CN103741961B - To boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key - Google Patents

To boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key Download PDF

Info

Publication number
CN103741961B
CN103741961B CN201410007484.2A CN201410007484A CN103741961B CN 103741961 B CN103741961 B CN 103741961B CN 201410007484 A CN201410007484 A CN 201410007484A CN 103741961 B CN103741961 B CN 103741961B
Authority
CN
China
Prior art keywords
circular hole
former
prefabricated circular
horizontal drilling
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410007484.2A
Other languages
Chinese (zh)
Other versions
CN103741961A (en
Inventor
董有
甄进平
吴保光
郑方昊遐
李薇
杨娜茵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Sethmic Technology Development Center
Original Assignee
BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201410007484.2A priority Critical patent/CN103741961B/en
Publication of CN103741961A publication Critical patent/CN103741961A/en
Application granted granted Critical
Publication of CN103741961B publication Critical patent/CN103741961B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

To boost sales after the present invention relates to the prefabricated circular hole slab of a kind of existing building the dark seismic strengthening of beams method of key, belong to technical field of anti-seismic reinforcement, it proposes the former masonry panel position, end, position, hole of pin key in the former prefabricated circular hole slab of existing building, longitudinally horizontal drilling is bored along its length along plate hole, drill through in metapore and wear reinforcing bar or steel strand, then in hole, pour into polymer mortar, key of boosting sales after longitudinally adjacent former prefabricated circular hole slab end forms floor, and increase dark beam after forming floor in plate hole.During operative constraint of the present invention earthquake, floor comes off and improves bearing capacity, improve whole building anti-seismic performance, without the need to destroying appearance and interior decoration, and all external procedure forms new antidetonation rod member, significantly can improve the anti-seismic performance of existing building, construction is simple, and cost is low, have wide range of applications, be applicable to all circular hole slab superstructures, roof system.

Description

To boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key
Technical field
To boost sales after the present invention relates to the prefabricated circular hole slab of a kind of existing building the dark seismic strengthening of beams method of key, belong to technical field of anti-seismic reinforcement.
Background technology
At present, whole nation existing apartment, hospital, the seismic hardening of agriculture residence starts to start, existing apartment or plate end not enough with the agriculture residence a large amount of masonry structure circular hole slab bearing length before 2000 is connected that measure is not in place does not meet current seismic design reinforcement specification before the eighties in last century, have a strong impact on its anti-seismic performance, the a lot of earthquake disaster of China shows in recent years, masonry structure floor comes off to cause injury and lethally in this class formation earthquake, account for larger specific gravity, floor comes off effective strong point that caused body of wall to lack, anti-seismic performance sharply declines, integral house local or entirety are collapsed instantaneously, strengthening effective connection and shelving length between precast floor slab reinforces particularly important for Hollow Block Masonry Structure Anti-seismic.The method that traditional design adopts angle steel to support is during construction reinforcement, and the common people are unwilling to allow construction of registering one's residence, and also has the impact of the angle steel of bright dew attractive in appearance, in addition difficulty of construction comparatively greatly, long to resident family's influence time, cost is high.Each R&D institution not yet takes out way effectively and solves this thing.
Summary of the invention
In order to overcome the problems referred to above, to boost sales after the present invention proposes the prefabricated circular hole slab of a kind of existing building the dark seismic strengthening of beams method of key, it is without the need to destroying appearance and interior decoration, whole external procedure forms new antidetonation rod member, significantly can improve the anti-seismic performance of existing building, solve the not enough problem of Seismic Bearing Capacity.
Technical scheme of the present invention is as follows:
To boost sales after the prefabricated circular hole slab of a kind of existing building the dark seismic strengthening of beams method of key, comprise former prefabricated circular hole slab and former masonry panel, described former prefabricated circular hole slab is provided with multiple plate hole, on the former masonry panel of described former at least one plate hole end of prefabricated circular hole slab, plate hole length direction is provided with horizontal drilling, the plate hole level that horizontal drilling on described former masonry panel is corresponding with on former prefabricated circular hole slab is through to be integrated, reinforcing bar or steel strand are equipped with in described horizontal drilling and corresponding plate hole, polymer mortar is perfused with in horizontal drilling and corresponding plate hole, to boost sales after the polymer mortar of the reinforcing bar in described horizontal drilling or steel strand and perfusion forms floor key, and the polymer mortar of reinforcing bar in former prefabricated circular hole slab plate hole or steel strand and perfusion increases dark beam after forming floor, described method adopts following steps:
Step one: by identifying existing building, detect former prefabricated circular hole slab plate hole locations, and in the enterprising row labels of former masonry panel, determine the polymer mortar intensity needing the format diameter of the aperture location of horizontal drilling, reinforcing bar or steel strand and inside to pour into through design;
Step 2: according to construction drawing determination horizontal drilling distance, and then select rig to prepare to carry out horizontal drilling, set up scaffold and erection construction platform;
Step 3: fix rig on operation platform, successively horizontal drilling construction operation is carried out to former masonry panel from the bottom to top, after horizontal drilling, whether the plate hole diameter corresponding with on former prefabricated circular hole slab conforms in detection level boring, if continue the former crack pouring concrete that penetrates between two pieces of former prefabricated circular hole slabs on former masonry panel interior wall of holing after conforming to, hole and completely hole is cleaned out and penetrate reinforcing bar or steel strand in horizontal drilling and corresponding plate hole;
Step 4: stand placed in the middle by reinforcing bar or steel strand frame, changes high-pressure slip-casting equipment and prepares to pour into polymer mortar;
Step 5: by horizontal drilling and corresponding plate hole through after hole sealing two ends, grouting equipment is adopted to pour into polymer mortar in horizontal drilling and corresponding plate hole, not spillage should be noted during level perfusion polymer mortar, by grouting port shutoff after perfusion polymer mortar, and namely through outside horizontal drilling after hole two ends anchor bolt is installed reinforcing bar or steel strand is fixed;
Step 6: the structure after construction reinforcement is carried out an acceptance inspection.
Further, increasing dark beam after the floor arranged in described former prefabricated circular hole slab is two, and key of boosting sales after the floor of its correspondence is also two.
Further, increase dark beam after two floors arranged in described former prefabricated circular hole slab to be symmetrical arranged along former prefabricated circular hole slab horizontal cross.
Further, described reinforcing bar or steel strand are positioned at horizontal drilling and corresponding plate hole center position.
Further, the connection between described reinforcing bar adopts overlap joint or welding.
Further, on described former masonry panel, the diameter of horizontal drilling is identical with the plate hole diameter on former prefabricated circular hole slab.
Wherein, polymer mortar adopts high-pressure injection pump to inject, and need in hole full, polymer mortar intensity is chosen according to design.Key of boosting sales after floor is the reinforced concrete member formed after polymer injection mortar, belongs to structure rod member, and reinforcing bar or steel strand model and required polymer mortar intensity are as the criterion to increase dark beam design determined value after floor.Increasing dark beam after floor is the steel concrete stressed member formed after polymer injection mortar, and arrangement of reinforcement is determined according to design.
Beneficial effect:
Key of boosting sales after floor of the present invention improves the switching performance between plate, compensate for the not enough deficiency with lacking effective drawknot each other of prefabricated circular hole slab shelving length; Increase the rod member of dark beam form floor in the middle part of plate after, improve the bearing capacity of prefabricated circular hole slab.Meanwhile, the present invention fully incorporates the advanced single technology of conglomerate in recent years, and each single technology is ripe, and speed of application is fast, small investment, the present invention do not register one's residence realize the larger raising of Seismic Behavior of Masonry and, construction is simple, and cost is low.The present invention has wide range of applications and is applicable to the prefabricated circular hole slab superstructure of all existing buildings, roof system, has higher economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is plane of arrangement figure of the present invention;
Fig. 2 is Fig. 1's sectional view;
Fig. 3 is Fig. 1's sectional view;
Fig. 4 is Fig. 2's place's enlarged drawing;
Fig. 5 is Fig. 3's place's enlarged drawing;
Fig. 6 is Fig. 3's place's enlarged drawing;
Fig. 7 is Fig. 3's place's enlarged drawing.
In figure, 1, key of boosting sales after floor; 2, dark beam is increased after floor; 3, former masonry panel; 4, reinforcing bar or steel strand; 5, polymer mortar; 6, former prefabricated circular hole slab; 7, anchor bolt; 8, former crack pouring concrete.
Detailed description of the invention
To boost sales after the prefabricated circular hole slab of a kind of existing building of the present invention the dark seismic strengthening of beams method of key, see shown in Fig. 1 to 7, comprise former prefabricated circular hole slab 6 and former masonry panel 3, described former prefabricated circular hole slab 6 is provided with multiple plate hole, on the former masonry panel 3 of prefabricated circular hole slab 6 two plate hole ends former described in every block, plate hole length direction is provided with horizontal drilling, the plate hole level that horizontal drilling on described former masonry panel 3 is corresponding with on former prefabricated circular hole slab 6 is through to be integrated, reinforcing bar or steel strand 4 are equipped with in described horizontal drilling and corresponding plate hole, reinforcing bar or steel strand 4 are positioned at horizontal drilling and corresponding plate hole center position, according to reinforcing bar, connection between reinforcing bar adopts overlap joint or welding, polymer mortar 5 is perfused with in horizontal drilling and corresponding plate hole, to boost sales after reinforcing bar in described horizontal drilling or steel strand 4 form floor with the polymer mortar 5 of perfusion key 1, and reinforcing bar in former prefabricated circular hole slab 6 plate hole or steel strand 4 increase dark beam 2 after forming floor with the polymer mortar 5 of perfusion, wherein, increasing dark beam 2 after the floor arranged in the former prefabricated circular hole slab 6 of every block is two, and key 1 of boosting sales after floor corresponding to its end is also two, and be symmetrical arranged along former prefabricated circular hole slab 6 horizontal cross.
Shockproof reinforcing method specifically adopts following steps:
Step one: by identifying existing building, detect former prefabricated circular hole slab 6 plate hole locations, and in the enterprising row labels of former masonry panel 3, determine polymer mortar 5 intensity needing the format diameter of the aperture location of horizontal drilling, reinforcing bar or steel strand 4 and inside to pour into through design;
Step 2: according to construction drawing determination horizontal drilling distance, and then select rig to prepare to carry out horizontal drilling, set up scaffold and erection construction platform;
Step 3: fix rig on operation platform, successively horizontal drilling construction operation is carried out to former masonry panel 3 from the bottom to top, after horizontal drilling, whether the plate hole diameter corresponding with on former prefabricated circular hole slab 6 conforms in detection level boring, if continue the former crack pouring concrete 8 that penetrates between two pieces of former prefabricated circular hole slabs 6 on former masonry panel 3 interior wall of holing after conforming to, hole and completely hole is cleaned out and penetrate reinforcing bar or steel strand 4 in horizontal drilling and corresponding plate hole;
Step 4: stand placed in the middle by reinforcing bar or steel strand 4 frame, changes high-pressure slip-casting equipment and prepares to pour into polymer mortar 5;
Step 5: by horizontal drilling and corresponding plate hole through after hole sealing two ends, adopt grouting equipment at horizontal drilling and
Step 4: stand placed in the middle by reinforcing bar or steel strand 4 frame, changes high-pressure slip-casting equipment and prepares to pour into polymer mortar 5;
Step 5: by horizontal drilling and corresponding plate hole through after hole sealing two ends, grouting equipment is adopted to pour into polymer mortar 5 in horizontal drilling and corresponding plate hole, not spillage should be noted during level perfusion polymer mortar 5, by grouting port shutoff after perfusion polymer mortar 5, and namely through outside horizontal drilling after hole two ends anchor bolt 7 is installed reinforcing bar or steel strand 4 is fixed;
Step 6: the structure after construction reinforcement is carried out an acceptance inspection.
Be more than an exemplary embodiment of the present invention, specific embodiment of the invention is not limited thereto.

Claims (5)

1. to boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key, comprise former prefabricated circular hole slab (6) and former masonry panel (3), described former prefabricated circular hole slab (6) is provided with multiple plate hole, on the former masonry panel (3) of described former at least one plate hole end of prefabricated circular hole slab (6), plate hole length direction is provided with horizontal drilling, horizontal drilling on described former masonry panel (3) is integrated with the upper corresponding plate hole level of former prefabricated circular hole slab (6) is through, reinforcing bar or steel strand (4) are equipped with in described horizontal drilling and corresponding plate hole, polymer mortar (5) is perfused with in horizontal drilling and corresponding plate hole, to boost sales after reinforcing bar in described horizontal drilling or steel strand (4) and the polymer mortar (5) of perfusion form floor key (1), and reinforcing bar in former prefabricated circular hole slab (6) plate hole or steel strand (4) increase dark beam (2) after forming floor with the polymer mortar (5) of perfusion, it is characterized in that:
Described method adopts following steps:
Step one: by identifying existing building, detect former prefabricated circular hole slab (6) plate hole locations, and in former masonry panel (3) enterprising row labels, determine polymer mortar (5) intensity needing the format diameter of the aperture location of horizontal drilling, reinforcing bar or steel strand (4) and inside to pour into through design;
Step 2: according to construction drawing determination horizontal drilling distance, and then select rig to prepare to carry out horizontal drilling, set up scaffold and erection construction platform;
Step 3: fix rig on operation platform, successively horizontal drilling construction operation is carried out to former masonry panel (3) from the bottom to top, after horizontal drilling, whether detection level boring conforms to the upper corresponding plate hole diameter of former prefabricated circular hole slab (6), if continue boring after conforming to penetrate former crack pouring concrete (8) between two pieces of former prefabricated circular hole slabs (6) on former masonry panel (3) interior wall, hole and completely hole is cleaned out and penetrate reinforcing bar or steel strand (4) in horizontal drilling and corresponding plate hole;
Step 4: stand placed in the middle by reinforcing bar or steel strand (4) frame, changes high-pressure slip-casting equipment and prepares to pour into polymer mortar (5);
Step 5: by horizontal drilling and corresponding plate hole through after hole sealing two ends, grouting equipment is adopted to pour into polymer mortar (5) in horizontal drilling and corresponding plate hole, not spillage should be noted during level perfusion polymer mortar (5), by grouting port shutoff after perfusion polymer mortar (5), and namely through outside horizontal drilling after hole two ends anchor bolt (7) is installed reinforcing bar or steel strand (4) is fixed;
Step 6: the structure after construction reinforcement is carried out an acceptance inspection.
2. to boost sales after the prefabricated circular hole slab of a kind of existing building according to claim 1 the dark seismic strengthening of beams method of key, it is characterized in that: increasing dark beam (2) after the floor arranged in described former prefabricated circular hole slab (6) is two, and key (1) of boosting sales after the floor of its correspondence is also two.
3. to boost sales after the prefabricated circular hole slab of a kind of existing building according to claim 2 the dark seismic strengthening of beams method of key, it is characterized in that: increase dark beam (2) after two floors arranged in described former prefabricated circular hole slab (6) and be symmetrical arranged along former prefabricated circular hole slab (6) horizontal cross.
4. to boost sales after the prefabricated circular hole slab of a kind of existing building according to claim 1 the dark seismic strengthening of beams method of key, it is characterized in that: described reinforcing bar or steel strand (4) are positioned at horizontal drilling and corresponding plate hole center position.
5. to boost sales after the prefabricated circular hole slab of a kind of existing building according to claim 1 the dark seismic strengthening of beams method of key, it is characterized in that: the connection between described reinforcing bar adopts overlap joint or welding.
CN201410007484.2A 2014-01-06 2014-01-06 To boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key Active CN103741961B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410007484.2A CN103741961B (en) 2014-01-06 2014-01-06 To boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410007484.2A CN103741961B (en) 2014-01-06 2014-01-06 To boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key

Publications (2)

Publication Number Publication Date
CN103741961A CN103741961A (en) 2014-04-23
CN103741961B true CN103741961B (en) 2015-09-09

Family

ID=50499018

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410007484.2A Active CN103741961B (en) 2014-01-06 2014-01-06 To boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key

Country Status (1)

Country Link
CN (1) CN103741961B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196256B (en) * 2014-07-24 2017-01-11 北京筑福建筑事务有限责任公司 Carbon fiber reinforcement structure and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005155139A (en) * 2003-11-25 2005-06-16 Oriental Construction Co Ltd Seismic reinforcing external frame construction method of existing building
CN101936074A (en) * 2010-08-05 2011-01-05 北京特希达科技有限公司 Fast building earthquake-resisting reinforcing method and device
CN102561717A (en) * 2011-12-31 2012-07-11 北京筑福建设工程有限责任公司 Method for reinforcing brick-concrete structure by utilizing angle steel frame
CN102864945A (en) * 2012-10-11 2013-01-09 北京筑福建设工程有限责任公司 Reinforced structure of mortar anchor rod masonry and reinforcement method thereof
CN103046764A (en) * 2012-10-31 2013-04-17 上海市建筑科学研究院(集团)有限公司 Method for reinforcing pre-stressed concrete core unit by using bar-mat reinforcement fine aggregate concrete

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005155139A (en) * 2003-11-25 2005-06-16 Oriental Construction Co Ltd Seismic reinforcing external frame construction method of existing building
CN101936074A (en) * 2010-08-05 2011-01-05 北京特希达科技有限公司 Fast building earthquake-resisting reinforcing method and device
CN102561717A (en) * 2011-12-31 2012-07-11 北京筑福建设工程有限责任公司 Method for reinforcing brick-concrete structure by utilizing angle steel frame
CN102864945A (en) * 2012-10-11 2013-01-09 北京筑福建设工程有限责任公司 Reinforced structure of mortar anchor rod masonry and reinforcement method thereof
CN103046764A (en) * 2012-10-31 2013-04-17 上海市建筑科学研究院(集团)有限公司 Method for reinforcing pre-stressed concrete core unit by using bar-mat reinforcement fine aggregate concrete

Also Published As

Publication number Publication date
CN103741961A (en) 2014-04-23

Similar Documents

Publication Publication Date Title
CN105804283B (en) Full assembly concrete-filled steel tube frame combined shear wall construction
CN203296175U (en) Rectangular steel pipe column assembly type column foot
CN106149768B (en) A kind of float Structure and its construction method of the underground structure of fender post combination Guan Liang
CN104213717B (en) Multi-storey building integration transformation method of construction
CN210887559U (en) Low multi-storey steel structure residential system
CN103758362B (en) After existing masonry building, increase the Shockproof reinforcing method of collar tie beam, constructional column and reinforcing pull rod
CN107355008B (en) Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure
CN103306283B (en) A kind of method improving nonmetal anti-float anchor rod shear strength
CN108999281A (en) A kind of novel precast concrete bean column node and its construction method
CN104295109A (en) Rapid reinforcing structure for home-entry-free balcony of old community and construction method of structure
CN103741961B (en) To boost sales after the prefabricated circular hole slab of existing building the dark seismic strengthening of beams method of key
CN103498567A (en) Method for conducting anti-seismic reinforcement through later-arranged dark ring beams in masonry panel and reinforcement structure thereof
CN206219974U (en) The assembled attachment structure of prefabricated bent cap and prefabricated stand column
CN103498574A (en) Method for conducting anti-seismic reinforcement through later-arranged core columns in masonry panel
CN105274997B (en) Muscle formula bracket and the method for pushing up road steel pipe support and top board using bracket construction
CN209114648U (en) A kind of assembling type outer wall structure
CN207160448U (en) A kind of assembled architecture reinforced concrete stairs structure
CN204825924U (en) Square steel tube concrete waist rail
CN203603523U (en) Structure for transforming inner portion of old factory building in floor adding mode
CN211899791U (en) Prefabricated floor preformed hole adopts and wears steel pull rod to consolidate masonry structure
CN104675138A (en) Method and structure for reinforcing modified sound-insulation and noise-reduction slab balcony
CN111075217A (en) Masonry structure reinforced by longitudinal drilling steel-penetrating pull rods and end plates and construction method thereof
CN103967208B (en) The light steel of Z-section-timber with small diameter combination bearing column and making method
CN204326072U (en) A kind of anti-float anchor rod node
CN204401627U (en) To pull-type prestressed pipe pile pit supporting construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180110

Address after: 102600, room 2, building 2212, pop Center, Xinghua street, Beijing, Daxing District

Patentee after: BEIJING YONGBO TECHNOLOGY CO.,LTD.

Address before: 100043 Shijingshan District, Yang Yang Street, No. 69, No. 1, building an international Park, Fu International

Patentee before: BEIJING AEIDO ENGINEERING TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201214

Address after: 233000 Room 102 north, No.11, No.2 building, liukm Huayuan commercial building, Changqing Township, Yuhui District, Bengbu City, Anhui Province

Patentee after: Anhui Licha Information Technology Co.,Ltd.

Address before: 102600 room 2212, building 2, Pope center, Xinghua street, Daxing District, Beijing.

Patentee before: BEIJING YONGBO TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221117

Address after: Room 312, No. 28, Suzhou Street, Haidian District, Beijing 100,089

Patentee after: Beijing Sethmic Technology Development Center

Address before: 233000 Room 102 north, No.11, No.2 building, liukm Huayuan commercial building, Changqing Township, Yuhui District, Bengbu City, Anhui Province

Patentee before: Anhui Licha Information Technology Co.,Ltd.

TR01 Transfer of patent right