CN103646315A - Method and device for data processing in electricity bureau engineering project workflow - Google Patents

Method and device for data processing in electricity bureau engineering project workflow Download PDF

Info

Publication number
CN103646315A
CN103646315A CN201310690120.4A CN201310690120A CN103646315A CN 103646315 A CN103646315 A CN 103646315A CN 201310690120 A CN201310690120 A CN 201310690120A CN 103646315 A CN103646315 A CN 103646315A
Authority
CN
China
Prior art keywords
task
flow nodes
node
project
approval
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310690120.4A
Other languages
Chinese (zh)
Inventor
方志杰
陆凯华
谢锦文
黄晓波
叶丹
杨萍
叶观兴
何璟峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Jiande Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Jiande Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd, Jiande Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310690120.4A priority Critical patent/CN103646315A/en
Publication of CN103646315A publication Critical patent/CN103646315A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a method and a device for data processing in an electricity bureau engineering project workflow. According to the method, each node is arranged in a computer, a task of a present node can be acquired by a computer according to context information of the present node and a previous mode, the task is sent to the present node, artificial transmission is not needed, and work efficiency is improved.

Description

Data processing method and device in power office's engineering project work stream
Technical field
The present invention relates to data processing field, in particular, relate to data processing method and device in power office's engineering project work stream.
Background technology
Development along with informatization, the application of workflow is more and more universal, and each business process system is managed more clearly and be flexible, simultaneously, business process system is also more and more higher to the requirement of workflow, and basic application cannot meet the demand of business process system.
In prior art, the engineering project work stream of power office is to take paper list as carrier, in workflow, the mode of each working node data transmission is the mode of transmitting with manual, after the artificial audit of a certain working node is passed through, artificially by manual next working node that is passed to of corresponding data, one-level one-level is signed after examination like this, and work efficiency is very low.
Summary of the invention
In view of this, the invention provides data processing method and device in a kind of power office engineering project work stream, to overcome the very low problem of work efficiency in prior art.
For achieving the above object, the invention provides following technical scheme:
A data processing method in power office's engineering project work stream, comprising:
The first task creating;
The described first task creating is sent to audit project verification flow nodes;
Detect audit project verification flow nodes by first task after, generate the indication that triggers Project design flow nodes;
According to the contextual information of described audit project verification flow nodes and described Project design flow nodes, determine the second task corresponding to described Project design flow nodes;
Described the second task is sent to described Project design flow nodes;
After described Project design flow nodes being detected the second task being disposed, generate the indication that triggers construction bid approval process node;
According to the contextual information of described construction bid approval process node and described Project design flow nodes, determine the 3rd task that described construction bid approval process node is corresponding;
Described the 3rd task is sent to described construction bid approval process node;
After described construction bid approval process node being detected the 3rd task being disposed, generate the indication that triggers contract approval flow nodes;
According to the contextual information of described contract approval flow nodes and described construction bid approval process node, determine the 4th task corresponding to described contract approval flow nodes;
Described the 4th task is sent to described contract approval flow nodes;
After described contract approval flow nodes being detected the 4th task being disposed, generate the indication that triggers the license approval process node that goes into operation;
According to the contextual information of described go into operation license approval process node and described contract approval flow nodes, the 5th task corresponding to license approval process node goes into operation described in determining;
The license approval process that goes into operation described in described the 5th task is sent to node;
After the license approval process that goes into operation described in detecting node is disposed the 5th task, generate the indication that triggers asset disposal approval flow nodes;
According to the contextual information of described go into operation license approval process node and described asset disposal approval flow nodes, determine the 6th task corresponding to described asset disposal approval flow nodes;
Described the 6th task is sent to described asset disposal approval flow nodes;
After described asset disposal approval flow nodes being detected the 6th task being disposed, generate the indication that triggers final acceptance of construction flow nodes;
According to the contextual information of described final acceptance of construction flow nodes and described asset disposal approval flow nodes, determine the 7th task corresponding to described final acceptance of construction flow nodes;
Described the 7th task is sent to described final acceptance of construction flow nodes;
After described final acceptance of construction flow nodes being detected the 7th task being disposed, generate the indication that triggers project final accounting approval process node;
According to the contextual information of described final acceptance of construction flow nodes and described project final accounting approval process node, determine the 8th task that described project final accounting approval process node is corresponding;
Described the 8th task is sent to described project final accounting approval process node;
After described project final accounting approval process node being detected the 8th task being disposed, result is fed back to destination node.
Wherein, after the first task of described establishment, also comprise:
When project information corresponding to described first task is the bundling project of electrical network overhaul, described first task is sent to engineering contact single process node;
After described engineering contact single process node being detected described first task being completed, result is fed back to described destination node.
Wherein, after described generation triggers the indication of the license approval process node that goes into operation, trigger the indication of asset disposal approval flow nodes in described generation before, also comprise:
After first pass node being detected and being triggered, the 9th task that described first pass node is corresponding is sent to described first pass node, and described first pass node comprises in project modification process node, management intermediate acceptance flow nodes and supervising engineer notice flow nodes one or more;
Described first pass node detected and complete after described the 8th task, carry out the operation that described generation triggers the indication of asset disposal approval flow nodes.
Wherein, described audit project verification flow nodes comprises that task completes deadline information and staff's contact method information, described detect audit project verification flow nodes by first task after, before generating the indication that triggers Project design flow nodes, also comprise:
Calculate the differential time of current time and initial time, the time that described audit project verification flow nodes receives described first task is described initial time;
When described differential time is more than or equal to described task and completes deadline information, according to described staff's contact method information, to relevant work personnel, send warning message.
Wherein, before the first task of described establishment, also comprise:
When receiving user and increasing the indication of the second flow nodes, judge described user's class information;
When described circle information is greater than pre-set level, increase described the second flow nodes.
A data processing equipment in power office's engineering project work stream, comprising:
Creation module, for the first task creating;
The first sending module, for being sent to the described first task creating audit project verification flow nodes;
The first generation module, for detection of to audit project verification flow nodes by first task after, generate the indication that triggers Project design flow nodes;
The first determination module, for according to the contextual information of described audit project verification flow nodes and described Project design flow nodes, determines the second task corresponding to described Project design flow nodes;
The second sending module, for being sent to described Project design flow nodes by described the second task;
The second generation module, after the second task being disposed to described Project design flow nodes, generates the indication that triggers construction bid approval process node;
The second determination module, for according to the contextual information of described construction bid approval process node and described Project design flow nodes, determines the 3rd task that described construction bid approval process node is corresponding;
The 3rd sending module, for being sent to described construction bid approval process node by described the 3rd task;
The 3rd generation module, after the 3rd task being disposed to described construction bid approval process node, generates the indication that triggers contract approval flow nodes;
The 3rd determination module, for according to the contextual information of described contract approval flow nodes and described construction bid approval process node, determines the 4th task corresponding to described contract approval flow nodes;
The 4th sending module, for being sent to described contract approval flow nodes by described the 4th task;
The 4th generation module, after the 4th task being disposed to described contract approval flow nodes, generates the indication that triggers the license approval process node that goes into operation;
The 4th determination module, for the contextual information of go into operation described in basis license approval process node and described contract approval flow nodes, the 5th task corresponding to license approval process node goes into operation described in determining;
The 5th sending module, for the license approval process node that goes into operation described in described the 5th task is sent to;
The 5th generation module, for detection of to described in go into operation after license approval process node is disposed the 5th task, generate the indication that triggers asset disposal approval flow nodes;
The 5th determination module, for the contextual information of go into operation described in basis license approval process node and described asset disposal approval flow nodes, determines the 6th task corresponding to described asset disposal approval flow nodes;
The 6th sending module, for being sent to described asset disposal approval flow nodes by described the 6th task;
The 6th generation module, after the 6th task being disposed to described asset disposal approval flow nodes, generates the indication that triggers final acceptance of construction flow nodes;
The 6th determination module, for according to the contextual information of described final acceptance of construction flow nodes and described asset disposal approval flow nodes, determines the 7th task corresponding to described final acceptance of construction flow nodes;
The 7th sending module, for being sent to described final acceptance of construction flow nodes by described the 7th task;
The 7th generation module, after the 7th task being disposed to described final acceptance of construction flow nodes, generates the indication that triggers project final accounting approval process node;
The 7th determination module, for according to the contextual information of described final acceptance of construction flow nodes and described project final accounting approval process node, determines the 8th task that described project final accounting approval process node is corresponding;
The 8th sending module, for being sent to described project final accounting approval process node by described the 8th task;
The 9th sending module, after the 8th task being disposed to described project final accounting approval process node, feeds back to destination node by result.
Wherein, also comprise:
The tenth sending module, for after the first task of described establishment, when project information corresponding to described first task is the bundling project of electrical network overhaul, is sent to engineering contact single process node by described first task;
Feedback module, after described first task being completed to described engineering contact single process node, feeds back to described destination node by result.
Wherein, also comprise:
Send task module, after being triggered to first pass node, the 9th task that described first pass node is corresponding is sent to described first pass node, and described first pass node comprises in project modification process node, management intermediate acceptance flow nodes and supervising engineer notice flow nodes one or more;
Trigger module, for detection of completing after described the 8th task to described first pass node, triggers described the 5th generation module.
Wherein, described audit project verification flow nodes comprises that task completes deadline information and staff's contact method information, and described device also comprises:
Computing module, for calculating the differential time of current time and initial time, the time that described audit project verification flow nodes receives described first task is described initial time;
Alarm module, while completing deadline information for being more than or equal to described task when described differential time, sends warning message according to described staff's contact method information to relevant work personnel.
Wherein, also comprise:
Judge module, while increasing the indication of the second flow nodes for receiving user, judges described user's class information;
Increase module, for when described circle information is greater than pre-set level, increase described the second flow nodes.
Known via above-mentioned technical scheme, compared with prior art, the embodiment of the present invention provides a kind of engineering project work stream data processing method of power office, the method by each Node configuration in computing machine, computing machine, according to the contextual information of present node and a upper node, can obtain the task of present node, thereby task is sent to present node, and do not need manually to transmit, thereby improved work efficiency.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only embodiments of the invention, for those of ordinary skills, do not paying under the prerequisite of creative work, other accompanying drawing can also be provided according to the accompanying drawing providing.
The schematic flow sheet of the data processing method in a kind of power office engineering project work stream that Fig. 1 provides for the embodiment of the present invention;
After audit project verification flow nodes being detected in data processing method in a kind of power office engineering project work stream that Fig. 2 provides for the embodiment of the present invention first task being disposed, generate the method flow schematic diagram of a kind of implementation of the indication that triggers Project design flow nodes;
After audit project verification flow nodes being detected in data processing method in a kind of power office engineering project work stream that Fig. 3 provides for the embodiment of the present invention first task being disposed, generate the method flow schematic diagram of a kind of implementation of the indication that triggers Project design flow nodes;
A kind of structural representation of management intermediate acceptance flow nodes in data processing method in a kind of power office engineering project work stream that Fig. 4 provides for the embodiment of the present invention;
A kind of structural representation of supervising engineer notice flow process in data processing method in a kind of power office engineering project work stream that Fig. 5 provides for the embodiment of the present invention;
The structural representation of the data processing equipment in a kind of power office engineering project work stream that Fig. 6 provides for the embodiment of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, obviously, described embodiment is only the present invention's part embodiment, rather than whole embodiment.Embodiment based in the present invention, those of ordinary skills, not making the every other embodiment obtaining under creative work prerequisite, belong to the scope of protection of the invention.
Refer to accompanying drawing 1, the schematic flow sheet of the data processing method in a kind of power office engineering project work stream providing for the embodiment of the present invention, the method comprises:
Step S101: the first task of establishment.
Step S102: the described first task creating is sent to audit project verification flow nodes.
Step S103: detect audit project verification flow nodes by first task after, generate the indication that triggers Project design flow nodes.
Step S104: according to the contextual information of described audit project verification flow nodes and described Project design flow nodes, determine the second task corresponding to described Project design flow nodes.
Step S105: described the second task is sent to described Project design flow nodes.
Step S106: after described Project design flow nodes being detected the second task being disposed, generate the indication that triggers construction bid approval process node.
Step S107: according to the contextual information of described construction bid approval process node and described Project design flow nodes, determine the 3rd task that described construction bid approval process node is corresponding.
Step S108: described the 3rd task is sent to described construction bid approval process node.
Step S109: after described construction bid approval process node being detected the 3rd task being disposed, generate the indication that triggers contract approval flow nodes.
Step S110: according to the contextual information of described contract approval flow nodes and described construction bid approval process node, determine the 4th task corresponding to described contract approval flow nodes.
Step S111: described the 4th task is sent to described contract approval flow nodes.
Step S112: after described contract approval flow nodes being detected the 4th task being disposed, generate the indication that triggers the license approval process node that goes into operation.
Step S113: according to the contextual information of described go into operation license approval process node and described contract approval flow nodes, the 5th task corresponding to license approval process node goes into operation described in determining.
Step S114: the license approval process that goes into operation described in described the 5th task is sent to node.
Step S115: after the license approval process that goes into operation described in detecting node is disposed the 5th task, generate the indication that triggers asset disposal approval flow nodes.
Step S116: according to the contextual information of described go into operation license approval process node and described asset disposal approval flow nodes, determine the 6th task corresponding to described asset disposal approval flow nodes.
Step S117: described the 6th task is sent to described asset disposal approval flow nodes.
Step S118: after described asset disposal approval flow nodes being detected the 6th task being disposed, generate the indication that triggers final acceptance of construction flow nodes.
Step S119: according to the contextual information of described final acceptance of construction flow nodes and described asset disposal approval flow nodes, determine the 7th task corresponding to described final acceptance of construction flow nodes.
Step S120: described the 7th task is sent to described final acceptance of construction flow nodes.
Step S121: after described final acceptance of construction flow nodes being detected the 7th task being disposed, generate the indication that triggers project final accounting approval process node.
Step S122: according to the contextual information of described final acceptance of construction flow nodes and described project final accounting approval process node, determine the 8th task that described project final accounting approval process node is corresponding.
Step S123: described the 8th task is sent to described project final accounting approval process node.
Step S124: after described project final accounting approval process node being detected the 8th task being disposed, result is fed back to destination node.
The user with corresponding authority can inquire about and check Entry Details to each node.Each node can be added, edit, a certain node can be deleted or increase.
Have step S101 and generated by workflow engine to the workflow of each node in step S124, the method that generates workflow is prior art, is not just repeating one by one here.
The embodiment of the present invention provides a kind of engineering project work stream data processing method of power office, the method by each Node configuration in computing machine, computing machine is according to the contextual information of present node and a upper node, can obtain the task of present node, thereby task is sent to present node, and do not need manually to transmit, thereby improved work efficiency.
Be understandable that, in the workflow of mentioning at above-described embodiment, can there is branch's flow process, after the first task of described establishment, also comprise: when project information corresponding to described first task is the bundling project of electrical network overhaul, described first task is sent to engineering contact single process node; After described engineering contact single process node being detected described first task being completed, result is fed back to destination node.
Described audit project verification flow nodes detected first task be disposed after, before generating the indication that triggers Project design flow nodes, also comprise: detect project information corresponding to described first task, described project information comprises bundling project neutron project information or single project information.
When project information corresponding to described first task is described bundling project neutron project information, described audit project verification flow nodes comprises that run unit establishment node, run unit responsible official examine node, project management group audit node, person in charge of the project head of the unit examines node and leader with specific duties examines node, and described first task comprises first task one, first task two, first task three, first task four and first task five.Refer to Fig. 2, after audit project verification flow nodes being detected in data processing method in a kind of power office engineering project work stream providing for the embodiment of the present invention first task being disposed, the method flow schematic diagram that generates a kind of implementation of the indication that triggers Project design flow nodes, the method comprises:
Step S201: after described run unit establishment node being detected described first task one being finished, generate and trigger the indication that described run unit responsible official examines node.
Step S202: the contextual information of examining node according to described run unit establishment node and described run unit responsible official, generates described first task two.
Step S203: described first task two is sent to described run unit responsible official and examines node.
Step S204: after described run unit responsible official being detected and examining node described first task two is finished, generate the indication that triggers described project management group audit node.
Step S205: the contextual information of examining node according to described project management group audit node and described run unit responsible official, generates described first task three.
Step S206: described first task three is sent to described project management group audit node.
Step S207: after described project management group audit node being detected described first task three being finished, generate and trigger the indication that described person in charge of the project head of the unit examines node.
Step S208: the contextual information of examining node and described project management group audit node according to described person in charge of the project head of the unit, generates described first task four.
Step S209: described first task four is sent to described person in charge of the project head of the unit and examines node.
Step S210: after described person in charge of the project head of the unit being detected and examining node described first task four is finished, generate and trigger the indication that described leader with specific duties examines node.
Step S211: examine according to the described person in charge of the project head of the unit contextual information that node and described leader with specific duties examine node, generate described first task five.
Step S212: described first task five is sent to described leader with specific duties and examines node.
Step S213: after described leader with specific duties being detected and examining node described first task five is finished, generate the indication that described first task completes.
When project information corresponding to described first task is described single project information, described audit project verification flow nodes comprises project management group establishment node, person in charge of the project head of the unit examines node and leader with specific duties examines node, described first task comprises first task three, first task four and first task five, refer to Fig. 3, after audit project verification flow nodes being detected in data processing method in a kind of power office engineering project work stream providing for the embodiment of the present invention first task being disposed, generate the method flow schematic diagram of a kind of implementation of the indication that triggers Project design flow nodes, the method comprises:
Step S301: after described project management group audit node being detected described first task three being finished, generate and trigger the indication that described person in charge of the project head of the unit examines node.
Step S302: the contextual information of examining node and described project management group audit node according to described person in charge of the project head of the unit, generates described first task four.
Step S303: described first task four is sent to described person in charge of the project head of the unit and examines node.
Step S304: after described person in charge of the project head of the unit being detected and examining node described first task four is finished, generate and trigger the indication that described leader with specific duties examines node.
Step S305: examine according to the described person in charge of the project head of the unit contextual information that node and described leader with specific duties examine node, generate described first task five.
Step S306: described first task five is sent to described leader with specific duties and examines node.
Step S307: after described leader with specific duties being detected and examining node described first task five is finished, generate the indication that described first task completes.
Audit project verification flow process provide entry property be sub-project in " electrical network overhaul " bundling project in addition and single project project verification audit with examine, realize the management of checking on of project entrance.Audit project verification flow process can be proposed as required by run unit and project management group, and detailed Project information is provided, and person in charge of the project unit and leader with specific duties are examined respectively and examine.After audit project verification flow nodes is finished the work, system can automatic activation " Project design flow nodes ".
Described Project design flow nodes can comprise design proposal submission node, project management group audit node, relevant speciality department head examines node, person in charge of the project head of the unit examines node and leader with specific duties examines node, described the second task comprises the second task one, the second task two, the second task three, the second task four and the second task five, after the embodiment of the present invention provides and described Project design flow nodes detected in the data processing method in a kind of power office engineering project work stream the second task is disposed, generate a kind of implementation of the indication that triggers construction bid approval process node, the method comprises: after described design proposal being detected and submitting to node that described the second task one is finished, generate the indication that triggers described project management audit node.The contextual information of submitting node and described project management group audit node according to described design proposal to, generates described the second task two.Described the second task two is sent to described project management group audit node.After described project management group audit node being detected described the second task two being finished, generate the indication that the described relevant speciality department head of triggering examines node.The contextual information of examining node according to described project management group audit node and described relevant speciality department head, generates described the second task three.Described the second task three is sent to described relevant speciality department head and examines node.After described relevant speciality department head being detected and examining node described the second task three is finished, generate and trigger the indication that described person in charge of the project head of the unit examines node.According to described relevant speciality department head, examine the contextual information that node and described person in charge of the project head of the unit examine node, generate described the second task four.Described the second task four is sent to described person in charge of the project head of the unit and examines node.Described person in charge of the project head of the unit detected and examine after the indication that node is finished described the second task four, generate and trigger the indication that described leader with specific duties examines node.According to described leader with specific duties, examine the contextual information that node and described person in charge of the project head of the unit examine node, generate described the second task five.Described the second task five is sent to described leader with specific duties and examines node.After described leader with specific duties being detected and examining node described the second task five is finished, generate the indication that triggers construction bid approval process node.
In Project design flow nodes, Project design flow nodes staff can see the details of approving and initiate a project and planning, and carries out based on this engineering design work.After having designed, need to submit to specifications, construction budget book, main material and tear the indispensable data of the engineerings such as used equipment inventory open.Design proposal is submitted to node, project management group audit node, relevant speciality department head to examine node, person in charge of the project head of the unit and is examined node and leader with specific duties and examine the staff that node is corresponding and examined respectively and examine.Project design flow process joint is by after tasks carrying, and workflow can automatic activation " Biding approval process node ".
The groundwork of Biding approval process node completes Bidding Work outward for supervisor of construction's line, and uploads notice on bid winning original paper scanned copy in computing machine corresponding to Biding approval process node.Biding approval process node by tasks carrying after, workflow can automatic activation " contract approval flow nodes ".
The standard contract masterplate that contract approval flow nodes provides according to province company, generates contract text automatically in conjunction with the design content through audit, and supervisor of construction signs after examination outward and import system after contract text scanning filed after flow process completing line.After all kinds of contracts have imported, system automatic activation " the license approval process that goes into operation node ".
Be understandable that, the license approval process that goes into operation node can comprise: unit in charge of construction's establishment node, supervisor's audit node, safety supervision portion audit node, supervision and examination unit's audit node and person in charge of the project unit's audit node, described the 5th task comprises: the 5th task one, the 5th task two, the 5th task three, the 5th task four and the 5th task five, after the license approval process node that goes into operation described in detecting in data processing method in a kind of power office engineering project work stream that the embodiment of the present invention provides is disposed the 5th task, the indication that generate to trigger asset disposal approval flow nodes comprises: after described unit in charge of construction establishment node being detected described the 5th task one being finished, generate the indication that triggers described supervisor audit node, contextual information according to described unit in charge of construction establishment node and described supervisor audit node, generates described the 5th task two, described the 5th task two is sent to described supervisor audit node, after described supervisor audit node being detected described the 5th task two being finished, generate and trigger the indication that described safety supervision department examines node, contextual information according to described supervisor audit node and described safety supervision department audit node, generates described the 5th task three, described the 5th task three is sent to described safety supervision department audit node, after described safety supervision department audit node being detected described the 5th task three being finished, generate and trigger the indication that described supervision and examination unit examines node, contextual information according to described safety supervision department's audit node and described supervision and examination unit audit node, generates described the 5th task four, described the 5th task four is sent to described supervision and examination unit audit node, detect after the indication that described supervision and examination unit audit node is finished described the 5th task four, generate the indication that triggers described person in charge of the project unit audit node, contextual information according to described person in charge of the project unit audit node and described supervision and examination unit audit node, generates described the 5th task five, described the 5th task five is sent to described person in charge of the project unit audit node, after described person in charge of the project unit audit node being detected described the 5th task five being finished, generate the indication that triggers assets processing approval process node.
The license approval process that goes into operation node is submitted to by unit in charge of construction's establishment, after unit in charge of construction's establishment node, supervisor's audit node, safety supervision portion audit node, supervision and examination unit's audit node and staff corresponding to audit node of person in charge of the project unit examine respectively, completes.Go into operation license approval process node by tasks carrying after, workflow can automatic activation " asset disposal approval flow nodes ".
Asset disposal approval flow nodes comprises: fill in recycle single node, project management group audit node, treasurer's department's audit node, unit in charge of construction fills in and reclaims several sections of points and logistic service center confirmation node, described the 6th task comprises: the 6th task one, the 6th task two, the 6th task three, the 6th task four and the 6th task five, after described asset disposal approval flow nodes being detected in data processing method in the embodiment of the present invention provides a kind of power office engineering project work stream the 6th task being disposed, the indication that generate to trigger final acceptance of construction flow nodes comprises: described in detecting, fill in after recycle single node is finished described the 6th task one, generate the indication that triggers described project management group audit node, according to the described contextual information of filling in recycle single node and described project management group audit node, generate described the 6th task two, described the 6th task two is sent to described project management group audit node, after described project management group audit node being detected described the 6th task two being finished, generate and trigger the indication that described treasurer's department examines node, contextual information according to described project management group audit node and described treasurer's department audit node, generates described the 6th task three, described the 6th task three is sent to described treasurer's department audit node, after described treasurer's department audit node being detected described the 6th task three being finished, generate and trigger the indication that the several sections of points of recovery are filled in by described unit in charge of construction, according to described treasurer's department audit node and described unit in charge of construction, fill in the contextual information that reclaims several sections of points, generate described the 6th task four, described the 6th task four is sent to described unit in charge of construction and fills in the several sections of points of recovery, described unit in charge of construction detected and fill in and reclaim after the indication that several sections of described the 6th tasks four of naming a person for a particular job are finished, generate and trigger the indication that described logistic service center is confirmed node, according to described logistic service center confirmation node and described unit in charge of construction, fill in the contextual information that reclaims several sections of points, generate described the 6th task five, described the 6th task five is sent to described logistic service center and confirms node, after described logistic service center being detected and confirming that node is finished described the 6th task five, generate the indication of triggering final acceptance of construction flow nodes.
Asset disposal approval flow nodes is carried out in engineering construction process, and waste and old material reclaims < < waste and old material management method (trying) the > > issuing according to Jiande City electric company and fulfils audit, confirms flow process.The examination and approval document of asset disposal approval flow nodes auto-generating method regulation.Asset disposal approval flow nodes by tasks carrying after, workflow can automatic activation " final acceptance of construction flow nodes ".
Final acceptance of construction flow nodes comprises: fill in final acceptance of construction application node, supervisor provides management data node, project management group is checked and accepted node, application node is reviewed by unit in charge of construction and project management group provides final acceptance of construction report node, described the 7th task comprises: the 7th task one, the 7th task two, the 7th task three, the 7th task four and the 7th task five, after described final acceptance of construction flow nodes being detected in data processing method in the embodiment of the present invention provides a kind of power office engineering project work stream the 7th task being disposed, the indication that generate to trigger project final accounting approval process node comprises: described in detecting, fill in after final acceptance of construction application node is finished described the 7th task one, generate and trigger the indication that described supervisor provides management data node, according to described, fill in the contextual information that final acceptance of construction application node and described supervisor provide management data node, generate described the 7th task two, described the 7th task two is sent to described supervisor management data node is provided, after described supervisor being detected and providing management data node that described the 7th task two is finished, generate and trigger the indication that described project management group is checked and accepted node, according to described supervisor, provide management data node and described project management group to check and accept the contextual information of node, generate described the 7th task three, described the 7th task three is sent to described project management group and checks and accepts node, after described project management group being detected and checking and accepting node described the 7th task three is finished, generate the indication that triggers described unit in charge of construction reinspection application node, the contextual information of checking and accepting node and described unit in charge of construction reinspection application node according to described project management group, generates described the 7th task four, described the 7th task four is sent to described unit in charge of construction and reviews application node, described unit in charge of construction detected and review after the indication that application node is finished described the 7th task four, generate and trigger the indication that described project management group provides final acceptance of construction report node, according to described project management group, provide final acceptance of construction report node and described unit in charge of construction to review the contextual information of application node, generate described the 7th task five, described the 7th task five is sent to described project management group final acceptance of construction report node is provided, after described project management group being detected and providing final acceptance of construction report node that described the 7th task five is finished, generate the indication of triggering project final accounting approval process node.
Final acceptance of construction flow nodes is submitted final acceptance of construction application to by unit in charge of construction, after whether management audit data is complete, by project management group, organized and implemented, the rear unit in charge of construction of examination rectifies and improves advice note according to defect and carries out engineering defect elimination and submit reinspection application to, provides final acceptance of construction report after the reinspection of project management group is qualified.After this flow process finishes, workflow automatic activation " project final accounting approval process node ".
Project final accounting approval process node comprises: unit in charge of construction provides clearing book node, the project management group node of submitting to a higher level for approval or revision, supervision and examination provide Audit Report node, unit in charge of construction confirms node, person in charge of the project unit confirms node and financial final accounts node, described the 8th task comprises: the 8th task one, the 8th task two, the 8th task three, the 8th task four, the 8th task five and the 8th task six, after described project final accounting approval process node being detected in data processing method in the embodiment of the present invention provides a kind of power office engineering project work stream the 8th task being disposed, result is fed back to destination node to be comprised: after described unit in charge of construction being detected and providing clearing book node that described the 8th task one is finished, generate to trigger the submit to a higher level for approval or revision indication of node of described project management group, the contextual information that provides clearing book node and described project management group to submit to a higher level for approval or revision node according to described unit in charge of construction, generates described the 8th task two, described the 8th task two is sent to the described project management group node of submitting to a higher level for approval or revision, described project management group detected and submit to a higher level for approval or revision after node is finished described the 8th task two, generate and trigger the indication that described supervision and examination provide Audit Report node, according to described project management group, submit to a higher level for approval or revision node and described supervision and examination provide the contextual information of Audit Report node, generate described the 8th task three, described the 8th task three is sent to described supervision and examination Audit Report node is provided, after described supervision and examination being detected and providing Audit Report node that described the 8th task three is finished, generate and trigger the indication that described unit in charge of construction confirms node, according to described supervision and examination, provide Audit Report node and described unit in charge of construction to confirm the contextual information of node, generate described the 8th task four, described the 8th task four is sent to described unit in charge of construction and confirms node, detect after the indication that described unit in charge of construction confirms that node is finished described the 8th task four, generate and trigger the indication that described person in charge of the project unit confirms node, according to described person in charge of the project unit, confirm that node and described unit in charge of construction confirm the contextual information of node, generate described the 8th task five, described the 8th task five is sent to described person in charge of the project unit and confirms node, after described person in charge of the project unit being detected and confirming that node is finished described the 8th task five, generate the indication of the financial final accounts node of triggering, the contextual information of confirming node and described financial final accounts node according to described person in charge of the project unit, generates described the 8th task six, described the 8th task six is sent to described financial final accounts node, described financial final accounts node detected and be finished after described the 8th task six, result is fed back to destination node.
Project final accounting approval process node is submitted Engineering Settlement book by unit in charge of construction to project management group, by project management group, send supervision and examination to audit, after audit finishes, by supervision and examination, submit audit data to, after unit in charge of construction and the confirmation of person in charge of the project unit, submit to finance to carry out financial final accounts.Project final accounting approval process node by tasks carrying after, the life cycle of whole project completes.
Be understandable that, after described generation triggers the indication of the license approval process node that goes into operation, trigger the indication of asset disposal approval flow nodes in described generation before, also comprise: after first pass node being detected and being triggered, the 9th task that described first pass node is corresponding is sent to described first pass node, and described first pass node comprises in project modification process node, management intermediate acceptance flow nodes and supervising engineer notice flow nodes one or more; Described first pass node detected and complete after described the 9th task, carry out the operation that described generation triggers the indication of asset disposal approval flow nodes.
When first pass node is project modification process node, first pass node completes the process of described the 9th task can be as described below.
Project modification process node comprises: unit in charge of construction's modification application node, supervisor's audit node, designing unit's audit node, run unit audit node, project management group audit node, designing unit's modification application node, unit in charge of construction's audit node, supervisor's audit node, run unit modification application node, designing unit's audit node, construction unit examines node, be in charge of vice president and examine node, general manager (GM) examines node, apply for checking and examination node and supervisor of unit in charge of construction checks and accepts node.
Project modification process node can be initiated respectively by unit in charge of construction, designing unit, run unit.
Unit in charge of construction proposes change, but do not relate to, design drawing revises.For example: the quantities that various technical measures are processed, external environment condition variation causes not being included in contract occurring in work progress increases and decreases, the advance approval items such as material replacement or other changes; Need survey the job of quantities because design alteration causes construction part dismounting (needing to indicate design alteration numbering), contractual spectifications, delay work etc. need to be confirmed item afterwards.Rear enforcement should be first examined in the change of advance approval, by unit in charge of construction, proposes engineering change request; Confirm that item is occurred in latter 7 days at change by unit in charge of construction afterwards, propose change in the work flow process.Idiographic flow: unit in charge of construction proposes the change in the work origin of an incident and change suggestion, be that unit in charge of construction's modification application node (is filled in change in the work examination and approval document, change scheme, change expenses statement is as annex)---(whether emphasis audit change is according to sufficient for supervisor's audit node, whether change scheme is feasible, whether quantities is true etc., Unified number)---designing unit's audit node (determining by project management group whether designing unit conutersigns as the case may be)---run unit audit node---project management group audit node (project management specific responsibility, skill through specific responsibility or skill through managerial personnel, project manager writes comments and sign one's name)---construction unit examines.
Unit in charge of construction proposes change, relates to that design drawing revises.Idiographic flow: unit in charge of construction proposes the change in the work origin of an incident and change suggestion, be that unit in charge of construction's modification application node (is filled in change in the work examination and approval document, change scheme, change expenses statement is as annex)---(whether emphasis audit change reason is sufficient and propose clear and definite management suggestion for supervisor audit node, Unified number)---designing unit's audit node (proposes design alteration scheme establishment change budget according to management suggestion, design alteration contact list and budget are as annex)---(the project management specific responsibility of run unit audit node-project management group audit node, skill is through personnel, project manager writes comments and sign one's name)---construction unit examines node.
Designing unit proposes change.Idiographic flow: designing unit proposes change scheme establishment change budget, be that designing unit's modification application node (is filled in change in the work examination and approval document, design alteration contact list and budget are as annex) (whether the emphasis audit change origin of an incident is sufficient for---unit in charge of construction's audit node (writing comments and sign one's name)---supervisor's audit node, whether change scheme is feasible, and clear and definite management suggestion, Unified number proposed)---construction unit examines node in run unit audit---project management group audit node (project management specific responsibility, skill are write comments and sign one's name through personnel, project manager)---.
Run unit proposes change.Idiographic flow: run unit proposes, being run unit modification application node (filling in change in the work examination and approval document),---project management group is examined node---designing unit audit node (determines whether designing unit conutersigns as the case may be, if desired Ze You designing unit proposes design alteration scheme establishment change budget, design alteration contact list and budget are as annex)---unit in charge of construction's audit node (writing comments and sign one's name)---(whether emphasis audit change scheme is feasible for supervisor's audit node, and clear and definite management suggestion proposed, Unified number)---construction unit examines node.
Change in the work examination and approval document must include but not limited to following content: the content way of the time of numbering, engineering name, generation, the position of generation or scope, change and cause description, the quantities of increase, the quantities of minimizing, relevant drawing explanation.Change in the work should be enclosed schematic diagram, indicates position, project, way, normal geometry etc., and accompanying drawing needs Supervision Project portion, project management specific responsibility to confirm.The changed content that relates to quantities is answered first-selected schematic diagram, sketch or sketch, secondly with calculating formulae express; While being really not suitable for adopting schematic diagram and formula, adding explanatory note explained by measured data, Supervision Project portion and project management specific responsibility must be carried out field verification, and during suggestion signature, clear and definite measured data is through field verification.
The change amount of money, below 20,000 yuan (containing), after being examined node and finished the work, directly triggers unit in charge of construction's node that applies for checking and examination by construction unit.
The change amount of money is 20,000 yuan of (contain)~50,000 yuan (containing), after being examined node and finished the work, triggers the pipe deputy general manager that calls the score and examines node by construction unit, be in charge of vice president examine node by tasks carrying after, the triggering unit in charge of construction node that applies for checking and examination.
The change amount of money is more than 50,000 yuan (containing), by construction unit examine node by tasks carrying after, triggering is in charge of vice president and is examined node, being in charge of vice president examines node and executes after corresponding task, trigger general manager (GM) and examine node, general manager (GM) examine node by the tasks carrying corresponding with it after, trigger unit in charge of construction's node that applies for checking and examination.
Unit in charge of construction's node that applies for checking and examination is finished after the task corresponding with it, trigger supervisor and check and accept node, supervisor check and accept node by the tasks carrying corresponding with it after, all tasks of this project final accounting approval process node have just completed.
After change in the work is examined according to the corresponding power of examination and approval, by supervisor, supervise relevant unit of taking part in building to carry out.Unit in charge of construction should propose " change in the work execution single inspection " after change is complete, by management, is examined; For concealed work etc., in change, carry out in single inspection and should describe the important contents such as schematic diagram or concrete engineering amount in detail, and provide the image data of obvious yardstick, without concealed work image data, must not provide examination reports.Examination must have particular view, forbids only signing principle suggestion or only signs without particular view, to guarantee to meet engineering valuation requirement.
When first pass node is management intermediate acceptance flow nodes, first pass node completes the process of described the 9th task can be as described below.
Refer to Fig. 4, a kind of structural representation of management intermediate acceptance flow nodes in the data processing method in a kind of power office engineering project work stream providing for the embodiment of the present invention.
Management intermediate acceptance flow nodes comprises that management initiation intermediate acceptance node 401, unit in charge of construction's feedback node 402 and supervisor confirm node 403.
The triggering sequencing of each node, as shown in the arrow in Fig. 4.Triggering method between each node and task creating method, as the data processing method in power office's engineering project work stream, repeat here no longer one by one.
Management intermediate acceptance flow nodes is initiated once after the license approval process node that goes into operation finishes automatically by workflow, also can manually be initiated repeatedly by supervisor.Supervisor provides defect notification list to unit in charge of construction, and unit in charge of construction rectifies and improves related defects for defect notification list, and fills in defect elimination performance on defect rectification receipt.After defect elimination, unit in charge of construction submits defect rectification receipt to supervisor, supervisor's signature audit opinion, filing.
When first pass node is supervising engineer notice flow process, first pass node completes the process of described the 9th task can be as described below.
Refer to Fig. 5, a kind of structural representation of supervising engineer notice flow process in the data processing method in a kind of power office engineering project work stream providing for the embodiment of the present invention.
Supervising engineer notice flow process comprises that supervising engineer notice node 501, unit in charge of construction's feedback node 402 and supervisor confirm node 403.
Supervising engineer notice flow process is manually initiated by supervisor.Supervisor provides supervising engineer notice to unit in charge of construction, and unit in charge of construction submits notification from supervising engineer reply sheet to after completing rectification, supervisor's signature audit opinion, filing.
In data processing method embodiment in above-mentioned arbitrary power office engineering project work stream, each node can comprise that its corresponding task completes deadline information and staff's contact method information, when staff goes beyond the time limit while still not finishing the work, send warning message just can to this staff.The audit project verification flow nodes of take below describes as example.Audit project verification flow nodes comprises that task completes deadline information and staff's contact method information, described detect audit project verification flow nodes by first task after, before generating the indication that triggers Project design flow nodes, also comprise: calculate the differential time of current time and initial time, the time that described audit project verification flow nodes receives described first task is described initial time; When described differential time is more than or equal to described task and completes deadline information, according to described staff's contact method information, to relevant work personnel, send warning message.
The user of different stage can also increase or delete the node in the workflow in the data processing method in power office's engineering project work stream, can also exercise supervision to the task status of each node, task status comprises completion status and unfinished state.Before the first task of described establishment, also comprise: when receiving user and increasing the indication of the second flow nodes, judge described user's class information; When described circle information is greater than pre-set level, increase described the second flow nodes.
In data processing method embodiment in above-mentioned arbitrary power office engineering project work stream, each node all can upload file data, in the embodiment of the present invention, can adopt third party's plug-in unit neat upload that file data is uploaded, because project management is from the project final accounting of approving and initiate a project, relate to numerous electronic document data, and the file size of these electronic document data is generally larger, common uploading file need to spend a few minutes even dozens of minutes just can complete, during handling and poor user experience.Third party's plug-in unit neat upload can realize big accessory and upload fast, and the file of hundreds of million sizes can in seconds easily be uploaded complete.In addition, third party's plug-in unit neat upload also supports to select a plurality of annexes to upload simultaneously.
In the disclosed embodiment of the invention described above, describe method in detail, for method of the present invention, can adopt the device of various ways to realize, therefore the invention also discloses a kind of device, provide specific embodiment below and be elaborated.
Refer to Fig. 6, the structural representation of the data processing equipment in a kind of power office engineering project work stream providing for the embodiment of the present invention, this device comprises: creation module 601, the first sending module 602, the first generation module 603, the first determination module 604, the second sending module 605, the second generation module 606, the second determination module 607, the 3rd sending module 608, the 3rd generation module 609, the 3rd determination module 610, the 4th sending module 611, the 4th generation module 612, the 4th determination module 613, the 5th sending module 614, the 5th generation module 615, the 5th determination module 616, the 6th sending module 617, the 6th generation module 618, the 6th determination module 619, the 7th sending module 620, the 7th generation module 621, the 7th determination module 622, the 8th sending module 623 and the 9th sending module 624, wherein:.
Creation module 601, for the first task creating;
The first sending module 602, for being sent to the described first task creating audit project verification flow nodes;
The first generation module 603, for detection of to audit project verification flow nodes by first task after, generate the indication that triggers Project design flow nodes;
The first determination module 604, for according to the contextual information of described audit project verification flow nodes and described Project design flow nodes, determines the second task corresponding to described Project design flow nodes;
The second sending module 605, for being sent to described Project design flow nodes by described the second task;
The second generation module 606, after the second task being disposed to described Project design flow nodes, generates the indication that triggers construction bid approval process node;
The second determination module 607, for according to the contextual information of described construction bid approval process node and described Project design flow nodes, determines the 3rd task that described construction bid approval process node is corresponding;
The 3rd sending module 608, for being sent to described construction bid approval process node by described the 3rd task;
The 3rd generation module 609, after the 3rd task being disposed to described construction bid approval process node, generates the indication that triggers contract approval flow nodes;
The 3rd determination module 610, for according to the contextual information of described contract approval flow nodes and described construction bid approval process node, determines the 4th task corresponding to described contract approval flow nodes;
The 4th sending module 611, for being sent to described contract approval flow nodes by described the 4th task;
The 4th generation module 612, after the 4th task being disposed to described contract approval flow nodes, generates the indication that triggers the license approval process node that goes into operation;
The 4th determination module 613, for the contextual information of go into operation described in basis license approval process node and described contract approval flow nodes, the 5th task corresponding to license approval process node goes into operation described in determining;
The 5th sending module 614, for the license approval process node that goes into operation described in described the 5th task is sent to;
The 5th generation module 615, for detection of to described in go into operation after license approval process node is disposed the 5th task, generate the indication that triggers asset disposal approval flow nodes;
The 5th determination module 616, for the contextual information of go into operation described in basis license approval process node and described asset disposal approval flow nodes, determines the 6th task corresponding to described asset disposal approval flow nodes;
The 6th sending module 617, for being sent to described asset disposal approval flow nodes by described the 6th task;
The 6th generation module 618, after the 6th task being disposed to described asset disposal approval flow nodes, generates the indication that triggers final acceptance of construction flow nodes;
The 6th determination module 619, for according to the contextual information of described final acceptance of construction flow nodes and described asset disposal approval flow nodes, determines the 7th task corresponding to described final acceptance of construction flow nodes;
The 7th sending module 620, for being sent to described final acceptance of construction flow nodes by described the 7th task;
The 7th generation module 621, after the 7th task being disposed to described final acceptance of construction flow nodes, generates the indication that triggers project final accounting approval process node;
The 7th determination module 622, for according to the contextual information of described final acceptance of construction flow nodes and described project final accounting approval process node, determines the 8th task that described project final accounting approval process node is corresponding;
The 8th sending module 623, for being sent to described project final accounting approval process node by described the 8th task;
The 9th sending module 624, after the 8th task being disposed to described project final accounting approval process node, feeds back to destination node by result.
The embodiment of the present invention provides a kind of engineering project work flow data processing device of power office, this installs each Node configuration in computing machine, computing machine is according to the contextual information of present node and a upper node, can obtain the task of present node, thereby task is sent to present node, and do not need manually to transmit, thereby improved work efficiency.
Data processing equipment embodiment in above-mentioned power office engineering project work stream can also comprise: the tenth sending module, for after the first task of described establishment, when project information corresponding to described first task is the bundling project of electrical network overhaul, described first task is sent to engineering contact single process node; Feedback module, after described first task being completed to described engineering contact single process node, feeds back to described destination node by result.
Data processing equipment embodiment in above-mentioned power office engineering project work stream can also comprise: send task module, after being triggered to first pass node, the 9th task that described first pass node is corresponding is sent to described first pass node, and described first pass node comprises in project modification process node, management intermediate acceptance flow nodes and supervising engineer notice flow nodes one or more; Trigger module, for detection of completing after described the 8th task to described first pass node, triggers described the 5th generation module.
Be understandable that, described audit project verification flow nodes comprises that task completes deadline information and staff's contact method information, data processing equipment embodiment in above-mentioned power office engineering project work stream can also comprise: computing module, for calculating the differential time of current time and initial time, the time that described audit project verification flow nodes receives described first task is described initial time; Alarm module, while completing deadline information for being more than or equal to described task when described differential time, sends warning message according to described staff's contact method information to relevant work personnel.
Data processing equipment embodiment in above-mentioned power office engineering project work stream can also comprise: judge module, while increasing the indication of the second flow nodes for receiving user, judges described user's class information; Increase module, for when described circle information is greater than pre-set level, increase described the second flow nodes.
It should be noted that, each embodiment in this instructions all adopts the mode of going forward one by one to describe, and each embodiment stresses is the difference with other embodiment, between each embodiment identical similar part mutually referring to.For device or system class embodiment, because it is substantially similar to embodiment of the method, so description is fairly simple, relevant part is referring to the part explanation of embodiment of the method.
Also it should be noted that, in this article, relational terms such as the first and second grades is only used for an entity or operation to separate with another entity or operational zone, and not necessarily requires or imply and between these entities or operation, have the relation of any this reality or sequentially.And, term " comprises ", " comprising " or its any other variant are intended to contain comprising of nonexcludability, thereby the process, method, article or the equipment that make to comprise a series of key elements not only comprise those key elements, but also comprise other key elements of clearly not listing, or be also included as the intrinsic key element of this process, method, article or equipment.The in the situation that of more restrictions not, the key element being limited by statement " comprising ... ", and be not precluded within process, method, article or the equipment that comprises described key element and also have other identical element.
The software module that the method for describing in conjunction with embodiment disclosed herein or the step of algorithm can directly use hardware, processor to carry out, or the combination of the two is implemented.Software module can be placed in the storage medium of any other form known in random access memory (RAM), internal memory, ROM (read-only memory) (ROM), electrically programmable ROM, electrically erasable ROM, register, hard disk, moveable magnetic disc, CD-ROM or technical field.
Above-mentioned explanation to the disclosed embodiments, makes professional and technical personnel in the field can realize or use the present invention.To the multiple modification of these embodiment, will be apparent for those skilled in the art, General Principle as defined herein can, in the situation that not departing from the spirit or scope of the present invention, realize in other embodiments.Therefore, the present invention will can not be restricted to these embodiment shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.

Claims (10)

  1. Data processing method in 1.Yi Zhong power office engineering project work stream, is characterized in that, comprising:
    The first task creating;
    The described first task creating is sent to audit project verification flow nodes;
    Detect audit project verification flow nodes by first task after, generate the indication that triggers Project design flow nodes;
    According to the contextual information of described audit project verification flow nodes and described Project design flow nodes, determine the second task corresponding to described Project design flow nodes;
    Described the second task is sent to described Project design flow nodes;
    After described Project design flow nodes being detected the second task being disposed, generate the indication that triggers construction bid approval process node;
    According to the contextual information of described construction bid approval process node and described Project design flow nodes, determine the 3rd task that described construction bid approval process node is corresponding;
    Described the 3rd task is sent to described construction bid approval process node;
    After described construction bid approval process node being detected the 3rd task being disposed, generate the indication that triggers contract approval flow nodes;
    According to the contextual information of described contract approval flow nodes and described construction bid approval process node, determine the 4th task corresponding to described contract approval flow nodes;
    Described the 4th task is sent to described contract approval flow nodes;
    After described contract approval flow nodes being detected the 4th task being disposed, generate the indication that triggers the license approval process node that goes into operation;
    According to the contextual information of described go into operation license approval process node and described contract approval flow nodes, the 5th task corresponding to license approval process node goes into operation described in determining;
    The license approval process that goes into operation described in described the 5th task is sent to node;
    After the license approval process that goes into operation described in detecting node is disposed the 5th task, generate the indication that triggers asset disposal approval flow nodes;
    According to the contextual information of described go into operation license approval process node and described asset disposal approval flow nodes, determine the 6th task corresponding to described asset disposal approval flow nodes;
    Described the 6th task is sent to described asset disposal approval flow nodes;
    After described asset disposal approval flow nodes being detected the 6th task being disposed, generate the indication that triggers final acceptance of construction flow nodes;
    According to the contextual information of described final acceptance of construction flow nodes and described asset disposal approval flow nodes, determine the 7th task corresponding to described final acceptance of construction flow nodes;
    Described the 7th task is sent to described final acceptance of construction flow nodes;
    After described final acceptance of construction flow nodes being detected the 7th task being disposed, generate the indication that triggers project final accounting approval process node;
    According to the contextual information of described final acceptance of construction flow nodes and described project final accounting approval process node, determine the 8th task that described project final accounting approval process node is corresponding;
    Described the 8th task is sent to described project final accounting approval process node;
    After described project final accounting approval process node being detected the 8th task being disposed, result is fed back to destination node.
  2. 2. method according to claim 1, is characterized in that, after the first task of described establishment, also comprises:
    When project information corresponding to described first task is the bundling project of electrical network overhaul, described first task is sent to engineering contact single process node;
    After described engineering contact single process node being detected described first task being completed, result is fed back to described destination node.
  3. 3. method according to claim 1, is characterized in that, after described generation triggers the indication of the license approval process node that goes into operation, before triggering the indication of asset disposal approval flow nodes, also comprises in described generation:
    After first pass node being detected and being triggered, the 9th task that described first pass node is corresponding is sent to described first pass node, and described first pass node comprises in project modification process node, management intermediate acceptance flow nodes and supervising engineer notice flow nodes one or more;
    Described first pass node detected and complete after described the 8th task, carry out the operation that described generation triggers the indication of asset disposal approval flow nodes.
  4. 4. method according to claim 1, it is characterized in that, described audit project verification flow nodes comprises that task completes deadline information and staff's contact method information, described detect audit project verification flow nodes by first task after, before generating the indication that triggers Project design flow nodes, also comprise:
    Calculate the differential time of current time and initial time, the time that described audit project verification flow nodes receives described first task is described initial time;
    When described differential time is more than or equal to described task and completes deadline information, according to described staff's contact method information, to relevant work personnel, send warning message.
  5. 5. method according to claim 1, is characterized in that, before the first task of described establishment, also comprises:
    When receiving user and increasing the indication of the second flow nodes, judge described user's class information;
    When described circle information is greater than pre-set level, increase described the second flow nodes.
  6. Data processing equipment in 6.Yi Zhong power office engineering project work stream, is characterized in that, comprising:
    Creation module, for the first task creating;
    The first sending module, for being sent to the described first task creating audit project verification flow nodes;
    The first generation module, for detection of to audit project verification flow nodes by first task after, generate the indication that triggers Project design flow nodes;
    The first determination module, for according to the contextual information of described audit project verification flow nodes and described Project design flow nodes, determines the second task corresponding to described Project design flow nodes;
    The second sending module, for being sent to described Project design flow nodes by described the second task;
    The second generation module, after the second task being disposed to described Project design flow nodes, generates the indication that triggers construction bid approval process node;
    The second determination module, for according to the contextual information of described construction bid approval process node and described Project design flow nodes, determines the 3rd task that described construction bid approval process node is corresponding;
    The 3rd sending module, for being sent to described construction bid approval process node by described the 3rd task;
    The 3rd generation module, after the 3rd task being disposed to described construction bid approval process node, generates the indication that triggers contract approval flow nodes;
    The 3rd determination module, for according to the contextual information of described contract approval flow nodes and described construction bid approval process node, determines the 4th task corresponding to described contract approval flow nodes;
    The 4th sending module, for being sent to described contract approval flow nodes by described the 4th task;
    The 4th generation module, after the 4th task being disposed to described contract approval flow nodes, generates the indication that triggers the license approval process node that goes into operation;
    The 4th determination module, for the contextual information of go into operation described in basis license approval process node and described contract approval flow nodes, the 5th task corresponding to license approval process node goes into operation described in determining;
    The 5th sending module, for the license approval process node that goes into operation described in described the 5th task is sent to;
    The 5th generation module, for detection of to described in go into operation after license approval process node is disposed the 5th task, generate the indication that triggers asset disposal approval flow nodes;
    The 5th determination module, for the contextual information of go into operation described in basis license approval process node and described asset disposal approval flow nodes, determines the 6th task corresponding to described asset disposal approval flow nodes;
    The 6th sending module, for being sent to described asset disposal approval flow nodes by described the 6th task;
    The 6th generation module, after the 6th task being disposed to described asset disposal approval flow nodes, generates the indication that triggers final acceptance of construction flow nodes;
    The 6th determination module, for according to the contextual information of described final acceptance of construction flow nodes and described asset disposal approval flow nodes, determines the 7th task corresponding to described final acceptance of construction flow nodes;
    The 7th sending module, for being sent to described final acceptance of construction flow nodes by described the 7th task;
    The 7th generation module, after the 7th task being disposed to described final acceptance of construction flow nodes, generates the indication that triggers project final accounting approval process node;
    The 7th determination module, for according to the contextual information of described final acceptance of construction flow nodes and described project final accounting approval process node, determines the 8th task that described project final accounting approval process node is corresponding;
    The 8th sending module, for being sent to described project final accounting approval process node by described the 8th task;
    The 9th sending module, after the 8th task being disposed to described project final accounting approval process node, feeds back to destination node by result.
  7. 7. method according to claim 6, is characterized in that, also comprises:
    The tenth sending module, for after the first task of described establishment, when project information corresponding to described first task is the bundling project of electrical network overhaul, is sent to engineering contact single process node by described first task;
    Feedback module, after described first task being completed to described engineering contact single process node, feeds back to described destination node by result.
  8. 8. install according to claim 6, it is characterized in that, also comprise:
    Send task module, after being triggered to first pass node, the 9th task that described first pass node is corresponding is sent to described first pass node, and described first pass node comprises in project modification process node, management intermediate acceptance flow nodes and supervising engineer notice flow nodes one or more;
    Trigger module, for detection of completing after described the 8th task to described first pass node, triggers described the 5th generation module.
  9. 9. install according to claim 6, it is characterized in that, described audit project verification flow nodes comprises that task completes deadline information and staff's contact method information, and described device also comprises:
    Computing module, for calculating the differential time of current time and initial time, the time that described audit project verification flow nodes receives described first task is described initial time;
    Alarm module, while completing deadline information for being more than or equal to described task when described differential time, sends warning message according to described staff's contact method information to relevant work personnel.
  10. 10. install according to claim 6, it is characterized in that, also comprise:
    Judge module, while increasing the indication of the second flow nodes for receiving user, judges described user's class information;
    Increase module, for when described circle information is greater than pre-set level, increase described the second flow nodes.
CN201310690120.4A 2013-12-16 2013-12-16 Method and device for data processing in electricity bureau engineering project workflow Pending CN103646315A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310690120.4A CN103646315A (en) 2013-12-16 2013-12-16 Method and device for data processing in electricity bureau engineering project workflow

