CN103306320A CN201310251433XA CN201310251433A CN103306320A CN 103306320 A CN103306320 A CN 103306320A CN 201310251433X A CN201310251433X A CN 201310251433XA CN 201310251433 A CN201310251433 A CN 201310251433A CN 103306320 A CN103306320 A CN 103306320A
Authority
CN
China
Prior art keywords
shear wall
crack
plastic pipe
pvc plastic
basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310251433XA
Other languages
Chinese (zh)
Inventor
高蕤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201310251433XA priority Critical patent/CN103306320A/en
Publication of CN103306320A publication Critical patent/CN103306320A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a method for treating crack water seepage of a shear wall of a basement. The method is characterized by comprising the steps that a groove is formed along a crack in the surface of the shear wall till a groove opening reaches the bottom of the shear wall; the interior of the groove opening is cleaned up; a PVC (Polyvinyl Chloride) plastic pipe is split into two parts from the middle; the split PVC plastic pipe is aligned to the crack and buckled in the groove; the external surface and the side edge of the PVC plastic pipe are compacted and floated by waterproof mortar; a 10mm-high small notch is reserved at the bottom, away from a ground floor slab, of the PVC plastic pipe; a surface layer of the ground floor slab at the notch is coated with a layer of waterproof mortar; and the notch inclines towards an indoor drainage ditch on the edge of the shear wall. The method has the advantages that the method is reasonable in structure, simple, convenient and practical; a material is convenient to take; construction processes are simplified; the working efficiency is improved; and the cost is lowered.

Description

The processing method of basement shear wall crack infiltration
Technical field
The present invention relates to the civil engineering technical field, especially relate to basement shear wall because a kind of job practices that the crack that temperature shrink to produce or the crack infiltration that produces because of outside pressurized are handled.
Background technology
Along with the development of society, development of technology, large-scale underground parking, market and civil air defense constructions and installations are more and more.For large-area basement, the length of shear wall tends to long, and the back metope of having constructed the crack can occur unavoidably, and mainly show as: first: concrete temperature shrinks the temperature joint that causes; Second: the extruding during the basement foundation ditch backfill or sedimentation cause the shearing cracking of wall surface.These cracks the infiltration phenomenon occurs through regular meeting.General processing method is to adopt grouting for water plugging, namely holes with electric drill at the crack location place, with special equipment grout material is carried out slip casting along eyelet then, to reach the leak stopping purpose.This method operation is more, and it is slower to construct, and needs that the professional operates, construction cost is higher.
Summary of the invention
Purpose of the present invention is exactly the problem that exists at prior art, and the processing method of basement shear wall crack infiltration is provided, and simplifies basement shear wall crack treatment working procedure, improves speed of application, reduces construction cost.
The object of the present invention is achieved like this: the processing method of basement shear wall crack infiltration, it is characterized in that: slot along the crack at the shearing metope, notch is opened to the shear wall bottom, to clean out in the notch, the PVC plastic pipe is rived from the centre, be divided into two, the PVC plastic pipe of riving aimed at the crack be buckled in the groove, outside and side waterproofing mortar compacting, floating.The high small gap of 10mm is stayed in PVC plastic pipe bottom overhead floor, smears one deck waterproofing mortar at indentation, there ground floor surface layer, the indoor drainage ditch on breach aspect shear wall limit.
Described groove width is 30 * 30mm deeply.
Described PVC plastic pipe diameter is 20mm.
Described waterproofing mortar is the polymer cement waterproof mortar.
The water that the shearing metope oozes out flows downstream into the indoor drainage ditch along the PVC plastic pipe, and infiltration can not impact the interior architecture surface layer.
Compared with prior art, advantage of the present invention is: simple and practical, rational in infrastructure, draw materials conveniently, and simplified working procedure, improved operating efficiency, reduced cost.
Description of drawings
Fig. 1: the positive elevational schematic view of construction is handled in the infiltration of basement shear wall crack.
Fig. 2: construction side elevation schematic diagram is handled in the infiltration of basement shear wall crack.
Among the figure: 1, PVC plastic pipe 2, groove 3, indoor drainage ditch 4, shear wall 5, waterproofing mortar 6, crack 7, ground floor 8, interior architecture surface layer.
The specific embodiment
For further describing the present invention, below in conjunction with embodiment and accompanying drawing the present invention is further described.
As shown in the figure, the processing method of basement shear wall crack infiltration, it is characterized in that: 4 of shear walls along the crack 6 flutings 2,2 mouthfuls of grooves are opened to shear wall 4 bottoms, clean out in 2 mouthfuls of the grooves, PVC plastic pipe 1 is rived from the centre, be divided into two, the PVC plastic pipe 1 of riving is aimed at crack 6 be buckled in the groove 2, outside and side waterproofing mortar 5 compactings, floating.The high small gap of 10mm is stayed from shear wall ground floor 7 in PVC plastic pipe 1 bottom, smears one deck waterproofing mortar 5 at indentation, there ground floor 7 surface layers, the indoor drainage ditch 3 on breach aspect shear wall 4 limits.
Described groove 2 is wide to be 30 * 30mm deeply.
Described PVC plastic pipe diameter is 20mm.
Described waterproofing mortar is the polymer cement waterproof mortar.
The water that shear wall 4 faces ooze out flows downstream into indoor drainage ditch 3 along PVC plastic pipe 1, and infiltration can not impact interior architecture surface layer 8.
The present invention is successful Application in the engineering of university science and technology park, Bangbu.

Claims (4)

1. the processing method of basement shear wall crack infiltration, it is characterized in that: shear wall (4) face along the crack (6) fluting (2), groove (2) mouth is opened to shear wall (4) bottom, to clean out in groove (2) mouth, PVC plastic pipe (1) is rived from the centre, be divided into two, the PVC plastic pipe (1) of riving aimed at crack (6) be buckled in the groove (2), waterproofing mortar (5) compacting, floating of outside and side; The high small gap of 10 mm is stayed in PVC plastic pipe (1) bottom overhead floor (7), smears one deck waterproofing mortar (5) at indentation, there ground floor (7) surface layer, the indoor drainage ditch (3) on breach aspect shear wall (4) limit.
2. the processing method of basement shear wall according to claim 1 crack infiltration, it is characterized in that: described groove width is 30 * 30mm deeply.
3. the processing method of basement shear wall according to claim 1 crack infiltration, it is characterized in that: described PVC plastic pipe diameter is 20mm.
4. the processing method of basement shear wall according to claim 1 crack infiltration, it is characterized in that: described waterproofing mortar is the polymer cement waterproof mortar.
CN201310251433XA 2013-06-24 2013-06-24 Method for treating crack water seepage of shear wall of basement Pending CN103306320A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310251433XA CN103306320A (en) 2013-06-24 2013-06-24 Method for treating crack water seepage of shear wall of basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310251433XA CN103306320A (en) 2013-06-24 2013-06-24 Method for treating crack water seepage of shear wall of basement

Publications (1)

Publication Number Publication Date
CN103306320A true CN103306320A (en) 2013-09-18

Family

ID=49132006

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310251433XA Pending CN103306320A (en) 2013-06-24 2013-06-24 Method for treating crack water seepage of shear wall of basement

Country Status (1)

Country Link
CN (1) CN103306320A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234090A (en) * 2014-09-04 2014-12-24 江苏南通三建集团有限公司 Method for treating crack water seepage of concrete floor and wall body
CN104294836A (en) * 2014-10-30 2015-01-21 中冶建工集团有限公司 Water table lowering method applied to situation that aquiclude of foundation pit is cracked
CN104234090B (en) * 2014-09-04 2017-01-04 江苏南通三建集团有限公司 A kind of administer concrete floor, wall body slit infiltration method
CN108678029A (en) * 2018-06-29 2018-10-19 中国建筑第五工程局有限公司 A kind of hills rich water area basement guarded drainage construction method near a river

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW451019B (en) * 2000-04-18 2001-08-21 C & Amp M Hi Tech Engineering Water-proof and damp-proof method for basement side wall
KR100798126B1 (en) * 2007-04-23 2008-01-28 강문수 Water construction structure having lightweight waterproof layer
CN202000365U (en) * 2011-03-04 2011-10-05 长江航运规划设计院 Seepage-proof structure for underground continuous wall

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW451019B (en) * 2000-04-18 2001-08-21 C & Amp M Hi Tech Engineering Water-proof and damp-proof method for basement side wall
KR100798126B1 (en) * 2007-04-23 2008-01-28 강문수 Water construction structure having lightweight waterproof layer
CN202000365U (en) * 2011-03-04 2011-10-05 长江航运规划设计院 Seepage-proof structure for underground continuous wall

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
中国十七冶蚌埠大学科技园项目部: "地下室渗水处理方案", 《HTTP://WK.BAIDU.COM/VIEW/1036EBE9172DED630B1CB》 *
刘广洁: "女儿墙墙体裂缝与渗漏水的处理", 《江西煤炭科技》 *
王孔藩等: "结构裂缝控制与渗漏防治", 《四川建筑科学研究》 *
陈薇薇等: "地下室外墙裂缝处理方案的探讨", 《科技致富向导》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234090A (en) * 2014-09-04 2014-12-24 江苏南通三建集团有限公司 Method for treating crack water seepage of concrete floor and wall body
CN104234090B (en) * 2014-09-04 2017-01-04 江苏南通三建集团有限公司 A kind of administer concrete floor, wall body slit infiltration method
CN104294836A (en) * 2014-10-30 2015-01-21 中冶建工集团有限公司 Water table lowering method applied to situation that aquiclude of foundation pit is cracked
CN104294836B (en) * 2014-10-30 2016-06-22 中冶建工集团有限公司 There is the precipitation processing method in crack in foundation ditch water barrier
CN108678029A (en) * 2018-06-29 2018-10-19 中国建筑第五工程局有限公司 A kind of hills rich water area basement guarded drainage construction method near a river
CN108678029B (en) * 2018-06-29 2023-12-26 中国建筑第五工程局有限公司 Water-rich land area basement water-proof and drainage construction method for river-facing hills

Similar Documents

Publication Publication Date Title
CN201635308U (en) Multi-channel exhausting-prevention waterproof structure of prefabricated external wallboards
CN107859064B (en) Waterproof structure for connection of prefabricated pipe gallery and cast-in-situ pipe gallery and construction method
CN202380463U (en) Grouting capsule type recyclable anchor cable
CN102852159B (en) Construction method of retaining wall
CN103696416B (en) A kind of method for processing foundation
CN106812219A (en) Filling wall top stuff up a crack construction method
CN204849820U (en) Unilateral formwork of shaped steel combination
CN106593470A (en) High-permeability water-rich sand shield terminal reinforcing system and construction method thereof
CN202660067U (en) Waterproof sleeve preventing wall body leakage
CN203546759U (en) Plugging structure for post-cast strip of underground building
CN103306320A (en) Method for treating crack water seepage of shear wall of basement
CN102022009A (en) Non-destructive dampproof course repairing method and rear dampproof course
CN105756102A (en) Waterproof structure and process of integrated underground diaphragm wall and basement exterior wall
CN101769157B (en) Construction method for tunnel working face counterpressure treatment during tunnel excavation
CN206432677U (en) A kind of tunnel all standing formula cable duct
CN202401561U (en) Multifunctional environment-friendly movable water channel
CN102425228A (en) Multifunctional environment-friendly movable water tank
CN203625883U (en) Steel sheet support pile with pipes for foundation pit construction
CN106381883B (en) Bar Seepage method through walls
CN202108045U (en) Sleeve pipe with anchor rod penetrating through underground continuous wall
CN204356738U (en) A kind of concrete face rockfill dam upstream face structure of preventing face slab dislocation
CN203755423U (en) Novel drainage ditch shaping device
CN102535462A (en) Method for constructing anchor cable on sand layer
CN104480905A (en) Upstream surface structure of concrete face rockfill dam for preventing face from disengagement and construction method thereof
CN104963364A (en) Disposing method for topdown structural slab lower side wall construction joint

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130918