CN103774637A - 一种路基夯实施工方法 - Google Patents

一种路基夯实施工方法 Download PDF

Info

Publication number
CN103774637A
CN103774637A CN201210414045.4A CN201210414045A CN103774637A CN 103774637 A CN103774637 A CN 103774637A CN 201210414045 A CN201210414045 A CN 201210414045A CN 103774637 A CN103774637 A CN 103774637A
Authority
CN
China
Prior art keywords
tamping
point
ramming
roadbed
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210414045.4A
Other languages
English (en)
Inventor
刘斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Longhai Engineering Construction Co Ltd
Original Assignee
Shaanxi Longhai Engineering Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Longhai Engineering Construction Co Ltd filed Critical Shaanxi Longhai Engineering Construction Co Ltd
Priority to CN201210414045.4A priority Critical patent/CN103774637A/zh
Publication of CN103774637A publication Critical patent/CN103774637A/zh
Pending legal-status Critical Current

Links

Abstract

一种路基夯实施工方法,采用单击夯击能量大于2000kN?m的点夯,以路基中心线为轴沿路基横向两侧对称布点,进行第一遍点夯,击夯次数为4-6击,固结稳定7天后,进行第二遍点夯,第二遍点夯夯完后,工作面固结稳定7天,进行满夯,本发明用夯锤自由下落对土体产生巨大的冲击能,使土体中出现冲击波和很大的应力,致使土中的气体迅速排出,原组织发生变化,空隙率减小,形成良好的排水通道,土体迅速固结,不仅能提高地基承载力,也可防止地基液化。

Description

一种路基夯实施工方法
技术领域
本发明涉及路基施工技术领域,特别涉及一种路基夯实施工方法。
背景技术
路基夯实是路基施工中的重要工序,现有的夯实工法土体固化较慢,地基承载力也有限。
发明内容
为了克服上述现有技术的不足,本发明的目的在于提供一种路基夯实施工方法。
为了实现上述目的,本发明采用的技术方案是:
一种路基夯实施工方法,采用单击夯击能量大于2000KN•m的点夯,以路基中心线为轴沿路基横向两侧对称布点,进行第一遍点夯,击夯次数为4-6击,固结稳定7天后,进行第二遍点夯,第二遍点夯夯完后,工作面固结稳定7天,进行满夯。
与现有技术相比,本发明用夯锤自由下落对土体产生巨大的冲击能,使土体中出现冲击波和很大的应力,致使土中的气体迅速排出,原组织发生变化,空隙率减小,形成良好的排水通道,土体迅速固结,不仅能提高地基承载力,也可防止地基液化。
具体实施方式
下面结合实施例对本发明进行更详尽的说明。
本发明为一种路基夯实施工方法,采用单击夯击能量大于2000KN•m的点夯,以路基中心线为轴沿路基横向两侧对称布点,进行第一遍点夯,击夯次数为4-6击,固结稳定7天后,进行第二遍点夯,第二遍点夯夯完后,工作面固结稳定7天,进行满夯。
其中,所述第一遍点夯的具体步骤是:首先布点,用全站仪放出第一遍夯点,用白灰标出夯点位置,并测量场地高程;夯击点位置根据施工场地类型,采用正方形布置,夯击点间距取6m,夯击前,在锤顶面位置做一红色标志,夯机就位,使夯锤对准夯点位置,将水准尺置于锤顶面红色标志处,测其点高程,待夯锤吊到预定13m高度,脱钩自由下落后,将水准尺放于标志处,测其高程,则第一锤高程减静止时锤高,得出第一次的夯沉量,若发现因坑底倾斜而造成锤歪斜时,应及时将坑底整平;重复上述步骤,对同一点进行夯击,两次夯击间隔时间为一分钟,夯沉量符合最后两击≤5cm要求,累计次数即为该点的夯击次数。
所述第二遍点夯的具体步骤是:用推土机将第一遍点夯工作面推平,用全站仪放出第二遍夯点位置,采用正方形布置,夯击点间距取6m,测量场地高程,随后对次夯点进行夯击观测同一点的夯沉量,夯沉量符合最后两击≤5cm要求,累计次数即为该点的夯击次数,依次对第二遍夯点进行夯击,完成全部夯点的夯击。
所述满夯的具体步骤是:用推土机将第二遍点夯工作面推平,夯点间距1.5-1.7m,测量场地高程,用夯机低能量对工作面进行低能量满夯,满夯夯击能大于2000KN•m,锤面三向重叠50cm,依次对第二遍夯点进行夯击,完成全部夯点的夯击,满夯后的地面沿路基中心线按3%的双侧路拱整平。
强夯施工完成一个月内对地基质量进行检验,证明地基承载力在220kpa之上,压实度在95%以上。

Claims (4)

1.一种路基夯实施工方法,其特征在于,采用单击夯击能量大于2000KN•m的点夯,以路基中心线为轴沿路基横向两侧对称布点,进行第一遍点夯,击夯次数为4-6击,固结稳定7天后,进行第二遍点夯,第二遍点夯夯完后,工作面固结稳定7天,进行满夯。
2.根据权利要求1所述的路基夯实施工方法,其特征在于,所述第一遍点夯的具体步骤是:首先布点,用全站仪放出第一遍夯点,用白灰标出夯点位置,并测量场地高程;夯击点位置根据施工场地类型,采用正方形布置,夯击点间距取6m,夯击前,在锤顶面位置做一红色标志,夯机就位,使夯锤对准夯点位置,将水准尺置于锤顶面红色标志处,测其点高程,待夯锤吊到预定13m高度,脱钩自由下落后,将水准尺放于标志处,测其高程,则第一锤高程减静止时锤高,得出第一次的夯沉量,若发现因坑底倾斜而造成锤歪斜时,应及时将坑底整平;重复上述步骤,对同一点进行夯击,两次夯击间隔时间为一分钟,夯沉量符合最后两击≤5cm要求,累计次数即为该点的夯击次数。
3.根据权利要求1所述的路基夯实施工方法,其特征在于,所述第二遍点夯的具体步骤是:用推土机将第一遍点夯工作面推平,用全站仪放出第二遍夯点位置,采用正方形布置,夯击点间距取6m,测量场地高程,随后对次夯点进行夯击观测同一点的夯沉量,夯沉量符合最后两击≤5cm要求,累计次数即为该点的夯击次数,依次对第二遍夯点进行夯击,完成全部夯点的夯击。
4.根据权利要求1所述的路基夯实施工方法,其特征在于,所述满夯的具体步骤是:用推土机将第二遍点夯工作面推平,夯点间距1.5-1.7m,测量场地高程,用夯机低能量对工作面进行低能量满夯,满夯夯击能大于2000KN•m,锤面三向重叠50cm,依次对第二遍夯点进行夯击,完成全部夯点的夯击,满夯后的地面沿路基中心线按3%的双侧路拱整平。
CN201210414045.4A 2012-10-25 2012-10-25 一种路基夯实施工方法 Pending CN103774637A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210414045.4A CN103774637A (zh) 2012-10-25 2012-10-25 一种路基夯实施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210414045.4A CN103774637A (zh) 2012-10-25 2012-10-25 一种路基夯实施工方法

Publications (1)

Publication Number Publication Date
CN103774637A true CN103774637A (zh) 2014-05-07

Family

ID=50567348

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210414045.4A Pending CN103774637A (zh) 2012-10-25 2012-10-25 一种路基夯实施工方法

Country Status (1)

Country Link
CN (1) CN103774637A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049407A (zh) * 2016-06-25 2016-10-26 中国水利水电第四工程局有限公司 一种地基强夯施工方法
CN108071104A (zh) * 2017-09-29 2018-05-25 广州子龙智能安防科技有限公司 一种斜坡的夯实装置
CN111501725A (zh) * 2020-04-29 2020-08-07 天津津港建设有限公司 一种强夯处理复杂场地地基的方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049407A (zh) * 2016-06-25 2016-10-26 中国水利水电第四工程局有限公司 一种地基强夯施工方法
CN108071104A (zh) * 2017-09-29 2018-05-25 广州子龙智能安防科技有限公司 一种斜坡的夯实装置
CN111501725A (zh) * 2020-04-29 2020-08-07 天津津港建设有限公司 一种强夯处理复杂场地地基的方法

Similar Documents

Publication Publication Date Title
CN101962928B (zh) 冲击碾压处理风积沙路基基底的施工方法
CN104358188B (zh) 湿陷性黄土路基填筑施工方法
CN106801417B (zh) 隧道穿越构筑物钢管隔离桩地层加固体系及其施工方法
CN104131546B (zh) 一种湿陷性黄土地基的处理方法
CN105696426B (zh) 一种处理临近既有线软土地基的施工方法及其路基结构
CN106049407A (zh) 一种地基强夯施工方法
CN104213485A (zh) 一种用于湖区土石混合抛填路基的组合强夯处理的施工方法
CN103774637A (zh) 一种路基夯实施工方法
CN102605698A (zh) 冲击式压路机增强碾压软土路基施工工法
CN103711114A (zh) 地基处理方法
CN102644265A (zh) 一种夯锤及夯实路基的方法
CN106320121B (zh) 一种路基修复结构及方法
CN103114569A (zh) 超高能级直接强夯进行低含水量湿陷性黄土处理工艺
CN106032667A (zh) 一种大能量强夯处理地基的工艺
CN110206054A (zh) 一种输电线安全区地基处理优化方法
CN102817298B (zh) 一种在冻土上的施工方法
CN104727295B (zh) 预成孔填料置换平锤强夯法
CN102031743A (zh) 泥岩填筑路堤的施工方法
CN109972635A (zh) 边坡贴坡中高填方质量控制施工方法
CN102031757B (zh) 一种顶进框架桥的底板导向层的施工方法
CN106869198B (zh) 一种利用井字梁加固杆塔基础加固松散土质下陷空区方法
CN110029652A (zh) 一种减少湿陷性黄土工后沉降的施工工艺
CN206298896U (zh) 一种隧道穿越构筑物钢管隔离桩地层加固体系
CN102635044B (zh) 一种强夯对路床挖方路基的处理方法
CN100365210C (zh) 定位夯实路基施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140507