CN208844417U - A kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place pier column - Google Patents
A kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place pier column Download PDFInfo
- Publication number
- CN208844417U CN208844417U CN201821222581.3U CN201821222581U CN208844417U CN 208844417 U CN208844417 U CN 208844417U CN 201821222581 U CN201821222581 U CN 201821222581U CN 208844417 U CN208844417 U CN 208844417U
- Authority
- CN
- China
- Prior art keywords
- grout sleeve
- cast
- place
- prefabricated components
- pier column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
A kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place pier column, including cast-in-place cushion cap, outer precast construction, embedded bar, and cast-in-place concrete layer, embedded bar is set to above cast-in-place cushion cap, grout sleeve bottom connecting hole is inserted into embedded bar, it includes prefabricated components that cast-in-place concrete layer, which is filled in precast construction inside the internal layer hollow frame body of prefabricated components, several vertical reinforcements, Grouting Pipe, circumferential stirrup and grout sleeve, prefabricated components are closed hollow frame body, vertical reinforcement, Grouting Pipe, circumferential stirrup and grout sleeve are arranged in prefabricated components, circumferential stirrup is looped around on vertical reinforcement, grout sleeve is set to the bottom end of prefabricated components, vertical reinforcement is arranged in grout sleeve, Grouting Pipe is connect with grout sleeve.The utility model is able to solve the technical problems such as the big unit construction bridge pier stud weight in constructing, prefabricated, transport, installation, and traditional construction process is avoided to set up the security risk of bracket, improve productivity effect.
Description
Technical field
The utility model relates to a kind of technical field of bridge construction, in particular to a kind of outer precast construction for pier column
And its outer prefabricated interior cast-in-place pier column.
Background technique
With the continuous propulsion of Urbanization in China, traffic jam issue becomes increasingly conspicuous, and is increasingly becoming influence urbanization
The key factor of development, in recent years, governmental infrastructure construction continue to increase investment, to solve traffic jam issue, city bridge
Big-and-middle small city construction is more and more at home for beam, however, bridge construction is still traditional form at present, mainly manually to bind steel
Based on muscle, poured in place concrete, site operation experience in recent years is summarized, a series of problem is mainly brought, first is that existing
Field construction need to set up a large amount of rack template, under high wind heavy rain external force, there is security risk of toppling of collapsing, risk is big;
Second is that field operation needs a large amount of labour's investment, construction efficiency is low, long construction period, especially in urban area construction period
It is longer, it is bigger to urban transportation, social influence;Third is that the interference of the environmental factors such as traditional construction dust, noise, light is big, it is difficult to
Meet Green civilization construction requirement.Prefabricated assembled pier column way on existing market is again due to prefabricated solid pier column weight
It measures larger, it has not been convenient to which transporting and hoisting largely effects on construction efficiency.
Summary of the invention
The purpose of this utility model is to provide a kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place bridges
Pier stud can be improved productivity effect.
To achieve the above object, the utility model uses following technical scheme:
For the outer precast construction of pier column, including prefabricated components, several vertical reinforcements, Grouting Pipe, circumferential stirrup and filling
Sleeve is starched, the prefabricated components are closed hollow frame body, the vertical reinforcement, Grouting Pipe, circumferential stirrup and grout sleeve
It is arranged in prefabricated components, the vertical reinforcement is vertically laid from the top of prefabricated components to bottom end, the circumferential stirrup
It is looped around on vertical reinforcement, the grout sleeve is set to the bottom end of prefabricated components, and the vertical reinforcement setting is covered in grouting
In cylinder, connecting hole is arranged in the grout sleeve bottom inner cavity, and the Grouting Pipe is connect with grout sleeve.
Further, the prefabricated components are circular cylindrical.
Outer prefabricated interior cast-in-place pier column, including cast-in-place cushion cap, outer precast construction, embedded bar and cast-in-place concrete layer, institute
The embedded bar stated is set to above cast-in-place cushion cap, and in the grout sleeve bottom connecting hole insertion embedded bar, described shows
Pouring concrete layer is filled in prefabricated components.
Further, it is additionally provided in pedestal, the circular pedestal on the outside of the outer precast construction and is equipped with ring wall
Reinforcing bar, the circular chassis interior are filled with concrete.
Further, the embedded bar is Ribbed Bar.
After adopting the above technical scheme, the utility model is able to solve the technical problem in constructing, prevents security risk, mentions
High productivity effect.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the utility model.
Fig. 2 is the prefabricated components diagrammatic cross-section of the utility model.
Fig. 3 is the prefabricated components schematic top plan view of the utility model.
Fig. 4 is the diagrammatic cross-section of the utility model.
Fig. 5 is the schematic top plan view of the utility model.
Primary clustering symbol description:
1: cushion cap, 2: outer precast construction, 21: prefabricated components, 22: vertical reinforcement, 23: stirrup, 24: grout sleeve, 25:
Grouting Pipe, 3: circular pedestal, 31: ring wall reinforcing bar, 4: embedded bar, 5: cast-in-place mixed mud layer.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation
Example, the present invention will be further described in detail.
As shown in fig. 1~fig. 5, present embodiment discloses a kind of outer precast constructions for pier column and its outer prefabricated interior existing
Pour pier column, including cushion cap 1, outer precast construction 2, circular pedestal 3, embedded bar 4.
Implementing procedure:
Step 1: outer precast construction (meet after strength grade transporting and hoisting to scene).
Outer precast construction 2 includes prefabricated components 21, vertical reinforcement 22, stirrup 23, grout sleeve 24 and Grouting Pipe 25, outer pre-
Component 21 processed is closed hollow frame body, and vertical reinforcement 22, stirrup 23, grouting cylinder 24 and Grouting Pipe 25 are arranged the two of outer prefabricated components
Between layer hollow frame body, vertical reinforcement 22 is vertically laid from the top of prefabricated components 21 to bottom end, and 23 lateral circular of stirrup is perpendicular
To on reinforcing bar 22, the bottom end of prefabricated components 22 is arranged in grout sleeve 24, and vertical reinforcement 22 is arranged in grout sleeve 24, grouting
24 bottom end of sleeve is equipped with a connecting hole, and Grouting Pipe 25 is arranged in the two sides of grout sleeve 24 and connect with grout sleeve 24.It is outer pre-
Structure 2 processed is transported after directly being made from factory toward construction site, and outer 2 structure of precast construction is simple, and lighter in weight is readily transported.
Step 2: cast-in-place cushion cap embedded bar:
Live cushion cap 1 uses cast-in-place form, and cushion cap 1 is equipped with the good connecting hole phase with 24 bottom end of grout sleeve pre-buried in advance
Corresponding embedded bar 4 and it is attached around pedestal 3 with precast construction 2, ring wall reinforcing bar 31 is equipped in pedestal 3, to outer prefabricated
When structure 2 is transported to construction site, the standing of outer precast construction 2 is placed into pedestal 3, embedded bar 4 is inserted into grouting
In the connecting hole of 24 bottom end of sleeve.Embedded bar 31 is Ribbed Bar.
Step 3: outer precast construction is connect with cushion cap:
The outer precast construction 2 in scene is connect using 24 type of attachment of grout sleeve with cushion cap 1, i.e., is inserted into pre-buried Ribbed Bar
Then the grout sleeve 24 in inner cavity band connection hole pours into dedicated high-strength, contraction-free grouting concrete, reach and connect higher than parent material of reinforcement rebar intensity
Effect is connect, then formwork erection cast-in-situ base at outside ring wall reinforcing bar 31, guarantees effective connection of outer precast construction 2 and cushion cap 1, finally
The empty intra-bladder instillation of outer precast construction 2 forms pier column after waiting by force, makes outer precast construction with the slightly expanded concrete of intensity again
2 are more bonded with cushion cap and around pedestal 3, and stability is higher.
In conclusion the utility model can effectively solve the problem that technical problem, social concern in construction, it is hidden to prevent safety
Suffer from, improves productivity effect.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art within the technical scope disclosed by the utility model, can readily occur in
Change or replacement, should be covered within the scope of the utility model.
Claims (5)
1. being used for the outer precast construction of pier column, it is characterised in that: including prefabricated components, several vertical reinforcements, Grouting Pipe, circumferential direction
Stirrup and grout sleeve, the prefabricated components are closed hollow frame body, the vertical reinforcement, Grouting Pipe, circumferential stirrup and
Grout sleeve is arranged in prefabricated components, and the vertical reinforcement is vertically laid from the top of prefabricated components to bottom end, described
Circumferential stirrup is looped around on vertical reinforcement, and the grout sleeve is set to the bottom end of prefabricated components, the vertical reinforcement setting
In grout sleeve, connecting hole is arranged in the grout sleeve bottom inner cavity, and the Grouting Pipe is connect with grout sleeve.
2. being used for the outer precast construction of pier column as described in claim 1, it is characterised in that: the prefabricated components are annular
Column.
Prefabricated interior cast-in-place pier column outside 3., it is characterised in that: including cast-in-place cushion cap, outer precast construction, embedded bar and cast-in-place mixed
Solidifying soil layer, the outer precast construction are structure described in claims 1 or 2 any one, and the embedded bar is set to existing
It pours above cushion cap, in the grout sleeve bottom connecting hole insertion embedded bar, the cast-in-place concrete layer is filled in pre-
In component processed.
4. outer prefabricated interior cast-in-place pier column as claimed in claim 3, it is characterised in that: also set on the outside of the outer precast construction
There is circular pedestal, ring wall reinforcing bar is equipped in the circular pedestal, the circular chassis interior is filled with concrete.
5. outer prefabricated interior cast-in-place pier column as claimed in claim 3, it is characterised in that: the embedded bar is band rib steel
Muscle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821222581.3U CN208844417U (en) | 2018-07-31 | 2018-07-31 | A kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place pier column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821222581.3U CN208844417U (en) | 2018-07-31 | 2018-07-31 | A kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place pier column |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208844417U true CN208844417U (en) | 2019-05-10 |
Family
ID=66354840
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821222581.3U Active CN208844417U (en) | 2018-07-31 | 2018-07-31 | A kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place pier column |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208844417U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110593303A (en) * | 2019-09-30 | 2019-12-20 | 吉林省热力工程设计研究有限责任公司 | Heat distribution pipeline prefabricated reinforced concrete fixed buttress and construction method |
CN113123222A (en) * | 2021-04-23 | 2021-07-16 | 上海市政工程设计研究总院(集团)有限公司 | Socket joint type connecting structure between prefabricated bridge pier column and bearing platform additionally provided with boss |
CN113737636A (en) * | 2021-09-18 | 2021-12-03 | 西安市政设计研究院有限公司 | Steel-concrete combined connecting structure suitable for assembly type pier stud and construction method thereof |
CN116377846A (en) * | 2023-04-24 | 2023-07-04 | 中铁一局集团市政环保工程有限公司 | Bridge pier construction structure and method |
-
2018
- 2018-07-31 CN CN201821222581.3U patent/CN208844417U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110593303A (en) * | 2019-09-30 | 2019-12-20 | 吉林省热力工程设计研究有限责任公司 | Heat distribution pipeline prefabricated reinforced concrete fixed buttress and construction method |
CN110593303B (en) * | 2019-09-30 | 2024-04-12 | 吉林省热力工程设计研究有限责任公司 | Prefabricated reinforced concrete fixed buttress for thermal pipeline and construction method |
CN113123222A (en) * | 2021-04-23 | 2021-07-16 | 上海市政工程设计研究总院(集团)有限公司 | Socket joint type connecting structure between prefabricated bridge pier column and bearing platform additionally provided with boss |
CN113737636A (en) * | 2021-09-18 | 2021-12-03 | 西安市政设计研究院有限公司 | Steel-concrete combined connecting structure suitable for assembly type pier stud and construction method thereof |
CN116377846A (en) * | 2023-04-24 | 2023-07-04 | 中铁一局集团市政环保工程有限公司 | Bridge pier construction structure and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208844417U (en) | A kind of outer precast construction for pier column and its outer prefabricated interior cast-in-place pier column | |
CN105569224B (en) | Concrete filled steel tube edge constraint overlaps monoblock type shear wall and preparation and installation method | |
CN104746422B (en) | A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method | |
CN105780935B (en) | Prefabricated assembled steel tube confinement energy consumption connecting node and construction method | |
CN107419824A (en) | The full precast shear wall structural system of regenerative steel skeleton and construction method | |
CN205954921U (en) | Novel big board shear wall structure is secretly supported in bolted connection's prefabricated assembled area | |
CN106869548B (en) | A kind of newel frame assembled underground parking structural system and construction method | |
CN202466845U (en) | Middle-layer node connecting structure for steel tube concrete column and steel reinforced concrete beam | |
CN106088326A (en) | The assembling frame rod structure printed based on 3D | |
CN110205921A (en) | The precast assembly pier stud construction and construction method of bellows connection are inserted by reinforcing bar | |
CN105926775A (en) | Novel concrete-filled steel tube beam column joint | |
CN102071747A (en) | Joint of square steel tube concrete column and reinforced concrete floor and production method thereof | |
CN106320537A (en) | Prefabricated concrete-filled square steel tube column and steel girder connecting joint | |
CN109914644A (en) | A kind of assembled heat insulation masonry wall and preparation method thereof | |
CN204097864U (en) | A kind of bridge prefabrication hollow pier stud delay-pour joint structure | |
CN105401580A (en) | Concrete pouring construction method for underground gallery | |
CN206928323U (en) | A kind of ring muscle fastens assembled pipe gallery | |
CN210737607U (en) | A hang braced system for reverse construction method beam slab construction | |
CN209397712U (en) | The connection structure of antidetonation steel pipe in a kind of shear wall | |
CN206428805U (en) | A kind of concrete prefabricated balcony of assembled steel | |
CN205382595U (en) | Integral shear force wall of steel pipe concrete edge constraint coincide | |
CN206359882U (en) | A kind of assembled solid steel tube constrains reinforced column squat pier | |
CN206205144U (en) | Node is poured after the secondary external permanent aluminium sheet external mold of framework | |
CN108019000A (en) | A kind of high-strength high ductility concrete of assembled exempts from sleeve connection structure and connection method | |
CN104908150B (en) | A kind of piping shaft making template and the method based on factorial praluction piping shaft |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |