CN103758520B - A kind of half-edge coal seam flexible type shield staged coal-mining method - Google Patents

A kind of half-edge coal seam flexible type shield staged coal-mining method Download PDF

Info

Publication number
CN103758520B
CN103758520B CN201310743965.5A CN201310743965A CN103758520B CN 103758520 B CN103758520 B CN 103758520B CN 201310743965 A CN201310743965 A CN 201310743965A CN 103758520 B CN103758520 B CN 103758520B
Authority
CN
China
Prior art keywords
adopt
storehouse
ladder
storehouses
push
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310743965.5A
Other languages
Chinese (zh)
Other versions
CN103758520A (en
Inventor
耿养谋
常宝才
马植胜
王新华
牛凤祥
王忠武
常士东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Haohua Energy Resource Co Ltd
Original Assignee
Beijing Haohua Energy Resource Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Haohua Energy Resource Co Ltd filed Critical Beijing Haohua Energy Resource Co Ltd
Priority to CN201310743965.5A priority Critical patent/CN103758520B/en
Publication of CN103758520A publication Critical patent/CN103758520A/en
Application granted granted Critical
Publication of CN103758520B publication Critical patent/CN103758520B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention opens a kind of half-edge coal seam flexible type shield staged coal-mining method of settling sth. according to policy or law, including formation, the perforating of ladder with blow out, take off coal and supporting, tear the eye several step of mouth support open, roadway layout of the present invention is simple, to geological transformation strong adaptability, multiple spot operation simultaneously can be realized, improve single face output.

Description

A kind of half-edge coal seam flexible type shield staged coal-mining method
Technical field
The present invention relates to a kind of coal-mining method.It is specifically related to a kind of half-edge coal seam flexible type shield staged adopt Coal method.
Background technology
During steeply-inclined seam mining, conventional exploitation is all that separate unit stepwise produces, and production efficiency is low, and The safety of workman is the most impacted, it is contemplated that the mode of design multi-stage stairs is mined, improves half-edge coal seam Safety production situation.
Summary of the invention
It is an object of the invention to realize multi-step back production simultaneously, improve the single rate of half-edge coal seam work surface, and Ensure the safety of operating worker.
In order to achieve the above object, the present invention has a following technical scheme:
One half-edge coal seam flexible type shield staged coal-mining method of the present invention, comprises the following steps:
(1) ladder formation process
The first step: eye mouth support is torn in No. 1 storehouse open, upwards pushes to adopt 6.0 meters and arranges ladder → No. 1, No. 1 the 1st, storehouse Eye mouth support is torn in storehouse again open, upwards pushes to adopt 1.0-2.0 rice and arranges No. 1 the 2nd, storehouse two, storehouse, ladder → No. 1 ladder Pushing to adopt forward storehouse, 4.0-5.0 rice → No. 1 tears eye mouth support again open simultaneously, upwards pushes to adopt 1.0-2.0 rice and arranges No. 1 The 3rd, storehouse ladder;
(2) normally push to adopt
Second step: in No. 1 storehouse, 3 ladders normally push to adopt simultaneously, treat that the 1st, No. 1 storehouse ladder pushes to adopt away from 1 Number storehouse upper end 5 meters stopping;
(3) No. 1 storehouse upper end or more than 2 storehouse changeover portions are pushed to adopt
3rd step: first carry out No. 2 storehouses and tear eye mouth support open, upwards pushes to adopt 6.0 meters and arranges rank, No. 2 the 1st, storehouses Ladder;
4th step: in then carrying out No. 1 storehouse, the 1st ladder pushes to adopt 5 meters to No. 2 Cang Yankou positions;
5th step: continue the 2nd, 3 ladders in No. 1 storehouse are pushed to adopt simultaneously, treat the 2nd ladder in No. 1 storehouse Push to adopt away from No. 1 storehouse upper end or No. 25 meters of storehouse stoppings;
6th step: tear eye mouth support again open from No. 2 storehouses again, upwards pushes to adopt 1.0-2.0 rice and arranges No. 2 storehouses the 2nd Individual ladder, then No. 2 two, storehouse ladders push to adopt forward 4.0-5.0 rice simultaneously;
7th step: continue the 2nd ladder in No. 1 storehouse to push to adopt 5 meters to No. 2 Cang Yankou positions;
8th step: tear eye mouth support again open from No. 2 storehouses again, upwards pushes to adopt 1.0-2.0 rice and arranges No. 2 storehouses the 3rd Individual ladder;
9th step: the most again the 3rd ladder in No. 1 storehouse is pushed to adopt to No. 2 Cang Yankou positions, so far No. 1 Storehouse has the most all pushed to adopt;
Tenth step: simultaneously push to adopt 3 ladders in No. 2 storehouses, in treating No. 2 storehouses, the 1st ladder pushes to adopt away from 3 Number storehouse upper end 5 meters stopping;
11st step: the way repeating No. 2 storehouse crosses remaining storehouse, it may be assumed that eye mouth support is torn in No. 3 storehouses open, to On push to adopt 6.0 meters arrange No. 3 the 1st, storehouse ladders, in No. 2 storehouses, the 1st ladder pushes to adopt 5 meters to No. 3 storehouse eyes Mouthful, in No. 2 storehouses, the 2nd, 3 ladders push to adopt simultaneously, and in treating No. 2 storehouses, the 2nd ladder pushes to adopt away from upper end, No. 2 storehouses 5 meters of stoppings, No. 3 storehouses tear eye mouth support again open, upwards push to adopt 1.0-2.0 rice and arrange No. 3 the 2nd, storehouse ladders, and 3 Two, number storehouse ladders push to adopt forward 4.0-5.0 rice simultaneously, and in No. 2 storehouses, the 2nd ladder pushes to adopt 5 meters to No. 3 storehouses Eye mouth, No. 3 storehouses are torn eye mouth support again open, are upwards pushed to adopt 1.0-2.0 rice and arrange No. 3 the 3rd, storehouse ladders, No. 2 storehouses In the 3rd ladder push to adopt to No. 3 storehouse eye mouths, in No. 3 storehouses, 3 ladders push to adopt simultaneously, treat in No. 3 storehouses the 1st Individual ladder pushes to adopt away from No. 3 storehouse upper ends 5 meters stopping, and in pushing to adopt No. 3 storehouses, the 1st ladder is to upper end, No. 3 storehouses Interior 2nd, 3 ladders push to adopt simultaneously, treat that the 2nd ladder is adopted to the 5 meters of stoppings of No. 3 storehouse upper ends, push to adopt 3 In number storehouse, the 2nd ladder is to upper end, and in pushing to adopt No. 3 storehouses, the 3rd ladder is to upper end.
Wherein, ladder number 3 in each storehouse.
Wherein, ladder height is less than or equal to 1.2 meters.
Wherein, the length 4.0-5.0 rice between ladder.
Wherein, the work surface gradient is less than or equal to 25 degree.
Owing to taking above technical scheme, it is an advantage of the current invention that: roadway layout is simple, to geological transformation Strong adaptability, it is possible to achieve multiple spot operation simultaneously, improves single face output.
Accompanying drawing explanation
Fig. 1 is first ladder layout drawing;
Fig. 2 is second ladder layout drawing;
Fig. 3 is the 3rd ladder layout drawing;
Fig. 4 is that the first ladder pushes to adopt figure.
Detailed description of the invention
Hereinafter implement to be used for illustrating the present invention, but be not limited to the scope of the present invention.
Seeing Fig. 1-Fig. 4, the technological process of the present invention includes:
One, ladder is formed
A: scheme one
(1) ladder formation process
The first step: eye mouth support is torn in No. 1 storehouse open, upwards pushes to adopt 6.0 meters and arranges ladder → No. 1, No. 1 the 1st, storehouse Eye mouth support is torn in storehouse again open, upwards pushes to adopt 1.0-2.0 rice and arranges No. 1 the 2nd, storehouse two, storehouse, ladder → No. 1 ladder Pushing to adopt forward storehouse, 4.0-5.0 rice → No. 1 tears eye mouth support again open simultaneously, upwards pushes to adopt 1.0-2.0 rice and arranges No. 1 The 3rd, storehouse ladder;
(2) normally push to adopt
Second step: in No. 1 storehouse, 3 ladders normally push to adopt simultaneously, treat that the 1st, No. 1 storehouse ladder pushes to adopt away from 1 Number storehouse upper end 5 meters stopping;
(3) No. 1 storehouse upper end or more than 2 storehouse changeover portions are pushed to adopt
3rd step: first carry out No. 2 storehouses and tear eye mouth support open, upwards pushes to adopt 6.0 meters and arranges rank, No. 2 the 1st, storehouses Ladder;
4th step: in then carrying out No. 1 storehouse, the 1st ladder pushes to adopt 5 meters to No. 2 Cang Yankou positions;
5th step: continue the 2nd, 3 ladders in No. 1 storehouse are pushed to adopt simultaneously, treat the 2nd ladder in No. 1 storehouse Push to adopt away from No. 1 storehouse upper end (or No. 2 storehouses) 5 meters stopping;
6th step: tear eye mouth support again open from No. 2 storehouses again, upwards pushes to adopt 1.0-2.0 rice and arranges No. 2 storehouses the 2nd Two, No. 2 storehouses of individual ladder → then ladders push to adopt forward 4.0-5.0 rice simultaneously;
7th step: continue the 2nd ladder in No. 1 storehouse to push to adopt 5 meters to No. 2 Cang Yankou positions;
8th step: tear eye mouth support again open from No. 2 storehouses again, upwards pushes to adopt 1.0-2.0 rice and arranges No. 2 storehouses the 3rd Individual ladder;
9th step: the most again the 3rd ladder in No. 1 storehouse is pushed to adopt to so far No. 1 storehouse, No. 2 Cang Yankou positions All push to adopt;
Tenth step: simultaneously push to adopt 3 ladders in No. 2 storehouses, in treating No. 2 storehouses, the 1st ladder pushes to adopt away from 3 Number storehouse upper end 5 meters stopping;
11st step: the way repeating No. 2 storehouse crosses remaining storehouse, it may be assumed that eye mouth support is torn in No. 3 storehouses open, to On push to adopt 6.0 meters and arrange that the 1st ladder pushes to adopt 5 meters to No. 3 storehouse eyes in storehouses, ladder → No. 2, No. 3 the 1st, storehouses In mouth → No. 2 storehouses, the 2nd, 3 ladders push to adopt simultaneously, and in treating No. 2 storehouses, the 2nd ladder pushes to adopt on No. 2 storehouses 5 meters, termination stops → No. 3 storehouses and tears eye mouth support again open, upwards pushes to adopt 1.0-2.0 rice and arranges rank, No. 3 the 2nd, storehouses In ladder → No. 3 two, storehouse ladders push to adopt forward storehouse, 4.0-5.0 rice → No. 2 simultaneously, the 2nd ladder pushes to adopt 5 meters extremely Eye mouth support is torn in storehouse, eye mouth → No. 3, No. 3 storehouses again open, upwards pushes to adopt 1.0-2.0 rice and arranges No. 3 the 3rd, storehouse ladders In → No. 2 storehouses, the 3rd ladder pushes to adopt to storehouse, eye mouth → No. 3, No. 3 storehouses 3 ladders and pushes to adopt simultaneously, treats No. 3 In storehouse, the 1st ladder pushes to adopt and stops → push to adopt in No. 3 storehouses the 1st ladder to upper end away from No. 3 storehouse upper ends 5 meters In storehouse, head → No. 3, the 2nd, 3 ladders push to adopt simultaneously, treat the 2nd ladder to adopt to No. 3 storehouse upper ends 5 meters and stop Stop → push to adopt in No. 3 storehouses the 2nd ladder to the 3rd ladder in upper end → push to adopt No. 3 storehouses to upper end.
B: scheme two
(1) ladder formation process
The first step: eye mouth support is torn in No. 1 storehouse open, upwards pushes to adopt 6.0 meters and arranges ladder → 1, No. 1 the 1st, storehouse Eye mouth support is torn in number storehouse again open, upwards pushes to adopt 1.0-2.0 rice and arranges Cang Liangge rank, the 2nd ladder → No. 1, No. 1 storehouse Push to adopt forward storehouse, 4.0-5.0 rice → No. 1 tears eye mouth support open to ladder more simultaneously, upwards pushes to adopt 1.0-2.0 rice and arranges 1 Number the 3rd, storehouse ladder;
(2) normally push to adopt
Second step: in No. 1 storehouse, 3 ladders push to adopt simultaneously, in treating No. 1 storehouse, the 1st ladder pushes to adopt to No. 2 Yan Kou position, storehouse stops;
(3) No. 1 storehouse upper end or more than 2 storehouse changeover portions are pushed to adopt
3rd step: tear eye mouth support in No. 2 storehouses open, upwards pushes to adopt 6.0 meters and arranges No. 2 the 1st, storehouse ladders;
4th step: then proceed to simultaneously push to adopt the 2nd, 3 ladders in No. 1 storehouse, treats in No. 1 storehouse the 2nd Individual ladder pushes to adopt and stops to No. 2 Cang Yankou positions;
5th step: tear eye mouth support again open from No. 2 storehouses again, upwards pushes to adopt 1.0-2.0 rice and arranges No. 2 storehouses the 2nd Individual ladder → then two, No. 2 storehouses ladder is pushed to adopt forward 4.0-5.0 rice simultaneously;
6th step: again the 3rd ladder in No. 1 storehouse is pushed to adopt to No. 2 storehouse eye mouths;
7th step: tear eye mouth support again open from No. 2 storehouses again, upwards pushes to adopt 1.0-2.0 rice and arranges No. 2 storehouses the 3rd In No. 2 storehouses of individual ladder → then, 3 ladders push to adopt simultaneously, and in treating No. 2 storehouses, the 1st ladder pushes to adopt to No. 3 storehouses Eye mouth position stops;
8th step: the way repeating No. 2 storehouse crosses remaining storehouse, it may be assumed that eye mouth support is torn in No. 3 storehouses open, to On push to adopt 6.0 meters and arrange that the 2nd, 3 ladders push to adopt in storehouses, ladder → No. 2, No. 3 the 1st, storehouses, treat 2 simultaneously In number storehouse, the 2nd ladder pushes to adopt and tears eye mouth support again open to storehouse, eye mouth → No. 3, No. 3 storehouses, upwards pushes to adopt 1.0-2.0 Rice arranges that two, storehouse, ladder → No. 3, No. 3 the 2nd, storehouses ladder pushes to adopt forward in storehouse, 4.0-5.0 rice → No. 2 simultaneously 3rd ladder pushes to adopt tears eye mouth support open again to storehouse, eye mouth → No. 3, No. 3 storehouses, upwards pushes to adopt 1.0-2.0 rice and arranges In storehouse, ladder → No. 3, No. 3 the 3rd, storehouses, the 3rd ladder pushes to adopt simultaneously, and in treating No. 3 storehouses, the 1st ladder pushes to adopt In stopping → push to adopt No. 3 storehouses to No. 3 storehouse upper ends 5 meters, the 1st ladder is in storehouse, upper end → No. 3 the 2nd, 3 Individual ladder pushes to adopt simultaneously, treat the 2nd ladder adopt stop → push to adopt No. 3 storehouses to No. 3 storehouse upper ends 5 meters in the 2nd Individual ladder is to the 3rd ladder in upper end → push to adopt No. 3 storehouses to upper end.
