CN103726666B - Full assembly structure component positioning supports construction method - Google Patents

Full assembly structure component positioning supports construction method Download PDF

Info

Publication number
CN103726666B
CN103726666B CN201410007996.9A CN201410007996A CN103726666B CN 103726666 B CN103726666 B CN 103726666B CN 201410007996 A CN201410007996 A CN 201410007996A CN 103726666 B CN103726666 B CN 103726666B
Authority
CN
China
Prior art keywords
supports
prefabricated post
support
assembly structure
full assembly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410007996.9A
Other languages
Chinese (zh)
Other versions
CN103726666A (en
Inventor
江建
江晓茜
成伟
江晓波
邢剑锋
吴俊�
周立飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Sijian Construction Group Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410007996.9A priority Critical patent/CN103726666B/en
Publication of CN103726666A publication Critical patent/CN103726666A/en
Application granted granted Critical
Publication of CN103726666B publication Critical patent/CN103726666B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of full assembly structure component positioning supports construction method, comprise the steps such as prefabricated post diagonal brace is fixed, precast beam supports, precast plate supports, full assembly structure support.Easy construction of the present invention, effective.Easy to implement, solve the Components installation high accuracy such as full precast construction slab column and require the technical barrier of bearing frame high strength, having saved circulation material, improve construction effect.

Description

Full assembly structure component positioning supports construction method
Technical field
The present invention relates to a kind of full assembly structure component positioning supports construction method.
Background technology
In full-prefabricated assembly structural, PC structure floor bulk is assembled, Components installation high accuracy such as slab column and require bearing frame high strength, the construction technology of traditional fastener type steel pipe scaffold, construction effect is low, precision bearing capacity is poor, cannot meet the needs of full assembly structure construction.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, effective full assembly structure component positioning supports construction method.
Technical solution of the present invention is:
A kind of full assembly structure component positioning supports construction method, is characterized in that: comprise the following steps:
(1) prefabricated post diagonal brace is fixed
The support of prefabricated post adopts Interal fixation, adopts the welding of 14mm steel plate;
Before tower crane lifting, supporting steel plate is fixed in prefabricated post by constructor after lifting component to relevant position, after prefabricated post is in place according to the line that surveyor throws in, constructor by the steel pipe support of diagonal brace on supporting steel plate and on the strong point of showing up;
(2) precast beam supports
The support of precast beam adopts speed to connect frame as support system, by the position of each support column unwrapping wire after floor has been cleared up, and accurate positioning;
Jacking precast beam low speed being connect to frame support carries out customization processing; The pre-buried S10 bolt of the prefabricated post at precast beam two ends is supported;
(3) precast plate supports
Wooden frame on jacking is that the 100mm*100mm lumps of wood supports as line;
(4) full assembly structure supports
A, superposed beam dish pin socket joint tool type scaffold:
B, superimposed sheet bracing frame:
Easy construction of the present invention, effective.Easy to implement, solve the Components installation high accuracy such as full precast construction slab column and require the technical barrier of bearing frame high strength, having saved circulation material, improve construction effect.
Below in conjunction with embodiment, the invention will be further described.
Detailed description of the invention
A kind of full assembly structure component positioning supports construction method, comprises the following steps:
(1) prefabricated post diagonal brace is fixed
The support of prefabricated post adopts Interal fixation, adopts the welding of 14mm steel plate;
Before tower crane lifting, supporting steel plate is fixed in prefabricated post by constructor after lifting component to relevant position, after prefabricated post is in place according to the line that surveyor throws in, constructor by the steel pipe support of diagonal brace on supporting steel plate and on the strong point of showing up;
(2) precast beam supports
The support of precast beam adopts speed to connect frame as support system, by the position of each support column unwrapping wire after floor has been cleared up, and accurate positioning;
Jacking precast beam low speed being connect to frame support carries out customization processing; The pre-buried S10 bolt of the prefabricated post at precast beam two ends is supported;
(3) precast plate supports
Wooden frame on jacking is that the 100mm*100mm lumps of wood supports as line;
(4) full assembly structure supports
A, superposed beam dish pin socket joint tool type scaffold:
B, superimposed sheet bracing frame:
This shows excellent effect of the present invention.

Claims (1)

1. a full assembly structure component positioning supports construction method, is characterized in that: comprise the following steps: that (1) prefabricated post diagonal brace is fixed
The support of prefabricated post adopts Interal fixation, adopts the welding of 14mm steel plate;
Before tower crane lifting, supporting steel plate is fixed in prefabricated post by constructor after lifting component to relevant position, after prefabricated post is in place according to the line that surveyor throws in, constructor by the steel pipe support of diagonal brace on supporting steel plate and on the strong point of showing up;
(2) precast beam supports
The support of precast beam adopts speed to connect frame as support system, by the position of each support column unwrapping wire after floor has been cleared up, and accurate positioning;
Jacking precast beam low speed being connect to frame support carries out customization processing; The pre-buried S10 bolt of the prefabricated post at precast beam two ends is supported;
(3) precast plate supports
Wooden frame on jacking is that the 100mm*100mm lumps of wood supports as line;
(4) full assembly structure supports
A, superposed beam dish pin socket joint tool type scaffold:
B, superimposed sheet bracing frame:
CN201410007996.9A 2014-01-08 2014-01-08 Full assembly structure component positioning supports construction method Active CN103726666B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410007996.9A CN103726666B (en) 2014-01-08 2014-01-08 Full assembly structure component positioning supports construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410007996.9A CN103726666B (en) 2014-01-08 2014-01-08 Full assembly structure component positioning supports construction method

Publications (2)

Publication Number Publication Date
CN103726666A CN103726666A (en) 2014-04-16
CN103726666B true CN103726666B (en) 2016-02-17

Family

ID=50450937

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410007996.9A Active CN103726666B (en) 2014-01-08 2014-01-08 Full assembly structure component positioning supports construction method

Country Status (1)

Country Link
CN (1) CN103726666B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476583A (en) * 2017-08-18 2017-12-15 国网上海市电力公司 A kind of concrete assembled building builds construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2411291Y (en) * 2000-03-30 2000-12-20 昆明理工大学 External prestressed structure for integral prestressed prefabricated sheet-pile buidling
JP2005188102A (en) * 2003-12-25 2005-07-14 Shimizu Corp Structure of building and construction method
CN201661086U (en) * 2010-03-15 2010-12-01 中山市快而居房屋预制件有限公司 Fully-prefabricated assembled integral reinforced concrete house
CN203174770U (en) * 2013-04-19 2013-09-04 深圳海龙建筑制品有限公司 Connection structure of prefabricated column and construction site base and building

Also Published As

Publication number Publication date
CN103726666A (en) 2014-04-16

Similar Documents

Publication Publication Date Title
CN102808509B (en) Pouring construction method for anchor assembly of prefabricated concrete prefabricated external wall panel
CN204552050U (en) A kind of anchor ear bearing frame and scaffolding platform assembly
CN106193589B (en) Concrete superelevation heavy type beam and overlapping board combining structure method for supporting
CN104453224A (en) Formwork support structure of basement exterior wall and construction method of formwork support structure
CN103266778B (en) Detachable triangular scaffold and steel truss assembly construction method
CN203938346U (en) Moving staircase girders connection structure
CN111173249B (en) Overhanging support system attached to rectangular beam and column
CN203223003U (en) Detachable triangular jig frame for steel truss assembling
CN203834926U (en) Formwork erecting structure for bare concrete basement exterior wall
CN103726666B (en) Full assembly structure component positioning supports construction method
CN203347205U (en) Overhung scaffold
CN204038921U (en) Wall-attached device for super high-rise tower crane
CN103758342A (en) Tool-type top form for buildings
CN204627001U (en) PC structure floor assembled prefabricated post diagonal brace support system
CN104074275A (en) Prefabricated concrete column connecting joint structure
CN203420359U (en) Rigid connection joint connected through beam columns and capable of bearing overlarge loads in steel structure support system
CN104481163B (en) A kind of L beam construction equipment for building structure reinforcing and method
CN204491420U (en) A kind of reinforcement structure of bracket
CN204059947U (en) A kind of self-stabilization type outer wall formwork of basement support system
CN113914348A (en) Movable modular assembly type tower crane steel bearing platform and mounting method
CN202416351U (en) Supporting frame for retaining wall
CN205242439U (en) Big shaped steel constructs post positioner
CN204826588U (en) Elevator shaft protection operation platform
CN105586830A (en) Bridge template support
CN104846734A (en) Unit-assembly type steel trestle

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Jiang Jian

Inventor after: Jiang Xiaoqian

Inventor after: Cheng Wei

Inventor after: Jiang Xiaobo

Inventor after: Xing Jianfeng

Inventor after: Wu Jun

Inventor after: Zhou Lifei

Inventor before: Cheng Jun

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160105

Address after: 226300, Nantong, Jiangsu province Tongzhou District Jinsha New Town West Building New Village No. 2

Applicant after: Jiang Jian

Applicant after: Jiang Xiaoqian

Address before: Tongzhou District Xingyuan road Jiangsu city of Nantong province sunshine mansion 226300 Building No. 63 room 2208

Applicant before: Cheng Jun

C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201207

Address after: 226300 New Century Avenue 999, Nantong high tech Zone, Jiangsu Province

Patentee after: NANTONG SIJIAN CONSTRUCTION GROUP Co.,Ltd.