KR20040017387A - Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device - Google Patents

Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device Download PDF

Info

Publication number
KR20040017387A
KR20040017387A KR1020020049438A KR20020049438A KR20040017387A KR 20040017387 A KR20040017387 A KR 20040017387A KR 1020020049438 A KR1020020049438 A KR 1020020049438A KR 20020049438 A KR20020049438 A KR 20020049438A KR 20040017387 A KR20040017387 A KR 20040017387A
Authority
KR
South Korea
Prior art keywords
grid
bar
reinforcement
fixing
construction
Prior art date
Application number
KR1020020049438A
Other languages
Korean (ko)
Inventor
정구상
김영섭
Original Assignee
김영섭
정구상
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김영섭, 정구상 filed Critical 김영섭
Priority to KR1020020049438A priority Critical patent/KR20040017387A/en
Publication of KR20040017387A publication Critical patent/KR20040017387A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/13Geometrical or physical properties having at least a mesh portion
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0084Geogrids
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Ocean & Marine Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PURPOSE: A grid-fixing unit for construction of mechanically stabilized earth walls and reinforced soil slopes and a construction method in a banking area and a cutting area using the grid-fixing unit are provided to construct the mechanically stabilized earth walls and reinforced soil slopes by applying a grid even when the securing of the reinforcing length of the grid is impossible. CONSTITUTION: A grid-fixing unit for construction of mechanically stabilized earth walls and reinforced soil slopes includes plural fixing bars(30) having drawing resistance force; reinforcing bars(40) combined to the fixing bars to connect the fixing bars at a predetermined height from the ground(10); and a grid(50). One end of the fixing bar is inserted into the ground of a banking area or a cutting area for constructing the mechanically stabilized earth walls and reinforced soil slopes, and the other end of the fixing bar is projected onto the ground. The end of the grid positioned to banked subsoil of the banking area or the cutting area is wound around the reinforcing bar and fixed.

Description

보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구 및 그를 이용한 성토부 및 절토부에서의 시공방법{GRID FIXING DEVICE FOR CONSTRUCTING OF MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES AND CONSTRUCT METHOD OF EXISTING BANKING AREA AND CUTTING AREA USING THE DEVICE}GRID FIXING DEVICE FOR CONSTRUCTING OF MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES AND CONSTRUCT METHOD OF EXISTING BANKING AREA AND CUTTING AREA USING THE DEVICE}

본 발명은 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구 및 그를 이용한 (기존) 성토부 및 절토부의 시공방법에 관한 것으로서, 좀 더 구체적으로는사면의 지반상태가 불량한 경우 또는 절토 면적을 작게 해야 하는 경우에도 그리드를 적용하여 시공할 수 있도록 하는 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구 및 그를 이용한 (기존) 성토부 및 절토부의 시공방법에 관한 것이다.The present invention relates to a grid fixing mechanism for the construction of reinforcement soil retaining wall and reinforcement slope, and to the construction method of (existing) fill portion and cut portion using the same, more specifically, when the ground state of the slope is poor or the cut area should be reduced. It also relates to a grid fixing mechanism for the construction of the reinforcement soil retaining wall and reinforcement slope to be applied by applying the grid, and the construction method (existing) fill and cut section using the same.

보강재(뒤채움재)를 이용한 보강토 공법에는 크게 보강토 옹벽(MSEW, Mechanically stabilized earth walls)과 보강사면(RSS, Reinforced soil slopes)이 있다. 보강토 옹벽은 도 1에서 보인 바와 같이 시공되는 형태로 보강재인 그리드(14)를 포설하여 다짐된 지반에 다양한 콘크리트 표면으로 마감 처리하는 방법이고, 보강사면은 도 2에서 보인 바와 같이 시공되는 형태로 뒤채움재의 요구조건이 보강토 옹벽보다 다소 덜 엄격하며 나빠도 70°정도까지 사면 경사도를 줄 수 있다. 일반적으로 사면 경사도가 45°이상이면 그리드를 휘감아서 시공된다.The reinforcement soil method using reinforcement (backfill) has largely mechanically stabilized earth walls (MSEW) and reinforced soil slopes (RSS). Reinforcement soil retaining wall is a method of installing the reinforcement grid 14 in the form of the construction as shown in Figure 1 to finish the various concrete surfaces on the compacted ground, the reinforcement slope is as shown in Figure 2 Filler requirements are somewhat less stringent than reinforced earth retaining walls, and can worsen slopes up to 70 °. Generally, when the slope is more than 45 °, it is constructed by winding the grid.

도 1 및 도 2를 참조하면, 보강토 옹벽은 배면에 자연상태의 지반(10)과 이 지반(10)의 절토면에 채워지는 토층(12) 및 전면에 적층되어 설치되는 블록층(또는 판넬층)(16)으로 이루어지고, 보강사면은 지반(10) 및 토층(12)으로 이루어진다. 여기에 사용되는 그리드(Grid)(14)는 보강재 또는 지반보강재와 동일한 용어로서 일례에는 특수자재판매 주식회사가 'Tensar Giogrid'라는 상품명으로 판매하고 있는 것이 있다. 이 그리드(14)는 고밀도 폴리에틸렌(HDPE, high density polyethylene) 재질의 망구조를 가지고 있는 것으로 토층(12) 내부에 수평으로 설치된다. 이와 같은 그리드(14)의 사용은 구조적 안정성뿐만 아니라 공사현장에 있는 굴착토를 재활용할 수 있도록 하고, 블록층의 축조와 동시에 토층 작업을 진행할 수 있어 공기단축이 가능하는 등 다양한 잇점을 가지고 있다.Referring to FIGS. 1 and 2, the reinforcement soil retaining wall has a ground layer 10 in its natural state, a soil layer 12 filled in the cut surface of the ground 10, and a block layer (or panel layer) stacked on the front surface. It consists of (16), the reinforcement slope consists of the ground 10 and the soil layer (12). The grid 14 used here is the same term as the reinforcing material or ground reinforcing material. For example, the special material sales company sells it under the trade name "Tensar Giogrid". The grid 14 has a network structure made of high density polyethylene (HDPE) and is horizontally installed inside the soil layer 12. The use of such a grid (14) has various advantages such as not only structural stability, but also to recycle the excavated soil in the construction site, and it is possible to shorten the air to proceed with the ground work at the same time as the construction of the block layer.

안전한 보강토 옹벽 및 보상사면의 시공을 위해 그리드(14)가 매우 중요하다. 특히 그리드의 보강길이는 조건에 따라 각기 다르지만 보강토 옹벽에서는 옹벽 높이의 약 0.7배 정도를 유지하도록 설계 기준 등에서 규정하고 있고 보강사면에서는 안전성 검토에 의해 결정하고 가능한 길게 하도록 하고 있다.The grid 14 is very important for the construction of safe reinforced retaining walls and compensating slopes. In particular, the reinforcement length of the grid is different depending on the conditions, but the design criteria, etc., maintain about 0.7 times the height of the retaining wall in the reinforced earth retaining wall, and the reinforcement slope is determined by the safety review and is made as long as possible.

그러나 그리드의 보강길이(L)를 확보할 수 없는 경우나 절토 면적을 최소화하여 기존 시설을 활용하면서 시공해야 하는 기존 성토부 또는 자연훼손을 작게 하기 위하여 절토면적을 작게하는 절토부에는 그리드를 사용하여 시공할 수 없는 문제점이 있다.However, when the reinforcement length (L) of the grid cannot be secured or the existing cut part that has to be constructed while minimizing the cut area, or the cut part that reduces the cut area in order to reduce the natural damage, the grid is used. There is a problem that can not be installed.

본 발명은 이와 같은 문제점을 해결하기 위한 것으로, 그 목적은 그리드의 보강길이를 확보할 수 없는 경우 및 절토 면적을 크게 하기 어려운 경우에도 그리드를 적용하여 시공할 수 있도록 하는 새로운 형태의 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구 및 그를 사용한 성토부 및 절토부의 시공방법을 제공하는데 있다.The present invention has been made to solve the above problems, and its object is to provide a new type of reinforcement soil retaining wall and reinforcement to apply the grid even when the reinforcement length of the grid cannot be secured and when the cut area is difficult to increase. It is to provide a grid fixing mechanism for the construction of the slope and the construction method of the fill section and cut section using the same.

도 1은 그리드를 사용하여 시공된 보강토 옹벽의 일례를 보여주는 도면;1 shows an example of a reinforced earth retaining wall constructed using a grid;

도 2는 그리드를 사용하여 시공된 보강사면의 일례를 보여주는 도면;2 shows an example of a reinforcement slope constructed using a grid;

도 3은 기존 성토부에 추가로 성토하여 구조물을 축조하는 경우를 설명하기 위한 도면;3 is a view for explaining a case of constructing a structure by additionally filling the existing fill portion;

도 4는 본 발명의 바람직한 실시예에 따른 그리드 고정기구를 설명하기 위한 도면;4 is a view for explaining a grid fixing mechanism according to a preferred embodiment of the present invention;

도 5는 도 4에서 고정 바인 락 볼트 또는 소일 네일 등에 보강바인 철근이 결합된 상태를 보여주는 평면도;FIG. 5 is a plan view illustrating a state in which a reinforcing bar reinforcing bar is coupled to a lock bolt or a soy nail in FIG. 4;

도 6는 도 5에서 라인 6-6을 따라 절취한 단면도;6 is a cross-sectional view taken along line 6-6 in FIG. 5;

도 7은 도 5에서 라인 7-7을 따라 절취한 단면도;7 is a cross-sectional view taken along line 7-7 in FIG. 5;

도 8a는 본 발명의 바람직한 실시예에서 고정바의 다른 예와 보강바의 결합형태를 보여주는 도면;Figure 8a is a view showing a coupling form of another example of the fixed bar and the reinforcement bar in a preferred embodiment of the present invention;

도 8b는 본 발명의 바람직한 실시예에서 고정바의 다른 연결방법을 이용하여보강바의 결합형태를 보여주는 도면;Figure 8b is a view showing the coupling form of the reinforcing bar using another connection method of the fixing bar in a preferred embodiment of the present invention;

도 9는 보강바와 그리드의 결합상태를 상세히 보여주는 평면도;9 is a plan view showing in detail the coupling state of the reinforcing bar and the grid;

도 10은 일반적인 보강토 옹벽의 시공방법을 순차적으로 보여주는 도면;10 is a view sequentially showing a construction method of a general reinforced earth retaining wall;

도 11은 도 10의 시공방법에 본 발명에 따른 그리드 고정기구를 이용한 시공방법을 적용한 예의 주요 공정을 보여주는 플로우 챠트;11 is a flow chart showing the main process of the example of applying the construction method using the grid fixing mechanism according to the present invention to the construction method of FIG.

도 12는 본 발명의 시공방법에 따라 절토부에 시공된 보강토 옹벽의 일례를 보여주는 도면;12 is a view showing an example of a reinforcement soil retaining wall constructed in the cut portion according to the construction method of the present invention;

도 13은 일반적인 보강사면의 시공방법을 순차적으로 보여주는 도면;13 is a view showing the construction method of the general reinforcement slope in sequence;

도 14는 본 발명의 시공방법에 따라 (기존) 성토부에 시공된 보강사면의 일례를 보여주는 도면이다.14 is a view showing an example of the reinforcement slopes constructed in the (existing) fill portion according to the construction method of the present invention.

* 도면의 주요 부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

10 : 지반, 기존 성토부12 : 뒷채움 토층10: ground, existing fill part 12: backfill soil

14, 50 : 그리드16 : 블록층14, 50 grid 16: block layer

20 : 그리드 고정기구30 : 고정바20: grid fixing mechanism 30: fixing bar

40 : 보강바60 : 연결바40: reinforcing bar 60: connecting bar

상술한 목적을 달성하기 위한 본 발명의 특징에 의하면, 본 발명은 그리드의 보강길이를 확보할 수 없는 경우 및 절토 면적을 크게 하기 어려운 경우에도 그리드를 적용하여 보강토 옹벽 및 보강사면을 시공할 수 있도록 하는 그리드 고정기구를 제공한다. 이 그리드 고정기구는 고정바, 보강바, 그리드를 구비하여 이루어진다. 고정바는 인발저항력을 가지며, 보강토 옹벽 및 보강사면을 시공하기 위한 기존 성토부 또는 절토부의 지반에 복수개로 설치된다. 보강바는 지반으로부터 일정한 높이(각각의 그리드가 포설되는 위치)에서 복수개의 고정바를 연결·결합된다. 그리드는 성토부 또는 절토부의 뒷채움 또는 성토되는 토층에 포설되며 그 끝단이 보강바에 감기어 고정된다.According to a feature of the present invention for achieving the above object, the present invention can be applied to the reinforcement soil retaining wall and reinforcing slopes by applying the grid even when the reinforcement length of the grid can not be secured and the cut area is difficult to increase To provide a grid fixture. The grid fixing mechanism includes a fixing bar, a reinforcing bar and a grid. The fixed bar has a pull-out resistance, and is installed in a plurality of grounds or existing cut section for constructing the reinforcement soil retaining wall and the reinforcement slope. The reinforcing bar connects and couples a plurality of fixed bars at a constant height from the ground (the position where each grid is laid). The grid is installed on the backfill or underfill soil layer in the fill or cut section, and its ends are fixed by winding on the reinforcement bar.

이와 같이 본 발명의 청구항 1에 의한 그리드 고정기구에서 상기 그리드는 상기 보강바의 일측으로부터 타측으로 감기어 반대방향으로 연장된 상태에서 상기 그리드의 타측면에 위치되는 연결바가 끝단에 삽입되므로써 고정될 수 있다.Thus, in the grid fixing mechanism according to claim 1 of the present invention, the grid can be fixed by inserting the connecting bar positioned on the other side of the grid at the end in a state in which the grid is wound from one side of the reinforcement bar to the other side and extended in the opposite direction. have.

이와 같이 본 발명의 청구항 1 또는 청구항 2에 의한 그리드 고정기구에서 상기 보강바는 하나 이상의 바가 상기 고정바의 길이 방향으로 서로 이격되어 설치되고, 두개 이상을 이용할 경우 그 사이에는 복수개의 간격 조절편이 일정한 간격으로 설치될 수 있다.As described above, in the grid fixing mechanism according to claim 1 or 2 of the present invention, the reinforcing bar is provided with one or more bars spaced apart from each other in the longitudinal direction of the fixing bar, and when using two or more, a plurality of gap adjusting pieces are fixed therebetween. Can be installed at intervals.

이와 같이 본 발명의 청구항 1 또는 청구항 2에 의한 그리드 고정기구에서 상기 고정바는 공사지반 위로 돌출되는 부분이 'U'자형으로 구부러져 형성된 끝단을 구비하고, 상기 보강바는 상기 끝단의 내측으로 삽입되어 상기 고정바에 결합될 수 있다.As described above, in the grid fixing mechanism according to claim 1 or 2 of the present invention, the fixing bar has an end portion formed by bending a 'U' shape protruding over the construction ground, and the reinforcing bar is inserted into the end of the end. It can be coupled to the fixed bar.

상술한 목적을 달성하기 위한 본 발명의 다른 특징에 의하면, 본 발명은 상기 그리드 고정기구를 사용한 보강토 옹벽 및 보강사면을 시공하기 위한 기존 성토부 또는 절토부의 지반의 일정한 위치에 인발저항력을 갖도록 복수개의 고정바를 설치하는 단계와; 그리드를 상기 고정바와 간섭되는 부분을 피해 두부처리하는 단계와; 상기 복수개의 고정바에 보강바를 고정하여 결합시키는 단계 및; 상기 그리드의 끝단을 상기 보강바에 감아서 고정하는 단계로 이루어진다.According to another feature of the present invention for achieving the above object, the present invention is a plurality of reinforcement soil retaining wall and the reinforcement slope using the grid fixing mechanism to have a pull-out resistance at a predetermined position of the ground of the existing fill section or cut section Installing a fixed bar; Tofu processing a grid avoiding a portion that interferes with the fixing bar; Fixing and reinforcing bars to the plurality of fixing bars; Winding the end of the grid to the reinforcing bar is fixed.

이와 같이 본 발명의 청구항 5에 의한 그리드 고정기구를 이용한 (기존) 성토부 및 절토부의 시공방법에서 상기 그리드를 상기 보강바에 고정하는 단계는 상기 그리드를 상기 보강바에 휘감고 연결바를 사용하여 두개의 그리드를 연결하는 단계를 구비할 수 있다.As described above, the step of fixing the grid to the reinforcing bar in the construction method of the (existing) fill part and the cut part using the grid fixing device according to the present invention includes winding the grid to the reinforcing bar and using two connecting bars. It may comprise the step of connecting.

보강토 옹벽 및 보강사면을 시공하는 방법은 지형에 따라 크게 2가지로 구분될 수 있다. 즉 성토부(성토구간)에 시공하는 경우와 절토부(절토구간)에 시공하는 경우로 나눌 수 있고, 성토부에 시공하는 경우는 (신설) 성토부에 구조물을 축조하는 것과 기존 성토부에 추가로 성토하여 구조물을 축조하는 것으로 나눌 수 있다. 일반적으로 신설 성토부의 보강토 옹벽 또는 보강사면의 시공은 그리드의 설치 길이에 제한을 받지 않고 시공할 수 있다. 그러나 도 3에서 보인 바와 같이 기존 성토부(10)에 추가로 성토하여 구조물을 축조하는 경우 확장(신설)되는 성토부(12)의 길이를 길게 확보하여 시공하여야 안정성을 확보할 수 있는데, 이 길이를 길게 하면 경제성이 나빠진다(일례로, 도심의 경우 토지가격의 고가로 인하여 성토부의 안정적인 길이 확보가 거의 불가능하다). 또한 성토부(12)의 길이를 줄이고자 하면 그리드를 적용해서 시공해야 하고, 이 경우(12') 안정된 그리드의 길이를 확보하기 위해 기존 성토부(10)의 절토 면적(A)을 증가시키면 기존 도로 등의 통행을 제한해야 하는 문제점이 발생하게 된다.Reinforced soil retaining wall and reinforcement slope construction method can be divided into two types according to the terrain. In other words, it can be divided into the case of construction in the filling section (fill section) and the case in the section of cutting section (cut section). It can be divided into building structure by filling with. In general, the construction of reinforcement retaining walls or reinforcement slopes of new fillets can be constructed without being limited by the installation length of the grid. However, as shown in FIG. 3, when building the structure by additionally filling the existing fill part 10, the length of the fill part 12 to be expanded (newly constructed) should be secured to ensure the stability. The longer the value, the worse the economic feasibility (for example, it is almost impossible to secure a stable length of landfill due to the high land price in the city center). In addition, if you want to reduce the length of the fill section 12, the construction should be applied by applying a grid, in this case (12 ') to increase the cut area (A) of the existing fill section 10 in order to secure a stable grid length There is a problem that must restrict traffic such as roads.

이에 대하여 본 발명은 그리드의 포설 연장길이를 확보할 수 없는 경우 및 절토 면적을 크게 하기 어려운 경우에도 보강토 옹벽 또는 보강사면을 시공할 수있도록 하는 그리드 고정기구 및 그를 사용한 시공방법을 제공한다. 또한 본 발명은 암벽이나 급경사의 사면에 보강토 옹벽 및 보강사면을 시공해야 하는 경우 작업성, 환경문제 등으로 인해 절토 면적을 크게 할 수 없고 성토부의 충분한 길이를 확보할 수 없어도 작은 절토 면적으로 보강토 옹벽 및 보강사면을 시공할 수 있도록 한다. 이와 같은 본 발명에 따르면 절토 면적을 최소화시키면서 그리드를 사용한 시공이 가능하도록 하고, 그리드의 길이를 충분히 확보할 수 없는 (기존) 성토부에서도 그리드를 사용한 시공이 가능하게 하여 시공의 경제성 및 편리성 향상시키고 공기를 단축시킬 수 있도록 한다. 또한 절토량을 최소화시켜 친환경적인 구조물을 시공할 수 있도록 하고, 시공비를 절감시킬 수 있는 효과를 갖는다.On the other hand, the present invention provides a grid fixing mechanism and a construction method using the same for reinforcing soil retaining wall or reinforcing slope even when the length of installation of the grid cannot be secured and when it is difficult to increase the cut area. In addition, the present invention can not increase the cut area due to workability, environmental problems, etc. when it is necessary to construct reinforcement earth retaining wall and reinforcement slope on the slope of rock wall or steep slopes, but the reinforcement earth retaining wall with small cut area And reinforcement slopes. According to the present invention, it is possible to construct using the grid while minimizing the cut area and to improve the economics and convenience of the construction by enabling the construction using the grid even in the (existing) fill section that cannot secure the length of the grid sufficiently. And shorten the air. In addition, it is possible to construct eco-friendly structures by minimizing cutting amount, and has an effect of reducing construction costs.

이하, 본 발명에 따른 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구를 첨부된 도면 4 내지 도 9에 의거하여 상세히 설명하고, 그리드 고정기구를 이용한 (기존) 성토부 및 절토부의 시공방법을 첨부된 도면 도 10 내지 도 14에 의거하여 상세히 설명한다. 이때 도 1 내지 도 14에 있어서 동일한 기능을 수행하는 구성 요소에 대해서는 동일한 참조 번호를 병기하고, 각 도면에서 주 요소들의 연결, 결합, 고정을 위한 구성요소의 도시는 간략히 하거나 생략하였으며, 일반적인 보강토 옹벽 및 보강사면의 시공으로부터 이 분야의 종사자들이 기본적으로 적용할 수 있는 구성요소들의 도시는 생략하고, 본 발명과 관련된 부분들을 중심으로 도시하였다. 특히, 요소들 사이의 크기 비가 다소 상이 하게 표현되거나 서로 결합되는 부품들 사이의 크기가 상이하게 표현된 부분도 있으나, 이와 같은 도면의 표현차이는 이 분야의 종사자들이 용이하게 이해할 수 있는 부분들이므로 별도의 설명을 생략한다.Hereinafter, the grid fixing mechanism for the construction of the reinforcement soil retaining wall and the reinforcement slope according to the present invention will be described in detail with reference to the accompanying drawings 4 to 9, and (conventional) the fill section and the cut section using the grid fixing mechanism are attached. 10 to 14 will be described in detail. In this case, the same reference numerals are given to the components that perform the same functions in FIGS. 1 to 14, and the components for connecting, coupling, and fixing the main elements are briefly or omitted in each drawing. From the construction of the reinforcement slope and the illustration of the components that can be basically applied by those skilled in the art, the illustration is centered on the parts related to the present invention. In particular, there are parts in which the size ratio between the elements is somewhat different or the sizes between the components coupled to each other are different. However, the representation difference in the drawings is easily understood by those skilled in the art. A separate description is omitted.

도 4 내지 도 9는 본 발명의 바람직한 실시예에 따른 그리드 고정기구를 설명하기 위한 도면들이다.4 to 9 are views for explaining a grid fixing mechanism according to a preferred embodiment of the present invention.

도 4 내지 도 9를 참조하면, 본 발명의 바람직한 실시예에 따른 그리드 고정기구(20)는 고정바(30), 보강바(40) 및 그리드(50) 등으로 구성된다. 고정바(30)는 그리드(50)를 포설하는 성토부 또는 절토부의 지반(10)에 일단이 삽입되고 타단이 지반(10) 위로 일정한 길이 돌출되도록 설치되어 레이진 또는 그라우팅 혹은 기계적 고정방법 등에 의해서 인발저항력을 갖도록 처리된 것이다. 고정바(30)는 그라우팅에 의할 경우 시멘트, 모르타르 등의 그라우트에 의해서 고정되는 소일 네일(Soil nail) 또는 락 볼트(Rock bolt)일 수 있고, 기계적 고정에 의할 경우 기계적인 체결구조에 의한 볼트 등일 수 있는 것으로, 그 고정방법 및 형상에는 제한이 없는 것이다. 또한 고정바(30)는 일반적인 강봉 또는 철근이 사용될 수 있으나 그 재질에 제한이 있는 것은 아니며 설계치내에서 허용되는 것이 사용될 수 있고, 그 설치 위치는 지반조건에 따라 임의로 설계될 수 있을 것이다(가능한 일정한 간격으로 설치하는 것이 추후 보강바를 설치하여 그리드를 고정하는데 용이할 것이다). 참고로 본 실시예에서는 그라우팅법을 적용하였고, 고정바(30)로는 철근을 적용하였다. 보강바(40)는 그리드에 작용되는 인장력에 따라 크기 및 재질을 조절하는 것으로 철근, H빔 등의 형강, 쇠파이프, 파이버 글래스(Fiber glass) 봉 등을 사용할 수 있는데 본 발명의 실시예에서는 D32와 SD40의 철근을 적용하였다. 또한 그리드(50)는 이 분야에서 사용되는 다양한 형태의 보강재를 사용할 수 있는 것으로, 본 발명의 실시예에서는 고밀도 폴리에틸렌(HDPE) 일체형 그리드(Geogrid)를 사용(상표명 : Tensar Giogrid)하였다.4 to 9, the grid fixing mechanism 20 according to the preferred embodiment of the present invention is composed of a fixing bar 30, a reinforcing bar 40 and the grid 50, and the like. The fixing bar 30 is installed so that one end is inserted into the ground 10 of the fill portion or cut portion for laying the grid 50 and the other end protrudes over the ground 10 by a lazy or grouting or mechanical fixing method. It is processed to have a pulling resistance. The fixing bar 30 may be a soy nail or a rock bolt fixed by grout such as cement or mortar by grouting, or by mechanical fastening by mechanical fixing. It may be a bolt or the like, there is no limitation on the fixing method and shape. In addition, the fixing bar 30 may be used as a general steel bar or reinforcing bar, but the material is not limited and can be used within the design value, the installation position may be arbitrarily designed according to the ground conditions (possible constant Installation at intervals will be easier to install the reinforcement bar later to fix the grid). For reference, in the present embodiment, the grouting method was applied, and the rebar was applied as the fixing bar 30. The reinforcing bar 40 is to adjust the size and material according to the tensile force applied to the grid can be used, such as reinforcing bars, H-beams, steel pipes, fiber glass rods, etc. In the embodiment of the present invention D32 And SD40 rebar were applied. In addition, the grid 50 may use various types of reinforcement materials used in this field, and in the embodiment of the present invention, a high density polyethylene (HDPE) integrated grid (trade name: Tensar Giogrid) was used.

한편 본 발명의 바람직한 실시예에서 모든 철근은 에폭시 코팅된(Epoxy-coating) 철근을 사용하였고, 필요시 모르타르(Mortar) 또는 콘크리트로 철근을 피복하였다. 철근 용접부는 에폭시 코팅이 파손되므로 용접부는 방청처리를 위해 에폭시 코팅과 같은 효과가 있는 헤비코테 T/U 녹색도료나 그 이상의 효과를 갖는 재질로 재방처리하였다. 보강바는 모멘트 분배를 위해 종방향으로 연속되도록 설치하였다. 또한 그리드 연결부분의 밀착을 위해 토압력만큼 그리드를 긴장한 후 성토재를 포설, 다짐하였다.Meanwhile, in the preferred embodiment of the present invention, all the reinforcing bars used epoxy-coated reinforcing bars, and, if necessary, the reinforcing bars were covered with mortar or concrete. Since the reinforcing welding part is damaged by epoxy coating, the welding part is retreated with heavy coating T / U green paint or more effective material such as epoxy coating for rust prevention treatment. The reinforcement bar was installed to be longitudinally continuous for moment distribution. In addition, after the grid was tensioned by the earth pressure for close contact with the grid connection part, the landfill material was laid and compacted.

다시 도 4 및 도 5를 참조하면, 본 발명의 바람직한 실시예에 따른 그리드 고정기구(20)는 고정바(30), 보강바(40) 및 그리드(50)를 구비한다. 고정바(30)는 일단이 지반(10)에 삽입된 후 그라우트되므로써 인발저항력을 갖도록 처리되고, 타단은 지반(10) 위로 일정한 길이 돌출되도록 설치된다. 이 고정바(30)에는 그리드(50)를 고정시키기 위한 적어도 하나의 보강바(40)가 용접되어 고정된다. 전술한 바와 같이 보강바(40)는 다양한 종류가 사용될 수 있는데, 본 실시예에서는 두 개의 철근(42,44)을 사용하고, 도 6에서 보인 바와 같이 고정바(30)의 길이 방향으로 서로 이격되도록 고정바(30)에 고정하여 그 사이에는 철근을 일정한 길이로 절단한 다수개의 간격 조절편(46)을 일정한 간격으로 설치하였다. 이 간격 조절편(46)은 도 7에서 보인 바와 같이 두 개의 철근(42,44)을 지지하면서 연결하도록 각 철근(42,44)에 용접되어 고정된다. 그리고 필요에 따라 용접 후 에폭시코팅 등으로 부식방지 처리한다.4 and 5, the grid fixing device 20 according to the preferred embodiment of the present invention includes a fixing bar 30, a reinforcing bar 40, and a grid 50. The fixed bar 30 is processed to have a pull-out resistance by grouting after one end is inserted into the ground 10, and the other end is installed to protrude a predetermined length over the ground 10. At least one reinforcing bar 40 for fixing the grid 50 is welded and fixed to the fixing bar 30. As described above, a variety of kinds of reinforcing bars 40 may be used. In this embodiment, two reinforcing bars 42 and 44 are used, and as shown in FIG. 6, the reinforcing bars 40 are spaced apart from each other in the longitudinal direction of the fixing bar 30. It was fixed to the fixed bar 30 so as to install a plurality of gap adjusting pieces 46 are cut at regular intervals between the reinforcing bars in a certain length. This gap adjusting piece 46 is welded and fixed to each of the rebars 42 and 44 so as to support and connect the two rebars 42 and 44 as shown in FIG. And if necessary, after welding, anti-corrosion treatment with epoxy coating.

한편 도 8a에서 보인 바와 같이 지반(10) 위로 돌출되는 부분이 'U'자형으로 구부러져 끝단(33)이 형성된 고정바(30')를 사용할 수 있다. 이 고정바(30')는 그라우팅 공법에 사용되는 소일 네일 또는 락 볼트의 한 종류이다. 이와 같은 고정바(30')를 사용하는 경우 전술한 보강바(40)에서 두 개의 철근(42',44')은 고정바(30')와 용접할 필요없이 'U'자형의 끝단(33)에 끼워서 고정할 수 있는 잇점이 있다. 또한 도 8b에서 보인 바와 같이 지반(10)에 박히는 소일 네일 또는 락 볼트의 끝단에 턴버클(turnbuckle)을 결합시킨 형태의 고정바(30")를 사용함으로써 지반(10)에 소일 네일 또는 락 볼트의 작업시 발생되는 오차를 조절하여 그리드의 설치를 용이하게 할 수 있다.Meanwhile, as shown in FIG. 8A, a portion protruding over the ground 10 is bent in a 'U' shape to use a fixing bar 30 ′ having an end 33 formed thereon. This fixing bar 30 'is a kind of soy nail or lock bolt used in the grouting method. In the case of using the fixing bar 30 ', the two reinforcing bars 42' and 44 'in the aforementioned reinforcing bar 40 need not be welded to the fixing bar 30' and have a 'U' shaped end 33 ), There is an advantage that can be fixed by inserting. In addition, as shown in Figure 8b by using a fixed bar (30 ") of the form of the turnbuckle (turnbuckle) coupled to the end of the soil nail or rock bolt nailed to the ground (10) of the soil nail or rock bolt on the ground (10) The installation of the grid can be facilitated by adjusting the errors generated during the work.

도 4 및 도 9에서 보인 바와 같이 상술한 바와 같이 설치된 보강바(40)에는 그리드(50)가 지반(10)에 위치되는 끝단이 감기어 고정된다. 즉 그리드(50)는 보강바(40)의 일측(52)으로부터 타측(54)으로 감기어 반대방향으로 연장된 상태에서 그리드(50)의 타측면(56)에 위치되는 연결바(60)가 끝단(58)에 삽입되므로써 고정된다. 이와 같이 그리드(50)를 연결바(60)로 연결하는 구성은 두 개의 그리드를 서로 연결하여 사용할 때에도 매우 유용하게 사용할 수 있는 방법이다. 즉 하나의 그리드를 보강바(40)에 감아서 고정한 상태에서 다른 그리드와 연결하여 연장시킬 수 있도록 하는 것이다.As shown in FIGS. 4 and 9, the ends of the grid 50 located on the ground 10 are wound and fixed to the reinforcement bar 40 installed as described above. In other words, the grid 50 is wound from one side 52 of the reinforcement bar 40 to the other side 54 and extends in the opposite direction, so that the connecting bar 60 located on the other side 56 of the grid 50 is It is fixed by being inserted into the end 58. The configuration of connecting the grid 50 to the connection bar 60 as described above is a very useful method even when using two grids connected to each other. In other words, one grid is wound around the reinforcing bar 40 so that it can be extended by connecting with another grid in a fixed state.

도 10은 일반적인 보강토 옹벽의 시공방법을 순차적으로 보여주는 도면이고, 도 11은 본 발명에 따른 그리드 고정기구를 이용한 시공방법을 적용한 예의 주요공정을 보여주는 플로우 챠트이며, 도 12는 본 발명의 시공방법에 따라 절토부에 시공된 보강토 옹벽의 일례를 보여주는 도면이다.10 is a view showing a construction method of the general reinforced earth retaining wall in sequence, Figure 11 is a flow chart showing the main process of the example of applying the construction method using the grid fixing mechanism according to the present invention, Figure 12 is a construction method of the present invention The figure shows an example of the reinforcement earth retaining wall constructed in the cut section.

도 11에서 보인 바와 같이 본 발명의 바람직한 실시예에 따른 그리드 고정기구를 이용한 성토부 및 절토부에 보강토 옹벽을 시공하는 방법은 기초저면 고르기와 첫단쌓기 및 뒷채움(S500), 고정바 설치(S510), 그리드 포설 및 두부처리(S520), 보강바 설치 후 그리드를 보강바에 고정(S530), 그리드를 블록에 고정(S540), 상단블록 쌓기, 뒷채움 및 배면 토층 성토(S550)하는 단계를 구비하여 이루어진다. 경우에 따라서는 절토공사시에 고정바를 그리드가 설치된 높이에 먼저 시공하여 두고 첫단쌓기 및 뒷채움, 그리드 포설 및 두부처리, 상단블록쌓기, 뒷채움 및 배면 토층을 성토하는 단계를 구비하여 이루어진다.As shown in FIG. 11, the method of constructing the reinforcement soil retaining wall using the grid fixing mechanism according to the preferred embodiment of the present invention includes the base bottom selection and the first stacking and back filling (S500) and the fixing bar installation (S510). , Grid installation and tofu treatment (S520), after the installation of the reinforcement bar fixed grid to the reinforcement bar (S530), the grid fixed to the block (S540), the top block stacking, backfilling and back ground fill (S550) . In some cases, the cut bar is first constructed at a height where the grid is installed, and the first step of stacking and backfilling, grid laying and tofu treatment, top block stacking, backfilling, and backing soil are formed.

이와 같은 방법은 도 10에서 보인 바와 같은 일반적인 보강토 옹벽의 시공방법에 본 발명의 그리드 고정기구를 설치하기 위한 공정이 혼합되는 것이다.Such a method is to mix the process for installing the grid fixing mechanism of the present invention in the construction method of the general reinforced earth retaining wall as shown in FIG.

도 10을 참조하면, 일반적인 보강토 옹벽의 시공방법에서 지반(10,기초저면)을 고른 뒤 첫단의 블록(16)을 쌓는 단계(S500,a)는 설계된 근입심도 및 기초두께에 따라 트렌치를 형성하고 절토 후 기초면은 두께 15mm 정도로 배수성이 좋은 토양(모래나 자갈 13mm∼25mm의 쇄석)을 표준 다짐법에 의해 90% 내지 95% 이상 다지고, 수평 정지작업 후 하부 블록을 수평으로 설치하는 공정을 진행한다. 본 실시예에서 사용한 블록은 상표명이 'KEYSTONE Retaining Wall System'인 제품이다. 이 제품의 블록은 파이버 글래스 핀(Fiberglass pin)이 제공되는데 이 핀은 그리드를 고정시켜서 블록과 그리드가 상호고정되도록 한다. 이 블록을 사용할 경우 파이버 글래스 핀을 각 블록에 쌍으로 형성된 구멍에 삽입(이때 블록이 상호 고정되고 핀에 의한 자동 셋백(setback)이 이루어짐)한다. 뒷채움은 옹벽 규모와 토질에 의해 계산된 작업설계도에 준하여 블록 뒷부분 및 블록 코아 부분을 13∼25mm의 쇄석이나 배수성이 뛰어난 토양으로 뒷채움 시공을 한다. 이와 같은 기초저면 고르기와 첫단쌓기 및 뒷채움 단계(S500)는 이 분야에서 실시하고 있는 다양한 형태가 적용할 수 있을 것이다.Referring to Figure 10, in the general construction method of reinforcement earth retaining wall step (S500, a) to select the ground (base 10, the base bottom) and to build the first block 16 to form a trench in accordance with the designed depth and foundation thickness After cutting, the foundation surface is 15mm thick and has good drainage soil (sand or gravel 13mm ~ 25mm crushed stone) by standard compaction method by 90% to 95% or more. Proceed. The block used in this embodiment is a product having the trade name 'KEYSTONE Retaining Wall System'. The block is supplied with a fiberglass pin, which holds the grid so that the block and grid are interlocked. When using this block, fiberglass pins are inserted into the paired holes in each block (the blocks are fixed to each other and automatic setback by the pins). Backfill is backfilled with 13-25mm of crushed stone or drained soil according to the work plan calculated by retaining wall size and soil quality. The base bottom picking and the first stacking and back filling step (S500) may be applied to various forms in the field.

다음으로 그리드를 포설하는 단계(b)는 전술한 바와 같은 본 발명에 따른 고정바 설치(S510), 그리드 포설 및 두부처리(S520), 보강바 설치 후 그리드를 보강바에 고정(S530), 그리드를 블록에 고정(S540)하는 단계를 수행하여 도 12에서 보인 바와 같이 필요한 부분에 본 발명에 따른 그리드 고정기구가 적용되도록 한다. 도 12를 참조하면, 고정바(30)를 설치하는 단계(S510)는 일정한 위치에 인발저항력을 갖도록 복수개의 고정바(30)를 설치하는 것으로 전술한 바와 같이 그라우팅 공법 또는 기계적인 방법을 통하여 이루어진다. 그리드(50)를 포설한 뒤 두부처리하는 단계(S520)는 토층(12)과 블록(16)상에 그리드(15)를 포설하고 고정바(30)와 그리드(50)가 간섭되는 부분을 피해 두부처리하는 것으로 고정바(30)와 그리드(50)간에 발생되는 간섭부분을 정리하여 그리드(50)가 토층(12)에 닿도록 함으로써 추후 보강바(40)를 설치한 후 그리드(50)를 보강바(40)에 용이하게 감기게 하도록 하기 위한 작업이다. 보강바(40)를 설치한 후 그리드(50)를 보강바(40)에 고정(S530)하는 단계는 토층(12)에 위치되는 그리드(50)의 끝단을 보강바(40)에 감아서 고정하는 것으로 보강바(40)에 그리드(50)를 고정하는 방법은 전술한 그리드 고정기구에서와 같은 방법으로 진행한다.Next, the step (b) of laying the grid is the fixed bar installation according to the present invention as described above (S510), grid laying and tofu treatment (S520), after the reinforcement bar installation to fix the grid to the reinforcement bar (S530), the grid Fixing to the block (S540) is performed so that the grid fixing mechanism according to the present invention is applied to the necessary portion as shown in FIG. Referring to FIG. 12, the step S510 of installing the fixing bar 30 is performed by a grouting method or a mechanical method as described above by installing a plurality of fixing bars 30 to have a pullout resistance at a predetermined position. . After laying the grid 50 to process the head (S520) to install the grid 15 on the soil layer 12 and the block 16, avoiding the portion where the fixed bar 30 and the grid 50 interferes The head 50 is disposed so that the interference portion generated between the fixed bar 30 and the grid 50 is arranged so that the grid 50 contacts the soil layer 12, and then the grid 50 is installed after the reinforcement bar 40 is installed. This is to make the reinforcement bar 40 easily wound. After installing the reinforcement bar 40 and fixing the grid 50 to the reinforcement bar 40 (S530), the end of the grid 50 positioned on the soil layer 12 is wound around the reinforcement bar 40 and fixed. The method of fixing the grid 50 to the reinforcing bar 40 is to proceed in the same manner as in the grid fixing mechanism described above.

한편 도 12에서 보인 바와 같이 암벽 또는 절토사면 등에 고정바(30)를 설치하는 경우에는 전술한 기초저면 고르기와 첫단쌓기 및 뒷채움 단계(S500)보다 먼저 실시할 수도 있다. 즉 일반적으로 암반 또는 절토사면의 절토시 상부로부터 절토하면서 그라우팅 작업을 하게 되는데, 본 발명에서도 이에 적용하여 절토시 고정바(30)를 설치하도록 하는 것이다. 물론 이 경우에는 추후 진행될 보강바(40)의 설치와 그리드(50)의 사용을 염두하고(설계하고) 고정바(30)의 설치 위치를 설정하는 것이 작업의 관리에 있어서 필요할 것이고, 그리드 포설 및 두부처리(S520), 보강바 설치 후 그리드를 보강바에 고정하는 단계(S530) 등은 성토하면서 진행하거나 고정바(30) 설치 후 바로 진행하고 추후 성토시 그리드(50)를 지면(10)에 붙이고 공정을 진행할 수 있을 것이다. 그리드(50)를 블록(16)에 고정하는 단계(S540)는 블록(16)에 위치되는 그리드(50)의 끝단을 팽팽하게 당겨서 블록(50)에 고정하는 것으로 전술한 블록에 제공되는 파이버 블래스 핀에 그리드(50)를 임시로 고정한다. 이와 같은 공정을 진행한 후 상단블록 쌓기, 뒷채움 및 토층 성토하는 단계(S550)를 반복적으로 시행하여 도 12에서 보인 바와 같은 보강토 옹벽을 시공하게 된다.On the other hand, as shown in FIG. 12, when the fixing bar 30 is installed on a rock wall or a cut slope, the above-described base bottom leveling and first stacking and back filling may be performed before the step S500. That is to say that the grouting operation is generally performed while cutting from the upper part of the rock or cut slope when cutting, and in the present invention, it is to install the fixing bar 30 when cutting. In this case, of course, it will be necessary in the management of the work to install the reinforcing bar 40 and the installation of the fixing bar 30 in consideration of the use of the grid 50 in the future. Tofu treatment (S520), the step of fixing the grid to the reinforcement bar after installing the reinforcement bar (S530), etc. proceeds while filling or proceeding immediately after the installation of the fixed bar 30 and later when the grid 50 is attached to the ground (10) You will be able to proceed with the process. The step S540 of fixing the grid 50 to the block 16 is to pull the end of the grid 50 positioned in the block 16 to fix it to the block 50 by tightening the ends of the grid 50 located in the block 16. Temporarily fix the grid 50 to the pins. After proceeding such a process, the step of stacking the top block, filling the backfill and filling the soil layer (S550) is repeatedly performed to construct the reinforced soil retaining wall as shown in FIG. 12.

이와 같은 본 발명의 바람직한 실시예에 따른 시공방법에 의하면 도 14에서 보인 바와 같이 기존 성토부의 절토 면적을 최대한 줄이면서 확장 도로부 등을 시공할 수 있도록 한다. 도 13은 일반적인 보강사면의 시공방법을 순차적으로 보여주는 도면이고, 도 14는 본 발명의 시공방법에 따라 (기존) 성토부에 시공된 보강사면의 일례를 보여주는 도면이다.According to the construction method according to the preferred embodiment of the present invention as shown in Figure 14 to allow the construction of the extension road portion while reducing the cut area of the existing fill portion as possible. 13 is a view showing a construction method of a general reinforcement slope in sequence, Figure 14 is a view showing an example of a reinforcement slope constructed in the (existing) fill portion according to the construction method of the present invention.

도 13을 참조하면, 보강사면의 시공은 토사사면체에 그리드를 설치하여 일반적인 토사사면보다 급하게 사면을 조성하는 공법이다. 보상사면은 보강토 옹벽과 달리 원지반을 굴착하여 발생되는 현장 잉여토를 활용할 수 있다. 보강사면은 전술한 보강토 옹벽의 시공방법과 비교하여 블록을 구성하지 않고 그리드(14)만으로 사면 전면부를 짧은 보강재를 추가로 설치하거나 보강재를 휘감아서 성토하는 과정(사면 경사가 45°이상일 경우)을 반복적으로 수행해서 이루어진다. 본 발명에 따른 그리드 기구를 이용한 그리드(50)의 포설은 전술한 방법과 같이 이루어지므로 상세한 설명은 생략한다. 도 14는 본 발명의 시공방법에 따라 시공된 보강사면의 일례를 보인 것으로, 이와 같은 보강사면은 절토 면적(A)을 줄임으로써 성토면적으로 줄임과 동시에 자연친화적인 시공이 가능하다.Referring to FIG. 13, the construction of the reinforcing slope is a method of forming a slope more urgently than a general soil slope by installing a grid on the soil slope. Compensation slopes can utilize on-site surplus soil generated by excavating the ground, unlike reinforced soil retaining walls. The reinforcement slope does not constitute a block compared to the construction method of the above-mentioned reinforcement soil retaining wall, but the process of installing a short reinforcement in the front of the slope with only the grid 14 or enclosing the reinforcement (when the slope is more than 45 °) It is done repeatedly. Since the grid 50 is installed using the grid mechanism according to the present invention as described above, detailed description thereof will be omitted. Figure 14 shows an example of the reinforcement slopes constructed in accordance with the construction method of the present invention, such a reinforcement slopes by reducing the cut area (A) can be reduced to the fill area and at the same time natural construction.

상술한 바와 같은, 본 발명의 바람직한 실시예에 따른 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구 및 그를 이용한 성토부 및 절토부의 시공방법을 상기한 설명 및 도면에 따라 도시하였지만, 이는 예를 들어 설명한 것에 불과하며 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 다양한 변화 및 변경이 가능하다는 것을 이 분야의 통상적인 기술자들은 잘 이해할 수 있을 것이다.As described above, the grid fixing mechanism for the construction of the reinforcement earth retaining wall and the reinforcement slope according to a preferred embodiment of the present invention and the construction method of the fill portion and the cut portion using the same according to the above description and drawings, for example Those skilled in the art will appreciate that various changes and modifications can be made without departing from the spirit and scope of the present invention.

본 발명에 의하면, 성토부의 터파기량을 최소화시키면서 그리드를 사용한 시공이 가능하도록 하고, 그리드의 길이를 충분히 확보할 수 없는 성토부에서도 그리드를 사용한 시공이 가능하게 하여 시공의 경제성 및 편리성 향상시키고 공기를 단축시킬 수 있도록 한다. 또한 절토부의 절토량을 최소화시켜 친환경적인 구조물을 시공할 수 있도록 하고, 시공비를 절감시킬 수 있는 효과를 갖는다.According to the present invention, it is possible to construct using the grid while minimizing the amount of breaks in the fill area, and to enable the use of the grid even in the fill area that cannot secure the length of the grid, thereby improving the economics and convenience of the construction and air. To shorten. In addition, it is possible to construct eco-friendly structures by minimizing the cut amount of the cut portion, and has an effect of reducing the construction cost.

Claims (6)

보강토 옹벽 및 보강사면을 시공하기 위한 성토부 또는 절토부의 지반에 일단이 삽입되고 타단이 상기 지반 위로 일정한 길이로 돌출되도록 설치되어 인발저항력을 갖도록 처리되는 복수개의 고정바와;A plurality of fixing bars, one end of which is inserted into the ground of the fill portion or the cut portion for constructing the reinforcement soil retaining wall and the reinforcement slope, and the other end of which is projected to have a predetermined length over the ground; 상기 지반으로부터 일정한 높이에서 상기 복수개의 고정바를 연결하도록 상기 고정바에 결합되는 보강바 및;A reinforcing bar coupled to the fixing bar to connect the plurality of fixing bars at a predetermined height from the ground; 상기 성토부 또는 절토부의 뒷채움 또는 성토되는 토층에 위치되는 끝단이 상기 보강바에 감기어 고정되는 그리드를 포함하여, 그리드의 포설 연장길이를 확보할 수 없는 경우 및 절토 면적을 크게 하기 어려운 경우에도 그리드를 적용할 수 있도록 하는 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구.Including the grid which is fixed to the backfill of the fill portion or the cut portion or the soil layer to be laid, the grid is fixed to the reinforcement bar, and the grid is not secured even if the length of the installation of the grid cannot be secured and the cut area is difficult to increase. Grid fasteners for the construction of reinforced earth retaining walls and reinforcement slopes. 제 1 항에 있어서,The method of claim 1, 상기 그리드는 상기 보강바의 일측으로부터 타측으로 감기어 반대방향으로 연장된 상태에서 상기 그리드의 타측면에 위치되는 연결바가 끝단에 삽입되므로써 고정되는 것을 포함하는 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구.The grid is fixed to the construction of the reinforcement soil retaining wall and reinforcing slopes, which is fixed by being inserted into the end of the connecting bar located on the other side of the grid in a state extending in the opposite direction from one side of the reinforcement bar to the other side Instrument. 제 1 항 또는 제 2 항에 있어서,The method according to claim 1 or 2, 상기 보강바는 두 개이상의 바가 상기 고정바의 길이 방향으로 서로 이격되어 설치되고, 그 사이에는 복수개의 간격 조절편이 일정한 간격으로 설치되는 것을포함하는 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구.The reinforcing bar is provided with two or more bars are spaced apart from each other in the longitudinal direction of the fixing bar, a plurality of space between the adjusting piece is installed at regular intervals between the grid anchor mechanism for the construction of the retaining soil retaining wall and reinforcing slopes. 제 1 항 또는 제 2 항에 있어서,The method according to claim 1 or 2, 상기 고정바는 공사지반 위로 돌출되는 부분이 'U'자형으로 구부러져 형성된 끝단을 구비하고, 상기 보강바는 상기 끝단의 내측으로 삽입되어 상기 고정바에 결합되는 것을 포함하는 보강토 옹벽 및 보강사면의 시공을 위한 그리드 고정기구.The fixing bar has an end portion formed by bending a 'U' shaped portion protruding above the construction ground, and the reinforcing bar is inserted into the inner end of the reinforcement soil retaining wall and reinforcing slopes, including being coupled to the fixing bar. Grid fixtures. 보강토 옹벽 및 보강사면을 시공하기 위한 성토부 또는 절토부의 지반의 일정한 위치에 인발저항력을 갖도록 복수개의 고정바를 설치하는 단계와;Installing a plurality of fixing bars to have a pull-out resistance at a predetermined position on the ground of the fill portion or the cut portion for constructing the reinforcement soil retaining wall and the reinforcement slope; 그리드를 상기 고정바와 간섭되는 부분을 피해 두부처리하는 단계와;Tofu processing a grid avoiding a portion that interferes with the fixing bar; 상기 복수개의 고정바를 연결하도록 보강바를 결합시키는 단계 및;Coupling a reinforcement bar to connect the plurality of fixing bars; 상기 그리드의 끝단을 상기 보강바에 감아서 고정하는 단계를 포함하는 그리드 고정기구를 이용한 성토부 및 절토부의 시공방법.Construction method of the fill section and cut section using a grid fixing mechanism comprising the step of winding the end of the grid to the reinforcement bar. 제 5 항에 있어서,The method of claim 5, wherein 상기 그리드를 상기 보강바에 고정하는 단계는 상기 그리드를 상기 보강바에 휘감고 연결바를 개재하여 두개의 그리드를 연결하는 단계를 포함하는 그리드 고정기구를 이용한 성토부 및 절토부의 시공방법.The fixing of the grid to the reinforcement bar comprises the step of winding the grid around the reinforcement bar and connecting the two grids via a connection bar, the construction method of the fill and cut section using a grid fixing mechanism.
KR1020020049438A 2002-08-21 2002-08-21 Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device KR20040017387A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020020049438A KR20040017387A (en) 2002-08-21 2002-08-21 Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020020049438A KR20040017387A (en) 2002-08-21 2002-08-21 Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020020024910U Division KR200295956Y1 (en) 2002-08-21 2002-08-21 Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes

Publications (1)

Publication Number Publication Date
KR20040017387A true KR20040017387A (en) 2004-02-27

Family

ID=37322941

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020020049438A KR20040017387A (en) 2002-08-21 2002-08-21 Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device

Country Status (1)

Country Link
KR (1) KR20040017387A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101257387B1 (en) * 2011-03-29 2013-04-25 (주)단우기술단 The Rataining Wall
CN104005370A (en) * 2013-05-16 2014-08-27 水利部交通运输部国家能源局南京水利科学研究院 Reinforced soil light revetment retaining wall for hollow brick ecological surface cover and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01219216A (en) * 1988-02-26 1989-09-01 Hazama Gumi Ltd Reinforcing ground construction
JPH11323937A (en) * 1998-05-18 1999-11-26 Mitsubishi Kagaku Sanshi Corp Connecting method of wall face material and ground reinforcing material
JP2000309923A (en) * 1999-04-27 2000-11-07 Maeda Kosen Kk Construction method of reinforcing filling and the reinforcing filling
KR20000075687A (en) * 1997-02-25 2000-12-26 오피신 마카페리 에스. 피. 에이. An element for forming ground covering, restraining and reinforcing structures, particularly for forming retaining walls
JP2001049668A (en) * 1999-08-09 2001-02-20 Mitsubishi Kagaku Sanshi Corp Connecting method for wall surface material and ground reinforcing material
JP2001131979A (en) * 1999-11-08 2001-05-15 Mitsubishi Kagaku Sanshi Corp Wall surface member-to-reinforcement member connection structure
KR100327465B1 (en) * 1999-07-02 2002-03-13 이은수 KORESWall system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01219216A (en) * 1988-02-26 1989-09-01 Hazama Gumi Ltd Reinforcing ground construction
KR20000075687A (en) * 1997-02-25 2000-12-26 오피신 마카페리 에스. 피. 에이. An element for forming ground covering, restraining and reinforcing structures, particularly for forming retaining walls
JPH11323937A (en) * 1998-05-18 1999-11-26 Mitsubishi Kagaku Sanshi Corp Connecting method of wall face material and ground reinforcing material
JP2000309923A (en) * 1999-04-27 2000-11-07 Maeda Kosen Kk Construction method of reinforcing filling and the reinforcing filling
KR100327465B1 (en) * 1999-07-02 2002-03-13 이은수 KORESWall system
JP2001049668A (en) * 1999-08-09 2001-02-20 Mitsubishi Kagaku Sanshi Corp Connecting method for wall surface material and ground reinforcing material
JP2001131979A (en) * 1999-11-08 2001-05-15 Mitsubishi Kagaku Sanshi Corp Wall surface member-to-reinforcement member connection structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101257387B1 (en) * 2011-03-29 2013-04-25 (주)단우기술단 The Rataining Wall
CN104005370A (en) * 2013-05-16 2014-08-27 水利部交通运输部国家能源局南京水利科学研究院 Reinforced soil light revetment retaining wall for hollow brick ecological surface cover and construction method thereof
CN104005370B (en) * 2013-05-16 2015-12-23 水利部交通运输部国家能源局南京水利科学研究院 The reinforced earth lightweight revetment barricade of the ecological mask of building-block and construction method thereof

Similar Documents

Publication Publication Date Title
US6280121B1 (en) Reinforced retaining wall
US5551810A (en) Retaining wall with an outer face and method of forming the same
US20050008438A1 (en) Synthetic deformed bars and retaining walls
KR20110077334A (en) Retaining wall structure and construction method of the retaining wall structure
KR102431393B1 (en) Construction Method of Underground Structures
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
CN111779006A (en) Green assembled slope supporting structure and construction method thereof
US20210017755A1 (en) Composite wall and methods of constructing a composite wall
US20030143038A1 (en) Multiple synthetic deformed bars and retaining walls
KR101015619B1 (en) adjustable anchor device, retaining wall and method for constructing a retaining wall with reinforcement soil
JP2000352296A (en) Method o constructing passage just under underground structure
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
KR102113291B1 (en) Soil retaining wall using phc pile and construction method thererof
KR100468034B1 (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
KR200295956Y1 (en) Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes
KR100372821B1 (en) Passive reinforced nail wall for cutting slope
KR102218755B1 (en) Construction and Repair Method of Reinforced Earth Retaining Wall
KR101032408B1 (en) Method of reinforced earth retaining wall for cutting face through reinforcing execution and concrete block
KR20040017387A (en) Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes and construct method of existing banking area and cutting area using the device
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels
KR101544756B1 (en) Retaining wall block construction method using stone
KR102150531B1 (en) Retaining wall structure using vertical underground insert and its construction method
KR20080059951A (en) Underground outer wall construction method using temporary retaining wall and connecting member strengthening shearing force therefor
KR200223114Y1 (en) A structure reinforcing for retaining wall for inclined plane which to cut off a rock wall
JP3120103B2 (en) Road widening structure

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E601 Decision to refuse application