproofing foundation pit structure, comprises the following steps,
(One)Foundation pile engineering construction:To being constructed in foundation ditch using one pile for one column mode, the one pile for one column refers to foundation ditch Inner column stake and the stanchion connected into of engineering pile, engineering pile are bored concrete pile, and stand column pile is concrete filled steel tube stand column pile, engineering pile It is arranged on below stand column pile, engineering pile bottom insertion water barrier or rock stratum, once designed elevation is arrived in construction at the top of stand column pile;Construction The middle perpendicularity for ensureing stand column pile, carries out grouting behind shaft or drift lining process, to ensure the bearing capacity of stand column pile and subtract to stake bottom and stake middle side part Few sedimentation;
(Two)Groundwater pressure is controlled, before foundation pit enclosure wall, basement reinforcing anti-seepage layer are built, the pressure of underground water is controlled Power, prevents from bottom heave and dashes forward to gush generation;
(Three)Foundation ditch is slotted, and opens up the supporting wall chase installed to foundation pit enclosure wall;
(Four)Diaphram wall is installed, after spliced splicing prefabricated wallboard is installed in supporting wall chase, will be filled using grouting way Slurry chamber and perforate are filled up, it is ensured that diaphram wall is firmly impermeable;
(Five)Basement reinforcing anti-seepage layer building, is changed the soil property of basement bottom by the way of injecting paste material high-pressure grouting Property, one piece of waterproof layer being connected with foundation pit enclosure is formed, basement reinforcing anti-seepage layer is used as;Basement reinforcing anti-seepage layer and base Pit enclosure forms the structure that a longitudinal cross-section is " H " type, i.e. basement reinforcing anti-seepage layer depth in Soft Soil Layer and is more than underground The depth of room bottom plate is less than the depth of foundation pit enclosure;
(Six)Earth excavation, digs out the earthwork in basement main body, and carry out basement floor build construction.
Preferably, in the step 2, Groundwater Control pressure mode is, in detection construction area artesian water buried depth and Head height, with reference to excavation of foundation pit depth, controls underground water using dewatering well and inverted well combined technology, prevents bottom heave And it is prominent gush generations, during earth excavation and basement reinforcing anti-seepage layer is constructed before forming intensity, artesian aquifer precipitation Well maintains pressure and keeps working condition.
Preferably, in the step 4, the armored concrete Guan Liang of closing should be set at the top of diaphram wall;Guan Liang Height and width are determined by calculating, and width is not preferably less than the thickness of diaphram wall, and diaphram wall is constructed using framing, wall Top sets elongated top beam in favor of strengthening the globality of diaphram wall, and top beam preferably meets Tu Mianping with diaphram wall Together, wall is led to retain, earth-retaining bank protection is played a part of to the wall top above soil body, it is to avoid have a negative impact to surrounding enviroment, The depth of underground continuous wall top insertion collar tie beam is not preferably less than 50mm, and the length that longitudinal reinforcement is anchored into collar tie beam is preferably anchored by tension It is required that determining.
Preferably, in the step 5, in high-pressure grouting, irrigating antiseepage extended layer, institute simultaneously outside foundation pit enclosure State antiseepage extended layer and extend 1~2 meter to outside foundation ditch.
Preferably, in the step 5, injecting paste material is injected into basement from foundation ditch top high-voltage by grout hole and added Gu 2 ~ 4 meters below impervious barrier position, the perforate depth for the stating grout hole room bottom plate located underground, carried out in grout hole after mud jacking Basement reinforcing anti-seepage layer is formed in the bottom of basement.
In summary, beneficial effects of the present invention:
1. a kind of basement waterproofing foundation pit structure of the present invention, foundation pit construction quality is easily controlled, and the waterproof of basement is good And it is easy to monitoring, quality control and repair and maintenance are easy.
2. a kind of basement waterproofing foundation pit structure of the present invention, it is not necessary to arrive the depth construction of foundation pit enclosure wall Subsurface rock layer, has saved building materials and engineering time, and foundation pit enclosure wall and basement reinforcing anti-seepage layer knot by " H " shape Structure, effectively prevent the seepage of underground water.
3. a kind of construction method of basement waterproofing foundation pit structure of the present invention, using spliced prefabricated panel, subtracts Lack scene and the time is poured to diaphram wall, efficiency of construction of having made a draft, and the stitching portion of spliced prefabricated panel is entered Row pours to strengthen water resistance.
Brief description of the drawings
Fig. 1 is the scheme of installation of neutral stanchion of the invention and engineering pile;
Fig. 2 is the structure schematic diagram of basement reinforcing anti-seepage layer in the present invention;
Fig. 3 is the structural representation of basement main body of the present invention;
Fig. 4 is the assembling schematic diagram of spliced prefabricated panel in the present invention;
Fig. 5 is the connection diagram of neutral stanchion of the invention and engineering pile.
Embodiment
Specific examples below is only explanation of the invention, and it is not limitation of the present invention, art technology Personnel can make the modification without creative contribution to the present embodiment as needed after this specification is read, but as long as All protected in scope of the presently claimed invention by Patent Law.
With embodiment, the present invention is described in detail below in conjunction with the accompanying drawings.
Embodiment 1:
According to Fig. 1~Fig. 5, a kind of basement waterproofing foundation pit structure, including:Basement main body 5, foundation pit enclosure wall 1, underground Many root posts stake 3 and engineering pile 4 in room reinforcing anti-seepage floor 2 and foundation ditch, root post stake 3 and an engineering pile 4 connect into one Engineering pile 4 is arranged on the lower section of stand column pile 3, the bottom of engineering pile 4 insertion water barrier or rock stratum, the top of stand column pile 3 in individual stanchion, stanchion It is concordant with foundation ditch elevation of top, according to Fig. 5, set between 3 bottoms of stand column pile and the stake top of engineering pile 4 and have grouting layer;Base Pit enclosure wall 1 is arranged on the side of basement main body 5, and the bottom of basement main body 5 is provided with basement bottom board 6;Foundation pit enclosure wall 1 is Diaphram wall is formed by the way of the spliced prefabricated panel 100 of polylith mutually splices, the top of foundation pit enclosure wall 1 is provided with envelope The armored concrete Guan Liang closed;Basement reinforcing anti-seepage layer 2 is arranged on the lower section of basement bottom board 6, its side and foundation pit enclosure Wall 1 is connected, and Formation cross-section is the structure of " H " shape.
According to Fig. 4, the both sides of spliced prefabricated panel 100 are provided with assembled portion 110, spliced prefabricated panel 100 Between be connected by assembled portion 110, be provided with assembled portion 110 grouting half mouthful 113, adjacent two pieces of spliced prefabricated panels 100 half mouthful 113 of grouting forms in grouting chamber 114, assembled portion 110 after splicing and is provided with the He of splicing bar 111 being mutually matched Splice to be provided with reinforcing bar 115 and concrete, the length direction of spliced prefabricated panel 100 in groove 112, grouting chamber 114 and set Have in perforate 120, perforate 120 and be provided with reinforcing bar 115 and concrete.
According to Fig. 1, Fig. 2 and Fig. 3, a kind of construction method of basement waterproofing foundation pit structure comprises the following steps,
First, foundation pile engineering construction:To being constructed in foundation ditch using one pile for one column mode, one pile for one column is referred in foundation ditch and stood The stanchion connected into of stanchion 3 and engineering pile 4, engineering pile 4 is bored concrete pile, and stand column pile 3 is concrete filled steel tube stand column pile, engineering pile 4 are arranged on the lower section of stand column pile 3, the bottom of engineering pile 4 insertion water barrier or rock stratum, and once designed elevation is arrived in construction to the top of stand column pile 4; Ensure the perpendicularity of stand column pile 3 in construction, grouting behind shaft or drift lining process is carried out to stake bottom and stake middle side part, to ensure the carrying of stand column pile 3 Power simultaneously reduces sedimentation.
2nd, groundwater pressure is controlled, before foundation pit enclosure wall 1, basement reinforcing anti-seepage layer 2 are built, construction area is detected Artesian water buried depth and head height in domain, with reference to excavation of foundation pit depth, control ground using dewatering well and inverted well combined technology Launching stress, during earth excavation and before the construction of basement reinforcing anti-seepage layer 2 forms intensity, artesian aquifer dewatering well Maintain pressure and keep working condition, prevent from bottom heave and dash forward to gush generation.
3rd, foundation ditch is slotted, and opens up the supporting wall chase installed to foundation pit enclosure wall 1.
The 4th, diaphram wall is installed, after the spliced splicing of prefabricated panel 100 is installed in supporting wall chase, using grouting side To be in the milk chamber 114 and perforate 120 of formula is filled up, it is ensured that diaphram wall is firmly impermeable;Closing is set at the top of diaphram wall Armored concrete Guan Liang;Guan Liang width is not preferably less than the thickness of diaphram wall, and diaphram wall is constructed using framing, and wall top is set Elongated top beam is put in favor of strengthening the globality of diaphram wall, it is concordant that top beam preferably meets native face with diaphram wall, with Just retain and lead wall, earth-retaining bank protection is played a part of to the wall top above soil body, it is to avoid have a negative impact to surrounding enviroment, underground connects The depth of continuous wall wall top insertion collar tie beam is not preferably less than 50mm, and the length that longitudinal reinforcement is anchored into collar tie beam preferably anchors requirement really by tension It is fixed.
5th, basement reinforcing anti-seepage layer 2 is built, by the soil property of basement bottom by the way of injecting paste material high-pressure grouting Modified, injecting paste material is injected into 2 position of basement reinforcing anti-seepage layer by grout hole 201 from foundation ditch top high-voltage, states grout hole 2 ~ 4 meters below 201 perforate depth room bottom plate located underground, formed after carrying out mud jacking in grout hole 201 in the bottom of basement One piece of waterproof layer for being connected with foundation pit enclosure 1, is used as basement reinforcing anti-seepage layer 2;Basement reinforcing anti-seepage layer 2 encloses with foundation ditch Shield 1 forms the structure that a longitudinal cross-section is " H " type, i.e. 2 depth of basement reinforcing anti-seepage layer in Soft Soil Layer and is more than basement The depth of bottom plate 6 is less than the depth of foundation pit enclosure 1, and basement reinforcing anti-seepage 2 thickness of layer are 2 ~ 3 meters, and in high-pressure grouting, Simultaneously in the outer filling antiseepage extended layer 21 of foundation pit enclosure 1, antiseepage extended layer 21 extends 1~2 meter to outside foundation ditch.
6th, earth excavation, digs out the earthwork in basement main body 5, and carry out basement floor build construction.

Claims (10)

1. a kind of basement waterproofing foundation pit structure, it is characterised in that including:Basement main body(5), foundation pit enclosure wall(1), underground Room reinforcing anti-seepage floor(2)With many root posts stake in foundation ditch(3)With engineering pile(4), a stand column pile(3)With described in one Engineering pile(4)Connect into engineering pile in a stanchion, the stanchion(4)It is arranged on stand column pile(3)Lower section, the engineering pile(4) Bottom is embedded in water barrier or rock stratum, the stand column pile(3)Top is concordant with foundation ditch elevation of top;The foundation pit enclosure wall(1)If Put in basement main body(5)Sideways, the basement main body(5)Bottom is provided with basement bottom board(6);The foundation pit enclosure wall (1)To use the spliced prefabricated panel of polylith(100)The mode mutually spliced forms diaphram wall;The basement is reinforced anti- Infiltration layer(2)It is arranged on the basement bottom board(6)Lower section, its side and the foundation pit enclosure wall(1)It is connected, Formation cross-section For the structure of " H " shape.
2. a kind of basement waterproofing foundation pit structure according to claim 1, it is characterised in that the spliced prefabricated panel (100)Both sides be provided with assembled portion(110), the spliced prefabricated panel(100)Between pass through assembled portion(110)It is connected Connect, the assembled portion(110)Inside it is provided with half mouthful of grouting(113), adjacent two pieces of spliced prefabricated panels(100)Grouting Half mouthful(113)After splicing, grouting chamber is formed(114).
3. a kind of basement waterproofing foundation pit structure according to claim 1 or 2, it is characterised in that the assembled portion(110) On be provided with the splicing bar being mutually matched(111)With splicing groove(112).
4. a kind of basement waterproofing foundation pit structure according to claim 3, it is characterised in that the grouting chamber(114)It is interior It is provided with reinforcing bar(115)And concrete.
5. a kind of basement waterproofing foundation pit structure according to claim 4, it is characterised in that the spliced prefabricated panel (100)Length direction on be provided with perforate(120).
6. a kind of basement waterproofing foundation pit structure according to claim 5, it is characterised in that the perforate(120)Inside set It is equipped with reinforcing bar(115)And concrete.
7. a kind of basement waterproofing foundation pit structure according to claim 1, it is characterised in that the stand column pile(3)Stake bottom With engineering pile(4)Set between stake top and have grouting layer.
8. a kind of construction method of basement waterproofing foundation pit structure, it is characterised in that comprise the following steps,
(One)Foundation pile engineering construction:To being constructed in foundation ditch using one pile for one column mode, the one pile for one column refers to foundation ditch Inner column stake(3)With engineering pile(4)The stanchion connected into, engineering pile(4)For bored concrete pile, stand column pile(3)For concrete filled steel tube Stand column pile, engineering pile(4)It is arranged on stand column pile(3)Lower section, engineering pile(4)Bottom is embedded in water barrier or rock stratum, stand column pile(4)Top Once construct to designed elevation in portion;Ensure stand column pile in construction(3)Perpendicularity, grouting behind shaft or drift lining work is carried out to stake bottom and stake middle side part Sequence, to ensure stand column pile(3)Bearing capacity and reduce sedimentation;
(Two)Groundwater pressure is controlled, in foundation pit enclosure wall(1), basement reinforcing anti-seepage layer(2)Before building, underground water is controlled Pressure, prevent bottom heave and prominent gush generation;
(Three)Foundation ditch is slotted, and is opened up to foundation pit enclosure wall(1)The supporting wall chase of installation;
(Four)Diaphram wall, spliced prefabricated panel are installed(100)After splicing is installed in supporting wall chase, using grouting way To be in the milk chamber(114)And perforate(120)Fill up, it is ensured that diaphram wall is firmly impermeable;
(Five)Basement reinforcing anti-seepage layer(2)Build, by the soil property of basement bottom by the way of injecting paste material high-pressure grouting It is modified, form one piece and foundation pit enclosure(1)The waterproof layer being connected, is used as basement reinforcing anti-seepage layer(2);Basement is reinforced anti- Infiltration layer(2)With foundation pit enclosure(1)The structure that a longitudinal cross-section is " H " type, i.e. basement reinforcing anti-seepage are formed in Soft Soil Layer Layer(2)Depth is more than basement bottom board(6)Depth be less than foundation pit enclosure(1)Depth;
(Six)Earth excavation, digs out basement main body(5)The interior earthwork, and carry out basement floor build construction.
9. a kind of construction method of basement waterproofing foundation pit structure according to claim 8, it is characterised in that the step In five, in high-pressure grouting, in foundation pit enclosure(1)It is outer to irrigate antiseepage extended layer simultaneously(21).
10. a kind of construction method of basement waterproofing foundation pit structure according to claim 8, it is characterised in that the step In rapid five, injecting paste material passes through grout hole(201)Basement reinforcing anti-seepage layer is injected into from foundation ditch top high-voltage(2)Position, institute State grout hole(201)Perforate depth room bottom plate located underground below 2 ~ 4 meters, grout hole(201)On ground after interior carry out mud jacking Basement reinforcing anti-seepage floor is formed on the bottom of lower room(2).
CN201710253029.4A 2017-04-18 2017-04-18 A kind of basement waterproofing foundation pit structure and its construction method Active CN107178088B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710253029.4A CN107178088B (en) 2017-04-18 2017-04-18 A kind of basement waterproofing foundation pit structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710253029.4A CN107178088B (en) 2017-04-18 2017-04-18 A kind of basement waterproofing foundation pit structure and its construction method