Implementation process should be noted that item:
Tailstock is torn in time open when 1, tearing eye mouth open.
When 2, pushing to adopt, in each storehouse, each ladder must be pushed ahead simultaneously, mustn't push to adopt by single ladder.
3, in each storehouse, each ladder pushes to adopt progress and wants consistent, forbids to push to adopt together two ladders.
4, when upper and lower storehouse pushes to adopt simultaneously, upper storehouse descends the mistake in storehouse away from the height that not can exceed that a ladder in advance.
5, frame is continued when upper end pushes to adopt in time.Push to adopt according to former soft coal-mining method of covering.
Two, perforating, blow out
1, borehole arrangement, quantity, angle, will according to coal seam thickness, hardness in operating regulation clearly Regulation.
2, borehole depth must not exceed 2 meters.
3, during hole placing, after keeping banger as far as possible, in each ladder, there is an effective single-column of supporting.
4, according to seam hardness, clear stipulaties charging means, dose and detonate in operating regulation blasting chart Sequentially.
5, must the powder charge of all ladders detonate in each storehouse simultaneously.
Three, coal and supporting are taken off
Must the most upwards take off coal from the most next ladder in each storehouse when 1, taking off coal after banger, forbid two or Multiple ladders take off coal simultaneously.
2, the regulation that strict implement " is taken off and made a call to ".Take off enough posts away from making a call to a column, between column Away from no more than 1.5 meters, and will be according to top board exposed area and roof condition, it is necessary to complement band cap stull in time.
3, work surface side drawing coal technology and technical safety measures must in operating regulation clear stipulaties.Respectively go up a hill In the range of work surface eye mouth and upper end 5 meters, frame back pad layer thickness less than 3 meters, near the coal discharge outlet of side 5 meters of models Enclose the some post of inner support and support before a post is not accomplished fluently in support bottom at defective and side coal discharge outlet, all forbid to carry out side Put coal operation after frame.
4, after operating regulation being wanted clear and definite work surface push to adopt, get the spacing of post and stull ready, specify top board and break The technical safety measures that broken or support upper limb should be taked after leaving top board.
Four, eye mouth support is torn open
1, support must be transferred at eye mouth in time and accomplish fluently a post (coupled columns) and stull is effectively controlled well at eye mouth Flexible shield support, reduce the top board exposed area at eye mouth.
2, often follow and push to adopt from eye mouth when starting new circulation, the most accurate use that to tear dilute back-propping plate open (the most accurate Tear the backboard of the 1 dilute frame of frame open) mode, forbid directly pushed to adopt by eye mouth support removing, it is ensured that ladder Highly it is not more than 1.2 meters, treats that ladder pushes to adopt support at 6 meters of rear dismountable eye mouths.
3, when tunnel widens the view mouth (layout ladder), operating regulation must be widened the view mouth by clear stipulaties Mode, the supporting requirement at eye mouth and technical safety measures.
4, the supporting in eye mouth Xia20 meter Li lane must be overhauled before tearing frame open, lack vertical brace, backboard, timely replacement, Top board lives stone process totally.
5, tear frame open must from top to bottom carry out by frame, tear frame mode open and tear the safety specifications of frame open on operation rule Must clear stipulaties in journey.
Obviously, the above embodiment of the present invention is only for clearly demonstrating example of the present invention, and not It it is the restriction to embodiments of the present invention.For those of ordinary skill in the field, in described above On the basis of can also make other changes in different forms.Here all of embodiment cannot be given With exhaustive.Every belong to obvious change or variation that technical scheme extended out still in this The row of the protection domain of invention.

Claims (4)

1. a half-edge coal seam flexible type shield staged coal-mining method, it is characterised in that include following step Rapid:
(1) ladder formation process
The first step: eye mouth support is torn in No. 1 storehouse open, upwards pushes to adopt 6.0 meters and arranges ladder → No. 1, No. 1 the 1st, storehouse Eye mouth support is torn in storehouse again open, upwards pushes to adopt 1.0-2.0 rice and arranges No. 1 the 2nd, storehouse two, storehouse, ladder → No. 1 ladder Pushing to adopt forward storehouse, 4.0-5.0 rice → No. 1 tears eye mouth support again open simultaneously, upwards pushes to adopt 1.0-2.0 rice and arranges No. 1 The 3rd, storehouse ladder;
(2) normally push to adopt
Second step: in No. 1 storehouse, 3 ladders normally push to adopt simultaneously, treat that the 1st, No. 1 storehouse ladder pushes to adopt away from 1 Number storehouse upper end 5 meters stopping;
(3) No. 1 storehouse upper end or more than 2 storehouse changeover portions are pushed to adopt
3rd step: first carry out No. 2 storehouses and tear eye mouth support open, upwards pushes to adopt 6.0 meters and arranges rank, No. 2 the 1st, storehouses Ladder;
4th step: in then carrying out No. 1 storehouse, the 1st ladder pushes to adopt 5 meters to No. 2 Cang Yankou positions;
5th step: continue the 2nd, 3 ladders in No. 1 storehouse are pushed to adopt simultaneously, treat the 2nd ladder in No. 1 storehouse Push to adopt away from No. 1 storehouse upper end or No. 25 meters of storehouse stoppings;
6th step: tear eye mouth support again open from No. 2 storehouses again, upwards pushes to adopt 1.0-2.0 rice and arranges No. 2 storehouses the 2nd Individual ladder, then No. 2 two, storehouse ladders push to adopt forward 4.0-5.0 rice simultaneously;
7th step: continue the 2nd ladder in No. 1 storehouse to push to adopt 5 meters to No. 2 Cang Yankou positions;
8th step: tear eye mouth support again open from No. 2 storehouses again, upwards pushes to adopt 1.0-2.0 rice and arranges No. 2 storehouses the 3rd Individual ladder;
9th step: the most again the 3rd ladder in No. 1 storehouse is pushed to adopt to so far No. 1 storehouse, No. 2 Cang Yankou positions The most all push to adopt;
Tenth step: simultaneously push to adopt 3 ladders in No. 2 storehouses, in treating No. 2 storehouses, the 1st ladder pushes to adopt away from 3 Number storehouse upper end 5 meters stopping;
11st step: the way repeating No. 2 storehouse crosses remaining storehouse, it may be assumed that eye mouth support is torn in No. 3 storehouses open, to On push to adopt 6.0 meters arrange No. 3 the 1st, storehouse ladders, in No. 2 storehouses, the 1st ladder pushes to adopt 5 meters to No. 3 storehouse eyes Mouthful, in No. 2 storehouses, the 2nd, 3 ladders push to adopt simultaneously, and in treating No. 2 storehouses, the 2nd ladder pushes to adopt away from upper end, No. 2 storehouses 5 meters of stoppings, No. 3 storehouses tear eye mouth support again open, upwards push to adopt 1.0-2.0 rice and arrange No. 3 the 2nd, storehouse ladders, and 3 Two, number storehouse ladders push to adopt forward 4.0-5.0 rice simultaneously, and in No. 2 storehouses, the 2nd ladder pushes to adopt 5 meters to No. 3 storehouses Eye mouth, No. 3 storehouses are torn eye mouth support again open, are upwards pushed to adopt 1.0-2.0 rice and arrange No. 3 the 3rd, storehouse ladders, No. 2 storehouses In the 3rd ladder push to adopt to No. 3 storehouse eye mouths, in No. 3 storehouses, 3 ladders push to adopt simultaneously, treat in No. 3 storehouses the 1st Individual ladder pushes to adopt away from No. 3 storehouse upper ends 5 meters stopping, and in pushing to adopt No. 3 storehouses, the 1st ladder is to upper end, No. 3 storehouses Interior 2nd, 3 ladders push to adopt simultaneously, treat that the 2nd ladder is adopted to the 5 meters of stoppings of No. 3 storehouse upper ends, push to adopt 3 In number storehouse, the 2nd ladder is to upper end, and in pushing to adopt No. 3 storehouses, the 3rd ladder is to upper end.
2. a kind of half-edge coal seam flexible type shield staged coal-mining method as claimed in claim 1, its feature Being, ladder height is less than or equal to 1.2 meters.
3. a kind of half-edge coal seam flexible type shield staged coal-mining method as claimed in claim 1, its feature It is, the length 4.0-5.0 rice between ladder.
4. a kind of half-edge coal seam flexible type shield staged coal-mining method as claimed in claim 1, its feature Being, the work surface gradient is less than or equal to 25 degree.
CN201310743965.5A 2013-12-28 2013-12-28 A kind of half-edge coal seam flexible type shield staged coal-mining method Active CN103758520B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310743965.5A CN103758520B (en) 2013-12-28 2013-12-28 A kind of half-edge coal seam flexible type shield staged coal-mining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310743965.5A CN103758520B (en) 2013-12-28 2013-12-28 A kind of half-edge coal seam flexible type shield staged coal-mining method

Publications (2)

Publication Number Publication Date
CN103758520A CN103758520A (en) 2014-04-30
CN103758520B true CN103758520B (en) 2016-10-05

Family

ID=50525819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310743965.5A Active CN103758520B (en) 2013-12-28 2013-12-28 A kind of half-edge coal seam flexible type shield staged coal-mining method

Country Status (1)

Country Link
CN (1) CN103758520B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103993883A (en) * 2014-05-20 2014-08-20 四川省华蓥山煤业股份有限公司李子垭南煤矿 Sharp inclined coal seam flexible shield support mining method
CN109779630A (en) * 2019-02-20 2019-05-21 北京昊华能源股份有限公司 A kind of half-edge coal seam coal-mining method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4512610A (en) * 1983-05-27 1985-04-23 Mobil Oil Corporation Mining system
CN1474032A (en) * 2003-08-08 2004-02-11 中南大学 Continuous mining method of stepped sectional extruding and ore caving followed by filling
CN1546839A (en) * 2003-12-11 2004-11-17 云南驰宏锌锗股份有限公司 Ladder type mining method using united pillars to support roof and partition stope
CN1657745A (en) * 2005-03-03 2005-08-24 开滦(集团)有限责任公司 Coal-minin method of high-dipping thick seam
CN101307692A (en) * 2008-07-14 2008-11-19 邹开科 Sharply inclined coal seam mining method
CN101429867A (en) * 2008-12-13 2009-05-13 山西焦煤集团有限责任公司 Major cycle slanting extraction method for coal mining work surface
CN101818643A (en) * 2010-05-18 2010-09-01 中南大学 Stepped non-pillar continuous filling mining method for deep well super high large breaking ore body panel
CN102418526A (en) * 2011-12-02 2012-04-18 瓮福(集团)有限责任公司 High-sublevel subdivision mining method of moderately thick heavy-pitch waste-rock-containing interlayer phosphate orebody along strike
CN102562066A (en) * 2012-01-16 2012-07-11 袁野 Method for mechanically mining coal by using steep seam pseudo inclination bracing type retractable flexible shield support
CN103061764A (en) * 2012-12-14 2013-04-24 北京昊华能源股份有限公司 Goaf waste rock filling coal mining method of flexible shield support in half-edge coal seam

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4512610A (en) * 1983-05-27 1985-04-23 Mobil Oil Corporation Mining system
CN1474032A (en) * 2003-08-08 2004-02-11 中南大学 Continuous mining method of stepped sectional extruding and ore caving followed by filling
CN1546839A (en) * 2003-12-11 2004-11-17 云南驰宏锌锗股份有限公司 Ladder type mining method using united pillars to support roof and partition stope
CN1657745A (en) * 2005-03-03 2005-08-24 开滦(集团)有限责任公司 Coal-minin method of high-dipping thick seam
CN101307692A (en) * 2008-07-14 2008-11-19 邹开科 Sharply inclined coal seam mining method
CN101429867A (en) * 2008-12-13 2009-05-13 山西焦煤集团有限责任公司 Major cycle slanting extraction method for coal mining work surface
CN101818643A (en) * 2010-05-18 2010-09-01 中南大学 Stepped non-pillar continuous filling mining method for deep well super high large breaking ore body panel
CN102418526A (en) * 2011-12-02 2012-04-18 瓮福(集团)有限责任公司 High-sublevel subdivision mining method of moderately thick heavy-pitch waste-rock-containing interlayer phosphate orebody along strike
CN102562066A (en) * 2012-01-16 2012-07-11 袁野 Method for mechanically mining coal by using steep seam pseudo inclination bracing type retractable flexible shield support
CN103061764A (en) * 2012-12-14 2013-04-24 北京昊华能源股份有限公司 Goaf waste rock filling coal mining method of flexible shield support in half-edge coal seam

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
复杂难采煤层评价方法与开采技术研究;霍丙杰;《中国博士学位论文全文数据库 工程科技Ⅰ辑》;20120515;B021-10 *

Also Published As

Publication number Publication date
CN103758520A (en) 2014-04-30

Similar Documents

Publication Publication Date Title
CN103453809B (en) Water-mist dust settling method implemented during blast excavation for large-scale underground project
CN104481543B (en) Stage shrink caved stopes
CN103967493B (en) A kind of slight slope and thin ore body ore pillar mining codes
CN103114855A (en) Jamb recovery and cushion layer formation integrated technology in process of mining from outdoors into underground
CN104329113B (en) A kind of method of surface drilling standing seat earth release mash gas extraction
CN110260731B (en) One-time well construction method for drop shaft and cutting well
CN103758520B (en) A kind of half-edge coal seam flexible type shield staged coal-mining method
CN101956556A (en) Roof and bottom pillar-free stage upward continuous filling and mining method
CN113446006A (en) Open stope mining method for steeply inclined vein-shaped ore body
CN105735996A (en) Presplitting type wall cutting and filling stoping method for thin ore vein
CN107339920B (en) The method of superdeep holes presplit blasting
CN107165635A (en) A kind of oblique pinpoint blasting mining codes for slight slope and thin ore body
CN104533517B (en) A kind of high sublevel falls dead zone, ore deposit zero following firms mining codes to deep hole
CN106121653A (en) One closes hole surface mine Ore stoping method
CN111596031A (en) Coal seam floor disaster simulation device and method
CN111963175B (en) Thick ore body mining method
CN103670423A (en) Method for excavating tunnel in layered phyllite body
CN107131805B (en) Mining method for improving ore removal grade of underground caving stope
CN106969676A (en) It is a kind of to improve the cloth hole method for trimming of demolition effect based on RTK blastholes location technology
CN108708721B (en) Mechanized upward segmented stoping method
CN109900175B (en) Low-damage blasting method for underground mine roadway tunneling
CN204009912U (en) Pre-control is pushed up the ore deposit afterwards filling mining sectional type blasting cartridge that paragraphs
CN112963147B (en) Medium-length hole blasting mining process for steeply inclined thin ore body
CN103967522B (en) Reserved roadway surrounding rock control comprehensive processing method
CN103670507A (en) Method for determining width of gob gangue-filled zone of steeply inclined fully mechanized mining face

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant