CN103114731B - The method for rapidly mounting of steel-structure factory building stone bolt - Google Patents

The method for rapidly mounting of steel-structure factory building stone bolt Download PDF

Info

Publication number
CN103114731B
CN103114731B CN201310044786.2A CN201310044786A CN103114731B CN 103114731 B CN103114731 B CN 103114731B CN 201310044786 A CN201310044786 A CN 201310044786A CN 103114731 B CN103114731 B CN 103114731B
Authority
CN
China
Prior art keywords
slab rubber
bamboo slab
stone bolt
reinforcing bar
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310044786.2A
Other languages
Chinese (zh)
Other versions
CN103114731A (en
Inventor
王惠荣
马君
行磊磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Taihang Construction Development Co Ltd
Original Assignee
Shanxi Taihang Construction Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Taihang Construction Development Co Ltd filed Critical Shanxi Taihang Construction Development Co Ltd
Priority to CN201310044786.2A priority Critical patent/CN103114731B/en
Publication of CN103114731A publication Critical patent/CN103114731A/en
Application granted granted Critical
Publication of CN103114731B publication Critical patent/CN103114731B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention relates to the mounting method of steel-structure factory building stone bolt, be specially a kind of method for rapidly mounting of steel-structure factory building stone bolt, solve the problem that when existing steel-structure factory building stone bolt is installed, efficiency of construction is lower.The method for rapidly mounting of steel-structure factory building stone bolt, comprises the steps: to get top bamboo slab rubber and bottom bamboo slab rubber; To all stone bolt of basic stand column reinforcing cage be put into successively through the locating hole on bottom bamboo slab rubber and top bamboo slab rubber; Often arrange common vertical on stone bolt to be welded with lower horizontal and to fix reinforcing bar, two row's stone bolt relatively between foot bolt common vertical be welded with lower vertical and fix reinforcing bar; The upper level be fixed on stone bolt is set above the bamboo slab rubber of top and fixes reinforcing bar and Upper vertical is fixed reinforcing bar and welds together with the main muscle in basic stand column reinforcing cage; Remove top bamboo slab rubber.Construction method efficiency of construction of the present invention is high, can be widely used in the installation of steel-structure factory building stone bolt.

Description

The method for rapidly mounting of steel-structure factory building stone bolt
Technical field
The present invention relates to the mounting method of steel-structure factory building stone bolt, be specially a kind of method for rapidly mounting of steel-structure factory building stone bolt.
Background technology
In steel-structure factory building work progress, stone bolt is the connecting elements connecting agent structure and basis, and thus the position control of stone bolt is the key of position control in foundation construction.Main muscle in stone bolt and basic stand column reinforcing cage is directly fixed together when installing by current stone bolt, bonding strength is low, poor reliability, in follow-up construction outside power particularly concrete vibrate effect under, stone bolt may produce larger displacement thus cause position control to be forbidden, to further increase in subsequent construction the measurement of stone bolt position and correction work amount, add construction cost.And single stone bolt is installed during construction, efficiency of construction is low, and overall axial line control difficulty is large, easily occurs deviation, directly affects the installation in position of steel work.
Summary of the invention
The present invention, in order to solve the problem that when existing steel-structure factory building stone bolt is installed, efficiency of construction is lower, provides a kind of method for rapidly mounting of steel-structure factory building stone bolt.
The present invention adopts following technical scheme to realize: the method for rapidly mounting of steel-structure factory building stone bolt, comprises the steps:
(1) the identical top bamboo slab rubber of geomery and bottom bamboo slab rubber is got, the equal symmetry in cross central line both sides of top bamboo slab rubber and bottom bamboo slab rubber has the locating hole of two row's diameters 2-3mm larger than the external diameter of stone bolt, and on top bamboo slab rubber and bottom bamboo slab rubber, the sum of locating hole is all equal with the sum of stone bolt; On top bamboo slab rubber and bottom bamboo slab rubber, the position of locating hole is mutually corresponding;
(2) on the outer wall of top bamboo slab rubber and bottom bamboo slab rubber, common vertical is fixing reinforces the lumps of wood thus top bamboo slab rubber and bottom bamboo slab rubber is linked together, and will put into all stone bolt of basic stand column reinforcing cage successively through the locating hole on bottom bamboo slab rubber and top bamboo slab rubber; Often arrange the lower horizontal that common vertical is welded with between top bamboo slab rubber and bottom bamboo slab rubber on stone bolt and fix reinforcing bar, two row's stone bolt relatively between foot bolt common vertical be welded with the lower vertical fixing reinforcement welding with lower horizontal and fix reinforcing bar;
(3) dismantle bottom bamboo slab rubber and reinforce the lumps of wood, the position of adjustment top bamboo slab rubber makes the center of top bamboo slab rubber and basic center superposition, lower horizontal is fixed reinforcing bar, lower vertical fixes reinforcing bar and main muscle in basic stand column reinforcing cage welds together (when namely offering locating hole on bamboo slab rubber, apart from the distance of bamboo slab rubber end, the spacing in adjacent positioned hole, locating hole should ensure that lower horizontal fixes reinforcing bar, lower vertical fix reinforcing bar and can weld together with the main muscle in basic stand column reinforcing cage);
(4) upper level be fixed on stone bolt is set above the bamboo slab rubber of top by the method for step (two) and fixes reinforcing bar and Upper vertical is fixed reinforcing bar and welds together with the main muscle in basic stand column reinforcing cage; Remove top bamboo slab rubber (upper and lower because of top bamboo slab rubber has fixing reinforcing bar, and when removing top bamboo slab rubber, the instrument destructiveness such as tup removes), complete the installation of stone bolt.
The present invention adopts bamboo slab rubber to be assembled by stone bolt as mould, again the stone bolt assembled is fixed reinforcing bar by level to be fixed together with the main muscle in vertical fixing reinforcing bar and basic stand column reinforcing cage, as long as the center of bamboo slab rubber and the center superposition on basis just can be controlled overall axis like a cork, bonding strength is high, reliability is strong, under the effect of external force, stone bolt can not produce larger displacement, position control is accurate, activity duration shortens 1/3rd, efficiency of construction is high, cost is low, facilitate the installation in position of steel work, avoid later rework.
Construction method efficiency of construction of the present invention is high, solves the problem that when existing steel-structure factory building stone bolt is installed, efficiency of construction is lower, can be widely used in the installation of steel-structure factory building stone bolt.
Accompanying drawing explanation
Fig. 1 is the structural representation of step of the present invention (one).
Fig. 2 is the structural representation of step of the present invention (two).
Fig. 3 is the structural representation of step of the present invention (four).
Fig. 4 is the top view of Fig. 3.
In figure: the bamboo slab rubber of 1-top; 2-bottom bamboo slab rubber; 3-stone bolt; 4-locating hole; 5-reinforces the lumps of wood; 6-lower horizontal fixes reinforcing bar; 7-lower vertical fixes reinforcing bar; The main muscle of 8-; 9-upper level fixes reinforcing bar; 10-Upper vertical fixes reinforcing bar.
Detailed description of the invention
The method for rapidly mounting of steel-structure factory building stone bolt, comprises the steps:
(1) the identical top bamboo slab rubber 1 of geomery and bottom bamboo slab rubber 2 is got, the equal symmetry in cross central line both sides of top bamboo slab rubber 1 and bottom bamboo slab rubber 2 has two row's diameters 2-3mm(2mm, 2.5mm, 3mm larger than the external diameter of stone bolt 3) locating hole 4, on top bamboo slab rubber 1 and bottom bamboo slab rubber 2, the sum of locating hole is all equal with the sum of stone bolt; On top bamboo slab rubber 1 and bottom bamboo slab rubber 2, the position of locating hole 4 is mutually corresponding;
(2) on the outer wall of top bamboo slab rubber 1 and bottom bamboo slab rubber 2, common vertical is fixing reinforces the lumps of wood 5 thus top bamboo slab rubber 1 and bottom bamboo slab rubber 2 is linked together, and will put into all stone bolt 3 of basic stand column reinforcing cage successively through the locating hole 4 on bottom bamboo slab rubber 2 and top bamboo slab rubber 1; Often arrange the common vertical lower horizontal be welded with between top bamboo slab rubber 1 and bottom bamboo slab rubber 2 on stone bolt to fix common vertical between relatively foot bolt 3 that reinforcing bar 6, two arranges stone bolt and be welded with and fix the lower vertical that reinforcing bar 6 welds with lower horizontal and fix reinforcing bar 7;
(3) to dismantle bottom bamboo slab rubber 2 and reinforce the lumps of wood 5, the position of adjustment top bamboo slab rubber 1 makes the center superposition on the center of top bamboo slab rubber 1 and basis, lower horizontal is fixed reinforcing bar 6, lower vertical fixes reinforcing bar 7 and weld together with the main muscle 8 in basic stand column reinforcing cage;
(4) upper level be fixed on stone bolt 3 is set above the bamboo slab rubber of top by the method for step (two) and fixes reinforcing bar 9 and Upper vertical is fixed reinforcing bar 10 and welds together with the main muscle 8 in basic stand column reinforcing cage; Remove top bamboo slab rubber 1, complete the installation of stone bolt.

Claims (1)

1. the method for rapidly mounting of steel-structure factory building stone bolt, is characterized in that: comprise the steps:
(1) the identical top bamboo slab rubber (1) of geomery and bottom bamboo slab rubber (2) is got, the equal symmetry in cross central line both sides of top bamboo slab rubber (1) and bottom bamboo slab rubber (2) has the locating hole (4) of two row's diameters 2-3mm larger than the external diameter of stone bolt (3), and the sum of top bamboo slab rubber (1) and the upper locating hole of bottom bamboo slab rubber (2) is all equal with the sum of stone bolt; The position of top bamboo slab rubber (1) and the upper locating hole (4) of bottom bamboo slab rubber (2) is mutually corresponding;
(2) on the outer wall of top bamboo slab rubber (1) and bottom bamboo slab rubber (2), common vertical is fixing reinforces the lumps of wood (5) thus top bamboo slab rubber (1) and bottom bamboo slab rubber (2) is linked together, and all stone bolt (3) putting into basic stand column reinforcing cage pass the locating hole (4) on bottom bamboo slab rubber (2) and top bamboo slab rubber (1) successively; Often arrange common vertical on stone bolt to be welded with the lower horizontal be positioned between top bamboo slab rubber (1) and bottom bamboo slab rubber (2) and to fix reinforcing bar (6), between the two relatively foot bolts (3) arranging stone bolt, common vertical is welded with and fixes the lower vertical that reinforcing bar (6) welds with lower horizontal and fix reinforcing bar (7);
(3) dismantle bottom bamboo slab rubber (2) and reinforce the lumps of wood (5), the position of adjustment top bamboo slab rubber (1) makes the center superposition on the center of top bamboo slab rubber (1) and basis, lower horizontal is fixed reinforcing bar (6), lower vertical fixes reinforcing bar (7) and weld together with the main muscle (8) in basic stand column reinforcing cage;
(4) upper level be fixed on stone bolt (3) is set above the bamboo slab rubber of top by the method for step (two) and fixes reinforcing bar (9) and Upper vertical is fixed reinforcing bar (10) and welds together with the main muscle (8) in basic stand column reinforcing cage; Remove top bamboo slab rubber (1), complete the installation of stone bolt.
CN201310044786.2A 2013-02-05 2013-02-05 The method for rapidly mounting of steel-structure factory building stone bolt Active CN103114731B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310044786.2A CN103114731B (en) 2013-02-05 2013-02-05 The method for rapidly mounting of steel-structure factory building stone bolt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310044786.2A CN103114731B (en) 2013-02-05 2013-02-05 The method for rapidly mounting of steel-structure factory building stone bolt

Publications (2)

Publication Number Publication Date
CN103114731A CN103114731A (en) 2013-05-22
CN103114731B true CN103114731B (en) 2015-09-02

Family

ID=48413160

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310044786.2A Active CN103114731B (en) 2013-02-05 2013-02-05 The method for rapidly mounting of steel-structure factory building stone bolt

Country Status (1)

Country Link
CN (1) CN103114731B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178091B (en) * 2016-03-10 2019-04-23 五冶集团上海有限公司 The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts
CN111889909B (en) * 2020-08-06 2021-12-21 中铁二十一局集团第三工程有限公司 Forming and welding process for steel structure embedded foundation bolts
CN112144567A (en) * 2020-09-08 2020-12-29 中国二十冶集团有限公司 Fixing method of directly-buried foundation bolt

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1025743A (en) * 1996-07-10 1998-01-27 Hitachi Metals Ltd Fixing structure 0f steel-framed column base
JP3290636B2 (en) * 1999-10-06 2002-06-10 株式会社アルテス Joint structure between steel column base and foundation concrete
CN201770992U (en) * 2010-07-22 2011-03-23 武汉一冶钢结构有限责任公司 Foundation bolt positioning device
CN202170636U (en) * 2011-07-14 2012-03-21 中建八局第四建设有限公司 Mould for pre-embedded foundation bolt of steel structural foundation
CN102619173A (en) * 2012-04-25 2012-08-01 中铁大桥局集团第五工程有限公司 Construction method of large bridge steel guardrail concrete base

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1025743A (en) * 1996-07-10 1998-01-27 Hitachi Metals Ltd Fixing structure 0f steel-framed column base
JP3290636B2 (en) * 1999-10-06 2002-06-10 株式会社アルテス Joint structure between steel column base and foundation concrete
CN201770992U (en) * 2010-07-22 2011-03-23 武汉一冶钢结构有限责任公司 Foundation bolt positioning device
CN202170636U (en) * 2011-07-14 2012-03-21 中建八局第四建设有限公司 Mould for pre-embedded foundation bolt of steel structural foundation
CN102619173A (en) * 2012-04-25 2012-08-01 中铁大桥局集团第五工程有限公司 Construction method of large bridge steel guardrail concrete base

Also Published As

Publication number Publication date
CN103114731A (en) 2013-05-22

Similar Documents

Publication Publication Date Title
CN203296175U (en) Rectangular steel pipe column assembly type column foot
CN103437425A (en) Connecting joint of prefabricated hollow steel-reinforced concrete column and steel beam and construction method
CN204662247U (en) A kind of Flange joint Concrete Filled double-walled steel pipe precast assembly bridge pier of additional power consumption reinforcing bar
CN202969586U (en) Prefabricated concrete beam-column anchor welding combined structure
CN105155684A (en) Steel frame integrated member for concrete core tube structures and assembly method thereof
CN103114731B (en) The method for rapidly mounting of steel-structure factory building stone bolt
CN205712590U (en) A kind of fabricated shear wall and the attachment structure of Prefabricated concrete-filled steel tube post
CN104196163A (en) Two-direction pre-stressed prefabricated hollow concrete slab and manufacturing method thereof
CN105239726A (en) Prefabricated steel-reinforced concrete combined special-shaped energy-dissipating column
CN102182276B (en) Manufacturing method of mega column in shape of double Chinese characters ya
CN203008136U (en) Concrete-filled steel tubular column and reinforced concrete beam middle joint connection structure
CN102619286B (en) Connecting joint of steel pipe concrete column and profile steel concrete beam
CN102505849A (en) Construction method of membrane shell ribbed floor formwork supporting system
CN103628569B (en) A kind of draw-in groove assembly concrete-filled steel tube post-steel beam connecting joint
CN203603526U (en) Reinforcing structure of reinforced concrete frame column
CN203640061U (en) Node connecting structure of reinforced concrete column of basement
JP6057579B2 (en) Seismic isolation device support structure and construction method of seismic isolation device support structure
CN204212058U (en) For the steel truss girder assembling support in the construction of steel concrete composite truss beam
CN103088997A (en) Channel steel guide rail for controlling floor elevation and method
CN203213301U (en) Steel column and concrete beam steel bar connection node structure
CN203008137U (en) Concrete-filled steel tubular column and reinforced concrete beam top joint connection structure
CN203412135U (en) Building base shock insulation device
CN205349372U (en) For a short time, construct to fold friendship tunnel controllable gate shaped steel frame apart from shield only
CN204781601U (en) Antidetonation type RC frame construction post
CN204662248U (en) A kind of Flange joint Concrete Filled double-walled steel pipe precast assembly bridge pier of additional damping device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant