CN103669331A - 高速铁路流塑状软土地基加固方法 - Google Patents

高速铁路流塑状软土地基加固方法 Download PDF

Info

Publication number
CN103669331A
CN103669331A CN201310721888.3A CN201310721888A CN103669331A CN 103669331 A CN103669331 A CN 103669331A CN 201310721888 A CN201310721888 A CN 201310721888A CN 103669331 A CN103669331 A CN 103669331A
Authority
CN
China
Prior art keywords
speed railway
foundation
plastic
stream
flow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310721888.3A
Other languages
English (en)
Inventor
史存林
张千里
叶阳升
蔡德钩
熊建珍
姚建平
杜晓燕
闫宏业
陈锋
宣言
孙加林
马莉
程爱君
王立军
程远水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Railway Engineering Research Institute of CARS
Original Assignee
Railway Engineering Research Institute of CARS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Railway Engineering Research Institute of CARS filed Critical Railway Engineering Research Institute of CARS
Priority to CN201310721888.3A priority Critical patent/CN103669331A/zh
Publication of CN103669331A publication Critical patent/CN103669331A/zh
Pending legal-status Critical Current

Links

Abstract

一种高速铁路流塑状软土地基加固方法,该方法是采用水泥粉煤灰碎石桩(CFG桩)联合排水固结两种地基处理方法对高速铁路流塑状软土地基进行价格,它包括如下步骤:首先查明流塑状软土的有关物理力学指标,确定采用水泥粉煤灰碎石桩(CFG桩)处理前,流塑状软土的粘聚力C,和内摩擦角φ需要达到的要求;在待加固的高速铁路流塑状软土地基采用排水固结处理;待排水固结土体达到设计要求的强度后,在待加固地基中进行CFG桩施工,即完成高速铁路流塑状软土地基的加固处理。水泥粉煤灰碎石桩(CFG桩)联合排水固结技术与传统的单一技术相比,充分发挥了两种地基处理方法的优点,安全质量可控,确保了高速铁路运营的安全。

Description

高速铁路流塑状软土地基加固方法
技术领域
本发明属于高速铁路地基处理技术领域,具体指一种高速铁路流塑状软土地基的加固方法。
背景技术
目前高速铁路软土地基处理大量采用桩体较强的CFG桩、管桩以及钢筋混凝土灌注桩等刚性桩。打入桩处理流塑状软土施工时,由于振动作用引起软土触变变形,造成加固区以外建筑物造成外挤、隆起的现象,影响建筑物的使用安全,某线施工时就发生临近的既有线变形。沿海铁路在路基填筑期间就曾出现桩体倾斜、边坡坍塌等问题,而且运营仅2年已经出现路基失稳、下沉等问题,部分区段路基沉降多达几十厘米。流塑状软土地基出现以上问题的主要原因有以下2个方面:
(1)采用CFG桩或搅拌桩处理深厚流塑状软土时,会对周边软土有扰动破坏作用,进行路基填筑时,桩可能会出现剪切、倾斜和弯曲的破坏现象。这种破坏类似于多米诺骨牌的效应,使路基快速产生外挤、下沉和开裂变形的破坏,对于搅拌桩的地基处理,在圆弧滑动破坏过程中,实际会出现桩的拉伸破坏和弯曲破坏同时发生。
(2)对于流塑状软土地层采用搅拌桩、CFG桩等进行地基处理时,桩网结构路堤的整体稳定性滑弧检算应考虑排桩受软基附加侧向荷载的外挤作用力及施工填筑过程中侧排桩的倾斜因素。以往所有的设计计算软件中都未考虑这些因素,稳定检算看似安全,但实际路基填筑过程中还出现多起失稳破坏的案例。
目前大量基础工程流塑状软土地基采用刚性桩复合地基处理,但设计方法存在问题,需要深入开展流塑状软土复合地基失效机理的研究,提出我国大面积流塑状软土地基的处理可靠的地基处理方法,避免工程事故,减少国家经济损失。为高速公路、高速铁路和机场地基流塑状软土地基处理和运营期间的养护维修提供技术理论支持。
发明内容
本发明的目的就是针对上述技术背景,提供一种高速铁路流塑状软土地基加固方法,该方法首先采用排水固结提高流塑状软土地基的强度,使其达到水泥粉煤灰桩(CFG桩)施工的条件,然后采用CFG桩进行地基处理,确保高速铁路路基足够稳定安全。为实现此目的,本发明所设计的高速铁路流塑状软土地基加固的方法,它包括如下步骤:
(1)查明流塑状软土的有关物理力学指标。确定采用水泥粉煤灰碎石桩(CFG桩)处理前,流塑状软土的粘聚力C,和内摩擦角φ需要达到的要求。
(2)在待加固的高速铁路流塑状软土地基采用排水固结处理;
(3)待排水固结土体达到设计要求的强度后,在待加固地基中进行CFG桩施工,即完成高速铁路流塑状软土地基的加固处理。
在所述步骤(1)中,首先对待处理的地基进行全面的地质勘探,包括现场十字板剪切试验和室内剪切试验,查明流塑状软土的粘聚力C,和内摩擦角φ。采用圆弧滑动法对路基的稳定性进行检算,确定流塑状软土地基需要达到的强度指标。稳定检算过程中,CFG桩的抗剪强度应根据流塑状软土的强度变化适当进行折减,稳定系数Fs依据高速铁路列车设计行车速度进行选择。
在所述步骤(2)中,依据步骤(1)确定的流塑状软土的强度指标,选择合适的排水固结施工方法,确定排水系统和加载系统的形式。排水系统选择塑料排水板,宽度10cm,厚度5mm,长度大于地基处理的深度,采用专门的插板机施工。加载系统可以考虑堆载法、真空预压、降低水位法、真空预压联合堆载法。
在所述步骤(2)前,在地基中布置孔隙水压力测试传感器,在路肩设置沉降观测桩,并在坡脚外设置两排侧斜观测桩。
所述的水泥粉煤灰碎石桩(CFG桩)的桩径范围为350~600mm,方形布置,桩间距取3~5倍桩径。CFG桩施工时采用跳桩施工,沿纵向间距3~5根桩施工,避免施工过程对相邻产生扰动,影响成桩质量。
排水固结施工期间,应加强地面沉降、孔隙水压力、水平位移观测,水平位移和地面沉降不超出20mm/天,孔隙水压力与荷载之比控制在小于0.5~0.6。
本发明采用水泥粉煤灰碎石桩(CFG桩)联合排水固结技术对高速铁路流塑状软土地基进行加处理,它具有如下优点:
(1)本发明专利提出了高速铁路流塑状软土地基处理的一种新型方法,解决了以往流塑状软土地基处理过程出现的各种问题,该方法采用常规两种地基处理:CFG桩和排水固结法,发挥两种方法的优点,达到了良好的加固效果。
(2)采用水泥粉煤灰碎石桩(CFG桩)联合排水固结技术可以避免以往单独采用CFG桩施工过程中出现的桩体破坏,地基失稳的问题。
(3)采用水泥粉煤灰碎石桩(CFG桩)联合排水固结技术相比单独的排水固结处理方法,大大缩减了地基处理时间。
综上所述,水泥粉煤灰碎石桩(CFG桩)联合排水固结技术与传统的单一技术相比,充分发挥了两种地基处理方法的优点,安全质量可控,确保了高速铁路运营的安全。
附图说明:
图1为本发明中高速铁路流塑状软土地基加固后的一种结构示意图
其中:1-水泥粉煤灰碎石桩(CFG桩)、2-流塑状软土地基、3-路基、4-孔隙水压力探头、5-塑料排水板、6-坡脚、7-路肩、8-侧斜观测桩。
具体实施方式:
以下结合附图和具体实施对本发明作进一步的详细说明:
一种高速铁路流塑状软土地基加固方法,它包括如下步骤:
1)在待加固地基进行十字板剪切试验,并取原状土样进行室内剪切试验,确定流塑软土的强度指标:粘聚力C,和内摩擦角φ。采用圆弧滑动法对路基的稳定性进行检算,确定流塑状软土地基采用CFG桩加固需要达到的强度指标。
2)在待加固路基3的路肩7设置观测桩,并在坡脚6处设置一排观测桩8,观测桩8的纵向间距为10m,用来监测排水固结过程中路基沉降和水平位移。在流塑状软土地基2中不同深度处埋设孔隙水压力探头4,用来测试排水固结施工过程中监测孔隙水压力的变化。
3)在地基2中采用专门的插板机将塑料排水板按照一定的间隔插入到流塑状软土地基中,形成排水系统。塑料排水板,宽度10cm,厚度5mm,长度大于地基处理的深度。
4)在地基表面进行堆载,施工过程中加强地面沉降、水平位移观测、孔隙水压力观测。排水固结施工所完成的沉降变形和平均固结度应满足设计要求,检验数量为每3000m2抽样检验6点。必要时,应对预压完成的地基土进行原位十字板剪切试验、室内土工试验及荷载试验。
5)排水固结加固后地基土体的强度达到设计要求后,卸掉地基面堆载,按照设计要求进行CFG桩施工。
6)CFG桩施工过程和施工完成后应对CFG桩进行桩身完整性、均匀性、桩身强度、单桩或复合地基承载力等。成桩7天内,可采用低应变检查桩身完整性,检查数量为施工总桩数的10%,且不少于3根。成桩28天后,应在桩中心处、桩长范围内垂直钻孔取芯,观察桩体完整性、均匀性,在桩身上、中、下取不同深度的不少于3个试样作抗压强度试验。检验数量为施工总桩数的2‰,且不少于3根。CFG桩宜在成桩28天后,进行单桩或复合地基载荷试验,检验数量为总桩数的2‰,且不少于3根。
本说明书中未作详细描述的内容属于本领域专业技术人员公知的现有技术。

