CN103938767B - Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete - Google Patents

Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete Download PDF

Info

Publication number
CN103938767B
CN103938767B CN201410108708.9A CN201410108708A CN103938767B CN 103938767 B CN103938767 B CN 103938767B CN 201410108708 A CN201410108708 A CN 201410108708A CN 103938767 B CN103938767 B CN 103938767B
Authority
CN
China
Prior art keywords
steel
mortar
wall
steel wire
boards
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410108708.9A
Other languages
Chinese (zh)
Other versions
CN103938767A (en
Inventor
曹万林
崔晓曦
张建伟
刘文超
马恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Huiyuan Building Material Co ltd
Beijing University of Technology
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201410108708.9A priority Critical patent/CN103938767B/en
Publication of CN103938767A publication Critical patent/CN103938767A/en
Application granted granted Critical
Publication of CN103938767B publication Critical patent/CN103938767B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00—Adapting or protecting infrastructure or their operation
    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00—Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/90—Passive houses; Double facade technology

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Building Environments (AREA)

Abstract

外包钢丝网砂浆板发泡混凝土槽形节能承重墙体及作法,涉及建筑施工领域。本发明将钢丝网砂浆板与发泡混凝土组合一起构成组合节能承重墙体。在墙体两端及拐角处的砂浆板之间设置钢框架增强砂浆板连接作用。在两砂浆板之间填充发泡混凝土。本发明外包钢丝网砂浆板发泡混凝土槽形节能承重墙体比现有墙体具有更好的耐久性,具有保温节能功能,重量轻,抗震性能好,墙体表面光滑平整可省去找平抹灰的工序,同时钢丝网砂浆板起到模板作用,省去了支模的过程,施工简单方便。

The utility model relates to a foamed concrete channel-shaped energy-saving load-bearing wall with a steel wire mesh mortar board and a method thereof, which relate to the field of building construction. The invention combines the steel wire mesh mortar board and the foamed concrete to form a combined energy-saving load-bearing wall. A steel frame is set between the mortar boards at both ends of the wall and at the corner to enhance the connection of the mortar boards. Fill foam concrete between two mortar boards. Compared with the existing wall, the foamed concrete groove-shaped energy-saving load-bearing wall of the outsourcing steel wire mesh mortar board of the present invention has better durability, has the function of heat preservation and energy saving, is light in weight, and has good seismic performance, and the surface of the wall is smooth and smooth, which can save the need for screeding. At the same time, the steel mesh mortar board acts as a formwork, which saves the process of setting up the formwork, and the construction is simple and convenient.

Description

外包钢丝网砂浆板发泡混凝土槽形节能承重墙体及作法Outsourcing steel wire mesh mortar board foam concrete channel energy-saving load-bearing wall and its method

技术领域technical field

本发明涉及一种节能承重墙体,特别涉及外包钢丝网砂浆板发泡混凝土槽形节能承重墙体及作法。The invention relates to an energy-saving load-bearing wall, in particular to a channel-shaped energy-saving load-bearing wall of outsourcing steel wire mesh mortar board foamed concrete and a method thereof.

背景技术Background technique

随着我国建筑节能工作的全面开展,各类围护结构墙体保温技术得到大量的研究和推广应用目前建筑节能外围护墙体的保温隔热主要采用外墙外保温技术,该技术具有质量轻保温隔热效果好适用范围广可基本消除热桥等优点,在国内外得以广泛应用,特别在寒冷和严寒地区应用更能显示其优越性但外墙外保温一般综合成本较高,施工工序较复杂,质量控制较难,保护层开裂空鼓渗水保温层脱落时有发生,特别是对外贴饰面砖的系统,常引起人们的担心另外,其保温层一般采用有机或含有机成分的高效绝热材料,通过粘贴喷涂粉刷等工艺,与墙基体连接成整体,表面抗裂保护层较薄,耐火性耐久性耐冲击较差,使用寿命为25年,远远短于建筑物寿命。相关人员开始关注自保温墙体技术等保温技术。With the full development of my country's building energy-saving work, various types of enclosure structure wall insulation technologies have been extensively studied and popularized. At present, the thermal insulation of building energy-saving enclosure walls mainly adopts external wall insulation technology, which has high quality. Good thermal insulation effect and wide application range can basically eliminate thermal bridges and other advantages. It has been widely used at home and abroad, especially in cold and severe cold areas to show its superiority. However, the overall cost of external wall insulation is generally high, and the construction process It is more complicated, quality control is difficult, and the protective layer cracks, hollows, water seepage, and the insulation layer falls off from time to time, especially the system with facing bricks on the outside, which often causes people to worry. In addition, the insulation layer generally adopts organic or high-efficiency heat insulation containing organic components. The material is connected to the wall base as a whole through pasting, spraying, painting and other processes. The surface crack resistance protection layer is thin, and the fire resistance, durability and impact resistance are poor. The service life is 25 years, which is far shorter than the life of the building. Relevant personnel began to pay attention to insulation technologies such as self-insulation wall technology.

自保温墙体主要是指采用轻集料砌块、复合保温砌块、轻质砂加气混凝土砌块、加气混凝土板页岩模数多孔砖、江湖淤泥烧结砖等具有较大热阻的墙体材料及相关的砌筑砂浆、连接件等配套材料砌筑、安装,配套合理的“冷桥”及“接缝”处理措施构成的外墙保温系统。与外墙外保温系统等复合保温技术相比较,自保温墙体具有耐久、防火、耐冲击、施工方便、综合成本低、质量通病少、与建筑物同寿命等优势,近年来在我国南方地区特别是夏热冬冷地区开始得到越来越多的关注。Self-insulation walls mainly refer to the use of light aggregate blocks, composite insulation blocks, light sand aerated concrete blocks, aerated concrete slab shale modulus porous bricks, river and lake silt sintered bricks, etc. Wall materials and related masonry mortar, connectors and other supporting materials are built and installed, and the external wall insulation system is composed of reasonable "cold bridge" and "joint" treatment measures. Compared with composite insulation technologies such as external wall insulation systems, self-insulation walls have the advantages of durability, fire prevention, impact resistance, convenient construction, low overall cost, less common quality problems, and the same lifespan as buildings. In recent years, they have been used in southern China Especially hot summer and cold winter regions began to receive more and more attention.

外包钢丝网砂浆板发泡混凝土槽形节能承重墙体是在两钢丝砂浆板之间填充发泡混凝土,并用钢框架或钢筋桁架将砂浆板连接在一起。其两种不同的材料使其具有不同的力学特性。该墙体重量轻,抗震性能好,具有保温节能功能,墙体表面光滑平整,且省去了支模的过程,施工简单方便。The energy-saving load-bearing wall of foamed concrete trough with steel wire mesh mortar board is filled with foamed concrete between two steel wire mortar boards, and the mortar boards are connected together by steel frame or steel bar truss. Its two different materials give it different mechanical properties. The wall is light in weight, good in earthquake resistance, has the function of heat preservation and energy saving, the surface of the wall is smooth and flat, and the process of supporting formwork is omitted, and the construction is simple and convenient.

发明内容Contents of the invention

本发明的目的在于提高墙体耐久性,使墙体具有良好的保温隔热功能,在保证墙体一定承载能力的条件下,提高抗震性能,同时使施工更为方便。将钢丝网砂浆板与发泡混凝土的优势进行组合,以达到相应目的。The purpose of the present invention is to improve the durability of the wall body, make the wall body have a good thermal insulation function, improve the anti-seismic performance under the condition of ensuring a certain bearing capacity of the wall body, and make the construction more convenient at the same time. Combine the advantages of steel mesh mortar board and foam concrete to achieve the corresponding purpose.

为实现上述目的,本发明采用的技术方案为外包钢丝网砂浆板发泡混凝土槽形节能承重墙体及作法,该墙体外围由钢丝网砂浆板围合而成,墙体内部填充发泡混凝土,在墙体两端及墙体拐角处的砂浆板之间设有钢筋或钢筋桁架连接件,并用螺母将钢筋两端与两钢丝网砂浆板固定,增强砂浆板连接作用;In order to achieve the above object, the technical solution adopted by the present invention is the outsourcing steel mesh mortar board foamed concrete trough-shaped energy-saving load-bearing wall and its method. , between the two ends of the wall and the mortar boards at the corners of the wall, there are steel bars or steel truss connectors, and nuts are used to fix the two ends of the steel bars to the two steel mesh mortar boards to enhance the connection of the mortar boards;

与现有技术相比,本发明具有如下有益效果。Compared with the prior art, the present invention has the following beneficial effects.

本发明将预制钢丝网砂浆板和发泡混凝土进行组合。使墙体具有良好的耐久性。发泡混凝土能够起到良好的保温隔热效果。预制钢丝网砂浆板强度较高,同时用钢筋或钢筋桁架对砂浆板进行连接,能够保证墙体的承载能力。整个墙体重量轻,地震惯性力小,抗震性能好。在浇筑发泡混凝土时,砂浆板起到模板作用,省去支模过程,使施工简单方便。同时砂浆板外侧光滑平整,可节省找平抹灰等工序。The invention combines the prefabricated steel mesh mortar board and foamed concrete. Make the wall have good durability. Foamed concrete can play a good thermal insulation effect. The prefabricated steel wire mesh mortar board has high strength, and the mortar board is connected by steel bars or steel trusses, which can ensure the bearing capacity of the wall. The whole wall is light in weight, small in seismic inertial force and good in seismic performance. When pouring foamed concrete, the mortar board acts as a template, which saves the formwork process and makes the construction simple and convenient. At the same time, the outer side of the mortar board is smooth and flat, which can save steps such as leveling and plastering.

附图说明Description of drawings

图1为本外包钢丝网砂浆板发泡混凝土槽形节能承重墙体剖面图。Figure 1 is a cross-sectional view of the foamed concrete groove-shaped energy-saving load-bearing wall of the outsourcing steel wire mesh mortar board.

图2为预制钢丝砂浆板之间钢筋桁架连接形式图。Figure 2 is a diagram of the connection form of steel bar trusses between prefabricated steel wire mortar boards.

图3为本外包钢丝网砂浆板发泡混凝土槽形节能承重墙体实体图。Fig. 3 is an entity diagram of the foamed concrete groove-shaped energy-saving load-bearing wall of the outsourcing steel wire mesh mortar board.

图中:1、钢丝网砂浆板,2、发泡混凝土,3、钢筋或钢筋桁架连接件,4、高强聚合砂浆。In the figure: 1. Steel wire mesh mortar board, 2. Foamed concrete, 3. Rebar or steel truss connector, 4. High-strength polymerized mortar.

具体实施方式detailed description

下面结合附图对本发明作进一步说明。The present invention will be further described below in conjunction with accompanying drawing.

外包钢丝网砂浆板发泡混凝土槽形节能承重墙体的结构示意图如图1、图2、图3所示。墙体外围是由钢丝网砂浆板1围合而成;墙体内部填充发泡混凝土2;在墙体两端的砂浆板1之间设置钢筋连接件3,并用螺母将钢筋两端与两钢丝网砂浆板1固定,钢丝网砂浆板1之间用高强聚合砂浆4进行粘结;其制作顺序如下,Figure 1, Figure 2, and Figure 3 show the structural schematic diagrams of the foamed concrete trough-shaped energy-saving load-bearing walls covered with steel wire mesh mortar boards. The periphery of the wall is surrounded by steel mesh mortar boards 1; the inside of the wall is filled with foamed concrete 2; steel bar connectors 3 are set between the mortar boards 1 at both ends of the wall, and the two ends of the steel bars are connected to the two steel wire meshes with nuts. The mortar board 1 is fixed, and the steel mesh mortar board 1 is bonded with high-strength polymer mortar 4; the production sequence is as follows,

S1选取直径约为6~8mm的HPB300钢筋或钢筋桁架连接件3,并在墙体两端及墙体拐角处的钢丝网砂浆板1上打出直径6~8mm的圆孔,以便钢筋或钢筋桁架连接件3穿过。圆孔设置在距离墙体端部水平距离100~150mm左右的范围内,竖向每隔300mm设置圆孔。同时若墙体较长则可在墙体上水平距离每隔600mm设置圆孔;S1 selects HPB300 steel bars or steel bar truss connectors 3 with a diameter of about 6-8 mm, and punches round holes with a diameter of 6-8 mm on the steel mesh mortar board 1 at both ends of the wall and at the corners of the wall to facilitate steel bars or steel bar trusses. Connector 3 goes through. The round holes are set within a range of about 100-150mm horizontally from the end of the wall, and round holes are set vertically every 300mm. At the same time, if the wall is longer, round holes can be set every 600mm horizontally on the wall;

S2将钢丝网砂浆板1用钢筋或钢筋桁架连接件3进行连接,并用螺母将砂浆板1和钢筋3两端固定;S2 connect the steel mesh mortar board 1 with a steel bar or a steel bar truss connector 3, and fix the two ends of the mortar board 1 and the reinforcement bar 3 with nuts;

S3将砂浆板1交错拼接,使用高强聚合砂浆4对钢丝网砂浆板1进行粘结,使钢丝网砂浆板1围合成墙体;S3 Stitching the mortar boards 1 alternately, using high-strength polymerized mortar 4 to bond the steel mesh mortar boards 1, so that the steel wire mortar boards 1 surround and form a wall;

S4浇筑发泡混凝土2,成型后即为外包钢丝网砂浆板发泡混凝土槽形节能承重墙体。S4 Pouring foamed concrete 2, after forming, it becomes the outer-wrapped steel mesh mortar board foamed concrete trough-shaped energy-saving load-bearing wall.

墙体由钢丝网砂浆板1拼接而成,钢丝网水泥砂浆板1的长高可以加工成相应的模数,如50、150、300、600mm等等,厚度为20~25mm。砂浆采用的是高性能砂浆,内部有钢丝密布网作为钢筋骨架,在加工钢丝网水泥砂浆板1时,只抛平一面作为浇筑模板的外面,粗糙的一面为浇筑模板的内面。The wall is formed by splicing steel mesh mortar boards 1, and the length and height of the steel mesh cement mortar boards 1 can be processed into corresponding modules, such as 50, 150, 300, 600mm, etc., and the thickness is 20-25mm. The mortar is high-performance mortar, and there is a steel wire mesh inside as the reinforcement skeleton. When processing the steel mesh cement mortar board 1, only the flat side is used as the outside of the pouring formwork, and the rough side is the inner surface of the pouring formwork.

钢丝网砂浆板1之间连接处用高强聚合砂浆4粘结,所述高强聚合砂浆4为钢丝网砂浆板1的柔性连接,涂抹厚度不超过5mm,以便于快速粘结硬化。The joints between the steel mesh mortar boards 1 are bonded with high-strength polymer mortar 4. The high-strength polymer mortar 4 is a flexible connection of the steel mesh mortar boards 1. The thickness of the coating is not more than 5mm, so as to facilitate rapid bonding and hardening.

钢筋或钢筋桁架连接件3使用HPB300钢筋,直径6~8mm,并在砂浆板1上打出直径6~8mm的圆孔以便钢筋穿过,当采用钢筋桁架链接时,钢筋与水平线夹角为45°,等间距布置,水平间距为250~300mm,竖向间距为400~500mm。The steel bar or steel bar truss connector 3 uses HPB300 steel bar with a diameter of 6-8mm, and punches a round hole with a diameter of 6-8mm on the mortar board 1 for the steel bar to pass through. When using a steel bar truss link, the angle between the steel bar and the horizontal line is 45° , Arranged at equal intervals, the horizontal spacing is 250-300mm, and the vertical spacing is 400-500mm.

钢筋或钢筋桁架连接件3设置在距离墙体端部及墙体拐角处水平距离100~150mm左右范围内,起到定位作用,竖向每隔300mm设置钢筋或钢筋桁架连接件3,同时若墙体较长则可在墙体两端的钢筋或钢筋桁架连接件3之间水平每隔600mm左右距离设置同样的钢筋或钢筋桁架连接件3。The steel bars or steel bar truss connectors 3 are set within a horizontal distance of about 100-150 mm from the end of the wall and the corner of the wall to play a positioning role. If the body is longer, the same steel bar or steel bar truss connector 3 can be set horizontally every 600mm or so between the steel bars at both ends of the wall or the steel bar truss connector 3 .

连接两钢丝网砂浆板1的钢筋或钢筋桁架连接件3也可是钢筋桁架或其他预制连接件。The steel bars or steel bar truss connectors 3 connecting the two steel mesh mortar panels 1 may also be steel bar trusses or other prefabricated connectors.

钢丝网砂浆板1拼接时采用交错拼接的方法,增强钢丝网砂浆板1之间的连接作用。When the steel wire mesh mortar boards 1 are spliced, a staggered splicing method is adopted to enhance the connection between the steel wire mesh mortar boards 1 .

以上是本发明的一个典型实施例,本发明的实施不限于此。The above is a typical embodiment of the present invention, and the practice of the present invention is not limited thereto.

Claims (2)

1.外包钢丝网砂浆板发泡混凝土槽形节能承重墙体的作法,其特征在于:该作法包括如下,1. The method of outsourcing steel wire mesh mortar board foamed concrete trough-shaped energy-saving load-bearing wall is characterized in that: the method includes the following, S1选取直径为6~8mm的钢筋或钢筋桁架连接件(3),并在墙体两端及墙体拐角处的钢丝网砂浆板(1)上打出直径6~8mm的圆孔,以便钢筋或钢筋桁架连接件(3)穿过;圆孔设置在距离墙体端部水平距离100~150mm左右的范围内,竖向每隔300mm设置圆孔;同时若墙体较长则可在墙体上水平距离每隔600mm设置圆孔;S1 Select steel bars or steel bar truss connectors (3) with a diameter of 6-8 mm, and drill round holes with a diameter of 6-8 mm on the steel mesh mortar boards (1) at both ends of the wall and at the corners of the wall, so that the steel bars or The steel bar truss connector (3) passes through; the round holes are set within the range of about 100-150mm horizontal distance from the end of the wall, and the round holes are set every 300mm vertically; Set round holes every 600mm in the horizontal distance; S2将钢丝网砂浆板(1)用钢筋或钢筋桁架连接件(3)进行连接,并用螺母将砂浆板(1)和钢筋或钢筋桁架连接件(3)两端固定;S2 connects the steel wire mesh mortar board (1) with a steel bar or a steel bar truss connector (3), and fixes both ends of the mortar board (1) and the steel bar or the steel bar truss connector (3) with nuts; S3将砂浆板(1)交错拼接,使用高强聚合砂浆(4)对钢丝网砂浆板(1)进行粘结,使钢丝网砂浆板(1)围合成墙体;S3 Stitching the mortar boards (1) staggeredly, using high-strength polymerized mortar (4) to bond the steel mesh mortar boards (1), so that the steel wire mortar boards (1) enclose a wall; S4浇筑发泡混凝土(2),成型后即为外包钢丝网砂浆板发泡混凝土槽形节能承重墙体;该墙体的外围是由钢丝网砂浆板(1)围合而成;墙体内部填充发泡混凝土(2);在墙体两端的砂浆板(1)之间设置钢筋连接件(3),并用螺母将钢筋两端与两钢丝网砂浆板(1)固定,钢丝网砂浆板(1)之间用高强聚合砂浆(4)进行粘结;墙体由钢丝网砂浆板(1)拼接而成,钢丝网水泥砂浆板(1)的长高可以加工成50、150、300、600mm相应的模数,厚度为20~25mm,砂浆采用的是高性能砂浆,内部有钢丝密布网作为钢筋骨架,在加工钢丝网水泥砂浆板时,只抛平一面作为浇筑模板的外面,粗糙的一面为浇筑模板的内面;钢丝网砂浆板(1)之间连接处用高强聚合砂浆(4)粘结,所述高强聚合砂浆为钢丝网砂浆板的柔性连接,涂抹厚度不超过5mm,以便于快速粘结硬化;连接两钢丝网砂浆板(1)的钢筋或钢筋桁架连接件(3)也可是钢筋桁架或其他预制连接件,当采用钢筋桁架连接时,钢筋采用HPB300型号,钢筋与水平线夹角为45°, 等间距布置,水平间距为250~300mm,竖向间距为400~500mm。S4 Pouring foamed concrete (2), after forming, it becomes the energy-saving and load-bearing wall of foamed concrete with steel mesh mortar board; the outer periphery of the wall is surrounded by steel mesh mortar board (1); Filling with foamed concrete (2); setting steel bar connectors (3) between the mortar boards (1) at both ends of the wall, and fixing the two ends of the steel bars with the two steel mesh mortar boards (1) with nuts, and the steel wire mortar boards ( 1) Bond with high-strength polymer mortar (4); the wall is made of steel mesh mortar boards (1), and the length and height of steel wire mesh cement mortar boards (1) can be processed into 50, 150, 300, 600mm Corresponding modulus, the thickness is 20-25mm, the mortar is high-performance mortar, and there is steel wire mesh inside as the reinforcement skeleton. When processing the steel wire mesh cement mortar board, only the flat side is used as the outside of the pouring formwork, and the rough side It is the inner surface of the pouring template; the joints between the steel mesh mortar boards (1) are bonded with high-strength polymer mortar (4), and the high-strength polymer mortar is a flexible connection of the steel wire mortar boards, and the thickness of the application is not more than 5mm, so as to facilitate rapid Bonding and hardening; the steel bar or steel truss connector (3) connecting the two steel mesh mortar boards (1) can also be a steel bar truss or other prefabricated connectors. When a steel bar truss is used for connection, the steel bar is HPB300, and the angle between the steel bar and the horizontal line 45°, arranged at equal intervals, with a horizontal interval of 250-300mm and a vertical interval of 400-500mm. 2.根据权利要求1所述的外包钢丝网砂浆板发泡混凝土槽形节能承重墙体的作法,其特征在于:钢丝网砂浆板(1)拼接时采用交错拼接的方法,增强钢丝网砂浆板(1)之间的连接作用。2. The method of outsourcing the steel wire mesh mortar board foamed concrete trough-shaped energy-saving load-bearing wall according to claim 1, characterized in that: when the steel wire mesh mortar board (1) is spliced, a staggered splicing method is used to strengthen the steel wire mesh mortar board (1) The connection between them.
CN201410108708.9A 2014-03-21 2014-03-21 Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete Active CN103938767B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410108708.9A CN103938767B (en) 2014-03-21 2014-03-21 Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410108708.9A CN103938767B (en) 2014-03-21 2014-03-21 Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete

Publications (2)

Publication Number Publication Date
CN103938767A CN103938767A (en) 2014-07-23
CN103938767B true CN103938767B (en) 2017-02-22

Family

ID=51186620

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410108708.9A Active CN103938767B (en) 2014-03-21 2014-03-21 Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete

Country Status (1)

Country Link
CN (1) CN103938767B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105421816B (en) * 2015-11-20 2017-08-15 刘斌 Insulation energy-saving assembling house and construction method
CN108517983A (en) * 2018-04-12 2018-09-11 合肥净龙环保科技有限公司 A kind of energy-saving earthquake-resistant wall
GB2574406B (en) * 2018-06-04 2020-07-08 Pbp Berlani Holding Ltd Improvements in or relating to building structures
CN109469189B (en) * 2018-12-25 2024-05-03 江苏富亚给排水科技有限公司 Assembled concrete prestress mould pressing box pump rainwater collecting tank and construction method thereof
CN111535483A (en) * 2020-05-12 2020-08-14 中建六局水利水电建设集团有限公司 Concrete anti-cracking wall and construction method thereof
CN113846768A (en) * 2021-08-18 2021-12-28 西北矿冶研究院 Environment-friendly energy-saving building wall and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2344691A1 (en) * 1976-03-15 1977-10-14 Metal Deploye PROCESS FOR CONSTRUCTING A WALL
CN2085821U (en) * 1991-02-27 1991-10-02 罗远才 Dolomitic sand double-layered concrete construction building board
CN200968053Y (en) * 2006-11-10 2007-10-31 文彦 Reinforced concrete detaching-free formwork
CN101769071A (en) * 2010-01-05 2010-07-07 梁林华 Insulation wall module and insulation wall constructed by same
CN103104094A (en) * 2010-04-21 2013-05-15 成都绿建科技有限公司 Construction method of lattice light-gauge steel house

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2344691A1 (en) * 1976-03-15 1977-10-14 Metal Deploye PROCESS FOR CONSTRUCTING A WALL
CN2085821U (en) * 1991-02-27 1991-10-02 罗远才 Dolomitic sand double-layered concrete construction building board
CN200968053Y (en) * 2006-11-10 2007-10-31 文彦 Reinforced concrete detaching-free formwork
CN101769071A (en) * 2010-01-05 2010-07-07 梁林华 Insulation wall module and insulation wall constructed by same
CN103104094A (en) * 2010-04-21 2013-05-15 成都绿建科技有限公司 Construction method of lattice light-gauge steel house

Also Published As

Publication number Publication date
CN103938767A (en) 2014-07-23

Similar Documents

Publication Publication Date Title
CN103835413B (en) Covered with Angles silk screen Mortar Plates in-line frame foamed concrete bearing wall and the practice
CN103046665B (en) Insulating mortar strengthening layer rowlock wall with steel wire mesh for setting hose tooth constructional column and manufacturing method thereof
CN103835404B (en) Covered with Angles silk screen Mortar Plates L-shaped frame foamed concrete bearing wall and the practice
CN205046685U (en) External heated board of prefabricated masonry wall
EP4582233A1 (en) Prefabricated component formed by reverse laying and production process therefor
CN103938767A (en) Trough type energy-saving bearing wall externally wrapped by steel wire mesh mortar plates and foamed concrete
CN215253698U (en) Ceramsite foam concrete exterior wall hanging plate in assembly type building
CN110295681A (en) The high-strength foam concrete filled-in panel external wall self-insulation system of precast light
WO2015120794A1 (en) Building component replacing plaster layer with prefabricated panel protection layer
CN211286074U (en) Self-heat-insulation system for prefabricated light high-strength foam concrete filled wallboard outer wall
CN108035485A (en) Assembled CF steam pressures porcelain powder air entrained concrete shear wall Side fascia and production method
CN108081699A (en) Assembled CF steam pressure porcelain powder aerated concrete outer wall hanging plates and production method
CN206815590U (en) A kind of wallboard installation node based on frame system
CN104032895A (en) High-performance cement mortar formwork heat preservation recycled concrete L-shaped column without demolition and its method
CN218990548U (en) Dry-wet combined secondary wall structure
CN211622098U (en) A semi-embedded external waterproof and internal thermal insulation external wall panel
CN104131647A (en) Basalt fiber reinforced sea sand cement-base composite heat insulation wall plate
CN103835401B (en) Covered with Angles silk screen Mortar Plates cross-frame foamed concrete bearing wall and the practice
CN207959692U (en) A kind of assembled CF steam pressures porcelain powder air entrained concrete shear wall Side fascia
CN108643346B (en) Assembled built-in heat preservation layer foamed concrete composite wall-light steel frame-floor connection node
CN104005511B (en) High-performance water cement mortar plate built-in light ecological material T-shaped insulating bearing building block
CN214423691U (en) Light concrete reinforced bar net frame composite thermal insulation wall board
CN103883042A (en) Externally-coated steel wire gauze mortar plate foamed concrete line-shaped energy-saving bearing wall and manufacturing method
CN103835403B (en) Covered with Angles silk screen Mortar Plates T-shaped frame foamed concrete bearing wall and the practice
CN107780567A (en) Concrete walls with through connection bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201221

Address after: 100124 No. 100 Chaoyang District Ping Tian Park, Beijing

Patentee after: Beijing University of Technology

Patentee after: Hebei Huiyuan Building Materials Co.,Ltd.

Address before: 100124 No. 100 Chaoyang District Ping Tian Park, Beijing

Patentee before: Beijing University of Technology

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100124 No. 100 Chaoyang District Ping Tian Park, Beijing

Patentee after: Beijing University of Technology

Patentee after: HEBEI HUIYUAN BUILDING MATERIAL Co.,Ltd.

Address before: 100124 No. 100 Chaoyang District Ping Tian Park, Beijing

Patentee before: Beijing University of Technology

Patentee before: Hebei Huiyuan Building Materials Co.,Ltd.