CN103452327B - Constructional column bar planting positioning construction method - Google Patents
Constructional column bar planting positioning construction method Download PDFInfo
- Publication number
- CN103452327B CN103452327B CN201310387323.6A CN201310387323A CN103452327B CN 103452327 B CN103452327 B CN 103452327B CN 201310387323 A CN201310387323 A CN 201310387323A CN 103452327 B CN103452327 B CN 103452327B
- Authority
- CN
- China
- Prior art keywords
- bar
- bar planting
- constructional column
- concrete
- reinforcing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention relates to a kind of construction method, be specially a kind of constructional column bar planting positioning construction method. Solve the inaccurate problem in location existing in the construction of post reinforcing steel implant, a kind of constructional column bar planting positioning construction method is provided. After concrete beam reinforcing and template install, prepare to carry out, before concreting, beam bottom board being cleared up; measure unwrapping wire, determine constructional column position, smear location at beam bottom board with red paint; cast concrete; form removal, according to the boring of red paint position, clear hole; injecting glue; bar planting, solidifies, protects, and checks and accepts. Compared with prior art, the key point of technical solution of the present invention is to install at concrete beam reinforcing and template, prepares to carry out before concreting. Use U-shaped reinforcing bar jig according to constructional column main reinforce position at beam bottom board correspondence position, smear location with red paint. Can dodge out reinforcing bar in beam. After beam concrete bottom die is removed, according to red paint position corresponding on the beam base concrete bar planting of holing, can ensure that a bar planting puts in place.
Description
Technical field
The present invention relates to a kind of construction method, be specially a kind of constructional column bar planting positioning construction method.
Background technology
When traditional constructional column bar planting is constructed, be to punch on the beams of concrete member of closely having constructed, then plantMuscle. Due to the three-dimensional steel muscles and bones frame systems such as principal rod, stirrup that gather in beam concrete component, while causing bar planting boring for dodgingFramework of steel reinforcement in the beam of having built, is offset serious construction quality problem ubiquity and produce constructional column reinforcement location,Through having formed the main mass defect in Constructional Col-umn Construction. As schematically shown in Figure 1, 2, position and the design attitude of bar planting are inconsistent,Cause like this flexural deformation of bar planting, affect the mechanical property of member integrated. Therefore, solve the construction method of this difficult problem non-Normal urgent.
Summary of the invention
The present invention, in order to solve the inaccurate problem in location existing in the construction of post reinforcing steel implant, provides a kind of constructional columnBar planting positioning construction method.
Technical scheme of the present invention is: a kind of constructional column bar planting positioning construction method, and in concrete beam reinforcing and template peaceAfter dress, prepare to carry out, before concreting, beam bottom board being cleared up, measure unwrapping wire, determine constructional column position, use chilli oilPaint is smeared location at beam bottom board, cast concrete, and form removal, according to the boring of red paint position, clear hole, injecting glue, bar planting, solidifies, protects,Check and accept.
Concrete steps are to install at concrete beam reinforcing and template, prepare to carry out before concreting, by template baseOn layer, clean out; Determine constructional column main reinforce position according to designing requirement and regulation and stipulation, and guarantee in bar planting depth boundsNo-reinforcing-bar and other members block; According to the position determining, the U-shaped reinforcing bar that uses width to make for the main muscle width of constructional column is determinedPosition mould, dips in red paint in the termination of orientation tool, smears location on beam bottom board, and the red anchor point of formation is mixed like thisSolidifying soil is built complete, and after form removal, red paint can form visual anchor point on beams of concrete bottom surface; Again according to visual anchor point positionPut and hole, hole depth meets bar planting requirement; Boring is cleared up, adopt behind the clear hole of compressed air, then be stained with third with absorbent cottonKetone is cleaned hole wall, and answers retaining hole inner drying; By glue kind join glue and to boring injecting glue; Adopt rustless reinforcing bar implant bore, rightReinforcing bar is rotated bonding in order to structure glue and the wall of a borehole, and the reinforcing bar of implantation does temporary fixed; After bar planting completes, according to bar plantingGlue type and environment temperature guarantee that planted reinforcing bar is cured at the appointed time, and setting up period is forbidden disturbance reinforcing bar; Structure glueAfter solidifying, the pull-out test that adopts instrument to carry out on-the-spot bar planting according to amount of inspection, to check the performance of bar planting, and wants by specificationAsk and carry out an acceptance inspection.
Compared with prior art, the key point of technical solution of the present invention is to install at concrete beam reinforcing and template,Preparation is carried out before concreting. Use U-shaped reinforcing bar jig according to constructional column main reinforce position at beam bottom board correspondence position, useRed paint is smeared location. Owing to being in concreting prelocalization, therefore can dodge out reinforcing bar in beam. Treat beam concrete bottom dieAfter dismounting, according to red paint position corresponding on the beam base concrete bar planting of holing, can ensure that a bar planting puts in place. Thereby keep awayExempt from the direction blindness in traditional bar planting construction, effectively improved efficiency of construction and construction quality.
Brief description of the drawings
Fig. 1 is one of state diagram after existing bar planting method construction
Fig. 2 is two of state diagram after the construction of existing bar planting method
Fig. 3 is SBR figure before bar planting of the present invention
Fig. 4 is U-shaped reinforcing bar jig
Fig. 5 is the state diagram after scheme construction of the present invention
The bar planting of 1-back timber, 2-distortion, 3-post reinforcing bar, 4-side form, 5-reinforcing bar beam, 6-side form, 7-reinforcing bar beam, 8-locationAnchor point at the bottom of point, 9-beam bottom board, 10-post reinforcing bar, 11-reinforcing bar, 12-soffit, 13-beam.
Detailed description of the invention
As Fig. 3,4,5 illustrate, a kind of constructional column bar planting positioning construction method, step is as follows:
1, install at concrete beam reinforcing 7,5 and side template 6,4, prepare to carry out before concreting. For ensureing matterAmount, will clean out in basic unit, do not wait and have water stain grade of greasy dirt to hinder the spot of painting brushing, and beam bottom board 9 should be smooth, must notDamaged cracking.
2, measure unwrapping wire, determine constructional column position
Determine constructional column main reinforce position according to designing requirement and regulation and stipulation, can within the scope of tolerance, suitably avoidThe position of beam main tendon. And guarantee that the interior no-reinforcing-bar of bar planting depth bounds and other members block.
3, smear location with red paint at beam bottom board
According to the position determining, use long 1.5m left and right, width is the U-shaped reinforcing bar location that the main muscle width of constructional column is madeMould, this mould structure is as Fig. 4. Dip in appropriate red paint in termination, then insert in template, on beam bottom board, smear location. ShapeThe anchor point 8 becoming is round point shape, and diameter is advisable for " drilling diameter "+5mm. This mould structure is simple, can pass slow setting Tu LiangThe bar-mat reinforcement that reinforcing bar forms.
4, casting concrete.
5, form removal, after form removal, red paint can be bonded at and on beams of concrete 12 bottom surfaces, form anchor point 13 at the bottom of beam, notes locationPoint is protected, and avoids colliding with.
6 hole according to red paint position
Hole according to anchor point 13 positions, boring should adopt electric hammer or air drill pore-forming, need ensure that hole is positioned at when pore-formingAnchor point center, and drill bit is vertical with soffit, without skew. Hole depth should meet bar planting requirement.
7 clear holes
Boring is cleared up, adopt behind the clear hole of compressed air, then be stained with acetone with absorbent cotton and clean hole wall, and answer retaining holeInner drying.
8 injecting glues
By glue kind join glue and to boring injecting glue, when injecting glue must get rid of boring in air, consumption with reinforcing bar implant after slightlyBe extruded as standard.
9 bar plantings
Adopt rustless reinforcing bar 11 implant bores, reinforcing bar is rotated to bonding in order to structure glue and the wall of a borehole, implantReinforcing bar do temporary fixed.
10 solidify, protect
After bar planting completes, guarantee that according to anchoring adhesive type and environment temperature planted reinforcing bar is cured within a certain period of time,Setting up period is forbidden disturbance reinforcing bar.
11 check and accept
After structure glue is solidified, adopt the instrument pull-out test that carries out on-the-spot bar planting according to amount of inspection, to check bar plantingPerformance, and carry out an acceptance inspection by code requirement.
Claims (2)
1. a constructional column bar planting positioning construction method, is characterized in that: after concrete beam reinforcing and template install, and standardFor carrying out, before concreting, beam bottom board being cleared up, measure unwrapping wire, determine constructional column position, use red paint at beam bottom boardSmear location, cast concrete, form removal, according to the boring of red paint position, clear hole, injecting glue, bar planting, solidifies, protects, and checks and accepts.
2. constructional column bar planting positioning construction method according to claim 1, is characterized in that: concrete steps are at concreteBeam steel and template install, and prepare to carry out, before concreting, on beam bottom board, cleaning out; According to designing requirement and ruleModel regulation is determined constructional column main reinforce position, and guarantees that the interior no-reinforcing-bar of bar planting depth bounds and other members block; According to determiningGood position, the U-shaped reinforcing bar jig that uses width to make for the main muscle width of constructional column, at the end of U-shaped reinforcing bar jigHead dips in red paint, smears location on beam bottom board, forms red anchor point, and concreting is complete like this, chilli oil after form removalPaint can form visual anchor point on beams of concrete bottom surface; Hole according to visual locating point position, hole depth meets bar planting againRequirement; Boring is cleared up, adopt behind the clear hole of compressed air, then be stained with acetone with absorbent cotton and clean hole wall, and answer in retaining holeDry; By glue kind join glue and to boring injecting glue; Adopt rustless reinforcing bar implant bore, reinforcing bar is rotated in order to glue and boringWall bonding, the reinforcing bar of implantation does temporary fixed; After bar planting completes, guarantee that according to glue type and environment temperature planted reinforcing bar is on ruleIn fixing time, be cured, setting up period is forbidden disturbance reinforcing bar; After adhesive curing, adopt instrument to carry out scene according to amount of inspection and plantThe pull-out test of muscle, to check the performance of bar planting, and carries out an acceptance inspection by code requirement.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310387323.6A CN103452327B (en) | 2013-08-30 | 2013-08-30 | Constructional column bar planting positioning construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310387323.6A CN103452327B (en) | 2013-08-30 | 2013-08-30 | Constructional column bar planting positioning construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103452327A CN103452327A (en) | 2013-12-18 |
CN103452327B true CN103452327B (en) | 2016-05-11 |
Family
ID=49735123
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310387323.6A Active CN103452327B (en) | 2013-08-30 | 2013-08-30 | Constructional column bar planting positioning construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103452327B (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105155669B (en) * | 2015-09-15 | 2017-12-12 | 成都市第四建筑工程公司 | Concealed beam floor framing rod structure construction method |
CN105888259A (en) * | 2016-03-31 | 2016-08-24 | 张友谊 | Concrete steel bar planting method |
CN108868158B (en) * | 2018-07-27 | 2020-10-30 | 中交一公局重庆城市建设发展有限公司 | Method for positioning assembled building steel bars |
CN109629421B (en) * | 2018-11-20 | 2020-11-27 | 同济大学 | Construction method for segment beam additionally provided with steel pipe and horizontally distributed steel bars |
CN110145059B (en) * | 2019-05-29 | 2021-02-26 | 中冶建工集团有限公司 | Construction process of antique soil wall |
CN110219374A (en) * | 2019-05-30 | 2019-09-10 | 中铁第四勘察设计院集团有限公司 | Connection structure and attachment device |
CN114370160A (en) * | 2021-12-30 | 2022-04-19 | 珠海华发人居生活研究院有限公司 | Vertical member porous linkage grouting reinforcement method |
CN218622648U (en) | 2022-11-28 | 2023-03-14 | 中国建筑第二工程局有限公司 | Constructional column bar planting pre-embedding device |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01223262A (en) * | 1988-03-01 | 1989-09-06 | Taisei Corp | Construction of assembled wall |
CN101974902A (en) * | 2010-10-14 | 2011-02-16 | 宁波大汇建设工程有限公司 | Construction process for planting reinforcement bars into cement piles |
CN102486049A (en) * | 2010-12-06 | 2012-06-06 | 上海伙隆实业有限公司 | Filler wall masonry tie bar planting method |
EP2492417A1 (en) * | 2011-02-25 | 2012-08-29 | Commissariat à l'Énergie Atomique et aux Énergies Alternatives | Method for assistance with the placement of construction elements of a civil engineering structure |
CN103161313A (en) * | 2013-03-14 | 2013-06-19 | 中国华冶科工集团有限公司 | Connection method of main reinforcement of constructional column of infilled wall and framed girder |
-
2013
- 2013-08-30 CN CN201310387323.6A patent/CN103452327B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01223262A (en) * | 1988-03-01 | 1989-09-06 | Taisei Corp | Construction of assembled wall |
CN101974902A (en) * | 2010-10-14 | 2011-02-16 | 宁波大汇建设工程有限公司 | Construction process for planting reinforcement bars into cement piles |
CN102486049A (en) * | 2010-12-06 | 2012-06-06 | 上海伙隆实业有限公司 | Filler wall masonry tie bar planting method |
EP2492417A1 (en) * | 2011-02-25 | 2012-08-29 | Commissariat à l'Énergie Atomique et aux Énergies Alternatives | Method for assistance with the placement of construction elements of a civil engineering structure |
CN103161313A (en) * | 2013-03-14 | 2013-06-19 | 中国华冶科工集团有限公司 | Connection method of main reinforcement of constructional column of infilled wall and framed girder |
Non-Patent Citations (1)
Title |
---|
梁底植筋成孔装置的改进;赵柏明等;《建筑工人》;20091130(第11期);第30-31页 * |
Also Published As
Publication number | Publication date |
---|---|
CN103452327A (en) | 2013-12-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103452327B (en) | Constructional column bar planting positioning construction method | |
CN103321436A (en) | Pre-installation construction method for wire box on building bricked body and pre-installation supporting frame thereof | |
CN204645268U (en) | A kind of infilled wall tie bar built-in fitting | |
CN206495501U (en) | A kind of cast-in-place concrete floor reserving hole template | |
CN103374923A (en) | Method for prefabricating and mounting underwater pier | |
CN212613903U (en) | Brick-concrete structure old building body composite reinforcement structure | |
CN204590047U (en) | A kind of protecting slope ecology sash | |
CN107065801B (en) | Simulative construction method is automatically assembled using the section of track production line of BIM technology | |
CN101899868A (en) | Construction method for rear planted wall steel tie | |
CN205421322U (en) | Pre -buried rag bolt crowd's positioning tool | |
CN103233482A (en) | Installation and construction method for embedded bolts of cable trench | |
CN105547467A (en) | Device for fixing explosion vibration measuring sensor on soil layer | |
JP6921536B2 (en) | Construction method of anchors to be installed in existing masonry and post-construction anchors | |
CN109016089A (en) | A kind of mold, manufacture craft and the installation method of small-sized gate stack | |
CN209163138U (en) | A kind of reservation device of the floor reserved steel bar for climbing formwork for construction | |
CN104314179A (en) | Anti-shear stud for GFRP concrete combined member and construction method thereof | |
CN211058060U (en) | Wall structure of grouting sleeve | |
CN205907820U (en) | Steel and concrete built -up connection component | |
CN108868189A (en) | A kind of bamboo clappers curved scissors reinforced concrete beam and manufacturing method | |
CN103352568A (en) | Method for building constructional column on foundation pad | |
CN104131697B (en) | Tool type formwork system for kitchen and bath concrete waterproof guide wall and construction method of tool type formwork system | |
CN206034257U (en) | Device of homophase out -phase road surface grooving | |
CN107419631B (en) | A kind of rapid constructing method on brick structure road surface | |
CN113073870A (en) | Installation method for reinforcing reinforced concrete member joint | |
CN218814878U (en) | Embedded prefabricated fair-faced concrete decorative board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |