CN113379377A - Power grid engineering construction approval processing method and device - Google Patents

Power grid engineering construction approval processing method and device Download PDF

Info

Publication number
CN113379377A
CN113379377A CN202110615030.3A CN202110615030A CN113379377A CN 113379377 A CN113379377 A CN 113379377A CN 202110615030 A CN202110615030 A CN 202110615030A CN 113379377 A CN113379377 A CN 113379377A
Authority
CN
China
Prior art keywords
approval
node
file
construction
target
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110615030.3A
Other languages
Chinese (zh)
Inventor
袁太平
彭飞
曾文龙
冷祥彪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Energy Development Research Institute of China Southern Power Grid Co Ltd
Original Assignee
Energy Development Research Institute of China Southern Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Energy Development Research Institute of China Southern Power Grid Co Ltd filed Critical Energy Development Research Institute of China Southern Power Grid Co Ltd
Priority to CN202110615030.3A priority Critical patent/CN113379377A/en
Publication of CN113379377A publication Critical patent/CN113379377A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F21/00Security arrangements for protecting computers, components thereof, programs or data against unauthorised activity
    • G06F21/60Protecting data
    • G06F21/62Protecting access to data via a platform, e.g. using keys or access control rules
    • G06F21/6218Protecting access to data via a platform, e.g. using keys or access control rules to a system of files or objects, e.g. local or distributed file system or database
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F21/00Security arrangements for protecting computers, components thereof, programs or data against unauthorised activity
    • G06F21/60Protecting data
    • G06F21/64Protecting data integrity, e.g. using checksums, certificates or signatures
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/018Certifying business or products
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/06Buying, selling or leasing transactions
    • G06Q30/08Auctions
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S50/00Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
    • Y04S50/10Energy trading, including energy flowing from end-user application to grid

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Health & Medical Sciences (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Finance (AREA)
  • General Health & Medical Sciences (AREA)
  • Computer Security & Cryptography (AREA)
  • Accounting & Taxation (AREA)
  • Software Systems (AREA)
  • Computer Hardware Design (AREA)
  • General Engineering & Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Bioethics (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Data Mining & Analysis (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Primary Health Care (AREA)
  • Databases & Information Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to a power grid engineering construction approval processing method and device. The method comprises the following steps: acquiring an approval file and a target approval node sent by a power grid engineering project node; verifying the approval file, and verifying whether the target approval node conforms to the preset approval workflow; when the examination and approval document and the target examination and approval node are verified to be qualified, the examination and approval document is sent to the corresponding target examination and approval node, and the target examination and approval node examines and approves the examination and approval document; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; and when the target approval node passes the approval, sending an approval result to the power grid engineering project node, and storing an approval file passing the approval to a safety database based on the block chain. The method solves the problems that a construction unit needs to report a large amount of engineering construction data and report repeatedly.

Description

Power grid engineering construction approval processing method and device
Technical Field
The application relates to the technical field of power grids, in particular to a power grid engineering construction approval processing method and device.
Background
The power grid engineering construction needs to be approved through a plurality of links from project establishment to completion, the number of related management departments is large, and the operation needs months, half a year or even longer. The approval phase, the management department and the related data requirements are also more, so that some problems often exist in the approval. For example, the amount of data and data to be reported is large. The construction unit responsible for handling the engineering construction program needs to continuously report the engineering project construction scheme, site selection scheme, technical measures, drawings and other data or data to each management department, and needs to report repeatedly in some links, and different management departments also need to review repeatedly, thereby increasing unnecessary workload.
Disclosure of Invention
In view of the above, it is necessary to provide a block chain power grid engineering construction approval processing method, device, computer device and storage medium capable of solving the problem of duplicate delivery.
A power grid engineering construction approval processing method comprises the following steps:
acquiring an approval file and a target approval node sent by a power grid engineering project node;
verifying the approval file, and verifying whether the target approval node conforms to a preset approval workflow;
after the examination and approval document and the target examination and approval node are verified to be qualified, the examination and approval document is sent to the corresponding target examination and approval node, and the target examination and approval node examines and approves the examination and approval document; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; the project establishment decision approval node, the construction early stage approval node, the bidding approval node, the reconnaissance design approval node and the construction approval node are approval nodes on a block chain technology-based collaborative approval platform;
and when the target approval node passes the approval, sending an approval result to the power grid engineering project node, and storing an approval file passing the approval to a safety database based on a block chain.
A power grid engineering construction approval processing apparatus includes:
the approval acquisition module is used for acquiring approval files and target approval nodes sent by the power grid engineering project nodes;
the checking module is used for checking the approval document and verifying whether the target approval node conforms to a preset approval workflow;
the approval module is used for sending the approval file to the corresponding target approval node after the approval file and the target approval node are verified to be qualified, and the target approval node approves the approval file; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; the project establishment decision approval node, the construction early stage approval node, the bidding approval node, the reconnaissance design approval node and the construction approval node are approval nodes on a block chain technology-based collaborative approval platform;
and the approval processing module is used for sending an approval result to the power grid engineering project node when the target approval node passes the approval, and storing an approval file passing the approval to a safety database based on a block chain.
A computer device comprising a memory and a processor, the memory storing a computer program, the processor implementing the following steps when executing the computer program:
acquiring an approval file and a target approval node sent by a power grid engineering project node;
verifying the approval file, and verifying whether the target approval node conforms to a preset approval workflow;
after the examination and approval document and the target examination and approval node are verified to be qualified, the examination and approval document is sent to the corresponding target examination and approval node, and the target examination and approval node examines and approves the examination and approval document; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; the project establishment decision approval node, the construction early stage approval node, the bidding approval node, the reconnaissance design approval node and the construction approval node are approval nodes on a block chain technology-based collaborative approval platform;
and when the target approval node passes the approval, sending an approval result to the power grid engineering project node, and storing an approval file passing the approval to a safety database based on a block chain.
A computer-readable storage medium, on which a computer program is stored which, when executed by a processor, carries out the steps of:
acquiring an approval file and a target approval node sent by a power grid engineering project node;
verifying the approval file, and verifying whether the target approval node conforms to a preset approval workflow;
after the examination and approval document and the target examination and approval node are verified to be qualified, the examination and approval document is sent to the corresponding target examination and approval node, and the target examination and approval node examines and approves the examination and approval document; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; the project establishment decision approval node, the construction early stage approval node, the bidding approval node, the reconnaissance design approval node and the construction approval node are approval nodes on a block chain technology-based collaborative approval platform;
and when the target approval node passes the approval, sending an approval result to the power grid engineering project node, and storing an approval file passing the approval to a safety database based on a block chain.
According to the power grid engineering construction approval processing method, the device, the computer equipment and the storage medium, approval is carried out based on the collaborative approval platform, for each approval node, after the approval file and the approval node are verified to be qualified, the approval file is sent to the approval node, and after the approval is passed, the approval file is stored in the safety database based on the block chain. Therefore, the method can realize the sharing of the approval document by relying on the database, repeatedly utilize the approval document and solve the problems that a construction unit needs to report a large amount of engineering construction data and report the data repeatedly.
Drawings
FIG. 1 is a diagram of an application environment of approval process for power grid engineering construction in one embodiment;
FIG. 2 is a schematic flow chart of approval process for power grid engineering construction in one embodiment;
fig. 3 is a block diagram of a power grid engineering construction approval processing apparatus in another embodiment;
FIG. 4 is a diagram illustrating an internal structure of a computer device according to an embodiment.
Detailed Description
In order to make the objects, technical solutions and advantages of the present application more apparent, the present application is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present application and are not intended to limit the present application.
The block chain-based power grid engineering supervision method can be applied to the application environment shown in fig. 1. The application environment is a collaborative approval platform based on a block chain technology. The collaborative approval platform is a platform which is established by utilizing a basic block chain technical hand based on the approval process of a power grid engineering project construction process program and division of work of department responsibilities. The platform can realize that different departments can share project approval information on the internet, realize communication interaction between a management department and a project construction unit, and realize on-line transmission of project program documents and on-line response approval.
And the Block chain comprises a series of blocks (blocks) which are mutually connected according to the generated chronological order, new blocks cannot be removed once being added into the Block chain, and recorded data submitted by nodes in the Block chain system are recorded in the blocks. The blockchain is a novel application mode of computer technologies such as distributed data storage, point-to-point transmission, a consensus mechanism and an encryption algorithm. A block chain (Blockchain), which is essentially a decentralized database, is a series of data blocks associated by using a cryptographic method, and each data block contains information of a batch of network transactions, so as to verify the validity (anti-counterfeiting) of the information and generate a next block. The blockchain may include a blockchain underlying platform, a platform product services layer, and an application services layer.
In an embodiment, as shown in fig. 2, the method is applied to a collaborative approval platform based on a block chain technology, and an approval processing method for power grid engineering construction is implemented, and includes the following steps:
and S202, acquiring an approval document and a target approval node sent by the power grid engineering project node.
Specifically, the power engineering project node refers to a project side node of a power engineering project. And the project direction submits the examination and approval document to each examination and approval node for examination and approval based on the collaborative examination and approval platform of the block chain technology.
And 204, verifying the approval document, and verifying whether the target approval node conforms to the preset approval workflow.
The verification of the approval document refers to the verification of whether the approval document meets the requirement of the target approval node. Different examination and approval nodes have different examination and approval contents and different corresponding required examination and approval files. For example, at the project decision approval node, project recommendation and feasibility analysis reports are approved. For example, in the pre-construction approval node, documents such as planning, territory, water conservancy and environmental protection are approved.
Whether the target approval node meets the preset approval workflow is verified, the approval process can meet the standard, and the next approval process can be carried out after the previous approval process is finished. The problem that examination and approval are carried out in the early stage of construction if an unclassified item passes through examination and approval due to disordered examination and approval processes is solved.
Step 206, after the examination and approval document and the target examination and approval node are verified to be qualified, the examination and approval document is sent to the corresponding target examination and approval node, and the target examination and approval node examines and approves the examination and approval document; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; the system comprises a project establishment decision approval node, a construction early-stage approval node, a bidding approval node, a survey design approval node and a construction approval node, wherein the acceptance node is an approval node on a block chain technology-based collaborative approval platform.
Specifically, the approval node for item establishment decision, the examination and approval node for early construction, the examination and approval node for bidding and tendering, the investigation and design examination and approval node and the construction examination and approval node take the acceptance node as the examination and approval node on the block chain technology-based collaborative examination and approval platform. The collaborative approval platform is constructed based on a block chain technology, and a database of the collaborative approval platform adopts distributed storage of a block chain, so that construction units of different projects can report data and data required by engineering construction programs based on the same management platform, and repeated declaration is reduced; different management departments can also audit the relevant data of the engineering construction based on the same management platform, and the audit result can be shared, so that repeated audit is avoided. By using the key technology of the block chain, necessary confidentiality can be carried out on engineering construction related data.
And when the examination and approval document and the target examination and approval node are verified to be qualified, namely the examination and approval document is matched with the examination and approval content of the target examination and approval node, and the target examination and approval node conforms to the examination and approval workflow, the examination and approval document is sent to the corresponding target examination and approval node, and the target examination and approval node examines and approves the examination document.
Specifically, the approval is carried out by an item establishment decision approval node, a construction early-stage approval node, a bidding approval node, a survey design approval node and a construction approval node through an acceptance node. Namely, the collaborative approval platform is utilized to approve links from generation to completion of the power grid engineering project.
And 208, when the target approval node passes the approval, sending an approval result to the power grid engineering project node, and storing an approval document passing the approval to a safety database based on the block chain.
Specifically, the approval result includes two cases of approval pass and approval fail. After the approval is passed, the approved file is stored in the safety database based on the block chain, so that when the file needs to be reused, the file in the safety database can be directly utilized without repeated reporting.
It can be understood that when the approval result is fed back to the power grid engineering project node, the reason why the approval fails can also be fed back for the approval result that fails, so that the power grid engineering project side can modify the approval result.
According to the power grid engineering construction approval processing method, approval is carried out based on the collaborative approval platform, for each approval node, after the approval file and the approval node are verified to be qualified, the approval file is sent to the approval node, and after the approval is passed, the approval file is stored in the safety database based on the block chain. Therefore, the method can realize the sharing of the approval document by relying on the database, repeatedly utilize the approval document and solve the problems that a construction unit needs to report a large amount of engineering construction data and report the data repeatedly.
In another embodiment, when the target approval node is an item establishment decision approval node, the approval document comprises an item establishment document; sending the approval file to a corresponding target approval node, comprising: and sending the establishment file to establishment decision approval nodes, wherein the establishment decision approval nodes comprise a modification department node and a financial department node, and the modification department node and the financial department node carry out establishment decision approval on the power grid project.
Specifically, the approval departments of the approval decision approval nodes are modification departments and financial departments, the corresponding approval documents include approval documents, and the approval documents include project recommendation and feasibility study reports. The project establishment decision approval node is a first approval node in a preset approval workflow, and after project establishment decision approval, a power grid work construction project is completed. And the modification department node and the financial department node respectively carry out project decision approval on the project recommendation and the feasibility study report from the modification and financial aspects.
In another embodiment, the pre-construction approval node comprises: planning an approval node, a state and soil approval node, a water conservancy approval node or an environmental protection approval node; when the target approval node is an approval node in the early stage of construction, the approval file comprises a planning approval file, a state and soil approval file, a water conservancy approval file or an environmental protection approval file; sending the approval file to a corresponding target approval node, comprising: and sending the planning approval file to a planning approval node, carrying out planning approval on the power grid engineering construction by the planning approval node, or sending the homeland approval file to a homeland approval department, carrying out homeland approval on the power grid engineering construction by the homeland approval node, or sending the water conservancy approval file to a water conservancy approval node, carrying out water conservancy approval on the power grid engineering construction by the water conservancy approval node, or sending the environmental protection approval file to an environmental protection approval node, and carrying out environmental protection approval on the power grid engineering construction by the environmental protection approval node.
In this embodiment, the examination and approval in the early stage of construction includes planning and approval by a planning department, national and local examination and approval by a national and local department, water conservancy examination and approval by a water conservancy department, and environmental protection examination and approval by an environmental protection department. Because the collaborative approval platform can be used for on-line approval, files required by the preliminary examination and approval of the construction can be submitted to all departments simultaneously, the project documents can be transmitted on line, all the preliminary examination and approval departments can examine and approve the related data of the same power grid project based on the collaborative approval platform, and repeated submission is avoided.
In another embodiment, when the target approval node is a survey design approval node, the approval document comprises: survey reports, design schemes and construction drawings; sending the approval file to a corresponding target approval node, comprising: and sending the survey report, the design scheme and the construction drawing to a survey design approval node, and carrying out survey design approval on the power grid engineering construction by the survey design approval node.
Specifically, the investigation and design approval comprises investigation report approval, design scheme approval and construction drawing approval. Specifically, the construction drawing examination and approval mechanism carries out examination and approval, and after the examination and approval are passed, the corresponding examination and approval results are sent to the power grid engineering project nodes.
In another embodiment, when the target approval node is a bidding approval node, the approval document comprises a bidding approval document, and the bidding approval document comprises a bidding announcement, a bidding document, an opening bid evaluation document and a contract; sending the approval file to a corresponding target approval node, comprising: and sending the bidding document to a bidding approval node, and performing bidding approval and supervision on the power grid project by the bidding approval node.
Specifically, the documents required for the examination and approval of bidding are bidding examination and approval documents, including bidding bulletins, bidding documents, bid opening and evaluation documents, and contracts. The bidding approval node is specifically a bidding supervision department which carries out approval supervision on various process files in the bidding process.
In another embodiment, when the target approval node is a construction approval node, the approval file comprises a construction approval file, and the construction approval file comprises a construction permission file, a quality supervision file and a safety supervision file; sending the approval file to a corresponding target approval node, comprising: and sending the construction approval file to a construction approval node, and carrying out construction approval and supervision on the power grid project by the construction approval node.
Specifically, the construction approval nodes comprise a construction department, a quality supervision station and a safety supervision station. The construction approval node supervises the construction process, and audits and supervises the construction permission file, the quality supervision file and the safety supervision file.
Specifically, the method for verifying the approval document includes: checking whether the approval file is repeated with the existing qualified file of the power grid engineering project; if not, checking whether the file name meets the requirement of the target approval node; and if the requirements are met, verifying that the approval file is qualified.
Specifically, at each approval node, the approved file is checked, and the checking mode includes file repetition checking and name checking. The file repetition check refers to checking whether the approved file is repeated with the existing qualified file of the power grid engineering project. The file repetition can be avoided through the file repetition check, and the repeated declaration is reduced. Through name verification, the submitted approval document can meet the requirements of the target approval node, and document mistransmission and documents arriving at the approval node are avoided not being the documents to be approved.
In another embodiment, the method for verifying whether the target approval node conforms to the preset approval workflow includes: and obtaining an approval workflow from the last approval node to the target approval node, comparing the approval workflow with a preset workflow, and determining whether the target approval node conforms to the preset workflow.
Specifically, the workflow technology is used for verifying the approval process, so that the approval work conforms to the preset workflow. That is, after the preset workflow is approved by the set previous approval node, the approval workflow from the previous approval node to the target approval node can be initiated.
It should be understood that, although the steps in the flowchart of fig. 2 are shown in order as indicated by the arrows, the steps are not necessarily performed in order as indicated by the arrows. The steps are not performed in the exact order shown and described, and may be performed in other orders, unless explicitly stated otherwise. Moreover, at least a portion of the steps in fig. 2 may include multiple steps or multiple stages, which are not necessarily performed at the same time, but may be performed at different times, which are not necessarily performed in sequence, but may be performed in turn or alternately with other steps or at least a portion of the other steps or stages.
In one embodiment, as shown in fig. 3, there is provided a power grid engineering construction approval processing apparatus, including:
the approval obtaining module 302 is used for obtaining approval files and target approval nodes sent by the power grid engineering project nodes;
the checking module 304 is used for checking the approval document and verifying whether the target approval node meets the preset approval workflow;
the approval module 306 is used for sending the approval document to the corresponding target approval node after the approval document and the target approval node are verified to be qualified, and approving the approval document by the target approval node; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; the system comprises a project establishment decision approval node, a construction early-stage approval node, a bidding approval node, a survey design approval node and a construction approval node, wherein the acceptance node is an approval node on a block chain technology-based collaborative approval platform;
and the approval processing module 308 is configured to send an approval result to the power grid engineering project node when the target approval node passes the approval, and store the approved approval file in the safety database based on the block chain.
According to the power grid engineering construction approval processing device, approval is carried out based on the collaborative approval platform, for each approval node, after the approval file and the approval node are verified to be qualified, the approval file is sent to the approval node, and after the approval is passed, the approval file is stored in the safety database based on the block chain. Therefore, the method can realize the sharing of the approval document by relying on the database, repeatedly utilize the approval document and solve the problems that a construction unit needs to report a large amount of engineering construction data and report the data repeatedly.
In another embodiment, when the target approval node is an item establishment decision approval node, the approval document comprises an item establishment document; the examination and approval module is used for sending the standing item file to a standing item decision examination and approval node, the standing item decision examination and approval node comprises a modification department node and a financial department node, and the modification department node and the financial department node conduct standing item decision examination and approval on the power grid project.
In another embodiment, the pre-construction approval node comprises: planning an approval node, a state and soil approval node, a water conservancy approval node or an environmental protection approval node; when the target approval node is an approval node in the early stage of construction, the approval module is used for sending the planning approval file to the planning approval node, the planning approval node carries out planning approval on the construction of the power grid project, or the homeland approval file is sent to a homeland approval department, the homeland approval node carries out homeland approval on the construction of the power grid project, or the water conservancy approval file is sent to the water conservancy approval node, the water conservancy approval node carries out water conservancy approval on the construction of the power grid project, or the environmental protection approval file is sent to the environmental protection approval node, and the environmental protection approval node carries out environmental protection approval on the construction of the power grid project.
In another embodiment, when the target approval node is a survey design approval node, the approval document comprises: survey reports, design schemes and construction drawings; and the approval module is used for sending the investigation report, the design scheme and the construction drawing to an approval node of investigation design, and the approval node of investigation design is used for carrying out approval of investigation design on the power grid engineering construction.
In another embodiment, when the target approval node is a bidding approval node, the approval document comprises a bidding approval document, and the bidding approval document comprises a bidding announcement, a bidding document, an opening bid evaluation document and a contract; and the approval module is used for sending the bidding document to the bidding approval node, and the bidding approval node performs bidding approval and supervision on the power grid project.
In another embodiment, when the target approval node is a construction approval node, the approval file comprises a construction approval file, and the construction approval file comprises a construction permission file, a quality supervision file and a safety supervision file; sending the approval file to a corresponding target approval node, comprising: and sending the construction approval file to a construction approval node, and carrying out construction approval and supervision on the power grid project by the construction approval node.
In another embodiment, when the target approval node is an as-built approval node, the approval file comprises an acceptance file comprising an as-built acceptance file, an asset management file, and an operation maintenance file; and the approval module is used for sending the acceptance file to completion acceptance nodes, and the completion acceptance nodes are used for carrying out completion acceptance approval and supervision on the power grid engineering.
In another embodiment, the verification module is used for verifying whether the approval document is repeated with the existing qualified document of the power grid engineering project; if not, checking whether the file name meets the requirement of the target approval node; and if the requirements are met, verifying that the approval file is qualified.
In another embodiment, the verification module is further configured to obtain an approval workflow from a previous approval node to the target approval node, compare the approval workflow with a preset workflow, and determine whether the target approval node meets the preset workflow.
For specific limitations of the power grid engineering construction approval processing device, reference may be made to the above limitations on the power grid engineering construction approval processing method, and details are not described herein again. All or part of each module in the power grid engineering construction approval processing device can be realized by software, hardware and a combination thereof. The modules can be embedded in a hardware form or independent from a processor in the computer device, and can also be stored in a memory in the computer device in a software form, so that the processor can call and execute operations corresponding to the modules.
In one embodiment, a computer device is provided, which may be a server, the internal structure of which may be as shown in fig. 4. The computer device includes a processor, a memory, and a network interface connected by a system bus. Wherein the processor of the computer device is configured to provide computing and control capabilities. The memory of the computer device comprises a nonvolatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program, and a database. The internal memory provides an environment for the operation of an operating system and computer programs in the non-volatile storage medium. The database of the computer device is used for storing the approval document. The network interface of the computer device is used for communicating with an external terminal through a network connection. The computer program is executed by the processor to realize a power grid engineering construction approval processing method.
Those skilled in the art will appreciate that the architecture shown in fig. 4 is merely a block diagram of some of the structures associated with the disclosed aspects and is not intended to limit the computing devices to which the disclosed aspects apply, as particular computing devices may include more or less components than those shown, or may combine certain components, or have a different arrangement of components.
In one embodiment, a computer device is provided, which comprises a memory and a processor, wherein the memory stores a computer program, and the processor implements the steps of the above implementation methods when executing the computer program.
In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored, which, when being executed by a processor, carries out the steps of the method of the embodiments described above.
It will be understood by those skilled in the art that all or part of the processes of the methods of the embodiments described above can be implemented by hardware instructions of a computer program, which can be stored in a non-volatile computer-readable storage medium, and when executed, can include the processes of the embodiments of the methods described above. Any reference to memory, storage, database or other medium used in the embodiments provided herein can include at least one of non-volatile and volatile memory. Non-volatile Memory may include Read-Only Memory (ROM), magnetic tape, floppy disk, flash Memory, optical storage, or the like. Volatile Memory can include Random Access Memory (RAM) or external cache Memory. By way of illustration and not limitation, RAM can take many forms, such as Static Random Access Memory (SRAM) or Dynamic Random Access Memory (DRAM), among others.
The technical features of the above embodiments can be arbitrarily combined, and for the sake of brevity, all possible combinations of the technical features in the above embodiments are not described, but should be considered as the scope of the present specification as long as there is no contradiction between the combinations of the technical features.
The above-mentioned embodiments only express several embodiments of the present application, and the description thereof is more specific and detailed, but not construed as limiting the scope of the invention. It should be noted that, for a person skilled in the art, several variations and modifications can be made without departing from the concept of the present application, which falls within the scope of protection of the present application. Therefore, the protection scope of the present patent shall be subject to the appended claims.

Claims (10)

1. A power grid engineering construction approval processing method comprises the following steps:
acquiring an approval file and a target approval node sent by a power grid engineering project node;
verifying the approval file, and verifying whether the target approval node conforms to a preset approval workflow;
after the examination and approval document and the target examination and approval node are verified to be qualified, the examination and approval document is sent to the corresponding target examination and approval node, and the target examination and approval node examines and approves the examination and approval document; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; the project establishment decision approval node, the construction early stage approval node, the bidding approval node, the reconnaissance design approval node and the construction approval node are approval nodes on a block chain technology-based collaborative approval platform;
and when the target approval node passes the approval, sending an approval result to the power grid engineering project node, and storing an approval file passing the approval to a safety database based on a block chain.
2. The method of claim 1, wherein when the target approval node is a project decision approval node, the approval document comprises a project document; the sending the approval file to the corresponding target approval node comprises: and sending the establishment file to an establishment decision approval node, wherein the establishment decision approval node comprises a modification department node and a financial department node, and the modification department node and the financial department node carry out establishment decision approval on the power grid project.
3. The method of claim 1, wherein the pre-construction approval node comprises: planning an approval node, a state and soil approval node, a water conservancy approval node or an environmental protection approval node; when the target approval node is an approval node in the early stage of construction, the approval file comprises a planning approval file, a homeland approval file, a water conservancy approval file or an environmental protection approval file; the sending the approval file to the corresponding target approval node comprises: and sending the planning approval file to a planning approval node, carrying out planning approval on the power grid engineering construction by the planning approval node, or sending the national and local approval file to a national and local approval department, carrying out national and local approval on the power grid engineering construction by the national and local approval node, or sending the water conservancy approval file to a water conservancy approval node, carrying out water conservancy approval on the power grid engineering construction by the water conservancy approval node, or sending the environment-friendly approval file to an environment-friendly approval node, and carrying out environment-friendly approval on the power grid engineering construction by the environment-friendly approval node.
4. The method of claim 1, wherein when the target approval node is a survey design approval node, the approval document comprises: survey reports, design schemes and construction drawings; the sending the approval file to the corresponding target approval node comprises: and sending the survey report, the design scheme and the construction drawing to a survey design approval node, and carrying out survey design approval on the power grid engineering construction by the survey design approval node.
5. The method according to claim 1, wherein when the target approval node is a bidding approval node, the approval document comprises a bidding approval document comprising a bidding announcement, a bidding document, an opening bid evaluation document and a contract; the sending the approval file to the corresponding target approval node comprises: and sending the bidding document to a bidding approval node, and carrying out bidding approval and supervision on the power grid project by the bidding approval node.
6. The method of claim 1, wherein when the target approval node is a construction approval node, the approval file comprises a construction approval file, the construction approval file comprises a construction approval file, a quality supervision file, and a security supervision file; the sending the approval file to the corresponding target approval node comprises: and sending the construction approval file to a construction approval node, and carrying out construction approval and supervision on the power grid project by the construction approval node.
7. The method of claim 1, wherein when the target approval node is an as-built approval node, the approval file comprises an approval file comprising an as-built approval file, an asset management file, and an operational maintenance file; the sending the approval file to the corresponding target approval node comprises: and sending the acceptance file to an completion acceptance node, and performing completion acceptance approval and supervision on the power grid project by the completion acceptance node.
8. The method of claim 1, wherein the means for verifying the approved document comprises:
checking whether the approval file is repeated with the existing qualified file of the power grid engineering project; if not, checking whether the file name meets the requirement of the target approval node; and if the requirements are met, verifying that the approval file is qualified.
9. The method according to claim 1, wherein the means for verifying whether the target approval node conforms to a preset approval workflow comprises:
and obtaining an approval workflow from the last approval node to the target approval node, comparing the approval workflow with a preset workflow, and determining whether the target approval node conforms to the preset workflow.
10. The utility model provides a grid engineering construction approval processing apparatus which characterized in that includes:
the approval acquisition module is used for acquiring approval files and target approval nodes sent by the power grid engineering project nodes;
the checking module is used for checking the approval document and verifying whether the target approval node conforms to a preset approval workflow;
the approval module is used for sending the approval file to the corresponding target approval node after the approval file and the target approval node are verified to be qualified, and the target approval node approves the approval file; the target approval node comprises: the method comprises the following steps of establishing a decision approval node, a construction early-stage approval node, a bidding approval node, a reconnaissance design approval node and a construction approval node for acceptance; the project establishment decision approval node, the construction early stage approval node, the bidding approval node, the reconnaissance design approval node and the construction approval node are approval nodes on a block chain technology-based collaborative approval platform;
and the approval processing module is used for sending an approval result to the power grid engineering project node when the target approval node passes the approval, and storing an approval file passing the approval to a safety database based on a block chain.
CN202110615030.3A 2021-06-02 2021-06-02 Power grid engineering construction approval processing method and device Pending CN113379377A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110615030.3A CN113379377A (en) 2021-06-02 2021-06-02 Power grid engineering construction approval processing method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110615030.3A CN113379377A (en) 2021-06-02 2021-06-02 Power grid engineering construction approval processing method and device

Publications (1)

Publication Number Publication Date
CN113379377A true CN113379377A (en) 2021-09-10

Family

ID=77575557

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110615030.3A Pending CN113379377A (en) 2021-06-02 2021-06-02 Power grid engineering construction approval processing method and device

Country Status (1)

Country Link
CN (1) CN113379377A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6308188B1 (en) * 1997-06-19 2001-10-23 International Business Machines Corporation System and method for building a web site with automated workflow
CN103646315A (en) * 2013-12-16 2014-03-19 国家电网公司 Method and device for data processing in electricity bureau engineering project workflow
CN106251122A (en) * 2016-08-03 2016-12-21 天津西瑞尔信息工程有限公司 A kind of workflow processing method and device
CN107516191A (en) * 2017-08-10 2017-12-26 广州市城市规划勘测设计研究院 " more rule unifications " " figure " Project cooperation approval system, method and instrument
CN109584079A (en) * 2018-11-29 2019-04-05 阿里巴巴集团控股有限公司 The measures and procedures for the examination and approval, device and the equipment that resource processing system, resource item are declared
CN109858751A (en) * 2018-12-26 2019-06-07 中国大唐集团科学技术研究院有限公司 Power engineering Evaluating Projects System
CN109858262A (en) * 2019-01-17 2019-06-07 平安科技(深圳)有限公司 Workflow examination and approval method, apparatus, system and storage medium based on block catenary system
CN109993503A (en) * 2019-04-02 2019-07-09 深圳智乾区块链科技有限公司 The intelligent measures and procedures for the examination and approval, device and computer readable storage medium
CN112712335A (en) * 2020-12-30 2021-04-27 北京宇信科技集团股份有限公司 Working method, server, medium and equipment of workflow engine

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6308188B1 (en) * 1997-06-19 2001-10-23 International Business Machines Corporation System and method for building a web site with automated workflow
CN103646315A (en) * 2013-12-16 2014-03-19 国家电网公司 Method and device for data processing in electricity bureau engineering project workflow
CN106251122A (en) * 2016-08-03 2016-12-21 天津西瑞尔信息工程有限公司 A kind of workflow processing method and device
CN107516191A (en) * 2017-08-10 2017-12-26 广州市城市规划勘测设计研究院 " more rule unifications " " figure " Project cooperation approval system, method and instrument
CN109584079A (en) * 2018-11-29 2019-04-05 阿里巴巴集团控股有限公司 The measures and procedures for the examination and approval, device and the equipment that resource processing system, resource item are declared
CN109858751A (en) * 2018-12-26 2019-06-07 中国大唐集团科学技术研究院有限公司 Power engineering Evaluating Projects System
CN109858262A (en) * 2019-01-17 2019-06-07 平安科技(深圳)有限公司 Workflow examination and approval method, apparatus, system and storage medium based on block catenary system
CN109993503A (en) * 2019-04-02 2019-07-09 深圳智乾区块链科技有限公司 The intelligent measures and procedures for the examination and approval, device and computer readable storage medium
CN112712335A (en) * 2020-12-30 2021-04-27 北京宇信科技集团股份有限公司 Working method, server, medium and equipment of workflow engine

Similar Documents

Publication Publication Date Title
CN110609869B (en) Block chain-based data storage method, related equipment and storage medium
US11102001B2 (en) Trust management system and trust management method
CN109064124B (en) Method and device for verifying and storing work history based on block chain
CN111435241A (en) Machine-to-machine transactions using distributed ledgers in a process control system
CN111435240A (en) Maintaining quality control, regulatory, and parameter measurement data using distributed ledger in a process control system
WO2022088606A1 (en) Gbdt and lr fusion method and apparatus based on federated learning, device, and storage medium
US11196564B2 (en) Hierarchical distributed ledger
CN111782723A (en) Double-layer product information tracing system architecture based on permission chain
CN111010282B (en) Block chain-based information processing method, related device and storage medium
EP3792849A1 (en) Apparatus and method for generating evaluation data of facilities and projects
CN111222853A (en) Project resource management method and device based on block chain and computer equipment
EP3542300B1 (en) Method for operating a peer-to-peer application
Aleksieva et al. Implementation of smart contracts based on hyperledger fabric blockchain for the purpose of insurance services
Li et al. Reputation-based trustworthy supply chain management using smart contract
Zhu [Retracted] Research on Real‐Time Tracking Algorithm of E‐Commerce Logistics Information Based on Blockchain Technology
CN117573768A (en) Block chain-based service handling data processing method, device, system and equipment
CN110727735B (en) Method, device and equipment for cooperatively completing task event based on block chain technology
CN111552989A (en) Service data processing method, device, equipment and storage medium based on block chain
CN113379377A (en) Power grid engineering construction approval processing method and device
Gu et al. ML on Chain: The Case and Taxonomy of Machine Learning on Blockchain
CN111861476B (en) Malicious associated transaction monitoring method and device based on blockchain and computer equipment
CN114549149A (en) Smart grid energy transaction data processing method and device and computer equipment
CN114564358A (en) Method, apparatus, device, medium and product for checking compliance of change operations
US11381401B2 (en) Blockchain transaction forwarding
CN111340333A (en) Payment service data processing method and device and computer equipment

Legal Events