CN103882871A - Rapid construction method for seepage-proof dam of salt pan - Google Patents
Rapid construction method for seepage-proof dam of salt pan Download PDFInfo
- Publication number
- CN103882871A CN103882871A CN201410037160.3A CN201410037160A CN103882871A CN 103882871 A CN103882871 A CN 103882871A CN 201410037160 A CN201410037160 A CN 201410037160A CN 103882871 A CN103882871 A CN 103882871A
- Authority
- CN
- China
- Prior art keywords
- foundation trench
- impervious material
- earthing
- seepage
- proboscis
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The invention discloses a rapid construction method for a seepage-proof dam of a salt pan. The rapid construction method specifically includes firstly, digging a foundation trench; secondly, putting a seepage-proof material to the bottom of the foundation trench, and filling the foundation trench with earth and grinding the earth; thirdly, directly lifting the seepage-proof material to a designed lift height after grinding; finally, earthing up and grinding synchronously on two sides of the seepage-proof material. The construction process includes the steps of foundation trench digging, filming, foundation trench filling, film lifting, earthing-up, grinding, re-earthing-up and re-grinding, and the conventional earth surface construction process, including earthing-up, grinding and film turning, for the seepage-proof dam is changed into earthing-up and grinding, so that process is simplified, construction period is shortened, extruding and folding of the seepage-proof material due to the action of natural angle of repose of the earth during layered and staggered earthling-up and grinding can be avoided, loss of the seepage-proof material is reduced, and construction cost of the seepage-proof dam is saved.
Description
Technical field
The present invention relates to antiseepage dam, a kind of salt pan construction method, relate in particular to a kind of antiseepage dam, salt pan fast construction method containing impervious material.
Background technology
Antiseepage dam, existing salt pan is built in and completes after foundation trench, then adopt the stagger mode that rolls of layering dam body is carried out repeatedly to earthing to roll in impervious material both sides, master operation is for digging foundation trench-lower film-fill out foundation trench-earthing-roll-turn over film-earthing again-roll-turn over film, this mode is completing after foundation trench, build dam operation for turning over film-earthing-roll, not only procedure connection is more complicated, and because being staggers and rolls in the layering of impervious material both sides, cause impervious material run-off the straight under the effect of each stratified soil natural repose angle, paving mode when paving mode when the paving mode of impervious material designs as shown in Figure 1 becomes the practice of construction shown in Fig. 2, therefore many consumptions impervious material 20-40% when practice of construction is than design, cause the significant wastage of artificial material, improved the cost on antiseepage dam simultaneously.
Summary of the invention
Technical problem to be solved by this invention is, provides a kind of procedure connection relatively simple, can save impervious material, reduces antiseepage dam, the salt pan fast construction method of antiseepage dam cost.
The technical solution adopted for the present invention to solve the technical problems is: antiseepage dam, a kind of salt pan fast construction method, and its construction process is for digging foundation trench-lower film-fill out foundation trench-lift film-earthing-roll-earthing again-roll again, and concrete steps are:
First dig foundation trench, dig after foundation trench, transfer impervious material from earth's surface (as plastic-coated canvas, geotextiles, HDPE film etc., in construction, also can be referred to as " film ") be connected to bottom foundation trench, then foundation trench is banketed and rolled, after having rolled, the close position of transferring impervious material on earth's surface, install a series of by pullover along the assembling of moving towards of transferring impervious material, extension bar, be embedded with the articulated section of plumb aligner, the tail bone linking together with articulated section, and the supporting rod of clip composition, when assembling is installed, first tail bone is inserted to earth's surface, then the external screw thread of articulated section is connected to the internal thread of extension bar lower end, pullover internal thread is connected to the external screw thread of extension bar upper end, then connect the pullover becket bridle of each supporting rod with hawser, then by extension bar and be connected to the pullover righting on extension bar, when righting, to be embedded in plumb aligner on articulated section as reference, in the time that the colored bulb in plumb aligner is parallel with two benchmark grooves, think supporting rod righting, then use clip seizing hinge in articulated section, and hawser two ends are strained and fixed, then tied a knot in stay cord one end, pinch out the clamp holder of proboscis folder, stinging head-clamp with the proboscis of proboscis folder lives after impervious material, the lacing hole that one end that stay cord is not tied a knot presss from both sides through proboscis is also walked around hawser, pulling down stay cord lifts impervious material to design height, then in impervious material both sides, synchronous layered earthing rolls simultaneously, after having rolled, reclaim supporting rod, proboscis folder, hawser and stay cord.
Further, supporting rod is installed one group along the trend of transferring impervious material every the assembling of 50-100 rice, and the proboscis that is installed with stay cord is clipped on hawser arranges one every 8-12 rice (preferably 10 meters).
Further, the situation of too loosening for earth's surface soil property, by be positioned at plan to build wedge angle rope on pullover of the supporting rod at two ends, antiseepage dam and by rope on ground piling reinforce.
One section of extension bar preferred length is 2 meters, lifts height according to the ground of the impervious material of design, rationally determines extension bar hop count.
For antiseepage dam, salt pan construction site vegetation sparse, lack trees, and the higher feature of design hoisting depth of film, in order to lift quickly and easily impervious material, the present invention is by supporting a whole set of impervious material handle system, comprise supporting rod, proboscis rope clamp, hawser, stay cord etc., can lift impervious material rapid large-area, realize antiseepage dam, salt pan fast construction.
Compared with prior art, the present invention has the following advantages:
(1) construction process of above ground, antiseepage dam, salt pan part is become and lifts film-earthing-roll-earthing again-roll again from turning over film-earthing-roll-turn over film-earthing again-roll again, circulating process becomes earthing-roll two steps from earthing-roll-turn over film three steps, simplify operation, thereby shortened antiseepage dam construction duration;
(2) before layering earthing rolls, impervious material is directly lifted to design attitude, can avoid the layering of impervious material both sides stagger earthing while rolling because native natural repose angle effect is folding to the extruding of impervious material, thereby reduce the loss of impervious material, the cost of saving antiseepage dam.
In sum, when the present invention can effectively solve the dam of salt pan antiseepage in the past and builds, long and layering earthing of complex procedures, duration rolls the problem of pushing a large amount of losses of impervious material that impervious material brings while turning over film.Through estimation, the present invention can reduce the consumption 20-40% left and right of impervious material in practice, the expenditure of construction on every kilometer of antiseepage dam can be saved ten thousand yuan of left and right of 10-20 and (consider reusing of membrane system, actual expense of saving will be more), do not affecting under the prerequisite of workmanship, both reduced the duration, reduced again investment.
Accompanying drawing explanation
Fig. 1 is the antiseepage dam plastic film mulch form of design;
Fig. 2 is antiseepage dam plastic film mulch form after prior art practice of construction;
Fig. 3 is that fast construction antiseepage dam, salt pan of the present invention lifts film schematic diagram;
Fig. 4 is the structural representation of the present invention's supporting rod used;
Fig. 5 is the pullover enlarged diagram of supporting rod shown in Fig. 4;
Fig. 6 is the articulated section enlarged diagram of supporting rod shown in Fig. 4;
Fig. 7 is the structural representation of the extension bar of supporting rod shown in Fig. 4;
Fig. 8 is the structural representation of the plumb aligner of supporting rod shown in Fig. 4;
Fig. 9 is the structural representation of the present invention's proboscis folder used;
In figure: 1, foundation trench, 2, supporting rod, 3, proboscis folder, 4, impervious material, 5, hawser, 6, stay cord, 7, pullover, 8, extension bar, 9, articulated section, 10, tail bone, 11, becket bridle, 12, wedge angle, 13, pullover internal thread, 14, the external screw thread of articulated section, 15, plumb aligner, 16, hinge, 17, clip, 18, the external screw thread of extension bar upper end, 19, the internal thread of extension bar lower end, 20, colored bulb, 21, benchmark groove, 22, clamp holder, 23, lacing hole, 24, proboscis stings head.
the specific embodiment
Below in conjunction with drawings and Examples, the invention will be further described.
Referring to Fig. 1-Fig. 2, final purpose of the present invention is that impervious material 4 is proofreaied and correct as shown in Figure 2 as shown in Fig. 1.
With reference to Fig. 3-Fig. 9, antiseepage dam, the salt pan fast construction method of the present embodiment, its construction process is for digging foundation trench-lower film-fill out foundation trench-lift film-earthing-roll-earthing again-roll again, and concrete steps are:
First dig foundation trench 1, dig after foundation trench 1, transfer impervious material 4 from earth's surface and be connected to foundation trench 1 bottom, then foundation trench 1 is banketed and rolled, after having rolled, the close position of transferring impervious material 4 on earth's surface, install one group by pullover 7 along the trend of transferring impervious material 4 every 100 meters of assemblings, extension bar 8, be embedded with the articulated section 9 of plumb aligner, the tail bone 10 linking together with articulated section 9, and the supporting rod 2 that forms of clip 17, when assembling is installed, first tail bone 10 is inserted to earth's surface, then the external screw thread of articulated section 14 is connected to the internal thread 19 of extension bar lower end, pullover internal thread 13 is connected to the external screw thread 18 of extension bar upper end, then connect the pullover becket bridle 11 of each supporting rod 2 with hawser 5, then by extension bar 8 and be connected to pullover 7 rightings on extension bar, when righting, using the plumb aligner 15 that is embedded in articulated section as reference, in the time that the colored bulb 20 in plumb aligner 15 is parallel with two benchmark grooves 21, think supporting rod 2 rightings, then use clip 17 seizing hinges 16 in articulated section, and hawser 5 two ends are strained and fixed, then by stay cord 6 one end knottings, then pinch out the clamp holder 22 of proboscis folder 3, stinging 24 with the proboscis of proboscis folder 3 clamps after impervious material 4, one end that stay cord 6 is not tied a knot presss from both sides 3 lacing hole 23 and walks around hawser 5 through proboscis, the proboscis folder 3 that is installed with stay cord 6 is arranged one every 10 meters on hawser, pulling down stay cord 6 lifts impervious material 4 to design height, then in impervious material both sides, synchronous layered earthing rolls simultaneously, after having rolled, reclaim supporting rod 2, proboscis folder 3, hawser 5 and stay cord 6.
The situation of too loosening for earth's surface soil property, will be positioned at the wedge angle 12 use ropes on the supporting rod 2 pullover 7 of planning to build two ends, antiseepage dam and rope be driven piles and reinforced on ground.
Claims (3)
1. a salt pan antiseepage dam fast construction method, is characterized in that, construction process is for digging foundation trench-lower film-fill out foundation trench-lift film-earthing-roll-earthing again-roll again, and concrete steps are:
First dig foundation trench, dig after foundation trench, transfer impervious material from earth's surface and be connected to foundation trench bottom, then foundation trench is banketed and rolled, after having rolled, the close position of transferring impervious material on earth's surface, install a series of by pullover along the assembling of moving towards of transferring impervious material, extension bar, be embedded with the articulated section of plumb aligner, the tail bone linking together with articulated section, and the supporting rod of clip composition, when assembling is installed, first tail bone is inserted to earth's surface, then the external screw thread of articulated section is connected to the internal thread of extension bar lower end, pullover internal thread is connected to the external screw thread of extension bar upper end, then connect the pullover becket bridle of each supporting rod with hawser, then by extension bar and be connected to the pullover righting on extension bar, when righting, to be embedded in plumb aligner on articulated section as reference, in the time that the colored bulb in plumb aligner is parallel with two benchmark grooves, think supporting rod righting, then use clip seizing hinge in articulated section, and hawser two ends are strained and fixed, then tied a knot in stay cord one end, pinch out the clamp holder of proboscis folder, sting head-clamp with the proboscis of proboscis folder and live impervious material, the lacing hole that one end that stay cord is not tied a knot presss from both sides through proboscis is also walked around hawser, pulling down stay cord lifts impervious material to design height, then in impervious material both sides, simultaneously synchronous earthing rolls, after having rolled, reclaim supporting rod, proboscis folder, hawser and stay cord.
2. antiseepage dam, salt pan according to claim 1 fast construction method, is characterized in that: supporting rod is installed one group along the trend of transferring impervious material every the assembling of 50-100 rice, and the proboscis that is installed with stay cord is clipped on hawser arranges one every 8-12 rice.
3. antiseepage dam, salt pan according to claim 1 and 2 fast construction method, it is characterized in that: the situation of too loosening for earth's surface soil property, by be positioned at plan to build wedge angle rope on pullover of the supporting rod at two ends, antiseepage dam and by rope on ground piling reinforce.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410037160.3A CN103882871B (en) | 2014-01-26 | 2014-01-26 | A kind of antiseepage dam, salt pan fast construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410037160.3A CN103882871B (en) | 2014-01-26 | 2014-01-26 | A kind of antiseepage dam, salt pan fast construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103882871A true CN103882871A (en) | 2014-06-25 |
CN103882871B CN103882871B (en) | 2015-08-19 |
Family
ID=50951974
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410037160.3A Expired - Fee Related CN103882871B (en) | 2014-01-26 | 2014-01-26 | A kind of antiseepage dam, salt pan fast construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103882871B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106564915B (en) * | 2016-10-26 | 2018-02-13 | 化工部长沙设计研究院 | A kind of plastic film mulch antiseepage salt pan and its construction method |
CN111877262A (en) * | 2020-07-30 | 2020-11-03 | 青海盐湖工业股份有限公司 | Antiseep structure in old bittern salt pan |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10246575A1 (en) * | 2002-10-05 | 2004-05-13 | Ströhl, Gerhard | Method for upgrading flood protection earth dam by driving in interlocking steel plates into the top of the dam using a mobile rig |
CN102561364A (en) * | 2012-01-20 | 2012-07-11 | 山西机械化建设集团公司 | 'Three-step three-layer method' landfill filling construction process of dimension stone high-fill dynamic compaction treatment foundation |
CN102745722A (en) * | 2012-07-20 | 2012-10-24 | 中蓝连海设计研究院 | Novel three-proofing salt field and construction method thereof |
CN102992356A (en) * | 2012-12-18 | 2013-03-27 | 莱州诚源盐化有限公司 | Method for rapidly building anti-seepage salt pond |
CN103466659A (en) * | 2013-09-24 | 2013-12-25 | 山东省海洋化工科学研究院 | Manufacturing method of salt pan sand pit plate |
-
2014
- 2014-01-26 CN CN201410037160.3A patent/CN103882871B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10246575A1 (en) * | 2002-10-05 | 2004-05-13 | Ströhl, Gerhard | Method for upgrading flood protection earth dam by driving in interlocking steel plates into the top of the dam using a mobile rig |
CN102561364A (en) * | 2012-01-20 | 2012-07-11 | 山西机械化建设集团公司 | 'Three-step three-layer method' landfill filling construction process of dimension stone high-fill dynamic compaction treatment foundation |
CN102745722A (en) * | 2012-07-20 | 2012-10-24 | 中蓝连海设计研究院 | Novel three-proofing salt field and construction method thereof |
CN102992356A (en) * | 2012-12-18 | 2013-03-27 | 莱州诚源盐化有限公司 | Method for rapidly building anti-seepage salt pond |
CN103466659A (en) * | 2013-09-24 | 2013-12-25 | 山东省海洋化工科学研究院 | Manufacturing method of salt pan sand pit plate |
Non-Patent Citations (1)
Title |
---|
高振忠等: "《盐田卤水的渗漏及其防治》", 《吉林工业大学学报》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106564915B (en) * | 2016-10-26 | 2018-02-13 | 化工部长沙设计研究院 | A kind of plastic film mulch antiseepage salt pan and its construction method |
CN111877262A (en) * | 2020-07-30 | 2020-11-03 | 青海盐湖工业股份有限公司 | Antiseep structure in old bittern salt pan |
CN111877262B (en) * | 2020-07-30 | 2021-11-16 | 青海盐湖工业股份有限公司 | Antiseep structure in old bittern salt pan |
Also Published As
Publication number | Publication date |
---|---|
CN103882871B (en) | 2015-08-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206457819U (en) | Anchor pole for slope retaining | |
CN203200746U (en) | High-pressure jet grouting hollow reinforced tubular pile | |
CN109056756B (en) | A kind of suspension device and its construction method of High water cut side slope | |
CN103867209A (en) | Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro | |
CN103882871A (en) | Rapid construction method for seepage-proof dam of salt pan | |
CN204000755U (en) | A kind of Chained slope protection building block | |
CN103485356B (en) | Overwater laying frame and method for filling sand pockets with same | |
CN206000258U (en) | A kind of gardens fence with pouring function | |
CN100459845C (en) | Invisible garden tree fixing method | |
CN206529712U (en) | Assembled steel reinforced concrete aliform type culvert opening | |
CN204097889U (en) | A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement | |
CN204000859U (en) | The mutual foundation drainage pile for prestressed pipe of a kind of soft or hard interlayer | |
CN203515607U (en) | Adjustable steel mould trolley of tunnel widening section | |
CN206486780U (en) | Electromagnetic type steel plate lays car | |
CN207919554U (en) | A kind of static pressed pile soil digging machine | |
CN204298829U (en) | A kind of prosthetic device being applied to underground large discharge seepage | |
CN203034790U (en) | Basic prefabricated concrete formwork for basement | |
CN208934703U (en) | A kind of construction joint of tunnel and deformation joint open defect renovate structure | |
CN111691396A (en) | Novel drainage plate vacuum preloading geotextile construction equipment and construction method thereof | |
CN207193912U (en) | Full-automatic numerical control can supertronic compare coffering machine | |
CN202543759U (en) | Concrete block for road construction | |
CN203129163U (en) | Reinforcing framework structure for dam foundation | |
CN205491690U (en) | Fertilizer applicator breaks ground | |
CN206789240U (en) | A kind of buried pipeline warning pile | |
CN207063110U (en) | A kind of removable gutter of open slope |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150819 Termination date: 20170126 |