CN103469807A - 输电线路配送式新旧基础快速装配方法 - Google Patents

输电线路配送式新旧基础快速装配方法 Download PDF

Info

Publication number
CN103469807A
CN103469807A CN2013103561179A CN201310356117A CN103469807A CN 103469807 A CN103469807 A CN 103469807A CN 2013103561179 A CN2013103561179 A CN 2013103561179A CN 201310356117 A CN201310356117 A CN 201310356117A CN 103469807 A CN103469807 A CN 103469807A
Authority
CN
China
Prior art keywords
assembly method
distribution type
rapid assembly
type rapid
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013103561179A
Other languages
English (en)
Inventor
梁东跃
杨雪锋
王力
罗正帮
邹本为
朱晓鹏
董江戎
肖俊俊
刘西民
陈彦焰
胡祖伟
于永洋
郑少将
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Huadian Engineering Consulting and Design Co Ltd
Original Assignee
Anhui Huadian Engineering Consulting and Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Huadian Engineering Consulting and Design Co Ltd filed Critical Anhui Huadian Engineering Consulting and Design Co Ltd
Priority to CN2013103561179A priority Critical patent/CN103469807A/zh
Publication of CN103469807A publication Critical patent/CN103469807A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

输电线路配送式新旧基础快速装配方法,它涉及高压输电线路技术领域。其步骤为:先在原基础上立柱及底板上打孔,埋入地脚螺栓;将预制好的基础底板与原基础底板用槽钢连接;将预制好的基础立柱与原基础立柱用角钢连接。本发明可满足新建铁塔基础尺寸和根开的需要,有效解决了施工时间和停电时间较长的问题,显著减少了工程材料量和中断供电所引起的费用。

Description

输电线路配送式新旧基础快速装配方法
技术领域:
本发明涉及高压输电线路技术领域,尤其涉及一种输电线路新旧基础改造方法。
背景技术:
在输电线路改造工程中,为了节约线路走廊,减少拆迁量,尽可能利用原线路通道走线,但由于新建杆塔基础尺寸和根开较原基础大,现行做法是拆除老基础,重新浇制新基础,但这种方法有以下两个缺点:
(1)因需要拆除原线路杆塔和基础并新建新基础,造成原线路停电时间长。
(2)基础工程量较大,带来工程投资较高。
发明内容:
本发明提供一种输电线路配送式新旧基础快速装配方法,它利用原有基础与配送式新基础进行快速铰链装配连接,将原线路基础作为装配的一部分,有效解决了施工时间和停电时间较长的问题,显著减少了工程材料量和中断供电所引起的费用。
为了解决背景技术所存在的问题,本发明采用以下技术方案,具体步骤如下:
一、先在原基础上立柱及底板上打孔,埋入地脚螺栓;
二、将预制好的基础底板与原基础底板用槽钢连接;
三、将预制好的基础立柱与原基础立柱用角钢连接。
本发明可满足新建铁塔基础尺寸和根开的需要,有效解决了施工时间和停电时间较长的问题,显著减少了工程材料量和中断供电所引起的费用。
附图说明:
图1为本发明基础改造前后的结构示意图;
图2为图1的俯视图。
具体实施方式:
图1-2为本发明基础改造前后的结构示意图,其具体步骤如下:
一、先在原基础上立柱及底板上打孔,埋入地脚螺栓,并用环氧树脂封堵;
二、将预制好的基础底板与原基础底板用槽钢连接;
三、将预制好的基础立柱与原基础立柱用角钢连接。
在旧基础进行改造时,原线路需停电并拆除导地线,开挖原基础,在原基础立柱及底板上打孔并埋入螺栓,用环氧树脂胶封堵,然后将预制好的基础立柱和底板用角钢和槽钢与旧基础立柱和底板连接,形成新的基础和立柱,形成新的基础,回填土体后可立即使用,这样即避免了原基础的拆除、又能在原塔位立塔,无需经过混凝土凝固过程,可大幅减少施工和停电时间,控制工程造价,提高工程设计质量,节省了工程投资。

Claims (1)

1.输电线路配送式新旧基础快速装配方法,其特征在于,具体步骤如下:
一、先在原基础上立柱及底板上打孔,埋入地脚螺栓;
二、将预制好的基础底板与原基础底板用槽钢连接;
三、将预制好的基础立柱与原基础立柱用角钢连接。
CN2013103561179A 2013-08-06 2013-08-06 输电线路配送式新旧基础快速装配方法 Pending CN103469807A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013103561179A CN103469807A (zh) 2013-08-06 2013-08-06 输电线路配送式新旧基础快速装配方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013103561179A CN103469807A (zh) 2013-08-06 2013-08-06 输电线路配送式新旧基础快速装配方法

Publications (1)

Publication Number Publication Date
CN103469807A true CN103469807A (zh) 2013-12-25

Family

ID=49794836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013103561179A Pending CN103469807A (zh) 2013-08-06 2013-08-06 输电线路配送式新旧基础快速装配方法

Country Status (1)

Country Link
CN (1) CN103469807A (zh)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11124865A (ja) * 1997-10-20 1999-05-11 Osamu Kuroishi 柱状構造物の基礎
CN201730106U (zh) * 2010-03-10 2011-02-02 江苏省电力设计院 一种输电线路铁塔复合基础
CN101994324A (zh) * 2010-12-22 2011-03-30 建研地基基础工程有限责任公司 一种加固基础及提高既有建筑刚性基础受弯剪能力的方法
CN202347529U (zh) * 2011-09-16 2012-07-25 中国电力科学研究院 金属装配式杆塔基础
CN202482887U (zh) * 2011-12-31 2012-10-10 电联工程技术有限公司 一种混凝土预制拼装基础

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11124865A (ja) * 1997-10-20 1999-05-11 Osamu Kuroishi 柱状構造物の基礎
CN201730106U (zh) * 2010-03-10 2011-02-02 江苏省电力设计院 一种输电线路铁塔复合基础
CN101994324A (zh) * 2010-12-22 2011-03-30 建研地基基础工程有限责任公司 一种加固基础及提高既有建筑刚性基础受弯剪能力的方法
CN202347529U (zh) * 2011-09-16 2012-07-25 中国电力科学研究院 金属装配式杆塔基础
CN202482887U (zh) * 2011-12-31 2012-10-10 电联工程技术有限公司 一种混凝土预制拼装基础

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
曹先龙等: "混凝土预制装配式扩展基础抗拔试验", 《工程力学》, vol. 30, no. 1, 31 January 2013 (2013-01-31), pages 215 - 220 *

Similar Documents

Publication Publication Date Title
CN203639932U (zh) 一种用于铁路高柱信号机机柱安装的预埋基础结构
CN204118627U (zh) 一种专用于混凝土结构的预埋接线电盒
CN203270599U (zh) 一种地脚螺栓预埋模具
CN105350987A (zh) 一种用于矿挖法台车上预埋槽道固定安装结构及方法
CN203188229U (zh) 一种铁塔底脚螺栓锚固装置
CN203583730U (zh) 一种嵌入式楼板结构
CN106193279B (zh) 主体结构墙预应力结构及主体结构墙的回筑方法
CN203445512U (zh) 电缆隧道地锚
CN104727339A (zh) 电力设备基础两步式施工方法
CN202280074U (zh) 地脚螺栓定位套
CN104153451A (zh) 预制托块混凝土管道安装施工方法
CN204401563U (zh) 一种低水头导流洞封堵挡水结构
CN103469807A (zh) 输电线路配送式新旧基础快速装配方法
CN204023791U (zh) 地脚螺栓预埋装置
CN203307931U (zh) 预埋件定位螺钉连接构造
CN104328795A (zh) 一种塔架连接支脚和安装地脚螺栓的定位器及使用方法
CN103292116A (zh) 一种t型头地脚螺栓
CN202788126U (zh) 一种锚栓式柱脚人字形构架
CN104821497A (zh) 一种旧断路器更换成新断路器用基础
CN201827604U (zh) 一种高精度万用机械设备底座
CN106894435A (zh) 一种输电线路快速装配方法
CN207775931U (zh) 一种支吊架预埋组件
CN108643216B (zh) 更换老旧隔离开关时基础不停电施工方法
CN202390850U (zh) 一种机床地基快速安装结构
CN203821425U (zh) 一种采用耐候钢连接的斜柱扩展板式装配基础

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131225