CN103867209A - Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro - Google Patents

Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro Download PDF

Info

Publication number
CN103867209A
CN103867209A CN201410090973.9A CN201410090973A CN103867209A CN 103867209 A CN103867209 A CN 103867209A CN 201410090973 A CN201410090973 A CN 201410090973A CN 103867209 A CN103867209 A CN 103867209A
Authority
CN
China
Prior art keywords
deck
way
transverse passage
scaffold
vertical shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410090973.9A
Other languages
Chinese (zh)
Inventor
宋战平
杨腾添
张丹锋
宋云财
张立华
戴文革
林吉兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Architecture and Technology
Original Assignee
Xian University of Architecture and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology filed Critical Xian University of Architecture and Technology
Priority to CN201410090973.9A priority Critical patent/CN103867209A/en
Publication of CN103867209A publication Critical patent/CN103867209A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a method of layered and segmental construction, excavation and holing of transverse passages of a vertical shaft of a metro. According to the method, the height of setting up a scaffold is effectively reduced in a process of carrying out construction, excavation and holing of the transverse passages through a layered and segmental holing manner, so that the set-up work amount of the scaffold and the loss of the scaffold due to muck burying are reduced, and the security risk caused by the height of setting up can be reduced.

Description

The layering of a kind of subway vertical shaft, segmentation turn adit construction and excavate the method into hole
Technical field
The present invention relates to a kind of method of excavating into hole, be specifically related to the layering of a kind of subway vertical shaft, segmentation turns adit construction and excavates the method into hole.
Background technology
Tradition multilayer accessory channel vertical shaft enters hole and adopts and set up scaffold after vertical shaft back cover and abolish, as shown in Figure 1, because multilayer accessory channel is conventionally highly higher, the scaffold of setting up is thereupon also higher, the scaffold of high height is not only set up and need to be expended a large amount of human and material resources, and the dregs that accessory channel when construction produces can bury scaffold bottom, cause a large amount of losses of scaffold, also can cause the vertical shaft inconvenience of slagging tap; Because scaffold height is higher, staff's security risk also can increase.
Summary of the invention
The object of the invention is to overcome the shortcoming of above-mentioned prior art, provide the layering of a kind of subway vertical shaft, segmentation to turn adit construction and excavated the method into hole, the method adopts the mode of layering, segmentation to enter hole, can effectively reduce the height of scaffold, reduces the security risk of construction.
For achieving the above object, subway vertical shaft of the present invention layering, segmentation turn adit construction and excavate into the method in hole and comprise the following steps:
1) by To Construction of Silo to N rice under first floor transverse passage-way inverted arch, then lay the interim back cover of first floor in the bottom of vertical shaft, and on the interim back cover of first floor, set up the scaffold of first floor, carrying out the portal of first floor transverse passage-way abolishes and excavation construction again, and then the scaffold of dismounting first floor, the excavation that completes first floor transverse passage-way enters hole;
2) abolish the interim back cover of last layer, by To Construction of Silo to N rice under lower one deck transverse passage-way inverted arch, then the interim back cover of one deck under laying in the bottom of vertical shaft, and on the interim back cover of lower one deck, set up the scaffold of lower one deck, carrying out the portal of lower one deck transverse passage-way abolishes and excavation construction again, then the scaffold of removing lower one deck, the excavation that completes lower one deck transverse passage-way enters hole;
3) repeating step 2), the excavation that completes all transverse passage-ways except last one deck transverse passage-way enters hole, then abolish the interim back cover of layer second from the bottom, by N rice under extremely last To Construction of Silo one deck transverse passage-way inverted arch, then lay final back cover in the bottom of vertical shaft, and setting up the scaffold of last one deck on final back cover, then the portal that carries out last one deck transverse passage-way is abolished and excavation construction, then remove the scaffold of last one deck, complete all adit constructions and excavate into hole.
Step 1) in the time that the length of first floor adit construction supporting is greater than the diameter of first floor transverse passage-way of 3 times, remove the scaffold of first floor;
Step 2) in when the length of one deck adit construction supporting is greater than the diameter of lower one deck transverse passage-way of 3 times instantly, remove the scaffold of lower one deck;
Step 3) in the time that the length of last one deck adit construction supporting is greater than the diameter of last one deck transverse passage-way of 3 times, remove the scaffold of last one deck.
N >=in 2, and N≤3.
The present invention has following beneficial effect:
Subway vertical shaft of the present invention layering, segmentation turn adit construction and excavate into the method in hole carrying out in the process of adit construction, the interconnection of every one deck is excavated respectively into hole, simultaneously to excavating in the process in hole except other layer of later interconnection of last one deck, only need carry out interim back cover in the bottom of vertical shaft, then scaffolding erecting, thereby effectively shorten the height of scaffold, save the material of scaffold, reduce greatly constructor's security risk simultaneously, really accomplish safety construction.
Brief description of the drawings
Fig. 1 is the schematic diagram of scaffold building in traditional multilayer transverse passage-way vertical shaft 1;
Fig. 2 is the front view of multilayer transverse passage-way vertical shaft 1;
Fig. 3 is the lateral view of multilayer transverse passage-way vertical shaft 1;
Fig. 4 is that in the present invention, first floor transverse passage-way 2 excavates the schematic diagram of setting up into the scaffold 41 of first floor in the process of hole;
Fig. 5 is that in the present invention, lower one deck transverse passage-way excavates the schematic diagram of setting up into the scaffold 42 of lower one deck in the process of hole.
Wherein, 1 be vertical shaft, 2 for first floor transverse passage-way, 3 for last one deck transverse passage-way, 41 be the scaffolds of first floor, 42 be lower one deck scaffolds, 51 interim back covers for the interim back cover of first floor, 52 times one decks.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is described in further detail:
With reference to figure 2, Fig. 3, Fig. 4 and Fig. 5, subway vertical shaft of the present invention layering, segmentation turn adit construction and excavate into the method in hole and comprise the following steps:
1) vertical shaft 1 is constructed to N rice under first floor transverse passage-way 2 inverted arch, then lay the interim back cover 51 of first floor in the bottom of vertical shaft 1, and on the interim back cover 51 of first floor, set up the scaffold 41 of first floor, carrying out the portal of first floor transverse passage-way 2 abolishes and excavation construction again, and then the scaffold 41 of dismounting first floor, the excavation that completes first floor transverse passage-way 2 enters hole;
2) abolish the interim back cover of last layer, vertical shaft 1 is constructed to N rice under lower one deck transverse passage-way inverted arch, then the interim back cover 52 of one deck under laying in the bottom of vertical shaft 1, and on the interim back cover 52 of lower one deck, set up the scaffold 42 of lower one deck, carrying out the portal of lower one deck transverse passage-way abolishes and excavation construction again, then the scaffold 42 of removing lower one deck, the excavation that completes lower one deck transverse passage-way enters hole;
3) repeating step 2), the excavation that completes all transverse passage-ways except last one deck transverse passage-way 3 enters hole, then abolish the interim back cover of layer second from the bottom, vertical shaft 1 is constructed to N rice under last one deck transverse passage-way 3 inverted arch, then lay final back cover in the bottom of vertical shaft 1, and setting up the scaffold of last one deck on final back cover, then the portal that carries out last one deck transverse passage-way 3 is abolished and excavation construction, then remove the scaffold of last one deck, complete all adit constructions and excavate into hole.
Step 1) in the time that the length of first floor transverse passage-way 2 construction supportings is greater than the diameter of first floor transverse passage-way 2 of 3 times, remove the scaffold 41 of first floor;
Step 2) in when the length of one deck adit construction supporting is greater than the diameter of lower one deck transverse passage-way of 3 times instantly, remove the scaffold 42 of lower one deck;
Step 3) in the time that the length of last one deck transverse passage-way 3 construction supportings is greater than the diameter of last one deck transverse passage-way 3 of 3 times, remove the scaffold of last one deck.
N >=in 2, and N≤3.
It should be noted that, in the time that multilayer transverse passage-way vertical shaft 1 is constructed, first vertical shaft 1 is constructed to 2-3m left and right (as interim dregs groove) under the inverted arch of accessory channel, upper strata, interim back cover is carried out in the bottom of vertical shaft 1, the mode of interim back cover is depending on geological condition, in the time that interim back cover position country rock is stablized, as clay, decayed rock etc., adopt double steel bar net to add the thick sprayed mortar of 20cm; In the time that interim back cover position country rock is unstable, as drift sand, carry out interim back cover with reference to design drawing vertical shaft 1 back cover mode.

Claims (3)

1. the layering of subway vertical shaft, segmentation turn adit construction and excavate the method into hole, it is characterized in that, comprise the following steps:
1) vertical shaft (1) is constructed to N rice under first floor transverse passage-way (2) inverted arch, then lay the interim back cover of first floor (51) in the bottom of vertical shaft (1), and on the interim back cover of first floor (51), set up the scaffold (41) of first floor, carrying out the portal of first floor transverse passage-way (2) abolishes and excavation construction again, and then the scaffold (41) of dismounting first floor, the excavation that completes first floor transverse passage-way (2) enters hole;
2) abolish the interim back cover of last layer, by vertical shaft (1) construction to N rice under lower one deck transverse passage-way inverted arch, then the interim back cover (52) of one deck under laying in the bottom of vertical shaft (1), and on the interim back cover (52) of lower one deck, set up the scaffold (42) of lower one deck, carrying out the portal of lower one deck transverse passage-way abolishes and excavation construction again, then the scaffold (42) of removing lower one deck, the excavation that completes lower one deck transverse passage-way enters hole;
3) repeating step 2), the excavation that completes all transverse passage-ways except last one deck transverse passage-way (3) enters hole, then abolish the interim back cover of layer second from the bottom, by N rice under extremely last vertical shaft (1) construction one deck transverse passage-way (3) inverted arch, then lay final back cover in the bottom of vertical shaft (1), and on final back cover, set up the scaffold of last one deck, carrying out the portal of last one deck transverse passage-way (3) abolishes and excavation construction again, then remove the scaffold of last one deck, complete all adit constructions and excavate into hole.
2. subway vertical shaft according to claim 1 layering, segmentation turn adit construction and excavate the method into hole, it is characterized in that,
Step 1) in the time that the length of first floor transverse passage-way (2) construction supporting is greater than the diameter of first floor transverse passage-way (2) of 3 times, remove the scaffold (41) of first floor;
Step 2) in when the length of one deck adit construction supporting is greater than the diameter of lower one deck transverse passage-way of 3 times instantly, remove the scaffold (42) of lower one deck;
Step 3) in the time that the length of last one deck transverse passage-way (3) construction supporting is greater than the diameter of last one deck transverse passage-way (3) of 3 times, remove the scaffold of last one deck.
3. subway vertical shaft according to claim 1 layering, segmentation turn adit construction and excavate the method into hole, it is characterized in that, and N >=in 2, and N≤3.
CN201410090973.9A 2014-03-12 2014-03-12 Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro Pending CN103867209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410090973.9A CN103867209A (en) 2014-03-12 2014-03-12 Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410090973.9A CN103867209A (en) 2014-03-12 2014-03-12 Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro

Publications (1)

Publication Number Publication Date
CN103867209A true CN103867209A (en) 2014-06-18

Family

ID=50906170

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410090973.9A Pending CN103867209A (en) 2014-03-12 2014-03-12 Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro

Country Status (1)

Country Link
CN (1) CN103867209A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104131816A (en) * 2014-06-20 2014-11-05 上海建工五建集团有限公司 Construction method for forming door opening in underground wall of subway tunnel in operation
CN108361036A (en) * 2018-03-14 2018-08-03 北京市政路桥股份有限公司 A kind of construction method that subway station accessory structure is plug-in
CN112081176A (en) * 2020-09-11 2020-12-15 北京住总集团有限责任公司 Pressure-bearing water layer vertical shaft construction method based on non-dewatering drainage
CN112112657A (en) * 2020-09-25 2020-12-22 中煤第三建设(集团)有限责任公司 New construction method for digging and building inclined shaft of coal mine
CN112282809A (en) * 2020-10-27 2021-01-29 聊城大学 Construction method and device for supporting multi-layer underground structure of building
CN114320376A (en) * 2022-03-17 2022-04-12 中国铁路设计集团有限公司 Supporting structure for underground excavation station to enter main tunnel from cross channel and construction method
CN117307176A (en) * 2023-11-29 2023-12-29 中铁三局集团广东建设工程有限公司 Transverse channel construction method based on formed pilot tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3831206C1 (en) * 1988-09-14 1990-05-03 Gewerkschaft Auguste Victoria, 4370 Marl, De Method of winning reserves in the vicinity of a shaft and shaft lining for carrying out this method
CN102953739A (en) * 2012-10-26 2013-03-06 中铁二十二局集团第六工程有限公司 Bidirectional punching method for underground excavation of subway station
CN103114857A (en) * 2013-02-26 2013-05-22 中铁十九局集团第二工程有限公司 Shield tunnel construction method
CN103452561A (en) * 2013-08-20 2013-12-18 中铁二局股份有限公司 Vertical in-tunnel construction method of multilayer transverse channel of underground excavation station of metro, and construction method on east side and west side
CN103517043A (en) * 2013-10-22 2014-01-15 中铁隧道集团二处有限公司 Safety control method for vertical shaft grab bucket hoisting system and control system of same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3831206C1 (en) * 1988-09-14 1990-05-03 Gewerkschaft Auguste Victoria, 4370 Marl, De Method of winning reserves in the vicinity of a shaft and shaft lining for carrying out this method
CN102953739A (en) * 2012-10-26 2013-03-06 中铁二十二局集团第六工程有限公司 Bidirectional punching method for underground excavation of subway station
CN103114857A (en) * 2013-02-26 2013-05-22 中铁十九局集团第二工程有限公司 Shield tunnel construction method
CN103452561A (en) * 2013-08-20 2013-12-18 中铁二局股份有限公司 Vertical in-tunnel construction method of multilayer transverse channel of underground excavation station of metro, and construction method on east side and west side
CN103517043A (en) * 2013-10-22 2014-01-15 中铁隧道集团二处有限公司 Safety control method for vertical shaft grab bucket hoisting system and control system of same

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104131816A (en) * 2014-06-20 2014-11-05 上海建工五建集团有限公司 Construction method for forming door opening in underground wall of subway tunnel in operation
CN104131816B (en) * 2014-06-20 2019-02-12 上海建工五建集团有限公司 The construction method in subway tunnel subterranean wall enabling hole in a kind of operation
CN108361036A (en) * 2018-03-14 2018-08-03 北京市政路桥股份有限公司 A kind of construction method that subway station accessory structure is plug-in
CN112081176A (en) * 2020-09-11 2020-12-15 北京住总集团有限责任公司 Pressure-bearing water layer vertical shaft construction method based on non-dewatering drainage
CN112081176B (en) * 2020-09-11 2022-02-01 北京住总集团有限责任公司 Pressure-bearing water layer vertical shaft construction method based on non-dewatering drainage
CN112112657A (en) * 2020-09-25 2020-12-22 中煤第三建设(集团)有限责任公司 New construction method for digging and building inclined shaft of coal mine
CN112112657B (en) * 2020-09-25 2022-04-19 中煤第三建设(集团)有限责任公司 New construction method for digging and building inclined shaft of coal mine
CN112282809A (en) * 2020-10-27 2021-01-29 聊城大学 Construction method and device for supporting multi-layer underground structure of building
CN114320376A (en) * 2022-03-17 2022-04-12 中国铁路设计集团有限公司 Supporting structure for underground excavation station to enter main tunnel from cross channel and construction method
CN114320376B (en) * 2022-03-17 2022-05-17 中国铁路设计集团有限公司 Supporting structure for underground excavation station to enter main tunnel from cross channel and construction method
CN117307176A (en) * 2023-11-29 2023-12-29 中铁三局集团广东建设工程有限公司 Transverse channel construction method based on formed pilot tunnel
CN117307176B (en) * 2023-11-29 2024-02-20 中铁三局集团广东建设工程有限公司 Transverse channel construction method based on formed pilot tunnel

Similar Documents

Publication Publication Date Title
CN103867209A (en) Method of layered and segmental construction, excavation and holing of transverse passages of vertical shaft of metro
CN104612698B (en) A kind of shallow-depth-excavation tunnel top bar interval wall construction method
CN106869944B (en) The extra small clear-distance tunnel construction method in underground interchange intersection under complex environment
CN104047623B (en) A kind of big across cavern excavation construction method
CN203756182U (en) Support structure applied to shallow road tunnel in weak rock area
CN102562099B (en) Method for carrying out rapid face excavation construction of loess tunnel by double rows of small conduits
CN104389610B (en) A kind of ultrashort step construction method of traversing operation freeway tunnel
CN104632227B (en) Subway station excavation technology of single-layer beam arch structure
CN103277106A (en) Highway tunnel three-step five-procedure excavation construction method
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN104806251B (en) Subsidiary inverted excavation construction method for urban subway station under complex environment
CN106194196B (en) A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method
CN101725358A (en) Excavation construction method of ultra-shallow buried uneven weathered stratum of tunnel
CN103628887A (en) Large-section water-rich saturated fine sand railway tunnel excavation method
CN207177933U (en) A kind of advanced plugging structure of high-pressure high-flow underground water
CN103821167A (en) Construction method for subway station body
CN106246192A (en) Large-scale karst cave treatment under a kind of tunnel basis and base plate and tunnel excavation method
CN104806267A (en) Shield end socket reinforcing system of scree soil layer advance large pipe roof and construction method thereof
CN107288642A (en) PBA construction technologies
CN103362513A (en) Transformation and construction method for existing cavity in underground excavation region
CN104563147B (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN104831733A (en) Arch bridge abutment tunnel type large-angle inclined pile construction method
CN105909256A (en) Large-span weak surrounding rock tunnel construction method adopting face pre-reinforcement core soil reserving three-step temporary inverted arch technology
CN105909262B (en) A kind of bored tunnel driving method
CN108374674B (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140618