CN103410152A - 一种用于狭长深基坑土方开挖的施工方法 - Google Patents

一种用于狭长深基坑土方开挖的施工方法 Download PDF

Info

Publication number
CN103410152A
CN103410152A CN2013102963790A CN201310296379A CN103410152A CN 103410152 A CN103410152 A CN 103410152A CN 2013102963790 A CN2013102963790 A CN 2013102963790A CN 201310296379 A CN201310296379 A CN 201310296379A CN 103410152 A CN103410152 A CN 103410152A
Authority
CN
China
Prior art keywords
soil
foundation pit
long
deep foundation
bulldozer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102963790A
Other languages
English (en)
Other versions
CN103410152B (zh
Inventor
闫亚鹏
赵举纲
宋来东
叶坤
李永辉
刘有利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC HIGHWAY MAINTENANCE ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
CCCC HIGHWAY MAINTENANCE ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC HIGHWAY MAINTENANCE ENGINEERING TECHNOLOGY Co Ltd filed Critical CCCC HIGHWAY MAINTENANCE ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201310296379.0A priority Critical patent/CN103410152B/zh
Publication of CN103410152A publication Critical patent/CN103410152A/zh
Application granted granted Critical
Publication of CN103410152B publication Critical patent/CN103410152B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种用于狭长深基坑土方开挖的施工方法,包括以下步骤:1)利用大型挖掘机将基坑部分整体开挖,基坑中央留槽,安装钢管斜撑;2)利用大型挖掘机将基坑土层顶面纵向拉坡,形成推土机推土条件;3)推土机在纵向拉坡上斜坡式推土作业,由低端向高端推土,具备钢支撑可安装的高度后,及时跟进安装钢支撑支护结构;4)围护桩附近预留土或推土机背后无法施工的土,采用小型挖掘机喂土,推土机向一端推土,集中外运;5)狭长深基坑土方开挖完成后,用吊车将挖掘设备从深基坑中吊出。本发明的有益效果为:安全、高效、经济、环保、节能。

