CN103683132B - The damaged insulating barrier restorative procedure of transmission pressure - Google Patents

The damaged insulating barrier restorative procedure of transmission pressure Download PDF

Info

Publication number
CN103683132B
CN103683132B CN201310619173.7A CN201310619173A CN103683132B CN 103683132 B CN103683132 B CN 103683132B CN 201310619173 A CN201310619173 A CN 201310619173A CN 103683132 B CN103683132 B CN 103683132B
Authority
CN
China
Prior art keywords
walking mechanism
transmission pressure
insulating barrier
insulating tape
restorative procedure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310619173.7A
Other languages
Chinese (zh)
Other versions
CN103683132A (en
Inventor
张贵民
吕波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Handan Power Supply Co of State Grid Hebei Electric Power Co Ltd
Linzhang Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Handan Power Supply Co of State Grid Hebei Electric Power Co Ltd
Linzhang Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Handan Power Supply Co of State Grid Hebei Electric Power Co Ltd, Linzhang Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310619173.7A priority Critical patent/CN103683132B/en
Publication of CN103683132A publication Critical patent/CN103683132A/en
Application granted granted Critical
Publication of CN103683132B publication Critical patent/CN103683132B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Electric Cable Installation (AREA)

Abstract

The present invention discloses the damaged insulating barrier restorative procedure of a kind of transmission pressure, and fix tool comprises side buckle-type insulating tape, and also comprise one and be articulated in walking mechanism on transmission pressure, the bottom of walking mechanism connects pull rope; Wiring is in succession fastened at the middle part of walking mechanism; The top of walking mechanism is provided with wins hook; Restorative procedure comprises the steps: the side buckle-type insulating tape first intercepting corresponding length; One end of side buckle-type insulating tape is connected with connecting line; A staff carries walking mechanism and climbs the head of the mast, walking mechanism is articulated on transmission pressure; Then while fasten side buckle-type insulating tape, pull pull rope and walking mechanism is walked along transmission pressure, until side buckle-type insulating tape fastens complete and is pulled into damaged insulating barrier place; Finally cut off connecting line, hook and pick hook taking, walking mechanism is taken off.The present invention is simple and efficient, can realize wire reparation without the need to crane, time saving and energy saving, safe and efficient.

Description

The damaged insulating barrier restorative procedure of transmission pressure
Technical field
The present invention relates to a kind of transmission pressure maintaining method, be specifically related to a kind of restorative procedure of transmission pressure insulating barrier.
Background technology
In electric power system, transmission pressure is all generally exposed, in order to ensure carrying out smoothly of power production and construction, safeguards public safety, and China has formulated " protection of electric power facility regulations " and carried out specification people safety utilization of electric power.But in the area that some safety utilizations of electric power consciousness is weaker, electric shock accidents still happens occasionally.In order to reduce with electrification, ensure that the safety and steady of electric power system runs, power department staff attempts to reduce electric shock accidents by coated insulation layer on the transmission line of densely inhabited district.This method implements mainly through following two kinds of approach: 1) apply one or more layers insulating coating in the outside of transmission pressure; 2) on transmission pressure, be set with the insulating barrier be made up of insulating material.
Wherein, 2nd), when approach of planting is implemented, often use a kind of side buckle-type insulating tape, this insulating tape is strip, the size of its Width is greater than the girth of the excircle of wire, is being provided with the buckling device such as felt, buckle along on two sides of its Width.When transmission pressure is set with insulating barrier, by crane, workmen is winched to transmission pressure place, insulating tape is fastened the outside being installed to transmission pressure by workmen, just can complete construction task.
But, because the insulating barrier of transmission pressure outside is chronically exposed to outdoor, be easily subject to the impact of harsh weather and breakage occur.Therefore, power department staff wants regularly to repair transmission pressure external insulation.If the position of breakage appears near electric pole or electric power pylon, so staff only needs climbing can repair easily on the head of the mast or steel tower, if the position of breakage appears in the middle part of the wire between two electric poles, then need, with crane, staff is delivered to wire place just can repair, maintenance cost is higher, and speed is slow, efficiency is low; For the narrow rugged remote districts of some roads, crane cannot drive near transmission pressure, is difficult to repair.
Summary of the invention
The technical issues that need to address of the present invention are to provide a kind of convenient and swift, without the need to crane and the damaged insulating barrier restorative procedure of attainable transmission pressure, to solve in conventional art, transmission pressure insulating barrier rehabilitation cost is high, speed is slow, the problem that do not have crane to construct.
For solving the problems of the technologies described above, the technical solution used in the present invention is as follows:
The damaged insulating barrier restorative procedure of transmission pressure, fix tool used comprises side buckle-type insulating tape, and fix tool used also comprises one and is articulated in the walking mechanism that transmission pressure also can move along transmission pressure, and the bottom of walking mechanism connects pull rope; The middle part of walking mechanism is fastened and is connected to connecting line; The top of walking mechanism is provided with wins hook;
The damaged insulating barrier restorative procedure of described transmission pressure comprises the steps:
The insulating barrier length of a) repairing as required, intercepts the side buckle-type insulating tape of corresponding length;
B) one end of side buckle-type insulating tape is connected with connecting line;
C) staff carries walking mechanism and climbs the head of the mast, walking mechanism is articulated on transmission pressure;
D) two sides of side buckle-type insulating tape fasten to together by the staff of the head of the mast, simultaneously, ground staff pulls pull rope and drives walking mechanism to walk along transmission pressure, until side buckle-type insulating tape fastens complete and is pulled into insulating barrier breakage, cover damaged insulating barrier;
E) cut off the connecting line between side buckle-type insulating tape and walking mechanism, hook and pick hook taking, walking mechanism is taken off.
Further improvement of the present invention is: in described step b), and adopt a pointed cone to open an aperture in the end of side buckle-type insulating tape, connecting line is connected together with side buckle-type insulating tape by aperture.
Further improvement of the present invention is: described walking mechanism comprises the first side wall and the second sidewall that are oppositely arranged, gap is provided with between the first side wall and the second sidewall, the width in gap is 1.2 ~ 1.8 times of transmission pressure diameter, the lower end of the first side wall arranges the camber beam to the second sidewall one lateral buckling, wiring inlet is formed at the bottom of described camber beam and the second sidewall, in described step c), transmission pressure is entered between the first side wall of walking mechanism and the second sidewall by wiring inlet.
Further improvement of the present invention is: between the first side wall and the second sidewall, bearing pin is provided with road wheel, and walking mechanism realizes motion by road wheel on transmission pressure.
Further improvement of the present invention is: in described step d), and ground staff observes the position of insulating barrier breakage by telescope.
Further improvement of the present invention is: in described step e), and ground staff completes the operation of cutting off connecting line as follows:
E1) get a scissors and an expansion link, scissors handheld terminal is fixed on the top of expansion link;
E2) bolt one insulating cord on another handheld terminal of scissors, insulating cord is walked around from expansion link top, then extends to the handheld terminal of expansion link;
E3) the hand-held expansion link of staff, the length of adjustment expansion link, makes connecting line enter in the cutting edge of the scissors at expansion link top;
E4) pull insulating cord that the cutting edge of scissors is closed, cut off connecting line.
Further improvement of the present invention is: in described step e), and ground staff to hook with the expansion link of hook with a top and picks hook taking, thus walking mechanism is taken off.
Owing to have employed technique scheme, the technological progress that the present invention obtains is as follows:
The present invention is simple and efficient, time saving and energy saving, by installing a walking mechanism on transmission pressure, the pull rope that walking mechanism is pulled by staff on ground provides power, and side buckle-type insulating tape is pulled the breakage of transmission pressure insulating barrier, the technical problem that the wire insulation solved in conventional art between two electric poles must rely on crane to repair, significantly decrease construction cost, and when adopting this method to repair, do not rely on main equipment, instrument is easy to carry, flexible operation mode, there is speed fast, efficiency is high, the advantage that fail safe is good.
In the present invention, walking mechanism realizes motion by road wheel on transmission pressure, in the course of work, when the staff be positioned at below wire pulls pull rope, can make road wheel tightly be pressed on transmission pressure, both wire can have been avoided to rock, can make again to form rolling friction between road wheel and transmission pressure, avoid the wearing and tearing of transmission pressure.
In the present invention, the operation of cutting off connecting line has been come by ground staff, by scissors handheld terminal is fixed on expansion link, another handheld terminal carrys out remote operation by insulating cord, can complete in any position of transmission pressure and cut off operation, there is the advantage that fast and easy, fail safe are high.
Accompanying drawing explanation
Fig. 1: the structural representation of equipment therefor of the present invention;
The right view of Fig. 2: Fig. 1;
Wherein: 1. walking mechanism, 11. the first side walls, 12. second sidewalls, 13. road wheels, 14. wiring inlets, 15. camber beams, 16. win hook, 2. bail, 21. pull ropes, 3. connecting hole.
Embodiment
Do further to describe in detail to the present invention below in conjunction with the drawings and specific embodiments:
The damaged insulating barrier restorative procedure of transmission pressure, the fix tool used comprises side buckle-type insulating tape, and a prosthetic device as depicted in figs. 1 and 2.Prosthetic device comprises walking mechanism 1, bail 2 and connecting hole 3.
Walking mechanism 1 comprises the first side wall 11 and the second sidewall 12, and the first side wall 11 together with the welded top of the second sidewall 12, and is fixed welding one win hook 16 at the position of welding.The first side wall 11 and the second sidewall 12 are oppositely arranged, and the distance between the first side wall 11 and the second sidewall 12 is 1.2 ~ 1.8 times of transmission pressure diameter dimension.Be provided with a bearing pin between the first side wall 11 and the second sidewall 12, bearing pin be provided with road wheel 13.The bottom of the first side wall 11 is provided with towards the bending camber beam 15 of the second sidewall 12, and the lower end of camber beam 15 and the second sidewall 12 forms wiring inlet 14.
Bail 2 is fixedly installed on the below of walking mechanism 1.Bail 2 is fixedly welded on the bottom of camber beam 15.In bail 2, bolt hangs with pull rope 21, and pull rope 21 provides power for the motion for walking mechanism.
Connecting hole 3 is fixedly installed on the middle part of walking mechanism 1.Connecting hole 3 is the circular holes being arranged on the second sidewall 12 bottom, and in circular hole, bolt hangs with connecting line.
The damaged insulating barrier restorative procedure of described transmission pressure comprises the steps:
A) according to the length of insulating barrier damaged on transmission pressure, the side buckle-type insulating tape of corresponding length is intercepted;
B) open an aperture with a pointed cone in the end of side buckle-type insulating tape, connecting line is connected together with side buckle-type insulating tape by aperture;
C) staff carries walking mechanism and climbs the head of the mast, walking mechanism is articulated on transmission pressure, and during mounting, transmission pressure enters between the first side wall of walking mechanism and the second sidewall by wiring inlet;
D) staff of the head of the mast is responsible for two sides of side buckle-type insulating tape to fasten to together, simultaneously, ground staff pulls pull rope along the bearing of trend of transmission pressure, now, walking mechanism is subject to the pulling force towards front lower place, road wheel between the first side wall and the second sidewall can compress transmission pressure, walking mechanism realizes motion by road wheel on transmission pressure, until side buckle-type insulating tape fastens complete and is pulled to insulating barrier breakage, cover damaged insulating barrier; In drawing process, ground staff can observe the position of insulating barrier breakage by telescope, to ensure that wire insulation breakage is completely covered;
E) get a scissors and an expansion link, scissors handheld terminal is fixed on the top of expansion link; Bolt one insulating cord on another handheld terminal of scissors, insulating cord is walked around from expansion link top, then extends to the handheld terminal of expansion link; The hand-held expansion link of staff, the length of adjustment expansion link, makes connecting line enter in the cutting edge of the scissors at expansion link top; Pull insulating cord that the cutting edge of scissors is closed, cut off connecting line; With a top with hook expansion link hook pick hook taking, walking mechanism is taken off and can complete reparation task.

Claims (7)

1. the damaged insulating barrier restorative procedure of transmission pressure, fix tool used comprises side buckle-type insulating tape, it is characterized in that: fix tool used also comprises one and is articulated in the walking mechanism of moving on transmission pressure and along transmission pressure, the bottom of walking mechanism connects pull rope; The middle part of walking mechanism is fastened and is connected to connecting line; The top of walking mechanism is provided with wins hook;
The damaged insulating barrier restorative procedure of described transmission pressure comprises the steps:
The insulating barrier length of a) repairing as required, intercepts the side buckle-type insulating tape of corresponding length;
B) one end of side buckle-type insulating tape is connected with connecting line;
C) staff carries walking mechanism and climbs the head of the mast, walking mechanism is articulated on transmission pressure;
D) two sides of side buckle-type insulating tape fasten to together by the staff of the head of the mast, simultaneously, ground staff pulls pull rope and drives walking mechanism to walk along transmission pressure, until side buckle-type insulating tape fastens complete and is pulled into insulating barrier breakage, cover damaged insulating barrier;
E) cut off the connecting line between side buckle-type insulating tape and walking mechanism, hook and pick hook taking, walking mechanism is taken off.
2. the damaged insulating barrier restorative procedure of transmission pressure according to claim 1, it is characterized in that: in described step b), adopt a pointed cone to open an aperture in the end of side buckle-type insulating tape, connecting line is connected together with side buckle-type insulating tape by aperture.
3. the damaged insulating barrier restorative procedure of transmission pressure according to claim 1, it is characterized in that: described walking mechanism comprises the first side wall and the second sidewall that are oppositely arranged, gap is provided with between the first side wall and the second sidewall, the width in gap is 1.2 ~ 1.8 times of transmission pressure diameter, the lower end of the first side wall arranges the camber beam to the second sidewall one lateral buckling, wiring inlet is formed at the bottom of described camber beam and the second sidewall, in described step c), transmission pressure is entered between the first side wall of walking mechanism and the second sidewall by wiring inlet.
4. the damaged insulating barrier restorative procedure of transmission pressure according to claim 3, it is characterized in that: between the first side wall and the second sidewall, bearing pin is provided with road wheel, walking mechanism realizes motion by road wheel on transmission pressure.
5. the damaged insulating barrier restorative procedure of transmission pressure according to claim 1, it is characterized in that: in described step d), ground staff observes the position of insulating barrier breakage by telescope.
6. the damaged insulating barrier restorative procedure of transmission pressure according to claim 1, it is characterized in that: in described step e), ground staff completes the operation of cutting off connecting line as follows:
E1) get a scissors and an expansion link, scissors handheld terminal is fixed on the top of expansion link;
E2) bolt one insulating cord on another handheld terminal of scissors, insulating cord is walked around from expansion link top, then extends to the handheld terminal of expansion link;
E3) the hand-held expansion link of staff, the length of adjustment expansion link, makes connecting line enter in the cutting edge of the scissors at expansion link top;
E4) pull insulating cord that the cutting edge of scissors is closed, cut off connecting line.
7. the damaged insulating barrier restorative procedure of transmission pressure according to claim 1, is characterized in that: in described step e), and ground staff picks hook taking with a top with the expansion link hook of hook, thus walking mechanism is taken off.
CN201310619173.7A 2013-11-29 2013-11-29 The damaged insulating barrier restorative procedure of transmission pressure Active CN103683132B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310619173.7A CN103683132B (en) 2013-11-29 2013-11-29 The damaged insulating barrier restorative procedure of transmission pressure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310619173.7A CN103683132B (en) 2013-11-29 2013-11-29 The damaged insulating barrier restorative procedure of transmission pressure

Publications (2)

Publication Number Publication Date
CN103683132A CN103683132A (en) 2014-03-26
CN103683132B true CN103683132B (en) 2016-03-02

Family

ID=50319821

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310619173.7A Active CN103683132B (en) 2013-11-29 2013-11-29 The damaged insulating barrier restorative procedure of transmission pressure

Country Status (1)

Country Link
CN (1) CN103683132B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105071308B (en) * 2015-09-10 2017-03-01 江苏省电力公司金湖县供电公司 Method for repairing damaged cable
CN108599032B (en) * 2018-07-12 2023-10-20 国网江苏省电力有限公司扬州供电分公司 Overhead cable epidermis restorer

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3819764A1 (en) * 1988-06-10 1989-12-21 Joachim Wuest Method and device for insulating short cable sections, in particular in the region of cable connections
CN202042837U (en) * 2011-01-24 2011-11-16 湖州电力局 Insulating rod adhesive tape winding device
CN102340116A (en) * 2011-09-02 2012-02-01 巩义市供电公司 Method for connecting ground wire of power cable terminal

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3819764A1 (en) * 1988-06-10 1989-12-21 Joachim Wuest Method and device for insulating short cable sections, in particular in the region of cable connections
CN202042837U (en) * 2011-01-24 2011-11-16 湖州电力局 Insulating rod adhesive tape winding device
CN102340116A (en) * 2011-09-02 2012-02-01 巩义市供电公司 Method for connecting ground wire of power cable terminal

Also Published As

Publication number Publication date
CN103683132A (en) 2014-03-26

Similar Documents

Publication Publication Date Title
CN103227431B (en) 220kV long span super high town suspension insulator charged for replacement method
CN209271749U (en) A kind of cable spray robot that cable is visual
CN204030456U (en) A kind of cable unreeling rack
CN105490213A (en) Equipment and method for installing wires of overhead power transmission line
CN103872622B (en) Built on stilts cable laying tractor and Special-purpose lifting instrument thereof
CN102545100A (en) Live installation tool for space bar of twin-bundled conductor
CN105186378A (en) Power transmission line channel crossing protection mechanism
CN206309110U (en) Electric pole pole centralizing device
CN103683132B (en) The damaged insulating barrier restorative procedure of transmission pressure
CN104410005A (en) Operation method for replacing overhead conductor and ground wire
CN203813314U (en) Elevating device
CN104196255A (en) Mobile safety net hanging method for plant roof installation
CN103390869B (en) A kind of high-tension cable repairing crossing frame
CN202495706U (en) Electrified installation tool for double split conductor spacer
CN205442567U (en) Steel -pipe pole operation platform
CN204376311U (en) The heavy electric power cable high-altitude of lifting formula is handed over across unfolding device
CN102182181B (en) Device for lowering anchor cable
CN201490619U (en) Cable monitoring equipment for power high-voltage line construction field
KR100974321B1 (en) Electric wire tension method using portable motor operated winch
CN203439984U (en) Handjack for pole
CN204216485U (en) A kind of transmission line show line device
CN205882560U (en) Special circulation cord rack device of distribution live working earth potential
CN104113014A (en) Upward carrying wire lifting trolley
CN203652959U (en) Gas well wire barrow integrating manual operation and electromotion
CN203631213U (en) Device for cladding insulating tape on transmission conductor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant