CN103138204A - Multifunctional installing rack used for replacing tension cross arm - Google Patents

Multifunctional installing rack used for replacing tension cross arm Download PDF

Info

Publication number
CN103138204A
CN103138204A CN2013100712105A CN201310071210A CN103138204A CN 103138204 A CN103138204 A CN 103138204A CN 2013100712105 A CN2013100712105 A CN 2013100712105A CN 201310071210 A CN201310071210 A CN 201310071210A CN 103138204 A CN103138204 A CN 103138204A
Authority
CN
China
Prior art keywords
cross arm
anchor ear
bracing wire
wire anchor
installing rack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100712105A
Other languages
Chinese (zh)
Other versions
CN103138204B (en
Inventor
白海军
王波
洪涛
荀福
赵增辉
曹柱琪
冯先智
麦克军
靳斌
唐怡雯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGXIA POWER Co WUZONG POWER SUPPLY BUREAU
State Grid Corp of China SGCC
Original Assignee
NINGXIA POWER Co WUZONG POWER SUPPLY BUREAU
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGXIA POWER Co WUZONG POWER SUPPLY BUREAU, State Grid Corp of China SGCC filed Critical NINGXIA POWER Co WUZONG POWER SUPPLY BUREAU
Priority to CN201310071210.5A priority Critical patent/CN103138204B/en
Publication of CN103138204A publication Critical patent/CN103138204A/en
Application granted granted Critical
Publication of CN103138204B publication Critical patent/CN103138204B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)
  • Details Of Indoor Wiring (AREA)

Abstract

The invention relates to a multifunctional installing rack used for replacing a tension cross arm. The multifunctional installing rack used for replacing the tension cross arm is characterized by comprising a pull wire embracing hoop (3), wherein a hanging hook (1) is fixed on the pull wire embracing hoop (3), a hand-operated tackle (2) is hung on the hanging hook (1), besides, four installing pipes (4) are fixed on the pull wire embracing hoop (3), and two support racks are inserted in the four installing pipes (4), so that the tension cross arm can be placed temporarily. Through trying out, due to the adoption of the multifunctional installing rack used for replacing the tension cross arm, the time for a single person to install the tension cross arm can be shortened to be within 20 minutes, and installing quality of the tension cross arm is effectively improved.

Description

Strain cross arm is changed and is used multi-functional installing rack
Technical field
The present invention relates to the multi-functional installing rack of a kind of strain cross arm replacing.
Background technology
In the real work of power department, often need to carry out the installation of strain cross arm and more change jobs new, old circuit.At present, in the installation and Renewal process of strain cross arm, because the weight of strain cross arm is very large, waste time and energy in the lifting process, bad operation when installing on shaft tower is wasted time and energy during adjustment, is difficult to reach fully the design and installation requirement.For example in the situation that present common single installation strain cross arm, just be easy to cause with the design and installation standard error large, do not meet mounting process, the phenomenon of installation quality even appears having a strong impact on.
Summary of the invention
The purpose of this invention is to provide a kind of strain cross arm replacing and use multi-functional installing rack, can increase work efficiency and reduce labour intensity.
A kind of strain cross arm is changed and is used multi-functional installing rack, its special feature is: comprise the bracing wire anchor ear, be fixed with a suspension hook on this bracing wire anchor ear, be hung with fly block on the other hand on this suspension hook, also be fixed with in addition four mounting pipe on this bracing wire anchor ear, place strain cross arm thereby be inserted with altogether two bracing frames in these four mounting pipe temporarily.
Wherein the bracing wire anchor ear adopts the adjustable variable bracing wire anchor ear of diameter.
Wherein variable bracing wire anchor ear comprises the bracing wire anchor ear that a side disconnects, and is separately installed with coiling ratchet and reel on the bracing wire anchor ear of this gap both sides, and all is wound with cotton rope on this coiling ratchet and reel.
Wherein suspension hook is fixed on the bracing wire anchor ear by connecting plate.
Wherein bracing frame comprises a L-type plate, can insert in two mounting pipe thereby be fixed with two support bars on this L-type plate.
Through probationary certificate, to adopt strain cross arm of the present invention to change and use multi-functional installing rack, the time of single installation strain cross arm can foreshorten in 20 minutes, and had effectively improved the installation quality of strain cross arm.
Description of drawings
Accompanying drawing 1 is structural representation of the present invention;
Accompanying drawing 2 is the structural representation of bracing frame in the present invention;
Accompanying drawing 3 is the left view of Fig. 2.
Embodiment
As shown in Figure 1, the present invention relates to the multi-functional installing rack of a kind of strain cross arm replacing, comprise bracing wire anchor ear 3, be fixed with a suspension hook 1 on this bracing wire anchor ear 3, be hung with fly block 2 on the other hand on this suspension hook 1, also be fixed with in addition four mounting pipe 4 on this bracing wire anchor ear 3, thereby be inserted with altogether two bracing frames and place strain cross arm temporarily these four mounting pipe 4 are interior.As shown in Fig. 2,3, bracing frame comprises a L-type plate 6, can insert in two mounting pipe 4 thereby be fixed with two support bars 7 on this L-type plate 6.
Wherein bracing wire anchor ear 3 adopts the adjustable variable bracing wire anchor ear 3 of diameter, this variable bracing wire anchor ear 3 specifically comprises the bracing wire anchor ear 3 that a side disconnects, be separately installed with coiling ratchet 5 and reel on the bracing wire anchor ear 3 of this gap both sides, and all be wound with cotton rope on this coiling ratchet 5 and reel.Certainly also can adopt existing variable bracing wire anchor ear 3 with other structure.Suspension hook 1 specifically is fixed on bracing wire anchor ear 3 by connecting plate in addition.
In the present invention, bracing wire anchor ear 3 and connecting plate, connecting plate and suspension hook 1, bracing wire anchor ear 3 and four mounting pipe 4 and bracing frame itself are welded by steel such as steel pipe, steel plates.
Using method of the present invention is:
As shown in Figure 1; at first the staff carries multi-functional installing rack of the present invention and climbs to the head of mast; then bracing wire anchor ear 3 is sleeved on shaft tower and fixes; then insert two bracing frames; coordinate with other staff on ground the strain cross arm of slinging by manual coaster 2 again; hang after proper height the staff and only strain cross arm need to be taken off that be placed on can be substantially fixing with strain cross arm on two bracing frames, and then strain cross arm is fixed on shaft tower by the design and installation requirement gets final product.

Claims (5)

1. a strain cross arm is changed and is used multi-functional installing rack, it is characterized in that: comprise bracing wire anchor ear (3), be fixed with a suspension hook (1) on this bracing wire anchor ear (3), be hung with fly block (2) on the other hand on this suspension hook (1), also be fixed with four mounting pipe (4) in addition on this bracing wire anchor ear (3), in these four mounting pipe (4) thus in be inserted with altogether two bracing frames and place strain cross arm temporarily.
2. a kind of strain cross arm as claimed in claim 1 is changed and used multi-functional installing rack, it is characterized in that: wherein bracing wire anchor ear (3) adopts the adjustable variable bracing wire anchor ear (3) of diameter.
3. a kind of strain cross arm as claimed in claim 2 is changed and is used multi-functional installing rack, it is characterized in that: wherein variable bracing wire anchor ear (3) comprises the bracing wire anchor ear (3) that a side disconnects, be separately installed with coiling ratchet (5) and reel on the bracing wire anchor ear (3) of this gap both sides, and all be wound with cotton rope on this coiling ratchet (5) and reel.
4. a kind of strain cross arm as claimed in claim 1 is changed and is used multi-functional installing rack, and it is characterized in that: wherein suspension hook (1) is fixed on bracing wire anchor ear (3) by connecting plate.
5. a kind of strain cross arm as claimed in claim 1 is changed and is used multi-functional installing rack, and it is characterized in that: wherein bracing frame comprises a L-type plate (6), be fixed with two support bars (7) on this L-type plate (6) thus can insert in two mounting pipe (4).
CN201310071210.5A 2013-03-07 2013-03-07 Strain cross arm is changed and is used multi-functional installing rack Expired - Fee Related CN103138204B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310071210.5A CN103138204B (en) 2013-03-07 2013-03-07 Strain cross arm is changed and is used multi-functional installing rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310071210.5A CN103138204B (en) 2013-03-07 2013-03-07 Strain cross arm is changed and is used multi-functional installing rack

Publications (2)

Publication Number Publication Date
CN103138204A true CN103138204A (en) 2013-06-05
CN103138204B CN103138204B (en) 2016-03-02

Family

ID=48497681

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310071210.5A Expired - Fee Related CN103138204B (en) 2013-03-07 2013-03-07 Strain cross arm is changed and is used multi-functional installing rack

Country Status (1)

Country Link
CN (1) CN103138204B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103701065A (en) * 2013-12-02 2014-04-02 国家电网公司 Mounting rack for replacing tension-resistant cross arms
CN106329437A (en) * 2016-10-12 2017-01-11 国网辽宁省电力有限公司鞍山供电公司 10kV cross arm brace of adjustable distribution overhead line and method of use
CN109428285A (en) * 2017-08-31 2019-03-05 国网河南省电力公司商水县供电公司 A kind of portable aerial work platform

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5228260A (en) * 1992-03-16 1993-07-20 Aluma-Form, Inc. Cross brace and support arm
CN201779102U (en) * 2010-07-07 2011-03-30 李一品 Diameter-variable anchor ear
CN202260340U (en) * 2011-10-14 2012-05-30 广西电网公司电力科学研究院 Power distribution network overhead line insulation tower head hoisting tool
CN102664377B (en) * 2012-05-09 2014-11-12 重庆市电力公司市区供电局 Double-cross arm assembler for single lever and double-cross arm mounting method
CN203119388U (en) * 2013-03-07 2013-08-07 宁夏电力公司吴忠供电局 Multifunctional mounting rack for changing tension-resistant crossarm

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103701065A (en) * 2013-12-02 2014-04-02 国家电网公司 Mounting rack for replacing tension-resistant cross arms
CN103701065B (en) * 2013-12-02 2016-08-17 国家电网公司 A kind of cross-arm changes tension installing rack
CN106329437A (en) * 2016-10-12 2017-01-11 国网辽宁省电力有限公司鞍山供电公司 10kV cross arm brace of adjustable distribution overhead line and method of use
CN106329437B (en) * 2016-10-12 2018-02-23 国网辽宁省电力有限公司鞍山供电公司 The adjustable distribution network overhead line cross arm support devices of 10kV and application method
CN109428285A (en) * 2017-08-31 2019-03-05 国网河南省电力公司商水县供电公司 A kind of portable aerial work platform

Also Published As

Publication number Publication date
CN103138204B (en) 2016-03-02

Similar Documents

Publication Publication Date Title
CN201704942U (en) Clip-type hanging basket suspension support
CN103138204B (en) Strain cross arm is changed and is used multi-functional installing rack
CN203998746U (en) Portable suspension installation
CN201215876Y (en) Assistant hanging rack for mounting top rack of electric pole
CN203119388U (en) Multifunctional mounting rack for changing tension-resistant crossarm
CN203278097U (en) Electric pole cross arm erecting device
CN204167793U (en) Straight line steel tube tower side, double loop cross-arm jig
CN205132955U (en) Hoist and mount operation of electric power industry low latitude is with hoist and mount frame
CN204068032U (en) A kind of bird-scaring unit erecting tools
CN204179569U (en) A kind of sister block wire grip of electric transmission line erection
CN203531381U (en) Temporary hanging and supporting device used for steel bar truss formworks
CN203289011U (en) Tension cross arm hoisting device
CN205034948U (en) Rack formula hanging beam device
CN203014282U (en) An overhead ground wire lifting device in a power transmission line
CN206494679U (en) A kind of power transformer installation system
CN203439918U (en) Fixture for lifting coil
CN204103342U (en) Line of power installs special purpose device
CN203653070U (en) Centre sill hanging tool of railway vehicle
CN202440227U (en) Device lifting support for electric pole
CN203939815U (en) Be used in the suspension centre fixing device on emergency first-aid repair tower
CN203312693U (en) Overhead ground wire lifter
CN202575837U (en) Multipurpose lifting pulley
CN204173813U (en) A kind of safety device arranged on tower crane crane arm for building
CN204131005U (en) Double loop tangent tower steeple head cross-arm jig
CN201345514Y (en) Insulated suspender for high-voltage live line work

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160302

Termination date: 20180307

CF01 Termination of patent right due to non-payment of annual fee