Description

一种用于狭长深基坑土方开挖的施工方法
技术领域
本发明涉及地基基础工程技术领域,具体涉及一种用于狭长深基坑土方开挖的施工方法。
背景技术
随着经济的发展与人们居住环境要求的提高,近年来建筑向高空发展的同时,向地下空间的发展也成为一个重要方向。高层及多层建筑的地下室、地下商场、地下车库等工程施工,都会面临基坑开挖,基坑开挖是一项复杂的综合性岩土工程,而且基坑的开挖深度也越来越深。由于受到基坑支撑结构等辅助装置的影响,常规挖机的功能发挥受到影响,特别是挖深大于20米后,常规挖机受动臂高度的制约,很难甚至不能发挥效能。采用何种施工方法才能保证狭长深基坑土方开挖高效、经济、节能和环保,显得尤为重要。
发明内容
本发明的目的是根据上述现有技术的不足之处,针对深基坑有支撑结构等辅助装置影响而形成的狭长深基坑土方开挖作业的特殊需要,提供一种用于狭长深基坑土方开挖的施工方法。
本发明的目的是通过以下技术方案来实现:
一种用于狭长深基坑土方开挖的施工方法,该方法包括以下步骤:
1)利用大型挖掘机将基坑部分整体开挖,基坑中央留槽,安装钢管斜撑; 
2)利用大型挖掘机将基坑土层顶面纵向拉坡,形成推土机推土条件;
3)推土机在纵向拉坡上斜坡式推土作业,由低端向高端推土,具备钢支撑可安装的高度后,及时跟进安装钢支撑支护结构;
4)围护桩附近预留土或推土机背后无法施工的土,采用小型挖掘机喂土,推土机向一端推土,集中外运,步骤4)进一步包括以下步骤:
(1)推土机将土推至可装车位置,然后用大型挖掘机装在自卸汽车上拉走;
(2)当具备第二道钢支撑可安装的高度后,及时安装第二道钢支撑;以及
(3)安装完成后基坑土方开挖一次见底,上、下层钢支撑安装随着挖土作业面依次先前跟进。
5)狭长深基坑土方开挖完成后,用吊车将挖掘设备从深基坑中吊出。
进一步的,步骤1)之前,根据工程现场条件选择进行松土作业;所述松土作业的机械为小型挖掘机,所述小型挖掘机反铲上的铲斗为独钩松土器。
进一步的,步骤1)中,采用大型挖掘机倒土的方法,自卸汽车从石渣换填的杂填土便道出土。
进一步的,步骤2)中,纵向拉坡至自卸汽车目前可以进入的场地处。
进一步的,步骤3)中,推土机从基坑中央留槽中间开始纵向由低端向高端推土。
优选的,狭长深基坑长度范围为130m~200m。
本发明的有益效果为:①安全性,该施工方法可实现支撑设施的及时跟进施工,可保证基坑支护结构的安全稳定,保证人身及财产安全;②高效性,由于推土机自身高度比较小,受支撑结构的影响小,干扰因素少、资源能较好的利用,方便施工,提高效率;③经济性,针对软弱土层采用宽履带式推土机,可减少施工便道等临时工程及材料投入量,避免临时迁移或拆除,具有较好的经济效益;④环保、节能性,合理配置推土机和运输车辆等施工机械,在节省能源的同时,还可减少排气及噪音污染。
附图说明
下面根据附图对本发明作进一步详细说明。
图1是本发明实施例中用于狭长深基坑土方开挖施工的剖面示意图;
图2为本发明实施例中狭长深基坑土方开挖及支撑结构及时跟进施工的示意图;
图3为本发明实施例中狭长深基坑土方开挖及支撑结构的俯视图;
图4为图1和图2中格构柱的构造图。
具体实施方式
如图1~4所示,本发明实施例所述的用于狭长深基坑土方开挖的施工方法,具体涉及到的施工机械主要有推土机、小型挖掘机、大型挖掘机和自卸汽车,涉及到的基坑支护设施主要是钢管撑和格构柱,具体的施工方法包括以下步骤:
1)通过大型挖掘机倒土的方法将欲挖基坑部分整体开挖至压顶梁顶面下3m,并在中央留槽,安装3组斜钢管撑,自卸汽车从石渣换填的杂填土便道出土;
2)采用利用大型挖掘机将基坑土层顶面纵向拉坡,直到自卸汽车目前可以进入的场地处,形成推土机推土条件后,让宽履带推土机进场;
3)采用斜坡式推土作业,用推土机从基坑中央留槽中间开始纵向由低端向高端推土,当推土高度达到能安装钢支撑的高度时,及时安装钢支撑并施加预应力,达到维护结构设计受力的目的;
4)对于围护桩附近预留土或推土机背后无法施工的土,通过小型挖掘机给推土机喂土的方法,推至可装车位置,然后用大型挖掘机装在自卸汽车上拉走。当具备第二道钢支撑可安装的高度后,及时安装第二道钢支撑,安装完成后基坑土方开挖一次见底。上、下层钢支撑安装随着挖土作业面依次先前跟进;以及
5)狭长深基坑土方开挖完成后,利用吊车将推土机等设备从深基坑中吊出。
该施工方法在于必要时先进行松土作业,主要通过将小型挖掘机反铲上的铲斗拆掉,安装上独钩松土器来实现,然后采用推土机推土施工,钢支撑等支护结构及时跟进的方法来实现狭长深基坑的土方开挖。所述的独钩松土器和挖掘机松土器均为小型挖掘机改装和配套的设备,具体参数型号通过工程现场情况试验确定。所述的推土机为宽履带式推土机,具体型号根据工程现场条件确定。
本发明不局限于上述最佳实施方式,任何人在本发明的启示下都可得出其他各种形式的产品,但不论在其形状或结构上作任何变化,凡是具有与本申请相同或相近似的技术方案,均落在本发明的保护范围之内。

Claims (8)

1.一种用于狭长深基坑土方开挖的施工方法,其特征在于,包括以下步骤:
1)利用大型挖掘机将基坑部分整体开挖,基坑中央留槽,安装钢管斜撑; 
2)利用大型挖掘机将基坑土层顶面纵向拉坡,形成推土机推土条件;
3)推土机在纵向拉坡上斜坡式推土作业,由低端向高端推土,具备钢支撑可安装的高度后,及时跟进安装钢支撑支护结构;
4)围护桩附近预留土或推土机背后无法施工的土采用小型挖掘机喂土,推土机向一端推土,集中外运;
5)狭长深基坑土方开挖完成后,用吊车将挖掘设备从深基坑中吊出。
2.根据权利要求1所述的用于狭长深基坑土方开挖的施工方法,其特征在于:步骤1)之前,根据工程现场条件选择进行松土作业。
3.根据权利要求2所述的用于狭长深基坑土方开挖的施工方法,其特征在于:所述松土作业的机械为小型挖掘机,所述小型挖掘机反铲上的铲斗为独钩松土器。
4.根据权利要求3所述的用于狭长深基坑土方开挖的施工方法,其特征在于:步骤1)中,采用大型挖掘机倒土的方法,自卸汽车从石渣换填的杂填土便道出土。
5.根据权利要求4所述的用于狭长深基坑土方开挖的施工方法,其特征在于:步骤2)中,纵向拉坡至自卸汽车目前可以进入的场地处。
6.根据权利要求5所述的用于狭长深基坑土方开挖的施工方法,其特征在于:步骤3)中,推土机从基坑中央留槽中间开始纵向由低端向高端推土。
7.根据权利要求6所述的用于狭长深基坑土方开挖的施工方法,其特征在于,步骤4)进一步包括以下步骤:
(1)推土机将土推至可装车位置,然后用大型挖掘机装在自卸汽车上拉走;
(2)当具备第二道钢支撑可安装的高度后,及时安装第二道钢支撑;以及
(3)安装完成后,基坑土方开挖一次见底,上、下层钢支撑安装随着挖土作业面依次先前跟进。
8.根据权利要求1-7任一项所述的用于狭长深基坑土方开挖的施工方法,其特征在于:狭长深基坑长度范围为130m~200m。
CN201310296379.0A 2013-09-05 2013-09-05 一种用于狭长深基坑土方开挖的施工方法 Active CN103410152B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310296379.0A CN103410152B (zh) 2013-09-05 2013-09-05 一种用于狭长深基坑土方开挖的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310296379.0A CN103410152B (zh) 2013-09-05 2013-09-05 一种用于狭长深基坑土方开挖的施工方法

Publications (2)

Publication Number Publication Date
CN103410152A true CN103410152A (zh) 2013-11-27
CN103410152B CN103410152B (zh) 2015-08-19

Family

ID=49603190

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310296379.0A Active CN103410152B (zh) 2013-09-05 2013-09-05 一种用于狭长深基坑土方开挖的施工方法

Country Status (1)

Country Link
CN (1) CN103410152B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695497A (zh) * 2014-12-30 2015-06-10 无锡三和重工机械有限公司 大型土石方工程的上土机施工工艺
CN105155546A (zh) * 2015-09-23 2015-12-16 重庆建工市政交通工程有限责任公司 一种预钻孔石方机械开挖的施工方法
CN105236275A (zh) * 2015-10-19 2016-01-13 中建一局集团建设发展有限公司 一种狭窄区域建筑深基坑施工的提土系统及提土方法
CN106759366A (zh) * 2017-01-25 2017-05-31 北京市政建设集团有限责任公司 一种基坑内土体开挖与马道布置的施工方法
CN108755697A (zh) * 2018-06-19 2018-11-06 江苏东珠景观股份有限公司 一种多雨天气下狭长深基坑土方开挖方法
CN109837909A (zh) * 2019-03-08 2019-06-04 北京正和恒基滨水生态环境治理股份有限公司 深基坑开挖方法
CN114086566A (zh) * 2021-11-10 2022-02-25 中铁第四勘察设计院集团有限公司 一种狭长型软土基坑开挖支护及土体运输方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4306364A (en) * 1979-12-14 1981-12-22 Shinko Kiko Co., Ltd. Vertical excavating arrangement
CN102535474A (zh) * 2010-12-13 2012-07-04 五冶集团上海有限公司 一种深基坑挖土的施工方法
CN102691300A (zh) * 2012-04-18 2012-09-26 浙江省建工集团有限责任公司 基坑土方的施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4306364A (en) * 1979-12-14 1981-12-22 Shinko Kiko Co., Ltd. Vertical excavating arrangement
CN102535474A (zh) * 2010-12-13 2012-07-04 五冶集团上海有限公司 一种深基坑挖土的施工方法
CN102691300A (zh) * 2012-04-18 2012-09-26 浙江省建工集团有限责任公司 基坑土方的施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
苗欣然: "有关深基坑挖土的安全措施", 《科技信息》, no. 5, 29 February 2012 (2012-02-29), pages 462 *
龙胜: "珠海南门涌水闸基础开挖及处理施工技术", 《四川水利》, no. 3, 30 June 2011 (2011-06-30) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695497A (zh) * 2014-12-30 2015-06-10 无锡三和重工机械有限公司 大型土石方工程的上土机施工工艺
CN105155546A (zh) * 2015-09-23 2015-12-16 重庆建工市政交通工程有限责任公司 一种预钻孔石方机械开挖的施工方法
CN105155546B (zh) * 2015-09-23 2018-02-02 重庆建工市政交通工程有限责任公司 一种预钻孔石方机械开挖的施工方法
CN105236275A (zh) * 2015-10-19 2016-01-13 中建一局集团建设发展有限公司 一种狭窄区域建筑深基坑施工的提土系统及提土方法
CN106759366A (zh) * 2017-01-25 2017-05-31 北京市政建设集团有限责任公司 一种基坑内土体开挖与马道布置的施工方法
CN108755697A (zh) * 2018-06-19 2018-11-06 江苏东珠景观股份有限公司 一种多雨天气下狭长深基坑土方开挖方法
CN109837909A (zh) * 2019-03-08 2019-06-04 北京正和恒基滨水生态环境治理股份有限公司 深基坑开挖方法
CN114086566A (zh) * 2021-11-10 2022-02-25 中铁第四勘察设计院集团有限公司 一种狭长型软土基坑开挖支护及土体运输方法

Also Published As

Publication number Publication date
CN103410152B (zh) 2015-08-19

Similar Documents

Publication Publication Date Title
CN103410152B (zh) 一种用于狭长深基坑土方开挖的施工方法
CN104652443B (zh) 深基坑临时水平支撑兼作永久结构梁的施工方法
CN106088650B (zh) 一种适用于砖混结构建筑物地下增层的方法及建筑物
CN106150506B (zh) 一种出入口明挖段倒挂井壁施工方法
CN102535474B (zh) 一种深基坑挖土的施工方法
CN102434717B (zh) 工字钢顶管工作坑的施工方法
CN104131565B (zh) 一种逆作土方正作开挖的施工方法
CN102758632A (zh) 岩质地层双初支分层法修建大型地下结构的方法
CN106436720A (zh) 顶管施工用小尺寸深基坑支护结构
CN102505704A (zh) 软弱地质竖井中大型沉井施工方法
CN104652444B (zh) 超大型深基坑中心岛式交替土方开挖的整体逆作施工方法
CN104532853A (zh) 型钢水泥土桩+易破除锚杆+自动监测预警的深基坑支护方法及系统
CN101824825B (zh) 一种深基坑明挖施工方法
CN110158603A (zh) 狭长深基坑土方开挖方法
CN109898556A (zh) 一种地下综合管廊结构及下沉式施工方法
CN106988337B (zh) 一种用于减小条形浅基础房屋不均匀沉降的加固方法
CN107165640B (zh) 隧道及地下工程自稳修建法
CN101532586A (zh) 一种地下管道安装施工装置及其方法
CN115506382A (zh) 一种用于筑岛平台桩板墙的施工方法
CN205502070U (zh) 一桩二用地下廊道结构
CN210459300U (zh) 一种盖挖车站的围护结构
CN103614999B (zh) 一种用于复杂地质条件下群桩深孔施工的方法
CN110485466A (zh) 一种预留门洞的装配式可回收圆形工作坑及其施工方法
CN106968271B (zh) 地下管廊开挖及支撑的施工方法
CN105113511A (zh) 砂岩结合土层的基坑综合支护施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant