CN206789240U CN201720703196.XU CN201720703196U CN206789240U CN 206789240 U CN206789240 U CN 206789240U CN 201720703196 U CN201720703196 U CN 201720703196U CN 206789240 U CN206789240 U CN 206789240U
Authority
CN
China
Prior art keywords
warning
pile
section
embedded
buried pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720703196.XU
Other languages
Chinese (zh)
Inventor
雷达
蒋华全
胡滨涛
柯真敏
周明兵
姜婷婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gas Storage Administrative Office Of Petrochina Southwest Oil & Gasfield Co
Original Assignee
Gas Storage Administrative Office Of Petrochina Southwest Oil & Gasfield Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gas Storage Administrative Office Of Petrochina Southwest Oil & Gasfield Co filed Critical Gas Storage Administrative Office Of Petrochina Southwest Oil & Gasfield Co
Priority to CN201720703196.XU priority Critical patent/CN206789240U/en
Application granted granted Critical
Publication of CN206789240U publication Critical patent/CN206789240U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Signs Or Road Markings (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of buried pipeline warning pile, include the pile of hollow structure made from fiberglass, above pile the warning section indicated is warned to be provided with, lower end is for embedded embedded section, it is characterized in that, pile upper end end face is provided with warning lid, and warning cap surface is provided with the warning material of red.The utility model have it is convenient improve embedded stability, be not easy to topple over, setting height(from bottom) can be adjusted as needed, there is preferably alarming effect, the advantages that more facilitating patrol officer's inspection to observe.

Description

A kind of buried pipeline warning pile
Technical field
It the utility model is related to energy conduit transportation art, more particularly to a kind of buried pipeline warning pile.
Background technology
Warning pile is also known as marking pile or identification pile, is usually used in electric power, communication, combustion gas, running water, railway underground pipe circuit Footpath Warning Mark.For open air, greenbelt, bushes, push pipe both sides pipeline path instruction, play warning function.
Warning pilework includes vertical pile, to be provided with the warning part of warning sign above pile, lower end for for Embedded embedded portion.Earliest warning pile is generally pile structure made from cement concrete, and a marker peg weighs 80 kilograms, Weight is big, and installation and transportation are very inconvenient, and this identification pile is particularly established in mountain area, it is necessary to multiple person cooperational could be completed, peace Dress is wasted time and energy, and installation cost is high;Cause to transport and construct it is extremely inconvenient.Now with social development, use It the warning pile of glass steel material, can greatly mitigate weight, reduce transport and construction cost.Such as ZL201521064073.3 A kind of disclosed marker peg, discloses the pile using glass fibre reinforced plastic structure.
But this existing warning pile, however it remains problems with:1st, to be buried by the way of direct-burried, steadiness is poor, Under the influence of the influence of high wind and wild animal, easily topple over, particularly now with rural urbanization and conceding the land to forestry etc. The progress of policy, causes the increase of wild animal, easily causes warning pile and topples over.2nd, warning pile traditional at present, warning part are Simple warning word, alarming effect is relatively low, while traditional warning pile is highly relatively low, and multi-line regression model is usually made after performing Overgrowed into weeds, create a further reduction warning pile alarming effect, be difficult to observe police in time when also resulting in patrol officer's inspection Show stake.
Utility model content
The technical problems to be solved in the utility model is:How a kind of convenient improve is provided and buries stability, is not easy to incline , its alarming effect while is further improved, the buried pipeline warning pile for more facilitating patrol officer's inspection to observe.
In order to solve the above-mentioned technical problem, the utility model employs following technical scheme.
A kind of buried pipeline warning pile, include the pile of hollow structure made from fiberglass, be to be provided with police above pile The warning section that indicating is shown, lower end are for embedded embedded section, it is characterised in that pile upper end end face is provided with warning lid, alert Show that cap surface is provided with the warning material of red.
So, the warning lid of red is additionally arranged in pile upper end end face, can preferably improve its alarming effect, especially just Just the inspection observation of patrol officer.
As optimization, it is red Noctilucent material to warn the warning material covered.So patrol officer's inspection to the colour of sky compared with When late, the presence of warning pile also can be conveniently observed.
As optimization, the warning lid is sophisticated structure for the upper end that multiple inclined-planes surround.
So, inclined-plane can preferably avoid dust stratification and beneficial to rainy day rain drop erosion to keep cleaning, and be provided with noctilucence It can also facilitate during material and sunlight is preferably absorbed on daytime to extend the noctilucence time;Upper end is that tip can avoid flying bird from landing Stop and covering of shitting reduces alarming effect.
As optimization, extended transversely through in embedded section and be provided with embedded bar cross-perforating.
So, when burying, buried after embedded bar cross-perforating being horizontally through by reinforcing bar, reach bar planting effect Fruit, improve the stability after warning pile is buried.
As optimization, embedded bar slanted apertures are additionally provided with above embedded bar cross-perforating in embedded section.
When so warning pile is embedded, it can further lean on reinforcing bar oblique and arrive embedded bar slanted apertures through setting, and to Under pass in oblique embedment stratum, and transverse steel is together, forms more three-dimensional embedded bar net effect, is greatly enhanced police Show stake it is embedded after stability.Further, the embedded bar cross-perforating and embedded bar slanted apertures it is each it is comfortable before and after With have setting in the both direction of left and right, so can preferably improve the three-dimensional consolidation effect of embedded bar, greatly carry High warning pile buries steadiness.
As optimization, embedded section upper end is arranged at intervals with maximum buried depth line and the minimum depth line.
So, it is convenient to be buried according to different soil property situations according to different buried depth line positions, leaned on when soil property is softer Nearly maximum buried depth line is buried, and close to lower section, the minimum depth line is buried when soil property is harder, ensures that various soil property situations are equal With preferable embedded stability.
As optimization, the maximum buried depth line and the minimum depth line be in the groove of indent brushing colored pigment obtain. Guarantee is so facilitated not fade.
As optimization, the regulation section available for regulation height is also set up between embedded section and warning section.
So, during convenient installation, warning pile height is according to circumstances adjusted, such as to be increased by its high in weeds higher field Degree, to facilitate warning and inspection, the occasion of the more public is waited to reduce setting height(from bottom) to increase stability by the road.
As optimization, the regulation section includes an inner cylinder, can slide vertically the outer barrel for coordinating and being socketed in outside inner cylinder, inner cylinder Lower end is connected with embedded section, and outer barrel upper end is connected with warning section, between inner cylinder and outer barrel on each comfortable at least two relative face A vertical setting of types screw is respectively vertically provided with, and coordinates the fixation after realizing regulation by bolt and screw.
So, there is the characteristics of simple in construction, regulation is fixed conveniently fast, and stability is high.
As optimization, the outer barrel cross sectional dimensions is consistent with the cross sectional dimensions of embedded section and warning section.
So, it is more convenient to improve globality, it is more attractive in appearance and beneficial to transport.
As optimization, warning is denoted as being recessed and applies coloured caution slogan.So it is not easy to fade and improve police Show effect.
In summary, there is the utility model convenient improve to bury stability, is not easy to topple over, can adjust peace as needed Dress height, has preferably alarming effect, the advantages that more facilitating patrol officer's inspection to observe.
Brief description of the drawings
Fig. 1 is the structure schematic diagram that the utility model implements 1.
Fig. 2 is the structural representation of second of embodiment of the warning lid used in the utility model.
Embodiment
The utility model is described in further detail with reference to the accompanying drawings and examples.
Embodiment:
As shown in figure 1, a kind of buried pipeline warning pile, include the pile 1 of hollow structure made from fiberglass, on pile 1 Side is is provided with the warning section of warning sign 2, and lower end is for embedded embedded section, and the upper end end face of pile 1 is provided with warning lid 3, warning lid 3 surface is provided with the warning material of red.
So, the warning lid of red is additionally arranged in pile upper end end face, can preferably improve its alarming effect, especially just Just the inspection observation of patrol officer.In the present embodiment, pile is that whole height is 3 meters, and width is 8cm square pile.
In the present embodiment, it is red Noctilucent material to warn the warning material on lid 3.So patrol officer's inspection is to the colour of sky When later, the presence of warning pile also can be conveniently observed.
In the present embodiment, the trapezoidal structure of the vertical cross-section of lid 3 is warned.As other embodiment, as shown in Fig. 2 institute It is that the upper end that multiple inclined-planes surround is the structure at tip to state warning lid 3.So, under inclined-plane can preferably avoid dust stratification and be beneficial to Rainy day rain drop erosion can also facilitate to keep cleaning, when being provided with Noctilucent material preferably absorbs sunlight to extend night on daytime Between light time;Upper end can avoid flying bird landing from stopping covering of shitting for tip reduces alarming effect.
In the present embodiment, extended transversely through in embedded section and be provided with embedded bar cross-perforating 4.
So, when burying, buried after embedded bar cross-perforating being horizontally through by reinforcing bar, reach bar planting effect Fruit, improve the stability after warning pile is buried.
In the present embodiment, the top of embedded bar cross-perforating 4 is additionally provided with embedded bar slanted apertures 5 in embedded section.
When so warning pile is embedded, it can further lean on reinforcing bar oblique and arrive embedded bar slanted apertures through setting, and to Under pass in oblique embedment stratum, and transverse steel is together, forms more three-dimensional embedded bar net effect, is greatly enhanced police Show stake it is embedded after stability.Further, the embedded bar cross-perforating and embedded bar slanted apertures it is each it is comfortable before and after With have setting in the both direction of left and right, so can preferably improve the three-dimensional consolidation effect of embedded bar, greatly carry High warning pile buries steadiness.
In the present embodiment, embedded section upper end is arranged at intervals with maximum buried depth line 6 and the minimum depth line 7.
So, it is convenient to be buried according to different soil property situations according to different buried depth line positions, leaned on when soil property is softer Nearly maximum buried depth line is buried, and close to lower section, the minimum depth line is buried when soil property is harder, ensures that various soil property situations are equal With preferable embedded stability.
In the present embodiment, the maximum buried depth line 6 and the minimum depth line 7 be in the groove of indent brushing colored pigment obtain Arrive.Guarantee is so facilitated not fade.
In the present embodiment, the regulation section available for regulation height is also set up between embedded section and warning section.
So, during convenient installation, warning pile height is according to circumstances adjusted, such as to be increased by its high in weeds higher field Degree, to facilitate warning and inspection, the occasion of the more public is waited to reduce setting height(from bottom) to increase stability by the road.
In the present embodiment, the regulation section includes an inner cylinder 8, can slide vertically the outer barrel for coordinating and being socketed in outside inner cylinder 8 9, the lower end of inner cylinder 8 is connected with embedded section, and the upper end of outer barrel 9 is connected with warning section, each comfortable at least two phase between inner cylinder and outer barrel To face on be respectively vertically provided with a vertical setting of types screw 10, and coordinate the fixation after realizing regulation by bolt 11 and screw 10.
So, there is the characteristics of simple in construction, regulation is fixed conveniently fast, and stability is high.
In the present embodiment, the cross sectional dimensions of outer barrel 9 is consistent with the cross sectional dimensions of embedded section and warning section.
So, it is more convenient to improve globality, it is more attractive in appearance and beneficial to transport.
In the present embodiment, warning sign 2 is to be recessed and apply coloured caution slogan.So it is not easy to fade and improve Alarming effect.
Therefore there is the warning pile of said structure convenient improve to bury stability, is not easy to topple over, can adjust peace as needed Dress height, has preferably alarming effect, the advantages that more facilitating patrol officer's inspection to observe.

Claims (10)

  1. It is to be provided with warning above pile 1. a kind of buried pipeline warning pile, including the pile of hollow structure made from fiberglass The warning section of sign, lower end are for embedded embedded section, it is characterised in that pile upper end end face is provided with warning lid, warning Cap surface is provided with the warning material of red.
  2. 2. buried pipeline warning pile as claimed in claim 1, it is characterised in that it is red night to warn the warning material covered Luminescent material.
  3. 3. buried pipeline warning pile as claimed in claim 1, it is characterised in that the warning lid surrounds upper for multiple inclined-planes Hold as the structure at tip.
  4. 4. buried pipeline warning pile as claimed in claim 1, it is characterised in that extended transversely through in embedded section and be provided with pre-buried steel Muscle cross-perforating.
  5. 5. buried pipeline warning pile as claimed in claim 4, it is characterised in that embedded bar cross-perforating is upper in embedded section Side is additionally provided with embedded bar slanted apertures.
  6. 6. buried pipeline warning pile as claimed in claim 1, it is characterised in that embedded section upper end is arranged at intervals with maximum buried depth Line and the minimum depth line.
  7. 7. buried pipeline warning pile as claimed in claim 6, it is characterised in that the maximum buried depth line and the minimum depth line are equal Obtained for brushing colored pigment in the groove of indent.
  8. 8. buried pipeline warning pile as claimed in claim 1, it is characterised in that also set up between embedded section and warning section available In the regulation section of regulation height.
  9. 9. buried pipeline warning pile as claimed in claim 8, it is characterised in that the regulation section includes an inner cylinder, can erect To the outer barrel that is socketed in outside inner cylinder of being slidably matched, inner cylinder lower end is connected with embedded section, and outer barrel upper end is connected with warning section, inner cylinder and A vertical setting of types screw is respectively vertically provided between outer barrel on each comfortable at least two relative face, and is coordinated in fact by bolt and screw Fixation after now adjusting.
  10. 10. buried pipeline warning pile as claimed in claim 9, it is characterised in that the outer barrel cross sectional dimensions and embedded section And the cross sectional dimensions of warning section is consistent.
CN201720703196.XU 2017-06-16 2017-06-16 A kind of buried pipeline warning pile Expired - Fee Related CN206789240U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720703196.XU CN206789240U (en) 2017-06-16 2017-06-16 A kind of buried pipeline warning pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720703196.XU CN206789240U (en) 2017-06-16 2017-06-16 A kind of buried pipeline warning pile

Publications (1)

Publication Number Publication Date
CN206789240U true CN206789240U (en) 2017-12-22

Family

ID=60717729

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720703196.XU Expired - Fee Related CN206789240U (en) 2017-06-16 2017-06-16 A kind of buried pipeline warning pile

Country Status (1)

Country Link
CN (1) CN206789240U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020108004A1 (en) * 2018-11-27 2020-06-04 广东电网有限责任公司 Cable marker post

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020108004A1 (en) * 2018-11-27 2020-06-04 广东电网有限责任公司 Cable marker post

Similar Documents

Publication Publication Date Title
WO2021010263A1 (en) Stress monitoring device, stress monitoring system, and monitoring system
CN104295448A (en) All-weather clean energy comprehensive electricity generating and energy saving method and facility manufacturing method thereof
US20140091100A1 (en) Wind-Resistant Magnetic Trash Can
CN206789240U (en) A kind of buried pipeline warning pile
CN113273399A (en) Desert rice field with unmanned aerial vehicle connected with air pipe and rice box
CN207891760U (en) Road sand storm protection system suitable for drift sand area
CN106171831A (en) Mechanization of agriculture water-saving spray irrigation system
CN202489024U (en) Cement pillar type greening shed
CN207733354U (en) A kind of Multifunctional protective tree construction suitable for paved road
CN204682224U (en) Plant modification Agasicles hygrophila facility is built
Pei Planning a sustainable, green industrial road with an ecological recycling economy in mind
CN101874458A (en) Novel light gutter-connected plastic tent
CN205138493U (en) A warning device for surveying and draw in operation
CN209145313U (en) A kind of means for mounting coupling parts of all bamboo structure column root
CN206978216U (en) A kind of highway employment path tree pit safety guard
CN206091416U (en) Multi -functional assembled suspension fretwork platform of ecological environment -friendly
RU136815U1 (en) WINTER ROAD CONSTRUCTION
CN208029690U (en) A kind of umbrella shape greenhouse
CN208055932U (en) A kind of municipal administration road direction of traffic instruction Anti-collision barrel
CN104776828A (en) Beach face gradient inclination observation system and application method thereof after closing of tailing warehouse
CN202559492U (en) Natural drainage system for step of side slope
CN204370354U (en) A kind of traffic guardrail of combined convenient dismounting
CN206363678U (en) A kind of new marker peg
CN206554116U (en) A kind of alternating expression underground traffic piping lane vehicle in and out port structure
CN103321417A (en) Method for constructing earth-rock fences on high-altitude grasslands of Tibet

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171222