CN103590393A - Construction method of composite pile - Google Patents

Construction method of composite pile Download PDF

Info

Publication number
CN103590393A
CN103590393A CN201310585342.XA CN201310585342A CN103590393A CN 103590393 A CN103590393 A CN 103590393A CN 201310585342 A CN201310585342 A CN 201310585342A CN 103590393 A CN103590393 A CN 103590393A
Authority
CN
China
Prior art keywords
pile
composite
composite pile
job practices
hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310585342.XA
Other languages
Chinese (zh)
Inventor
邢峰
朱建新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310585342.XA priority Critical patent/CN103590393A/en
Publication of CN103590393A publication Critical patent/CN103590393A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a construction method of a composite pile. The construction method includes the steps of moving a machine in place, and forming a hollow pile at the center of a constructed peripheral pile through the internal tamping technology or the internal tamping interaction technology or the internal screwing technology or the bilateral bushing technology; directly placing a reinforcement cage into the hollow pile and then pouring concrete, or pouring concrete through pressure and then placing the reinforcement cage, and forming the composite pile; or includes the steps of enabling a tubular pile to be sunken into the hollow pile, filling the tubular pile and the peripheral gap with fillers to form a sandwich layer, and forming the composite pile. According to the construction method of the composite pile, construction is convenient to conduct, the formed composite pile is reasonable in structure and high in work efficiency, and the method is high in cost performance and can be widely applied to foundation engineering.

Description

The job practices of composite pile
Technical field
The present invention relates to a kind of job practices of composite pile.
Background technology
Existing composite pile, due to reasons such as structures, work efficiency is not high, has undesirable going out; For playing the interim stake acting on, its inner core stake can not reuse, and causes waste.
Summary of the invention
The object of the present invention is to provide a kind of rational in infrastructure, the job practices of the composite pile that work efficiency is high.
Technical solution of the present invention is:
A job practices for composite pile, is characterized in that: comprise the following steps:
(1) telephone-moving is in place, rams, interior rammer is mutual, inside spin or two sleeve pipe technique formation hollow pile in the center of the outer skirt piles of having constructed adopts;
(2) adopt in hollow pile and directly first place reinforcing cage concreting again, or first guncreting is put reinforcing cage, formation composite pile again;
Or in hollow pile, sinking to pile tube, formation sandwich of layers is filled with filler in pile tube and around space, forms composite pile.
Described sandwich of layers is water, and through the ice sheet of freezing formation.
Described sandwich of layers is the layer of heat-fusible material of easy hot melt.
Described hot melt material is paraffin, grease, pitch or sulphide mastic.
Described sandwich of layers is sand, salt, soil, lime or Flyash Layer, at pile tube outsourcing barrier film or be coated with anti-friction composition outward.
Inner frame system is set in pile tube, and inner frame system is steel plate, shaped steel, i iron, four-bladed vane or reinforcing cage etc.; Described pile tube is steel pipe pile, Plastic Steel Pipe, glass reinforced plastic pipe, rubber plastic pipe or pre-stress hollow pile pipe etc.
Easy construction of the present invention, the composite pile of formation is rational in infrastructure, and work efficiency is high; Cost performance is high, can be widely used in Foundation Design.
Below in conjunction with embodiment, the invention will be further described.
The specific embodiment
Embodiment 1:
A job practices for composite pile, comprises the following steps:
(1) telephone-moving is in place, rams, interior rammer is mutual, inside spin or two sleeve pipe technique formation hollow pile in the center of the outer skirt piles of having constructed adopts;
(2) adopt in hollow pile and directly first place reinforcing cage concreting again, or first guncreting is put reinforcing cage, formation composite pile again.
Embodiment 2:
A job practices for composite pile, is characterized in that: comprise the following steps:
(1) telephone-moving is in place, rams, interior rammer is mutual, inside spin or two sleeve pipe technique form hollow pile in adopting;
(2) in hollow pile, sink to pile tube, formation sandwich of layers is filled with filler in pile tube and around space, forms composite pile.
Described sandwich of layers is water, and through the ice sheet of freezing formation.In pile tube, arrange water is carried out to freezing cooling pipe.
Or described sandwich of layers is the layer of heat-fusible material of easy hot melt, described hot melt material is paraffin, grease, pitch or sulphide mastic, and the water back that hot melt material is carried out to heat fused is set in pile tube.
Or described sandwich of layers is sand, salt, soil, lime or Flyash Layer, at pile tube outsourcing barrier film or be coated with anti-friction composition outward.
Inner frame system is set in pile tube, and inner frame system is steel plate, shaped steel, i iron, four-bladed vane or reinforcing cage etc.; Described pile tube is steel pipe pile, Plastic Steel Pipe, glass reinforced plastic pipe, rubber plastic pipe or pre-stress hollow pile pipe etc.
While needing, by ice sheet or hot melt material are melted, pile tube and/or inner frame system are taken out to Reusability.

Claims (6)

1. a job practices for composite pile, is characterized in that: comprise the following steps:
(1) telephone-moving is in place, rams, interior rammer is mutual, inside spin or two sleeve pipe technique formation hollow pile in the center of the outer skirt piles of having constructed adopts;
(2) adopt in hollow pile and directly first place reinforcing cage concreting again, or first guncreting is put reinforcing cage, formation composite pile again;
Or in hollow pile, sinking to pile tube, formation sandwich of layers is filled with filler in pile tube and around space, forms composite pile.
2. the job practices of composite pile according to claim 1, is characterized in that: described sandwich of layers is water, and through the ice sheet of freezing formation.
3. the job practices of composite pile according to claim 1, is characterized in that: described sandwich of layers is the layer of heat-fusible material of easy hot melt.
4. the job practices of composite pile according to claim 3, is characterized in that: described hot melt material is paraffin, grease, pitch or sulphide mastic.
5. the job practices of composite pile according to claim 1, is characterized in that: described sandwich of layers is sand, salt, soil, lime or Flyash Layer, at pile tube outsourcing barrier film or be coated with anti-friction composition outward.
6. according to the job practices of the composite pile described in claim 1,2,3,4 or 5, it is characterized in that: inner frame system is set in pile tube, and inner frame system is steel plate, shaped steel, i iron, four-bladed vane or reinforcing cage; Described pile tube is steel pipe pile, Plastic Steel Pipe, glass reinforced plastic pipe, rubber plastic pipe or pre-stress hollow pile pipe.
CN201310585342.XA 2013-11-21 2013-11-21 Construction method of composite pile Pending CN103590393A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310585342.XA CN103590393A (en) 2013-11-21 2013-11-21 Construction method of composite pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310585342.XA CN103590393A (en) 2013-11-21 2013-11-21 Construction method of composite pile

Publications (1)

Publication Number Publication Date
CN103590393A true CN103590393A (en) 2014-02-19

Family

ID=50080695

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310585342.XA Pending CN103590393A (en) 2013-11-21 2013-11-21 Construction method of composite pile

Country Status (1)

Country Link
CN (1) CN103590393A (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1050421A (en) * 1990-11-12 1991-04-03 中国建筑科学研究院珠海科研设计部 The piling method of casting prefabricated composite pile
CN1272574A (en) * 2000-04-03 2000-11-08 王光明 Immersed tube bored concrete composite pile construction method
CN1414186A (en) * 2002-05-10 2003-04-30 贾燎 Sleeve pile and designing method
CN1542235A (en) * 2003-04-29 2004-11-03 天津市水利科学研究所 Strong-core deep injection stirring pile-making method and special drill bit therefor
CN101270572A (en) * 2008-04-24 2008-09-24 杨举 Dam construction method using refrigeration technique
CN101962951A (en) * 2010-09-14 2011-02-02 东南大学 Construction method of composite pile of fiber reinforced composite deep-water bridge and composite pile thereof
CN102587360A (en) * 2012-03-22 2012-07-18 沙焕焕 Large-diameter strong composite pile
CN102644269A (en) * 2012-05-04 2012-08-22 朱建新 Non-earth-borrowing composite pile and construction method thereof
CN102733376A (en) * 2012-07-02 2012-10-17 朱建新 Composite pile and construction method thereof
JP2013163941A (en) * 2012-02-13 2013-08-22 Kentec Inc Foundation reinforcing pile and construction method of foundation reinforcing pile
CN103397633A (en) * 2013-07-26 2013-11-20 张继红 Self-drilling RCA (recycling composite anchor) rod and construction method thereof

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1050421A (en) * 1990-11-12 1991-04-03 中国建筑科学研究院珠海科研设计部 The piling method of casting prefabricated composite pile
CN1272574A (en) * 2000-04-03 2000-11-08 王光明 Immersed tube bored concrete composite pile construction method
CN1414186A (en) * 2002-05-10 2003-04-30 贾燎 Sleeve pile and designing method
CN1542235A (en) * 2003-04-29 2004-11-03 天津市水利科学研究所 Strong-core deep injection stirring pile-making method and special drill bit therefor
CN101270572A (en) * 2008-04-24 2008-09-24 杨举 Dam construction method using refrigeration technique
CN101962951A (en) * 2010-09-14 2011-02-02 东南大学 Construction method of composite pile of fiber reinforced composite deep-water bridge and composite pile thereof
JP2013163941A (en) * 2012-02-13 2013-08-22 Kentec Inc Foundation reinforcing pile and construction method of foundation reinforcing pile
CN102587360A (en) * 2012-03-22 2012-07-18 沙焕焕 Large-diameter strong composite pile
CN102644269A (en) * 2012-05-04 2012-08-22 朱建新 Non-earth-borrowing composite pile and construction method thereof
CN102733376A (en) * 2012-07-02 2012-10-17 朱建新 Composite pile and construction method thereof
CN103397633A (en) * 2013-07-26 2013-11-20 张继红 Self-drilling RCA (recycling composite anchor) rod and construction method thereof

Similar Documents

Publication Publication Date Title
CN105862916A (en) Superimposed assembled type underground pipe gallery system and construction and manufacturing process
CN103074890A (en) Plastic sleeve and steel pipe combined cast-in-place concrete hollow pipe pile and construction method thereof
CN206189455U (en) Piping lane
CN105839667A (en) Construction and manufacturing process of total-prefabricated superimposed assembly type underground pipe gallery
CN206706791U (en) Base pit dewatering well plugging structure
CN103510511A (en) Top-reinforced cast-in-place concrete thin-wall pipe pile and construction method
CN108560542A (en) A kind of waste tire cladding builds the two-directed reinforcement and its construction method of slag
CN106593470A (en) High-permeability water-rich sand shield terminal reinforcing system and construction method thereof
CN106677551A (en) Method for compositely strengthening steel pipe column through external sleeveing of circular steel pipe concrete fibre composite materials
CN208844417U (en) A kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place pier column
CN106437034A (en) Steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and preparation method thereof
CN105200983A (en) PVC pipe and thick wall steel tube composite hollow recycled concrete pile
CN108412506A (en) Ground fissure region tunnel lining structure based on shield tunnel and its construction method
CN201943086U (en) Underground building wall body
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN106481347B (en) A kind of anti-internal water pressure composite shield section of jurisdiction
CN103133004A (en) Technological process of ground prefabrication and installation of inner shaft wall of freezing shaft
CN208040386U (en) A kind of ground fissure region tunnel lining structure based on shield tunnel
CN206338075U (en) A kind of anti-internal water pressure composite shield section of jurisdiction
CN205314372U (en) Steel reinforcement cage protective layer cushion
CN106759857B (en) Steel tube regeneration monolith assembling structure
CN103590393A (en) Construction method of composite pile
CN202989911U (en) Post-grouting pile of precast concrete
CN203066063U (en) Plastic sleeve and steel tube combined cast-in-situ concrete hollow pipe pile
CN107905368A (en) A kind of assembled beam and assembled column connection structure and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140219