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310690120.4A CN103646315A (en) 2013-12-16 2013-12-16 Method and device for data processing in electricity bureau engineering project workflow

Publications (1)

Publication Number Publication Date
CN103646315A true CN103646315A (en) 2014-03-19

Family

ID=50251526

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310690120.4A Pending CN103646315A (en) 2013-12-16 2013-12-16 Method and device for data processing in electricity bureau engineering project workflow

Country Status (1)

Country Link
CN (1) CN103646315A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279616A (en) * 2015-11-23 2016-01-27 中铁四局集团有限公司 Method and apparatus for graded management
CN107680003A (en) * 2016-08-01 2018-02-09 北京地厚云图科技有限公司 The node tree generation method and device of project supervision task
CN107688922A (en) * 2016-08-04 2018-02-13 北京地厚云图科技有限公司 Project supervision task processing method and device based on node tree
CN108280624A (en) * 2018-01-24 2018-07-13 鑫银科技集团股份有限公司 A kind of node tracking method and device
CN109146724A (en) * 2018-08-31 2019-01-04 万翼科技有限公司 Output value accounting method, device and computer readable storage medium
CN109345379A (en) * 2018-10-24 2019-02-15 新疆玖富万卡信息技术有限公司 A kind of intelligence credit method and apparatus
CN109740849A (en) * 2018-12-03 2019-05-10 上海夫卡实业发展有限公司 Structure design work management method, platform and the system quickly delivered
CN110866708A (en) * 2019-12-25 2020-03-06 国网辽宁省电力有限公司沈阳供电公司 Power grid dispatching management system and application method thereof
CN111815168A (en) * 2020-07-09 2020-10-23 北京中百信信息技术股份有限公司 Information system engineering supervision project quality management system
CN111815281A (en) * 2020-07-09 2020-10-23 北京中百信信息技术股份有限公司 Information system project supervision project bid management system
CN112308244A (en) * 2020-10-21 2021-02-02 岭东核电有限公司 Nuclear power station maintenance license management and control method and device, storage medium and terminal equipment
CN113379377A (en) * 2021-06-02 2021-09-10 南方电网能源发展研究院有限责任公司 Power grid engineering construction approval processing method and device
CN116976840A (en) * 2023-07-28 2023-10-31 北京梦诚科技有限公司 Multi-person collaborative engineering quantity calculation book auditing method and system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004102454A2 (en) * 2003-05-07 2004-11-25 Sap Aktiengesellschaft An end user oriented workflow approach including structured processing of ad hoc workflows with a collaborative process engine
CN101082970A (en) * 2007-07-05 2007-12-05 山东浪潮齐鲁软件产业股份有限公司 Method for realizing government affairs examination and approval workflow engines system
CN102446309A (en) * 2010-10-13 2012-05-09 清华大学 Process pattern based dynamic workflow planning system and method
CN103092996A (en) * 2013-02-21 2013-05-08 用友软件股份有限公司 Document data acquisition device and document data acquisition method
CN103136626A (en) * 2011-11-29 2013-06-05 北京建龙重工集团有限公司 On-line management method for engineering project
US8583466B2 (en) * 2005-08-09 2013-11-12 Oracle International Corporation System and method for routing workflow items based on workflow templates in a call center

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004102454A2 (en) * 2003-05-07 2004-11-25 Sap Aktiengesellschaft An end user oriented workflow approach including structured processing of ad hoc workflows with a collaborative process engine
US8583466B2 (en) * 2005-08-09 2013-11-12 Oracle International Corporation System and method for routing workflow items based on workflow templates in a call center
CN101082970A (en) * 2007-07-05 2007-12-05 山东浪潮齐鲁软件产业股份有限公司 Method for realizing government affairs examination and approval workflow engines system
CN102446309A (en) * 2010-10-13 2012-05-09 清华大学 Process pattern based dynamic workflow planning system and method
CN103136626A (en) * 2011-11-29 2013-06-05 北京建龙重工集团有限公司 On-line management method for engineering project
CN103092996A (en) * 2013-02-21 2013-05-08 用友软件股份有限公司 Document data acquisition device and document data acquisition method

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279616A (en) * 2015-11-23 2016-01-27 中铁四局集团有限公司 Method and apparatus for graded management
CN107680003A (en) * 2016-08-01 2018-02-09 北京地厚云图科技有限公司 The node tree generation method and device of project supervision task
CN107688922A (en) * 2016-08-04 2018-02-13 北京地厚云图科技有限公司 Project supervision task processing method and device based on node tree
CN108280624A (en) * 2018-01-24 2018-07-13 鑫银科技集团股份有限公司 A kind of node tracking method and device
CN109146724A (en) * 2018-08-31 2019-01-04 万翼科技有限公司 Output value accounting method, device and computer readable storage medium
CN109345379A (en) * 2018-10-24 2019-02-15 新疆玖富万卡信息技术有限公司 A kind of intelligence credit method and apparatus
CN109740849A (en) * 2018-12-03 2019-05-10 上海夫卡实业发展有限公司 Structure design work management method, platform and the system quickly delivered
CN110866708A (en) * 2019-12-25 2020-03-06 国网辽宁省电力有限公司沈阳供电公司 Power grid dispatching management system and application method thereof
CN111815168A (en) * 2020-07-09 2020-10-23 北京中百信信息技术股份有限公司 Information system engineering supervision project quality management system
CN111815281A (en) * 2020-07-09 2020-10-23 北京中百信信息技术股份有限公司 Information system project supervision project bid management system
CN111815168B (en) * 2020-07-09 2021-10-12 北京中百信信息技术股份有限公司 Information system engineering supervision project quality management system
CN112308244A (en) * 2020-10-21 2021-02-02 岭东核电有限公司 Nuclear power station maintenance license management and control method and device, storage medium and terminal equipment
CN113379377A (en) * 2021-06-02 2021-09-10 南方电网能源发展研究院有限责任公司 Power grid engineering construction approval processing method and device
CN116976840A (en) * 2023-07-28 2023-10-31 北京梦诚科技有限公司 Multi-person collaborative engineering quantity calculation book auditing method and system
CN116976840B (en) * 2023-07-28 2024-03-15 北京梦诚科技有限公司 Multi-person collaborative engineering quantity calculation book auditing method and system

Similar Documents

Publication Publication Date Title
CN103646315A (en) Method and device for data processing in electricity bureau engineering project workflow
Hwang et al. Rework and schedule performance: A profile of incidence, impact, causes and solutions
Safapour et al. Identifying effective project-based communication indicators within primary and secondary stakeholders in construction projects
Noorzai Performance analysis of alternative contracting methods for highway construction projects: Case study for Iran
Perrenoud et al. Using best-value procurement to measure the impact of initial risk-management capability on qualitative construction performance
KR101683441B1 (en) Mobile based completion inspection method and system
Robinson A Contractor's Guide to the FIDIC Conditions of Contract
US20230015535A1 (en) Digital project based competitive bidding in government contracts
JP6292841B2 (en) Supplier selection support device, supplier selection support method, and supplier selection support program
Hughes et al. Assessing the “clerk of works” role in delivering quality affordable housing: a UK case study
Mutikanga et al. Postaward construction and contract management of engineering, procurement, and construction hydropower projects: Two case studies from Uganda
Wang et al. Adopting BIM to facilitate dispute management in the construction industry: A conceptual framework development
Boadu et al. Client-led promotion of health and safety through the procurement process on public construction projects in developing countries
Yuan A dynamic model for assessing the effectiveness of construction and demolition waste management
Mufti et al. Quality Metric Design As A Tool To Control The Quality Of Project
CN112150240A (en) Information interaction system and method
Hooper et al. Whole-life infrastructure asset management: good practice guide for civil infrastructure
CN114331507B (en) Pricing method and system suitable for railway engineering
Akhtar Dealing with EPC Project Management Problems and Challenges A Case Study on Petrochemical, Oil and Gas EPC Projects in Middle-East
Radzuan et al. The Importance of Building Condition Survey Report for New House Buyers
Anticona Digital transformation of standard contracts into E-contracting
Leite et al. Premature start impact analysis tool: Preventing unintended construction interruptions and associated impacts
Gunduz et al. Damage to treasury: Abnormally low tenders in public construction works
Arumsari et al. Identification of dominant factors for the delays in building construction project in kepulauan Anambas
Carter Small modular reactor deployment: Learning from the past and the present

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140319

RJ01 Rejection of invention patent application after publication