Claims (1)

1.一种高速铁路流塑状软土地基加固方法,其特征在于,它包括如下步骤:
1)查明流塑状软土的有关物理力学指标。确定采用水泥粉煤灰碎石桩(CFG桩)处理前,流塑状软土的粘聚力C,和内摩擦角φ需要达到的要求。
2)在待加固的高速铁路流塑状软土地基采用排水固结处理;
3)待排水固结土体达到设计要求的强度后,在待加固地基中进行CFG桩施工,即完成高速铁路流塑状软土地基的加固处理。
CN201310721888.3A 2013-12-25 2013-12-25 高速铁路流塑状软土地基加固方法 Pending CN103669331A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310721888.3A CN103669331A (zh) 2013-12-25 2013-12-25 高速铁路流塑状软土地基加固方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310721888.3A CN103669331A (zh) 2013-12-25 2013-12-25 高速铁路流塑状软土地基加固方法

Publications (1)

Publication Number Publication Date
CN103669331A true CN103669331A (zh) 2014-03-26

Family

ID=50308046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310721888.3A Pending CN103669331A (zh) 2013-12-25 2013-12-25 高速铁路流塑状软土地基加固方法

Country Status (1)

Country Link
CN (1) CN103669331A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104746507A (zh) * 2015-04-01 2015-07-01 江苏建院营造有限公司 一种建筑垃圾再生排水cfg桩地基及其施工方法
CN109778831A (zh) * 2018-11-28 2019-05-21 中交一公局桥隧工程有限公司 夯扩挤密碎石桩加固杂填土地基施工工法
CN111501722A (zh) * 2020-05-21 2020-08-07 中铁工程设计咨询集团有限公司 一种真空预压联合cfg长短组合桩地基处理方法
CN111576387A (zh) * 2020-05-29 2020-08-25 中铁隧道局集团有限公司 一种含水量偏大的软土地基处理方法
CN111997038A (zh) * 2020-08-24 2020-11-27 丁思华 一种在抛填块石层下实施深层软土加固和置换处理的工法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1439778A (zh) * 2003-02-20 2003-09-03 河海大学 水泥粉煤灰碎石桩在高速公路软基处理中的施工方法
CN1793519A (zh) * 2005-12-29 2006-06-28 徐士龙 快速“高真空击密、桩基”复合软地基处理方法
CN101024951A (zh) * 2007-03-16 2007-08-29 陈俊生 一种地基处理方法
CN101220588A (zh) * 2007-01-09 2008-07-16 同济大学 一种软基处理方法
CN102011391A (zh) * 2010-11-11 2011-04-13 河北建设勘察研究院有限公司 一种软弱地基的加固处理方法
JP2012012878A (ja) * 2010-07-02 2012-01-19 Fudo Tetra Corp 地下空洞部を有する地盤の改良工法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1439778A (zh) * 2003-02-20 2003-09-03 河海大学 水泥粉煤灰碎石桩在高速公路软基处理中的施工方法
CN1793519A (zh) * 2005-12-29 2006-06-28 徐士龙 快速“高真空击密、桩基”复合软地基处理方法
CN101220588A (zh) * 2007-01-09 2008-07-16 同济大学 一种软基处理方法
CN101024951A (zh) * 2007-03-16 2007-08-29 陈俊生 一种地基处理方法
JP2012012878A (ja) * 2010-07-02 2012-01-19 Fudo Tetra Corp 地下空洞部を有する地盤の改良工法
CN102011391A (zh) * 2010-11-11 2011-04-13 河北建设勘察研究院有限公司 一种软弱地基的加固处理方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
姚建平等: "流塑状软土复合地基失效机理及处理方法研究", 《第十四届中国科协年会第13分会场:软土路基工程技术研讨会论文集》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104746507A (zh) * 2015-04-01 2015-07-01 江苏建院营造有限公司 一种建筑垃圾再生排水cfg桩地基及其施工方法
CN109778831A (zh) * 2018-11-28 2019-05-21 中交一公局桥隧工程有限公司 夯扩挤密碎石桩加固杂填土地基施工工法
CN111501722A (zh) * 2020-05-21 2020-08-07 中铁工程设计咨询集团有限公司 一种真空预压联合cfg长短组合桩地基处理方法
CN111501722B (zh) * 2020-05-21 2022-06-03 中铁工程设计咨询集团有限公司 一种真空预压联合cfg长短组合桩地基处理方法
CN111576387A (zh) * 2020-05-29 2020-08-25 中铁隧道局集团有限公司 一种含水量偏大的软土地基处理方法
CN111997038A (zh) * 2020-08-24 2020-11-27 丁思华 一种在抛填块石层下实施深层软土加固和置换处理的工法

Similar Documents

Publication Publication Date Title
CN103669331A (zh) 高速铁路流塑状软土地基加固方法
CN103276639B (zh) 一种深厚层松软土地区的路基结构
CN202227214U (zh) 高速铁路深厚软土地基路堤构造
CN201495468U (zh) 处于湿地软基处的公路路基结构
CN203346750U (zh) 一种深厚层松软土地区的长短桩桩筏结构路基
CN204940030U (zh) 改扩建工程新旧路基路面拼接结构
CN204401385U (zh) 一种处理深厚软土岩溶地基的路基结构
CN101962929B (zh) 一种新型桩承式加筋技术处理软土路基的方法
CN202830649U (zh) 微扰动既有高速铁路路基变形病害整治结构
CN105220680B (zh) 一种排水松木桩加固软黏土地基的施工方法
Cheng et al. An innovative Geonail system for soft ground stabilization
Zhang et al. Numerical modeling of floating geosynthetic-encased stone column–supported embankments with basal reinforcement
CN202672162U (zh) 一种复合式支挡结构
CN104532714A (zh) 一种处理深厚软土岩溶地基的路基结构
CN206233257U (zh) 一种加固倾斜软基的组合型复合地基
CN203007761U (zh) 一种运行条件下既有铁路路基钢花管注浆加固结构
CN205420939U (zh) 双向螺旋挤土灌注桩桩网的路基结构
CN202787211U (zh) 低强度刚性桩-透水性混凝土桩新型二元复合地基
Zhai et al. Experimental study and numerical analysis on bearing characteristics of large diameter ultra long bored piles with post grouting on the tip and side
CN203373764U (zh) 一种砼芯砂石桩复合地基
CN103449784B (zh) 适用于膨胀土地区铁路路堑基床的水泥基防水抗裂材料
CN204662417U (zh) 一种深厚软土区水塘路基地基加固结构
CN101793037B (zh) 堆石体道基高填方结构表面沉降速率法
CN205024667U (zh) 一种排水松木桩加固软黏土地基
CN203200739U (zh) 公路路基碎石桩

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140326