CN106437034A - Steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and preparation method thereof - Google Patents
Steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and preparation method thereof Download PDFInfo
- Publication number
- CN106437034A CN106437034A CN201611067584.XA CN201611067584A CN106437034A CN 106437034 A CN106437034 A CN 106437034A CN 201611067584 A CN201611067584 A CN 201611067584A CN 106437034 A CN106437034 A CN 106437034A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- semi
- steel tube
- concrete
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/34—Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/14—Producing shaped prefabricated articles from the material by simple casting, the material being neither forcibly fed nor positively compacted
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/32—Columns; Pillars; Struts of metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention discloses a steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and a preparation method thereof. The steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column is characterized in that a column of the steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column comprises a steel tube, a recycled block concrete prefabricated core column and cast-in-place recycled aggregate concrete between the steel tube and the recycled block concrete prefabricated core column, reinforcing ribs are arranged on the inner side of the steel tube, the recycled block concrete prefabricated core column is concentrically arranged in a cavity of the steel tube, and the recycled aggregate concrete is poured between the steel tube and the recycled block concrete prefabricated core column. The steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and the preparation method have the advantages that the steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column can be integrally conveniently and quickly manufactured and is high in economic benefit, the load bearing capacity and the deformation performance of structures can be improved, and the ductility of components can be improved; the steel tube is provided with the reinforcing ribs, accordingly, the steel tube and the recycled aggregate concrete can be closely cemented, and the integrity of the steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column can be improved; the steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column is applicable to heavy load, industrial factory buildings, high-rise buildings, long-span structures and the like.
Description
Technical field
The invention belongs to technical field of civil engineering is and in particular to construction refuse regenerated concrete is as the material of filling
Concrete filled steel tube column preparation method.
Technical background
Among municipal refuse, building waste accounts for the 30%~40% of rubbish total amount.In future, with urban construction from extensional mode
Develop the extensive reconstruction of the old city town with connotative to develop simultaneously, China's building waste yield will sustainable growth.In the face of increasingly serious
Land supply that environmental pollution, day are becoming tight and day by day exhaust mineral resources the problems such as, the building waste of enormous amount certainly will
People, environment, the contradiction situation between resource, the coordinated development of impact urban ecological environment can be aggravated, carry out the comprehensive of building waste
Close using very urgent.
According to statistics, the annual building waste producing of China, only discarded concrete total amount just reaches more than 120,000,000 tons.To build
Manufacture the component in building structure after discarded concrete in building refuse is broken as regenerated aggregate, natural aggregate money can be solved
The nervous problem in source, realizes the regeneration of concrete and recycles it is achieved that sustainable development.
The construction development of domestic city high-rise building is swift and violent at present, and concrete filled steel tube is as a kind of emerging combination knot
Structure, has been widely used in super-high building structure.Mainly based on the compression member of axial compression and active force small eccentricity,
It is widely used in frame structure (as Factory Building and high level).Steel tube regeneration concrete combination column involved in the present invention combines
Conventional steel concrete technology maturity and the big advantage of the two of China's building waste amount, are fabricated to carry on tube wall and put more energy into
The coupled column of rib, preferably improves overall performance, stress performance and the workability of steel pipe column, has low cost, construction letter
Single, the duration is shorter, and the many merits such as be conducive to preferably preserving the ecological environment.
Content of the invention
For solving above-mentioned technical problem, the invention provides a kind of energy-conserving and environment-protective, overall performance is good, and intensity is very high
Steel pipe half cast-in-place construction refuse regenerated concrete combination column prefabricated with half.By steel pipe and regeneration monolith prefabricated core column with
And cast-in-place regenerated aggregate concrete composition, use construction refuse regenerated aggregate between steel pipe and regeneration monolith prefabricated core column
Concreting, thus prepare a kind of steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column.
In order to solve the above problems and realize above-mentioned requirements, the present invention takes following technical solution:A kind of steel pipe
Half cast-in-place construction refuse regenerated concrete combination column prefabricated with half, including steel pipe, regeneration monolith prefabricated core column and steel pipe
Interlayer and regeneration monolith prefabricated core column between.
1st, steel pipe selected by spinous process of the seventh cervical vertebra frame.The length and width of steel tube body and the high size suitable according to practice of construction requirement selection;Internal
The length and width of regeneration monolith prefabricated core column and high require to select suitable size according to practice of construction.
2nd, steel pipe upper band ribbed stiffener at regular intervals.Ribbed stiffener is uniformly distributed around pipe direction, spacing 10cm, vertical direction
Interval 15cm.
3rd, the prismoid groove of deep 30cm in is opened on regeneration monolith prefabricated core column top, and prismoid groove pushes up
Face is the square of length of side 20cm, and bottom surface is the square of length of side 15cm, regenerates monolith prefabricated core column bottom simultaneously
The square being a high 25cm is raised, and the square length of side is 10cm, and upper prop section can be made raised upper and lower with hypomere post section groove
It is mutually butted, cement mortar is closed admittedly in junction, formed overall.
4th, the interlayer between steel pipe and regeneration monolith prefabricated core column is poured using regenerated aggregate concrete.
5th, regenerate the construction technology of monolith prefabricated core column:Make forming panel in the way of keeping flat, and pre- in advance
Bury lifting crotch, in advance waste and old concrete block is fully poured water-wet.When pouring, throw in pre-wetting in forming panel
Waste and old concrete block, add novel concrete, the weight of regeneration monolith and novel concrete ratio is 2:1-4:Between 1
Optimum.Block used by regeneration monolith is that old buildings, structures, road, bridge or dykes and dams are removed and removed protection
Waste and old concrete block after layer and all or part of reinforcing bar.Used by regeneration monolith, the size of block should be according to reality
Design requirement is chosen, unsuitable excessive or too small.Pour the globality it is ensured that structure using novel concrete between block.
Advantages of the present invention:
1. the present invention is applied to the mixed structure of steel and concrete, regenerates block coagulation prefabricated core column factorial praluction, intensity
High, corrosion-resistant, excellent in durability, construction is convenient.
2nd, carry the design of the steel pipe of ribbed stiffener with surface, pouring regenerated aggregate concrete, steel pipe and coagulation can be increased
Soil Interface cohesive force, significantly improves ultimate bearing capacity, deformability and the ductility of component, effectively prevents steel pipe and coagulation pedosphere
Emaciated face is empty, and improves the effect of contraction to core concrete for the steel pipe, more preferable stability can be kept it is ensured that structure strong
Degree.
3rd, select construction refuse regenerated concrete, instead of normal concrete, green, energy-conservation, high-strength light and durability
Well, greatly reduce cost simultaneously.
4. the groove of regeneration monolith prefabricated core column upper and lower ends and bulge-structure, can interconnect, Ke Yiguang
General apply in skyscraper, make construction work facilitation, sequencing.
5th, do prefabricated core column using regeneration monolith, enormously simplify when waste and old concrete recycles broken,
The processing procedures such as screening, purification, save a large amount of manpowers, time and the energy, and the efficient circulation of achievable building waste utilizes.Remove
Outside this, from monolith, it is possible to achieve the globality of well-formed.Greatly improve the intensity of this cylinder.
Brief description:
Fig. 1 is that a kind of square-section steel pipe regenerates monolith prefabricated core column top view with circular cross-section.
In figure:1 steel pipe;2 cast-in-place regenerated aggregate concretes;3 regeneration monolith prefabricated core columns;4 put more energy into
Rib.
Fig. 2 is that a kind of circular cross-section steel pipe regenerates monolith prefabricated core column top view with circular cross-section.
Fig. 3 is that a kind of circular cross-section steel pipe regenerates monolith prefabricated core column top view with square-section.
Fig. 4 is that a kind of square-section steel pipe regenerates monolith prefabricated core column top view with square-section.
Fig. 5 is a kind of steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column shaft side figure.
In figure:3 regeneration monolith prefabricated core columns;5 is raised;6 grooves.
Specific embodiment
With reference to Figure of description 1-5, the present invention will be further described.
As illustrated, a kind of steel pipe described in the embodiment of the present invention and half prefabricated half cast-in-place construction refuse regenerated Combined concrete
Post, described coupled column by cast-in-place regenerated aggregate concrete 2 between steel pipe 1 and steel pipe and regeneration monolith prefabricated core column with
And regeneration monolith prefabricated core column 3 forms.Internal regeneration monolith prefabricated core column 3 has template to be obtained, inside steel pipe 1
With ribbed stiffener 4, monolith prefabricated core column 3 is concentric with steel pipe 1 places for regeneration.A kind of present invention steel pipe and half prefabricated half
Cast-in-place construction refuse regenerated concrete combination column replaces conventional steel bar concrete post, and the steel pipe of the present invention prefabricated with half half cast-in-place is built
Building refuse regeneration concrete coupled column, the convenient high financial profit of integral manufacturing, and can effectively improve structure bearing capacity and
Improve its deformation performance, increase the ductility of component.Wherein the design with ribbed stiffener 4 for the steel pipe 1 can make steel pipe mix with regeneration aggregate
Solidifying soil adhesive property more preferably, improves the globality of coupled column.
Embodiment 1:
1. select the steel plate of the suitable dimension of suitable intensity grade, continuous rolling ribbed stiffener 4 thereon, ribbed stiffener 4 is highly suitable,
Again the steel plate of ribbed stiffener 4 is carried out bent jointing for steel pipe 1 with the 1/4. of the difference of regeneration monolith prefabricated core column 3 radius,
Make the steel pipe 1 with difference d of prefabricated regeneration monolith column internal diameter more than 10cm for the cavity inside diameter.
2. make forming panel in the way of keeping flat, make and pre-buried in advance during regeneration monolith prefabricated core column 3 hang well
Dress crotch, and waste and old concrete block is fully poured water-wet.When pouring, throw in the waste and old mixed of pre-wetting in forming panel
Solidifying soil block body, adds novel concrete, part by weight 2:1.
3. the prismoid groove 6 of deep 30cm in, prismoid groove 6 are opened in regeneration monolith prefabricated core column 3 top
Upper top surface is the square of length of side 20cm, and bottom surface is the square of length of side 15cm, regenerates monolith prefabricated core column 3 simultaneously
The square projection 5 of an evagination 25cm is done in bottom, and the square length of side is 10cm.
4., when installing, prefabricated regeneration monolith stem stem is transported to job site, first it is fully watered
The regeneration monolith sections of moistened surface is first fixed by lifting crotch by moistening using loop wheel machine, then installs steel pipe with one heart
1.
5. pour regenerated aggregate concrete 2 to the sandwich portion of steel pipe 1 and regeneration monolith prefabricated core column 3, and insert
Enter vibrating head fully to vibrate, until the space within steel pipe 1 is filled, maintenance, to hardening, is finally smeared in steel pipe 1 external mortar
Face, obtains steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column after its solidification.
Embodiment 2:
1. select the steel plate of the suitable dimension of suitable intensity grade, continuous rolling ribbed stiffener 4 thereon, ribbed stiffener 4 is highly suitable,
For steel pipe 1 and the 1/4 of the difference of regeneration monolith prefabricated core column 3 radius, then the steel plate of ribbed stiffener 4 is carried out bent jointing,
Make the steel pipe 1 with difference d of prefabricated regeneration monolith column radius more than 10cm for the cavity inside diameter.
2. make forming panel in the way of keeping flat, make and pre-buried in advance during regeneration monolith prefabricated core column 3 hang well
Dress crotch, and waste and old concrete block is fully poured water-wet.When pouring, throw in the waste and old mixed of pre-wetting in forming panel
Solidifying soil block body, adds novel concrete, part by weight 3:1.
3. the prismoid groove 6 of deep 30cm in, prismoid groove 6 are opened in regeneration monolith prefabricated core column 3 top
The upper top surface length of side is the square of 20cm, and bottom surface is the square of length of side 15cm, regenerates monolith prefabricated core column 3 simultaneously
The square projection 5 of an evagination 25cm is done in bottom, and the square length of side is 10cm.
4., when installing, prefabricated regeneration monolith stem stem is transported to job site, first it is fully watered
The regeneration concrete sections of moistened surface is first fixed by lifting crotch by moistening using loop wheel machine, then installs steel pipe 1 with one heart.
5. pour regenerated aggregate concrete 2 to the sandwich portion of steel pipe 1 and regeneration monolith prefabricated core column 3, and insert
Enter vibrating head fully to vibrate, until the space within steel pipe 1 is filled, maintenance, to hardening, is finally smeared in steel pipe 1 external mortar
Face, obtains steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column after its solidification.
Embodiment 3:
1. select the steel plate of the suitable dimension of suitable intensity grade, continuous rolling ribbed stiffener 4 thereon, ribbed stiffener 4 is highly suitable,
For steel pipe 1 and the 1/4 of the difference of regeneration monolith prefabricated core column 3 radius, then the steel plate of ribbed stiffener 4 is carried out bent jointing,
Make the steel pipe 1 with difference d of prefabricated regeneration monolith column radius more than 10cm for the cavity inside diameter.
2. make forming panel in the way of keeping flat, make and pre-buried in advance during regeneration monolith prefabricated core column 3 hang well
Dress crotch, and waste and old concrete block is fully poured water-wet.When pouring, throw in the waste and old mixed of pre-wetting in forming panel
Solidifying soil block body, adds novel concrete, part by weight 4:1.
3. the prismoid groove 6 of deep 30cm in, prismoid groove 6 are opened in regeneration monolith prefabricated core column 3 top
Upper top surface is the square of length of side 20cm, and bottom surface is the square of length of side 15cm, regenerates monolith prefabricated core column 3 bottom simultaneously
The square projection 5 of an evagination 25cm is done at end, and the square length of side is 10cm.
4., when installing, prefabricated regeneration monolith stem stem is transported to job site, first it is fully watered
The regeneration monolith sections of moistened surface is first fixed by lifting crotch by moistening using loop wheel machine, then installs steel pipe with one heart
1.
5. pour regenerated aggregate concrete 2 to the sandwich portion of steel pipe 1 and regeneration monolith prefabricated core column 3, and insert
Enter vibrating head fully to vibrate, until the space within steel pipe 1 is filled, maintenance, to hardening, is finally smeared in steel pipe 1 external mortar
Face, obtains steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column after its solidification.
In being embodied as, preferably the ribbed stiffener 4 on steel pipe 1 can be various forms, and rib end can be square, triangle
Shape, trapezoidal or formation steel wire.
More than, only presently preferred embodiments of the present invention, but protection scope of the present invention is not limited thereto, any it is familiar with basis
Those skilled in the art the invention discloses technical scope in, the change or replacement that can readily occur in, all should cover
Within the scope of the present invention.Therefore, protection scope of the present invention should be defined by the protection domain that claim is defined.
Claims (4)
1. a kind of steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column:It is characterized in that, including steel pipe conduct
Spinous process of the seventh cervical vertebra frame, the length and width of steel tube body and the high size suitable according to practice of construction requirement selection;Internal regeneration monolith is pre-
The length and width of coremaking post and the high size suitable according to practice of construction requirement selection, steel pipe upper band ribbed stiffener at regular intervals, then
A prismoid groove is opened on raw monolith prefabricated core column top, and regeneration monolith prefabricated core column bottom does one simultaneously
Square is raised, and the interlayer between steel pipe and regeneration monolith prefabricated core column pours for regenerated aggregate concrete and forms.
2. a kind of steel pipe according to claim 1 and half prefabricated half cast-in-place construction refuse regenerated concrete combination column, it is special
Levy and be, steel pipe is welded by the steel plate with ribbed stiffener, for the form of remaining silent, ribbed stiffener is distributed on the one side of steel plate,
The inner side of steel plate, the ribbed stiffener on steel plate is continuous or interrupted.
3. a kind of steel pipe according to claim 1 and half prefabricated half cast-in-place construction refuse regenerated concrete combination column, it is special
Levy and be, the ribbed stiffener length on steel plate is the 1/4 of the difference of regeneration monolith prefabricated core column and steel pipe radius, ribbed stiffener around
The spacing in pipe direction is 10cm, and on vertical direction, the spacing of ribbed stiffener is 15cm.
4. a kind of steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column preparation method it is characterised in that with
The mode keeping flat makes forming panel, and shifts to an earlier date pre-buried lifting crotch well, in advance fully waste and old concrete block is poured water-wet,
In forming panel, when pouring, throw in the waste and old concrete block of pre-wetting, add novel concrete, regenerate monolith
With the weight of novel concrete than 2:1-4:Optimum between 1, it is recessed that a prismoid is opened on regeneration monolith prefabricated core column top
Groove, regenerates monolith prefabricated core column bottom simultaneously and does a square projection, in upper prop section projection and hypomere post section groove
Under be mutually butted, in junction, cement mortar is closed admittedly, is formed overall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611067584.XA CN106437034A (en) | 2016-11-29 | 2016-11-29 | Steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and preparation method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611067584.XA CN106437034A (en) | 2016-11-29 | 2016-11-29 | Steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and preparation method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106437034A true CN106437034A (en) | 2017-02-22 |
Family
ID=58219890
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611067584.XA Pending CN106437034A (en) | 2016-11-29 | 2016-11-29 | Steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and preparation method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106437034A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107165338A (en) * | 2017-07-05 | 2017-09-15 | 中国地震局工程力学研究所 | Fiber reinforcement steel core concrete column, and combinations thereof post and manufacture method |
CN109356285A (en) * | 2018-11-15 | 2019-02-19 | 江西建工第二建筑有限责任公司 | A kind of prefabricated column component, assembled combination prefabricated post and its assembly method |
CN109356284A (en) * | 2018-11-15 | 2019-02-19 | 江西建工第二建筑有限责任公司 | A kind of assembled group frame beam column construction and its assembly method |
CN110206229A (en) * | 2019-06-10 | 2019-09-06 | 上海建工四建集团有限公司 | A kind of concrete column splicing structure and its construction method |
CN110512723A (en) * | 2019-08-13 | 2019-11-29 | 成都犀安智慧工程技术有限公司 | Combined member, prefab-form, formwork for placing and production technology are assembled based on regeneration concrete |
CN113356037A (en) * | 2021-05-31 | 2021-09-07 | 郑州大学 | Cast-in-place UHPC-NC combination formula antidetonation pier in outer assembly |
CN115627877A (en) * | 2022-09-19 | 2023-01-20 | 华南理工大学 | Concrete-filled steel tube column with built-in compacted cement soil segments and construction method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2765965Y (en) * | 2004-03-10 | 2006-03-22 | 徐国林 | Hollow steel pipe concrete column |
CN101487333A (en) * | 2009-02-13 | 2009-07-22 | 江苏南通二建集团有限公司 | Recycled concrete superposed column and its implementing method |
CN101748859A (en) * | 2008-11-28 | 2010-06-23 | 沈阳建筑大学 | Steel-reinforced concrete core column and manufacturing method thereof |
CN103669725A (en) * | 2013-09-16 | 2014-03-26 | 北京工业大学 | Hybrid FRP (fiber reinforced plastic) pipe high-strength reinforcing steel bar active powder concrete column and preparation method thereof |
CN103967210A (en) * | 2014-04-12 | 2014-08-06 | 北京工业大学 | Square steel pipe waste concrete core spiral hoop stiffening composite column with T-shaped ribbed stiffeners |
CN204919952U (en) * | 2015-07-09 | 2015-12-30 | 杭州恒麟环保科技有限公司 | Straw building insulating brick |
CN206289865U (en) * | 2016-11-29 | 2017-06-30 | 南昌大学 | A kind of steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column |
-
2016
- 2016-11-29 CN CN201611067584.XA patent/CN106437034A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2765965Y (en) * | 2004-03-10 | 2006-03-22 | 徐国林 | Hollow steel pipe concrete column |
CN101748859A (en) * | 2008-11-28 | 2010-06-23 | 沈阳建筑大学 | Steel-reinforced concrete core column and manufacturing method thereof |
CN101487333A (en) * | 2009-02-13 | 2009-07-22 | 江苏南通二建集团有限公司 | Recycled concrete superposed column and its implementing method |
CN103669725A (en) * | 2013-09-16 | 2014-03-26 | 北京工业大学 | Hybrid FRP (fiber reinforced plastic) pipe high-strength reinforcing steel bar active powder concrete column and preparation method thereof |
CN103967210A (en) * | 2014-04-12 | 2014-08-06 | 北京工业大学 | Square steel pipe waste concrete core spiral hoop stiffening composite column with T-shaped ribbed stiffeners |
CN204919952U (en) * | 2015-07-09 | 2015-12-30 | 杭州恒麟环保科技有限公司 | Straw building insulating brick |
CN206289865U (en) * | 2016-11-29 | 2017-06-30 | 南昌大学 | A kind of steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107165338A (en) * | 2017-07-05 | 2017-09-15 | 中国地震局工程力学研究所 | Fiber reinforcement steel core concrete column, and combinations thereof post and manufacture method |
CN109356285A (en) * | 2018-11-15 | 2019-02-19 | 江西建工第二建筑有限责任公司 | A kind of prefabricated column component, assembled combination prefabricated post and its assembly method |
CN109356284A (en) * | 2018-11-15 | 2019-02-19 | 江西建工第二建筑有限责任公司 | A kind of assembled group frame beam column construction and its assembly method |
CN109356285B (en) * | 2018-11-15 | 2023-10-27 | 江西建工第二建筑有限责任公司 | Assembled prefabricated column component, assembled combined prefabricated column and assembling method thereof |
CN110206229A (en) * | 2019-06-10 | 2019-09-06 | 上海建工四建集团有限公司 | A kind of concrete column splicing structure and its construction method |
CN110512723A (en) * | 2019-08-13 | 2019-11-29 | 成都犀安智慧工程技术有限公司 | Combined member, prefab-form, formwork for placing and production technology are assembled based on regeneration concrete |
CN110512723B (en) * | 2019-08-13 | 2024-03-26 | 成都犀安智慧工程技术有限公司 | Assembled combined member, prefabricated template, pouring template and production process based on recycled concrete |
CN113356037A (en) * | 2021-05-31 | 2021-09-07 | 郑州大学 | Cast-in-place UHPC-NC combination formula antidetonation pier in outer assembly |
CN115627877A (en) * | 2022-09-19 | 2023-01-20 | 华南理工大学 | Concrete-filled steel tube column with built-in compacted cement soil segments and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106437034A (en) | Steel tube and semi-prefabricated semi-cast-in-place construction waste recycled concrete combined column and preparation method thereof | |
US10273691B2 (en) | Method of constructing a reinforced compound concrete beam containing demolished concrete lumps | |
CN105298020B (en) | Semi-precast circular steel pipe regenerated mixed concrete pillar and preparation method thereof | |
CN106284044A (en) | A kind of Novel steel concrete composite bridge and construction method thereof | |
CN106869015A (en) | A kind of FRP pipes cast-in-place with half half prefabricated regeneration concrete prestressing force overlapping bridge pier and preparation method | |
CN106869386A (en) | A kind of recycled concrete superposed beam of high-strength construction waste and its construction method | |
CN108086113A (en) | A kind of road surface precast assembly fast repairing method for being suitable for southern damp-heat area | |
CN206737118U (en) | A kind of prefabricated regeneration concrete bean column node of reinforcement | |
CN102677901B (en) | Construction method of horizontal combined member by using large-size waste concrete block | |
CN202644847U (en) | CFST (Concrete Filled Steel Tube) combination column | |
CN106812248A (en) | A kind of construction refuse regenerated concrete superposed column and its construction technology | |
CN204266136U (en) | Stone arch bridge cover arch rib shotcrete ruggedized construction | |
CN106869121A (en) | A kind of FRP pipes cast-in-place with half half prefabricated regeneration concrete prestressing force overlapping pile foundation and preparation method | |
CN206599918U (en) | A kind of construction refuse regenerated concrete superposed column | |
CN101451380B (en) | Processing method of prefabricating common concrete outer plate recycled concrete core shear wall | |
CN110344844A (en) | A kind of track engineering section of track well construction method | |
CN109356185A (en) | A kind of prefabricated pier foundation of regeneration monolith and its construction method | |
CN206736708U (en) | A kind of FRP pipes and half prefabricated half cast-in-place regeneration concrete prestressing force overlapping bridge pier | |
CN106381956A (en) | Concrete prefabricated shell-regenerated mixed concrete combination column and preparation method thereof | |
CN206289865U (en) | A kind of steel pipe and half prefabricated half cast-in-place construction refuse regenerated concrete combination column | |
CN106968244A (en) | A kind of FRP pipes and half prefabricated half cast-in-place regeneration concrete prestressing force overlapping pile foundation and preparation method | |
CN105926652B (en) | Method and structure for reinforcing inclined retaining wall | |
CN206599895U (en) | A kind of recycled concrete superposed beam of high-strength construction waste | |
CN206289866U (en) | A kind of FRP pipes and half prefabricated half cast-in-place construction refuse regenerated concrete combination column | |
CN107558606A (en) | A kind of prefabricated construction construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170222 |
|
RJ01 | Rejection of invention patent application after publication |