CN103212928B - 防止悬臂梁底板焊接变形的方法 - Google Patents

防止悬臂梁底板焊接变形的方法 Download PDF

Info

Publication number
CN103212928B
CN103212928B CN201310119829.9A CN201310119829A CN103212928B CN 103212928 B CN103212928 B CN 103212928B CN 201310119829 A CN201310119829 A CN 201310119829A CN 103212928 B CN103212928 B CN 103212928B
Authority
CN
China
Prior art keywords
base plate
cantilever beam
beam base
track girder
welding deformation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310119829.9A
Other languages
English (en)
Other versions
CN103212928A (zh
Inventor
陆海
王国威
卢玉春
吴正峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhenghua Heavy Industries Co Ltd
Original Assignee
Shanghai Zhenghua Heavy Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhenghua Heavy Industries Co Ltd filed Critical Shanghai Zhenghua Heavy Industries Co Ltd
Priority to CN201310119829.9A priority Critical patent/CN103212928B/zh
Publication of CN103212928A publication Critical patent/CN103212928A/zh
Application granted granted Critical
Publication of CN103212928B publication Critical patent/CN103212928B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明揭示了一种防止悬臂梁底板焊接变形的方法,其特征在于,包括以下步骤:步骤一,将轨道梁放置在平台上;步骤二,将悬臂梁底板放置在轨道梁上;步骤三,将悬臂梁底板与轨道梁压紧、预制反变形;步骤四,焊接。采用了本发明的技术方案,主要对悬臂梁底板焊接时的固定方式做了改进,有效的减小了悬臂梁底板焊接后产生的变形,从而能提高悬臂梁底板的焊接质量,提高悬臂梁底板产品的质量。

Description

防止悬臂梁底板焊接变形的方法
技术领域
本发明涉及自升式钻井平台悬臂梁建造的方法,更具体地说,涉及一种防止悬臂梁底板焊接变形的方法。
背景技术
自升式海洋钻井平台是近海油气勘探与开发不可或缺的海洋工程重要装备,悬臂梁结构作为自升式钻井平台的关键设备,其性能和精度控制的优劣直接影响到平台的安全和使用效果。其中悬臂梁底板的精度控制是悬臂梁制作过程中精度要求最高的部分,对于底板精度控制的成功与否直接关系到悬臂梁整体结构制作的质量。
目前,多数300尺自升式钻井平台制造厂家在制造过程中只是利用卡马固定悬臂梁底板,不利于最终对于悬臂梁底板变形的精度控制,结果往往超过了图纸要求的制作精度要求,在悬臂梁整体安装上船后,由于底板与悬臂梁甲板支座的接触面的减少,影响到平台的安全和使用效果。
现有技术中对于钢板的焊接防止变形的方法比较麻烦,需要以下的几个步骤:
1.两端对正点住。
2.中间对正点住。
3.然后以中间对称,两侧依次取中间对正点住。
4.对称的依次将钢板对正,并将焊点加密,每个焊点不超过5毫米长。直至焊点间隔不大于4毫米。
5.对称的将焊缝跑满。
6.焊的时候注意两面同时焊接。
7.有条件时,焊口打磨后,开平机校正。
300尺自升式钻井平台建造的过程中,采用新型的悬臂梁底板焊接控制变形新技术是对300尺自升式钻井平台建造技术的一次革新,还未见有任何报道。
发明内容
本发明的目的旨在提供一种防止悬臂梁底板焊接变形的方法,来解决现有技术中悬臂梁底板焊接不良率较高,精度不高的问题。
根据本发明,提供一种防止悬臂梁底板焊接变形的方法,其特征在于,包括以下步骤:步骤一,将轨道梁放置在平台上;步骤二,将悬臂梁底板放置在轨道梁上;步骤三,将悬臂梁底板与轨道梁压紧、预制反变形;步骤四,焊接。
根据本发明的一实施例,在步骤一之前,先加工轨道梁的轨道面以及轨道面上的垫板。
根据本发明的一实施例,垫板共两块,分别设置于轨道面的边缘,悬臂梁底板设置于垫板上。
根据本发明的一实施例,轨道面上两块垫板的中间为轨道板,轨道板略高于垫板。
根据本发明的一实施例,轨道板和垫板为整体加工成型。
根据本发明的一实施例,步骤一放置完毕之后,测量并调整轨道面的高低差至水平。
根据本发明的一实施例,步骤一放置完毕后,利用挡块沿轨道梁宽度方向将轨道梁与平台固定。
根据本发明的一实施例,步骤三利用油压千斤顶在悬臂梁底板宽度方向两侧同时挤压,将悬臂梁底板与轨道梁压紧。
根据本发明的一实施例,每压好一段悬臂梁底板,利用楔块、卡马将悬臂梁底板固定。
采用了本发明的技术方案,主要对悬臂梁底板焊接时的固定方式做了改进,有效的减小了悬臂梁底板焊接后产生的变形,从而能提高悬臂梁底板的焊接质量,提高悬臂梁底板产品的质量。
附图说明
在本发明中,相同的附图标记始终表示相同的特征,其中:
图1是本发明防止悬臂梁底板焊接变形的方法流程图;
图2是轨道梁与平台的放置示意图;
图3是千斤顶预制反变形示意图;
图4是悬臂梁底板刚性固定示意图。
具体实施方式
下面结合附图和实施例进一步说明本发明的技术方案。
300尺悬臂梁底板6宽610mm,长度近39000mm,大部分厚度达到了76mm,由于底板需要与腹板及两侧V板焊接,不仅焊缝长度长、而且全部为全熔透焊缝、焊接后一旦产生大的变形很难进行矫正,所以焊前进行反变形及刚性固定是关键,本发明公开了一种控制悬臂梁底板6焊接变形的新技术,有效的减小了悬臂梁底板6焊接后产生的变形。
参照图1,本发明防止悬臂梁底板6焊接变形的方法包括8个主要的步骤:
S1:加工轨道梁1的轨道面以及轨道面上的垫板3。
如图2所示,轨道面上两块垫板3的中间为轨道板2,轨道板2略高于垫板3。在原轨道梁1两侧间断焊焊接两块垫板3(通长),垫板3分别设置于轨道面的边缘,整体加工轨道板2及两侧垫板3,使轨道板2和垫板3为整体加工成型,两侧垫板3比中间轨道板2略低。
S2:将轨道梁1放置在平台4上
S3:测量并调整轨道面的高低差至水平
将加工后的轨道梁1放置在平台4上,利用激光经纬仪测量轨道面高低差,调整轨道面水平至全长范围内控制在公差要求范围内。
S4:利用挡块5沿轨道梁1宽度方向将轨道梁1与平台4固定
S5:将悬臂梁底板6放置在轨道梁1上,具体来说,悬臂梁底板6设置于垫板3上。
S6:如图3所示,将悬臂梁底板6与轨道梁1压紧、预制反变形
利用两个油压千斤顶7在悬臂梁底板6宽度方向两侧同时挤压,预制反变形,将悬臂梁底板6与轨道梁1压紧。
S7:如图4所示,每压好一段悬臂梁底板6,利用楔块9、卡马8等将悬臂梁底板6固定,使悬臂梁全长范围内都进行刚性固定,依次进行直至利用卡马8将悬臂梁全长范围内全部刚性固定好
S8:焊接
采用了本发明的方法,这种控制底板焊接变形的新技术改变了以往传统的的建造方式,虽然中间过程增加了机加工、千斤顶7反变形、刚性固定的工作环节,增加了一定的工作量,但对最终悬臂梁底板6的焊接控制起到了关键的作用,提高了300尺自升式钻井平台4悬臂梁总体建造质量,其主要优点如下:
1、轨道梁1与平台4并未完全固定,长度方向可以自由收缩,能使悬臂梁底板6在焊前加热后可以自由伸缩。
2、利用油压千斤顶7使悬臂梁底板6进行预制反变形,保证焊后精度要求。
3、利用卡马8与楔块9将悬臂梁刚性固定,减少焊接变形。
本技术领域中的普通技术人员应当认识到,以上的说明书仅是本发明众多实施例中的一种或几种实施方式,而并非用对本发明的限定。任何对于以上所述实施例的均等变化、变型以及等同替代等技术方案,只要符合本发明的实质精神范围,都将落在本发明的权利要求书所保护的范围内。

Claims (8)

1.一种防止悬臂梁底板焊接变形的方法,其特征在于,包括以下步骤:
步骤一,将轨道梁放置在平台上,放置完毕后,利用挡块沿轨道梁宽度方向将轨道梁与平台固定;
步骤二,将悬臂梁底板放置在轨道梁上;
步骤三,将悬臂梁底板与轨道梁压紧、预制反变形;
步骤四,焊接。
2.如权利要求1所述的防止悬臂梁底板焊接变形的方法,其特征在于,在步骤一之前,先加工轨道梁的轨道面以及轨道面上的垫板。
3.如权利要求2所述的防止悬臂梁底板焊接变形的方法,其特征在于,垫板共两块,分别设置于轨道面的边缘,悬臂梁底板设置于垫板上。
4.如权利要求1所述的防止悬臂梁底板焊接变形的方法,其特征在于,轨道面上两块垫板的中间为轨道板,轨道板略高于垫板。
5.如权利要求3或4所述的防止悬臂梁底板焊接变形的方法,其特征在于,轨道板和垫板为整体加工成型。
6.如权利要求1所述的防止悬臂梁底板焊接变形的方法,其特征在于,步骤一放置完毕之后,测量并调整轨道面的高低差至水平。
7.如权利要求1所述的防止悬臂梁底板焊接变形的方法,其特征在于,步骤三利用油压千斤顶在悬臂梁底板宽度方向两侧同时挤压,将悬臂梁底板与轨道梁压紧。
8.如权利要求4所述的防止悬臂梁底板焊接变形的方法,其特征在于,每压好一段悬臂梁底板,利用楔块、卡马将悬臂梁底板固定。
CN201310119829.9A 2013-04-08 2013-04-08 防止悬臂梁底板焊接变形的方法 Active CN103212928B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310119829.9A CN103212928B (zh) 2013-04-08 2013-04-08 防止悬臂梁底板焊接变形的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310119829.9A CN103212928B (zh) 2013-04-08 2013-04-08 防止悬臂梁底板焊接变形的方法

Publications (2)

Publication Number Publication Date
CN103212928A CN103212928A (zh) 2013-07-24
CN103212928B true CN103212928B (zh) 2015-09-16

Family

ID=48811260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310119829.9A Active CN103212928B (zh) 2013-04-08 2013-04-08 防止悬臂梁底板焊接变形的方法

Country Status (1)

Country Link
CN (1) CN103212928B (zh)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103862235B (zh) * 2014-02-26 2016-03-30 招商局重工(江苏)有限公司 一种自升式钻井平台悬臂梁轨道的制作方法
CN107687163B (zh) * 2016-08-05 2019-11-01 中集海洋工程研究院有限公司 自升式平台悬臂梁的耐磨板更换方法
CN106272159A (zh) * 2016-08-29 2017-01-04 福建东南造船有限公司 一种船体自由边矫直工装及矫直方法
CN111139808B (zh) * 2019-12-30 2021-08-17 南通振华重型装备制造有限公司 一种自升式钻井平台悬臂梁搭载方法
CN111687572A (zh) * 2020-04-30 2020-09-22 广州文冲船厂有限责任公司 一种船舶合拢用的装配装置及使用方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101239412A (zh) * 2008-03-14 2008-08-13 唐山轨道客车有限责任公司 大尺寸对接连接型材的焊接及压卡工艺
CN201175813Y (zh) * 2008-04-02 2009-01-07 四川省建科工程技术公司 薄板自动焊夹具
CN201324922Y (zh) * 2008-12-23 2009-10-14 天津重钢机械装备股份有限公司 可调式箱型梁焊接组对装置
CN201446366U (zh) * 2009-09-02 2010-05-05 江阴市振江钢结构有限公司 反变形工装
CN102049646A (zh) * 2010-12-23 2011-05-11 唐山轨道客车有限责任公司 工装支撑板、正装焊接工装及弧度型材焊接方法
CN202028896U (zh) * 2011-04-21 2011-11-09 廊坊广厦新源石化设备制造有限公司 防接管变形工装
CN102275044A (zh) * 2011-07-13 2011-12-14 铁道部运输局 板料焊接方法
CN102717221A (zh) * 2012-06-07 2012-10-10 中建钢构江苏有限公司 厚板超窄翼缘h型钢的制作方法

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3341831B2 (ja) * 1996-08-06 2002-11-05 株式会社日立製作所 摩擦接合方法とその構造体及び摩擦接合装置

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101239412A (zh) * 2008-03-14 2008-08-13 唐山轨道客车有限责任公司 大尺寸对接连接型材的焊接及压卡工艺
CN201175813Y (zh) * 2008-04-02 2009-01-07 四川省建科工程技术公司 薄板自动焊夹具
CN201324922Y (zh) * 2008-12-23 2009-10-14 天津重钢机械装备股份有限公司 可调式箱型梁焊接组对装置
CN201446366U (zh) * 2009-09-02 2010-05-05 江阴市振江钢结构有限公司 反变形工装
CN102049646A (zh) * 2010-12-23 2011-05-11 唐山轨道客车有限责任公司 工装支撑板、正装焊接工装及弧度型材焊接方法
CN202028896U (zh) * 2011-04-21 2011-11-09 廊坊广厦新源石化设备制造有限公司 防接管变形工装
CN102275044A (zh) * 2011-07-13 2011-12-14 铁道部运输局 板料焊接方法
CN102717221A (zh) * 2012-06-07 2012-10-10 中建钢构江苏有限公司 厚板超窄翼缘h型钢的制作方法

Also Published As

Publication number Publication date
CN103212928A (zh) 2013-07-24

Similar Documents

Publication Publication Date Title
CN103212928B (zh) 防止悬臂梁底板焊接变形的方法
CN101011781B (zh) 桥梁钢塔柱制造过程中焊接变形控制方法
CN105735129A (zh) 一种全焊桁架节段模块化拼装方法
CN102979319A (zh) 一种加固框架节点的方法
CN102966033B (zh) 全焊铁路连续钢桁梁多节点弦杆及制造方法
CN110104548B (zh) 一种龙门吊主梁结构建造方法
CN100509379C (zh) 结构夹层板件的连接件
CN203751615U (zh) 核电站结构模块顶法兰组焊及防变形工装
CN110593431A (zh) 一种可更换耗能梁段的π型钢-端板连接结构及方法
CN102373668B (zh) 桥梁钢锚箱组装方法
CN203808237U (zh) 一种预制装配式防屈曲钢板剪力墙高层建筑结构体系
EP3868979A1 (en) Method for tensioning prefabricated component employing centroid tracking and seam width control
CN203700931U (zh) 新型钢箱梁顶板单元结构
CN102061807B (zh) 一种大跨度h型钢桁架梁的组装方法
CN114799753B (zh) 一种空间异形多曲面钢结构的制造方法
CN111571072A (zh) 一种箱型细长梁的焊接精度控制方法
CN109590675B (zh) 一种塔式锅炉钢架叠合式大板梁制作方法
CN115180092A (zh) 船体薄板分段连接方法和船体
CN109371803A (zh) 一种钢板梁的加工方法
CN204728217U (zh) 钢箱梁节段拼装定位板装置
CN204413464U (zh) 一种箱型柱组立装置
CN104153386B (zh) 桩基承台周边立面垫层工具式钢模及其施工方法
CN113523688A (zh) 行车行走工字形梁的现场焊接工装及其组装焊接方法
CN107513936B (zh) 上字形边主梁结构及制作方法
CN112222779A (zh) 一种模板制造工艺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant