CN103898925B - 一种防沉降井盖换装方法 - Google Patents

一种防沉降井盖换装方法 Download PDF

Info

Publication number
CN103898925B
CN103898925B CN201410154736.4A CN201410154736A CN103898925B CN 103898925 B CN103898925 B CN 103898925B CN 201410154736 A CN201410154736 A CN 201410154736A CN 103898925 B CN103898925 B CN 103898925B
Authority
CN
China
Prior art keywords
well lid
road surface
asphalt mixture
manhole cover
colander
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410154736.4A
Other languages
English (en)
Other versions
CN103898925A (zh
Inventor
刘帮银
吴祥燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Chengbang Road Surface Materials Co.,Ltd.
Original Assignee
CHONGQING CHENGBANG ROAD SURFACE MATERIALS CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING CHENGBANG ROAD SURFACE MATERIALS CO LTD filed Critical CHONGQING CHENGBANG ROAD SURFACE MATERIALS CO LTD
Priority to CN201410154736.4A priority Critical patent/CN103898925B/zh
Publication of CN103898925A publication Critical patent/CN103898925A/zh
Application granted granted Critical
Publication of CN103898925B publication Critical patent/CN103898925B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种防沉降井盖换装方法,属于市政工程技术领域。该换装方法包括以下工艺步骤:a.取出旧井盖;b.放线并切割破除检查井周边至标准宽度和深度;c.井盖基座找平;d.安放井盖调节圈;e.安插防漏锅;f.填充环氧沥青混合料,分层压实;g.再次填充环氧沥青混合料高出原路面1~2cm,拔出防漏锅;h.插入防沉降井盖,并将井盖压入路面,使之与路面水平;i.封水罩面。本发明方法操作简单易行,设备要求低,具有强度高、耐久实用、价格低廉等优点,在城市道路日常维护中有推广价值。

Description

一种防沉降井盖换装方法
技术领域
本发明属于市政工程技术领域,涉及一种防沉降井盖换装方法。
背景技术
随着城市交通量迅猛增加,城市道路检查井及井盖周边经常出现沉降、开裂、行车时跳车、噪音等现象。目前,井盖下沉已成为我国许多城市的通病。分析原因主要为井座是预埋方式,不好准确确定标高,在调整井座标高与路面几公分高差时,施工人员往往用石块、瓦片等材料随意填充。井盖安装好后,在车辆冲击震动下,这些填充材料极易粉碎。随着井座周边雨水的渗入,填充材料会逐渐流失,井座自然下沉。随着井座与路面标高差距加大,井盖受到汽车冲击震动越来越大,井座加速下沉,导致井盖破损和井座周边路面松散、开裂、下陷等,以至于必须重新更换井座,恢复沉陷的路面。
井盖下沉及周边破损等问题,已成为制约城市道路工程质量的瓶颈,严重影响了城市道路交通安全和服务水平,影响了道路的平整度和美观。
发明内容
本发明为了弥补现有技术的不足,提供了一种操作简单易行,设备要求低,具有强度高、耐久实用、价格低廉等优点的防沉降井盖换装方法,在城市道路日常维护中有推广价值。
本发明的目的通过如下技术方案实现:
一种防沉降井盖换装方法,其特征在于包括以下步骤:
a.取出旧井盖;
b.放线并切割破除检查井周边至标准宽度和深度;
c.井盖基座找平;
d.安放井盖调节圈;
e.安插防漏锅;
f.填充环氧沥青混合料,分层压实;
g.再次填充环氧沥青混合料高出原路面1~2cm,拔出防漏锅;
h.插入防沉降井盖,并将井盖压入路面,使之与路面水平;
i.封水罩面。
所述的环氧沥青混合料为在施工现场,将液体环氧沥青与级配料按照1:(5~6)的比例在立式强制搅拌机中拌和1~3min而成的材料。
所述的封水罩面是将液体环氧沥青均匀涂布于井盖周边新铺路面上,然后均匀撒布一层粒径为1-3mm的骨料,在25℃晴朗天气养生2-4小时后即可开放交通使用。
相对于现有技术,本技术发明的优点:
(1)本发明的防沉降井盖换装方法操作简单易行,设备要求低,能随时组织对破损井盖进行换装,便于推广应用。
(2)本发明将环氧沥青混合料用到防沉降结构中,因其具有极高的强度、刚度以及良好的高温抗塑性和低温抗裂性、抗疲劳性等优点,大大提高了结构的稳定性和使用耐久性。
(3)本发明提供了一层抗滑磨耗层可对原路面与井盖的衔接平顺度进行调节,保证整体平整度,分散车辆对井盖及其周边的冲击力,同时可将环氧沥青混合料与原路面紧密连接在一起,并对路面进行封水处理防止雨水对井盖及其周边路面结构的破坏。
具体实施方式
为了更好的理解本发明,下面通过实施例1、2对发明的防沉降井盖换装方法进行详细说明。
本发明所涉及的液体环氧沥青(为重庆诚邦路面材料有限公司提供,产品型号CML-Ⅰ),防沉降井盖为上海吉信金属制品有限公司提供。
实施例1:
当旧井盖周边有轻微破损且基座良好的情况时,一种防沉降井盖换装方法,包括以下步骤:
a.取出旧井盖;
b.以旧井盖为中心,按照1.0米的直接进行放线并切割破除检查井周边至标准宽度,深度控制在12~15cm;
c.将井盖基座表面清理干净,计算需要填补的体积估算环氧沥青混合料用量,然后按照液体环氧沥青:AC10级配料(材质为石灰岩)为1:(5~6)的比例在立式强制搅拌机中将两者充分拌和1~3min待用,最后,采用环氧沥青混合料将井盖基座找平;
d.安放井盖调节圈;
e.安插防漏锅;
F.将拌和好的环氧沥青混合料填充于井圈周边,按照每层5~8cm的填充厚度进行分层压实,直至与原路面基本齐平;
g.再次填充环氧沥青混合料高出原路面1~2cm,拔出防漏锅;
h.插入防沉降井盖,并将井盖压入路面,使之与路面水平;
i.将液体环氧沥青均匀涂布于井盖周边新铺路面上,然后均匀撒布一层粒径为1-3mm的骨料(材质为玄武岩),在25℃晴朗天气养生2-4小时后即可开放交通使用。
经检测,在常温下养生1小时,环氧沥青混合料马歇尔强度(检测方法为JTG E20-2011《公路工程沥青及沥青混合料试验规程》中的T0709-2011)为15.2KN,浸水马歇尔强度养生24小时,马歇尔强度为32.5KN。路面摆值、构造深度、渗水等技术指标符合JTG F40-2004《公路沥青路面施工技术规范》相关规定。
实施例2:
当旧井盖周边有严重破损且基座不好的情况时,一种防沉降井盖换装方法,包括以下步骤:
a.取出旧井盖;
b.以旧井盖为中心,按照实际破损的范围进行放线并切割破除检查井周边至标准宽度,深度按照实际情况进行开挖。深度超过15cm的应用水泥砖砌筑保证深度在12~15cm;
c.将井盖基座表面清理干净,计算需要填补的体积估算环氧沥青混合料用量,然后按照液体环氧沥青:AC13级配料(材质为玄武岩)为1:(5~6)的比例在立式强制搅拌机中将两者充分拌和1~3min待用,最后,采用环氧沥青混合料将井盖基座找平;
d.安放井盖调节圈;
e.安插防漏锅;
F.将拌和好的环氧沥青混合料填充于井圈周边,按照每层5~8cm的填充厚度进行分层压实,直至与原路面基本齐平;
g.再次填充环氧沥青混合料高出原路面1~2cm,拔出防漏锅;
h.插入防沉降井盖,并将井盖压入路面,使之与路面水平;
i.将液体环氧沥青均匀涂布于井盖周边新铺路面上,然后均匀撒布一层粒径为1-3mm的骨料(材质为陶瓷颗粒),在25℃晴朗天气养生2-4小时后即可开放交通使用。
经检测,在常温下养生1小时,环氧沥青混合料马歇尔强度(检测方法为JTG E20-2011《公路工程沥青及沥青混合料试验规程》中的T0709-2011)为15.9KN,浸水马歇尔强度养生24小时,马歇尔强度为32.5KN。路面摆值、构造深度、渗水等技术指标符合JTG F40-2004《公路沥青路面施工技术规范》相关规定。

Claims (1)

1.一种防沉降井盖换装方法,其特征在于包括以下步骤:
a.取出旧井盖;
b.放线并切割破除检查井周边至标准宽度和深度;
c.井盖基座找平;
d.安放井盖调节圈;
e.安插防漏锅;
f.填充环氧沥青混合料,按照每层5~8cm的填充厚度进行分层压实,直至与原路面基本齐平;
g.再次填充环氧沥青混合料高出原路面1~2cm,拔出防漏锅;
h.插入防沉降井盖,并将井盖压入路面,使之与路面水平;
i.封水罩面,将液体环氧沥青均匀涂布于井盖周边新铺路面上,然后均匀撒布一层粒径为1~3mm的骨料,对原路面与井盖的衔接平顺度进行调节,在25度晴朗天气养生2~4小时后即可开放交通使用;
其中,所述的环氧沥青混合料为在施工现场,将液体环氧沥青与级配料按照1:(5~6)的比例在立式强制搅拌机中拌和1~3min而成的材料。
CN201410154736.4A 2014-04-18 2014-04-18 一种防沉降井盖换装方法 Active CN103898925B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410154736.4A CN103898925B (zh) 2014-04-18 2014-04-18 一种防沉降井盖换装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410154736.4A CN103898925B (zh) 2014-04-18 2014-04-18 一种防沉降井盖换装方法

Publications (2)

Publication Number Publication Date
CN103898925A CN103898925A (zh) 2014-07-02
CN103898925B true CN103898925B (zh) 2019-05-17

Family

ID=50990478

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410154736.4A Active CN103898925B (zh) 2014-04-18 2014-04-18 一种防沉降井盖换装方法

Country Status (1)

Country Link
CN (1) CN103898925B (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106012731A (zh) * 2016-05-30 2016-10-12 广州市市政工程设计研究总院 一种沥青路面分期实施的方法
CN106638702A (zh) * 2016-12-29 2017-05-10 成都市市政开发总公司 可调式防沉降检查井盖病害治理施工工艺
CN106930327B (zh) * 2017-03-06 2019-02-12 温州市市政工程建设开发公司 井盖施工安装方法
CN112922037A (zh) * 2021-01-25 2021-06-08 武汉市汉阳市政建设集团有限公司 一种防沉降井盖安装与路面铺设沥青的同步施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012031668A (ja) * 2010-07-31 2012-02-16 Sanko Kikaku Kk 路面用防護シート及び舗装方法
KR20120015588A (ko) * 2010-08-12 2012-02-22 한국건설기술연구원 조립식 초고성능 콘크리트 맨홀 뚜껑
CN102644295A (zh) * 2012-04-28 2012-08-22 江苏阳湖建设项目管理有限公司 防止路面检查井周边和局部沉降的施工方法
CN202416377U (zh) * 2012-02-20 2012-09-05 刘建华 一种加固检查井井盖基座的构造
CN103114607A (zh) * 2013-03-04 2013-05-22 济南城建集团有限公司 防沉降检查井盖及其施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012031668A (ja) * 2010-07-31 2012-02-16 Sanko Kikaku Kk 路面用防護シート及び舗装方法
KR20120015588A (ko) * 2010-08-12 2012-02-22 한국건설기술연구원 조립식 초고성능 콘크리트 맨홀 뚜껑
CN202416377U (zh) * 2012-02-20 2012-09-05 刘建华 一种加固检查井井盖基座的构造
CN102644295A (zh) * 2012-04-28 2012-08-22 江苏阳湖建设项目管理有限公司 防止路面检查井周边和局部沉降的施工方法
CN103114607A (zh) * 2013-03-04 2013-05-22 济南城建集团有限公司 防沉降检查井盖及其施工方法

Also Published As

Publication number Publication date
CN103898925A (zh) 2014-07-02

Similar Documents

Publication Publication Date Title
CN103898925B (zh) 一种防沉降井盖换装方法
US10407839B2 (en) System and method for roadway maintenance and repair
CN101857409A (zh) 一种流动化回填土及制备和施工方法
CN106149500B (zh) 一种水泥乳化沥青砂浆贯入式半柔性路面的施工方法
De Visscher et al. Ravelling by traffic: Performance testing and field validation
Lee et al. Evaluating pavement performance in bus rapid transit systems: Lessons from Seoul, South Korea
CN109870557B (zh) 一种确定碎石封层最大沥青用量的测试方法
CN102515636A (zh) 一种贯入式水泥混凝土材料及其制备方法和用途
CN204139206U (zh) 一种井盖防沉降结构
CN102787547B (zh) 半刚性基层沥青路面设计施工的方法
CN102337715A (zh) 一种花岗岩混凝土路面砖及其制作方法
CN109235457B (zh) 一种道路竖井井周回填方法
Jamion et al. Performance of micro surfacing on expressway
CN107476160B (zh) 一种红土沙砾路面基层的改良方法
Sharma et al. Utilization of Quarry dust in cement concrete paver blocks for rural Roads
Zahir Performance of local aggregate in high friction surface treatment
CN203007780U (zh) 一种水泥稳定碎石拌和站的防成品料含水量波动和离析的装置
Brotman et al. Roller compacted concrete pavement: Properties, design, and construction
CN201730033U (zh) 一种花岗岩混凝土路面砖
Strynadka et al. Performance Review of the Light-coloured Pavement of the 2009 Front Street Project in Dawson City Yukon
CN107021683A (zh) 一种路面快速修复使用的水泥砂浆混凝土及其施工方法
Soto-Espitia et al. Performance of Portland cement stabilized bases in Mexico
Wang Common Problems in Construction of Road and Bridge and the Application of Quality Inspection Technology
Abate Concrete paving blocks: an overview
CN105256686A (zh) 一种高等级公路高寒路面微表处预防性养护施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20180116

Address after: 400000 factory building, No. 3-4, Jiangqiao Road, Nan'an District, Chongqing, 6

Applicant after: Chongqing sincere Technology Group Co., Ltd.

Address before: 401336 Jiangqiao Road, Nanan District, Chongqing 3-4

Applicant before: Chongqing Chengbang Road Surface Materials Co.,Ltd.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20180604

Address after: No. 6, No. 3-4, Jiangqiao Road, Nanan District, Chongqing City, Chongqing

Applicant after: Chongqing Chengbang Road Surface Materials Co.,Ltd.

Address before: No. 6, No. 3-4, Jiangqiao Road, Nanan District, Chongqing City, Chongqing

Applicant before: Chongqing sincere Technology Group Co., Ltd.

GR01 Patent grant
GR01 Patent grant