Publications (2)

Publication Number Publication Date
CN107178088A true CN107178088A (en) 2017-09-19
CN107178088B CN107178088B (en) 2019-02-15

Family

ID=59830881

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710253029.4A Active CN107178088B (en) 2017-04-18 2017-04-18 A kind of basement waterproofing foundation pit structure and its construction method

Country Status (1)

Country Link
CN (1) CN107178088B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110056011A (en) * 2019-04-17 2019-07-26 周峻宇 A kind of basement ground waterproof structure and construction technology
CN111236245A (en) * 2020-01-10 2020-06-05 深圳市蛇口招商港湾工程有限公司 Small foundation pit excavation protection structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201835293U (en) * 2010-10-29 2011-05-18 贵阳铝镁设计研究院 Structure of post-cast strip for underground building
CN102127974A (en) * 2011-04-18 2011-07-20 上海现代建筑设计(集团)有限公司 Design and construction method of additional cellar under existing building
CN103103988A (en) * 2013-01-21 2013-05-15 安徽省城建设计研究院 Foundation ditch construction method of horizontal bracing structure of central island floor slaps
JP2015117545A (en) * 2013-12-19 2015-06-25 鹿島建設株式会社 Construction method for underground tunnel
CN204898684U (en) * 2015-08-11 2015-12-23 泰兴市第一建筑安装工程有限公司 Super dark excavation supporting system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201835293U (en) * 2010-10-29 2011-05-18 贵阳铝镁设计研究院 Structure of post-cast strip for underground building
CN102127974A (en) * 2011-04-18 2011-07-20 上海现代建筑设计(集团)有限公司 Design and construction method of additional cellar under existing building
CN103103988A (en) * 2013-01-21 2013-05-15 安徽省城建设计研究院 Foundation ditch construction method of horizontal bracing structure of central island floor slaps
JP2015117545A (en) * 2013-12-19 2015-06-25 鹿島建設株式会社 Construction method for underground tunnel
CN204898684U (en) * 2015-08-11 2015-12-23 泰兴市第一建筑安装工程有限公司 Super dark excavation supporting system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110056011A (en) * 2019-04-17 2019-07-26 周峻宇 A kind of basement ground waterproof structure and construction technology
CN111236245A (en) * 2020-01-10 2020-06-05 深圳市蛇口招商港湾工程有限公司 Small foundation pit excavation protection structure and construction method thereof

Also Published As

Publication number Publication date
CN107178088B (en) 2019-02-15

Similar Documents

Publication Publication Date Title
CN105464686B (en) Multi-layer underground space curtain posture excavating construction method and supporting construction under existing facility
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN103741714A (en) Construction method for full cover-excavation reverse method of underground engineering
CN105464134B (en) Multi-layer underground space is along inverse combining construction method and supporting construction under existing facility
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN104612143A (en) Bored composite pile structure under karst cave/soil cave geological condition
US20160376762A1 (en) Construction method for planting hollow columns in a seabed of a marine environment for supporting waterborne structures thereon
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN107178088B (en) A kind of basement waterproofing foundation pit structure and its construction method
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
US20140026518A1 (en) Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
CN107012871B (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction
CN102425179B (en) Structure of reinforced soil sewer supported by bored concrete piles of mini steel tubes
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN105862721A (en) Grouting composite ground suitable for consolidation and deviation rectification of high-rise building structure and provided with adjustable pre-buried steel pipe and construction method thereof
CN108570997A (en) Cofferdam and construction method are built in returning for seabed tunnel point storehouse construction
CN101603311B (en) Jet grouting pile construction method adopting heavy hammer-tamping compaction soil preformed hole
CN104110038A (en) Construction method for large-area pit support structure in deep-sludge type soft soil area
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
CN110512613A (en) A kind of red sand rock stratum water proof combined bolting and shotcrete method and its water barrier device
CN205530218U (en) Slip casting composite foundation suitable for high -rise building structural strengthening is rectified
CN202007407U (en) Deep foundation pit supporting system
CN105887757A (en) Ecological slope protection composite retaining wall structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190102

Address after: 430000 Training Building No. 312-A43, 3rd Floor, Dawning Plaza, 465 Guanshan Avenue, Donghu New Technology Development Zone, Wuhan City, Hubei Province

Applicant after: Wuhan Zhengyuan Geotechnical Technology Co., Ltd.

Address before: 430061 Jiaxin Garden, Xujiapeng, Wuchang District, Wuhan City, Hubei Province, Phase 2, 1 Building, 1 Unit 1802

Applicant before: Wuhan Chi and Geotechnical Engineering Co., Ltd.

TA01 Transfer of patent application right
GR01 Patent grant