CN107178091B - The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts - Google Patents

The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts Download PDF

Info

Publication number
CN107178091B
CN107178091B CN201610135150.2A CN201610135150A CN107178091B CN 107178091 B CN107178091 B CN 107178091B CN 201610135150 A CN201610135150 A CN 201610135150A CN 107178091 B CN107178091 B CN 107178091B
Authority
CN
China
Prior art keywords
posting
concrete foundation
positioning
foundation
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610135150.2A
Other languages
Chinese (zh)
Other versions
CN107178091A (en
Inventor
李志红
董健
刘贵斌
刘宗宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201610135150.2A priority Critical patent/CN107178091B/en
Publication of CN107178091A publication Critical patent/CN107178091A/en
Application granted granted Critical
Publication of CN107178091B publication Critical patent/CN107178091B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

A kind of pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts, characterized by the following steps: a, prefabricated posting, b, prefabricated positioning upright bar (7), retention bar (8), position vertical pole (9) and wood block filler (10), c, it is popped up on concrete foundation (1) vertical, cross central line, d, foundation bolt (2) is put into anchor bolt box, e, it is arranged wood block filler (10), f, posting is installed, g, stationary positioned cross bar, h, stationary positioned vertical pole, i, un-rotatably foot bolt (2) when removing adjusting nut (16), reach the accurate positioning of can-type calcine furnace steel construction pillar embedding anchor bolts.The present invention has posting apparatus structure simple, easy to make, and rationally, each step is closely engaged the design of embedding anchor bolts construction procedure, it is mutually coordinated, reach embedding anchor bolts to be accurately positioned requirement and accelerate steel column installation speed, reduces the advantages of crane uses the time, reduces engineering cost.

Description

The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts
Technical field
The present invention relates to a kind of foundation bolt installation methods of industrial machinery, specifically, being a kind of pot type calcining The pinpoint method of furnace steel construction pillar embedding anchor bolts.
Background technique
It is construction that the support of industrial machinery or the suspension column of equipment steel construction and basis are attached by foundation bolt It is middle through frequently with a kind of equipment or equipment steel construction fixing means.Specific to the embedding anchor bolts project of construction unit, It is required that foundation bolt is used to fix can-type calcine furnace steel construction pillar, there are 4 Φ 200mm foundation bolts are pre- on each column foundation It boxes out, bolt hole transverse center spacing is 515mm, and longitudinal center's spacing is 450mm.Fig. 1 is known can-type calcine furnace steel knot Embedding anchor bolts of the structure pillar in concrete foundation require schematic diagram.The required precision of can-type calcine furnace Steel Structure Installation is high, To guarantee pillar installation accuracy, construction unit also requires to install again after being first accurately positioned on column foundation by foundation bolt and is pre-buried Steel construction pillar.
Due to can-type calcine furnace Steel Structure Installation required precision height, foundation bolt positioning, and top end surface absolute altitude, which reach, to be wanted Rear bottom is asked not contact with preformed hole bottom, foundation bolt positioning and absolute altitude must remain unchanged when grouting, or have allowed band Interior small variations.
Therefore known can-type calcine furnace steel construction pillar embedding anchor bolts mode there is above-mentioned various inconvenience and is asked Topic.
Summary of the invention
The purpose of the present invention is to propose that a kind of solution embedding anchor bolts are accurately positioned difficult can-type calcine furnace steel construction The pinpoint method of pillar embedding anchor bolts.
To achieve the above object, the technical solution of the invention is as follows:
A kind of pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts, the concrete of steel construction pillar On the basis of there are 4 Φ 200mm anchor bolt boxs, the transverse center spacing of anchor bolt box is 515mm, lower margin spiral shell Longitudinal center's spacing of bolt preformed hole is 450mm, it is characterised in that the following steps are included:
A, prefabricated posting
Posting is the rectangle frame made by the L70X5 angle steel of 2 root long 795mm and the L70X5 angle steel of 2 root long 510mm, Rectangle frame upper surface processes the posting hole of 4 Φ 43mm, and posting cross central line and posting longitudinal centre line on bullet, The transverse center spacing in 4 posting holes is 515mm, and longitudinal center's spacing is 4 backup lands on 450mm, with concrete foundation The concrete foundation transverse center spacing of bolt holes is consistent with concrete foundation longitudinal center spacing;
B, prefabricated positioning upright bar, retention bar, positioning vertical pole and wood block filler
Using 4 positioning upright bars of steel bar meter, the Φ 14mm screw-thread steel that upright bar is 200mm long is positioned;Use steel bar meter 2 Root retention bar, retention bar are the Φ 20mm screw-thread steel of 715mm long;4 positioning vertical poles, the Φ that positioning vertical pole is 860mm long 20mm screw-thread steel;2 wood block fillers are processed using timber, wood block filler is having a size of 40mmX80mmX560mm;
C, concrete foundation longitudinal centre line and concrete foundation cross central line are popped up in concrete foundation, are then existed 4 diameter 14mm are bored on concrete foundation surface, and depth is the positioning upright bar hole of 100mm, and 4 positioning upright bars are hammered into 4 and are determined In the upright bar hole of position, the long 100mm in part that upright bar is exposed on concrete foundation surface is positioned;
D, it after 4 foundation bolts respectively being screwed on a location nut, is respectively put into 4 anchor bolt boxs;
E, by 2 wood block fillers, direction is individually placed to basic longitudinal centre line both sides of the edge along the longitudinal centerline;
F, posting is installed
Posting is placed on 2 wood block fillers, 4 foundation bolts are penetrated in the posting hole of posting, and is installed Upper plain washer and adjusting nut make posting cross central line and posting longitudinal center with the position of hand hammer adjustment posting Line is aligned with concrete foundation cross central line and concrete foundation longitudinal centre line respectively, then with adjusting nut come adjustably Foot bolt upper surface absolute altitude, after reaching design requirement absolute altitude, the position of fixed adjusting nut makes adjusting nut lower surface and coagulation Earth foundation upper surface is substantially flush;
G, 2 retention bars are close to concrete foundation upper surface and are welded on concrete foundation longitudinal centre line between two parties respectively In 2 positioning upright bars of two sides;
H, after 2 location nuts that 4 positioning vertical poles are clamped to cross central line two sides two-by-two, it is vertical that 2 positioning are welded on On bar;
I, it is positioned since foundation bolt is welded to each other by positioning upright bar, retention bar, positioning vertical pole, location nut, Posting, adjustment bolt, plain washer, wood block filler are removed into after-pouring pea gravel concreten grouting material, it can not when removing adjusting nut Foundation bolt is rotated, the accurate positioning of can-type calcine furnace steel construction pillar embedding anchor bolts is reached.
The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts of the invention can also use following Technical measures further realize.
Method above-mentioned, wherein concrete foundation longitudinal centre line two sides are arranged in positioning upright bar hole in the step c On 2 anchor bolt box lines of centres, and all in anchor bolt box close to the side at concrete foundation edge.
Method above-mentioned, wherein adjusting nut lower surface is concordant with concrete foundation upper surface in the step f.
After adopting the above technical scheme, can-type calcine furnace steel construction pillar embedding anchor bolts of the invention are pinpoint Method has the advantage that
1, posting apparatus structure is simple, easy to make;
2, rationally, each step is closely engaged the design of embedding anchor bolts construction procedure, mutually coordinated, and it is pre- to reach foundation bolt Accurate positioning is buried to require;
3, first pillar is lifted in place with tradition, then mounting foot bolt is compared, accelerates steel column installation speed, reduce crane Using the time, construction cost is reduced.
Detailed description of the invention
Fig. 1 is that embedding anchor bolts of the can-type calcine furnace steel construction pillar in concrete foundation require schematic diagram;
Fig. 2 is the posting structural schematic diagram of the embodiment of the present invention;
Fig. 3 is that the installation of the embodiment of the present invention positions upright bar schematic diagram;
Fig. 4 is the installation location nut schematic diagram of the embodiment of the present invention;
Fig. 5 is the installation wood block filler schematic diagram of the embodiment of the present invention;
Fig. 6 is the installation posting schematic diagram of the embodiment of the present invention;
Fig. 7 is the installation retention bar schematic diagram of the embodiment of the present invention;
Fig. 8 is that the installation of the embodiment of the present invention positions vertical pole schematic diagram;
Fig. 9 is that the foundation bolt adjustment of the embodiment of the present invention terminates to wait casting concrete grouting material schematic diagram.
In figure: 1 concrete foundation, 2 foundation bolts, 3 pea gravel concreten grouting materials, 4 posting longitudinal centre lines, 5 positioning Frame cross central line, 6 posting holes, 7 positioning upright bars, 8 retention bars, 9 positioning vertical poles, 10 wood block fillers, 11 concrete foundations are vertical To center line, 12 concrete foundation cross central lines, 13 positioning upright bar holes, 14 anchor bolt boxs, 15 location nuts, 16 are adjusted Whole nut.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts of the invention, steel construction pillar mix There are 4 Φ 200mm anchor bolt boxs 14 on solidifying earth foundation 1, the transverse center spacing of anchor bolt box is 515mm, longitudinal center's spacing of anchor bolt box are 450mm, Specific construction the following steps are included:
It is embedding anchor bolts requirement of the can-type calcine furnace steel construction pillar in concrete foundation referring now to Fig. 1, Fig. 1 Schematic diagram.
Fig. 2 is the posting structural schematic diagram of the embodiment of the present invention.
A, prefabricated posting
Posting is the rectangle frame made by the L70X5 angle steel of 2 root long 795mm and the L70X5 angle steel of 2 root long 510mm, Rectangle frame upper surface processes the posting hole 6 of 4 Φ 43mm, and posting cross central line 5 and posting longitudinal center on bullet The transverse center spacing in 4,4 posting holes 6 of line is 515mm, and longitudinal center's spacing is 4 on 450mm, with concrete foundation 1 The concrete foundation transverse center spacing of anchor bolt box 14 is consistent with concrete foundation longitudinal center spacing;
B, prefabricated positioning upright bar 7, retention bar 8, positioning vertical pole 9 and wood block filler 10
Using the 4 positioning upright bars 7 of useless steel bar meter, the Φ 14mm screw-thread steel that upright bar is 200mm long is positioned;Using reinforcing bar plus 2 retention bars 8 of work, retention bar are the Φ 20mm screw-thread steel of 715mm long;4 positioning vertical poles, positioning vertical pole are 860mm long Φ 20mm screw-thread steel;2 wood block fillers are processed using timber, wood block filler is having a size of 40mmX80mmX560mm.
Fig. 3 is that the installation of the embodiment of the present invention positions upright bar schematic diagram.
C, concrete foundation longitudinal centre line 11 and concrete foundation cross central line 12 are popped up in concrete foundation 1, Then 4 diameter 14mm are bored on concrete foundation surface, depth is the positioning upright bar hole 13 of 100mm, and by 4 positioning upright bars 7 It hammers into 4 positioning upright bar holes, the long 100mm in part that positioning upright bar is exposed on concrete foundation surface;
In the step c, the both lateral sides edge of anchor bolt box 14 is arranged in positioning upright bar hole 13.
Fig. 4 is the installation location nut schematic diagram of the embodiment of the present invention.
D, it after 4 foundation bolts 2 respectively being screwed on a location nut 15, is respectively put into 4 anchor bolt boxs 14.
Fig. 5 is the installation wood block filler schematic diagram of the embodiment of the present invention.
E, by 2 wood block fillers 10, direction is individually placed to basic longitudinal centre line both sides of the edge along the longitudinal centerline;
Fig. 6 is the installation posting schematic diagram of the embodiment of the present invention.
F, posting is installed
Posting is placed on 2 wood block fillers 10,4 foundation bolts 2 are penetrated in the posting hole 6 of posting, and Plain washer and adjusting nut 16 are installed, with the position of hand hammer adjustment posting, keeps posting cross central line 5 and posting vertical It is aligned respectively with concrete foundation cross central line 12 and concrete foundation longitudinal centre line 11 to center line 4, then with adjustment Nut 16 adjusts 2 upper surface absolute altitude of foundation bolt, and after reaching design requirement absolute altitude, the position of fixed adjusting nut 16 makes to adjust Whole 16 lower surface of nut is substantially flush with 1 upper surface of concrete foundation;16 lower surface of adjusting nut and 1 upper surface of concrete foundation In the adjusting being substantially flush, it is very accurate not require, in order to which 1 upper surface of concrete foundation places energy after positioning vertical pole 9 Location nut 15 is set to be clamped and be welded and fixed by positioning vertical pole 9.
Fig. 7 is the installation retention bar schematic diagram of the embodiment of the present invention.
G, 2 retention bars 8 are close to 1 upper surface of concrete foundation and are welded on concrete foundation longitudinal center between two parties respectively In 2 positioning upright bars 7 of 11 two sides of line;
Fig. 8 is that the installation of the embodiment of the present invention positions vertical pole schematic diagram.
H, after 2 location nuts 15 that 4 positioning vertical poles 9 are clamped to cross central line two sides two-by-two, 2 positioning are welded on On vertical pole 9;
Fig. 9 is that the foundation bolt adjustment of the embodiment of the present invention terminates to wait casting concrete grouting material schematic diagram.
I, since foundation bolt 2 has been welded to each other by positioning upright bar 7, retention bar 8, positioning vertical pole 9, location nut 15 and Posting, adjustment bolt 16, plain washer, wood block filler 10 are removed after-pouring pea gravel concreten grouting material 3, remove adjustment by positioning The accurate positioning of can-type calcine furnace steel construction pillar embedding anchor bolts is reached in un-rotatably foot bolt 2 when nut 16.
The present invention has substantive distinguishing features and significant technological progress, can-type calcine furnace steel construction pillar lower margin of the invention The pinpoint method of bolt embedment utilizes posting location measure, successfully solves foundation bolt and positions problem, improves lower margin Bolt positioning accuracy guarantees pillar installation accuracy, to ensure that the installation accuracy of calcining furnace steel construction pillar, it is ensured that construction matter Amount.The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts of the invention greatly speeds up steel column installation speed Degree reduces crane and uses the time, saves cost.First pillar is lifted in place with tradition, then mounting foot bolt is compared, this is used After inventive method is pre-buried to foundation bolt progress, when calcining furnace steel construction pillar is installed, directly pillar is lifted in place, is then used After nut is fixed can decoupling device immediately lift next pillar, eliminate the time using installation and adjustment foundation bolt when crane, Installation procedure is simplified, installation effectiveness is improved, reduces crane machine-team usage amount, save construction cost.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent Technical solution also should belong to scope of the invention, should be limited by each claim.

Claims (3)

1. a kind of pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts, the coagulation soil matrix of steel construction pillar There are 4 Φ 200mm anchor bolt boxs (14) on plinth (1), the transverse center spacing of anchor bolt box is 515mm, Longitudinal center's spacing of anchor bolt box is 450mm, it is characterised in that the following steps are included:
A, prefabricated posting
Posting is by the rectangle frame of the L70X5 angle steel production of the L70X5 angle steel and 2 root long 510mm of 2 root long 795mm, in rectangle Frame upper surface processes the posting hole (6) of 4 Φ 43mm, and posting cross central line (5) and posting longitudinal center on bullet Line (4), the transverse center spacing of 4 posting holes (6) are 515mm, and longitudinal center's spacing is 450mm, with concrete foundation (1) The concrete foundation transverse center spacing of upper 4 anchor bolt boxs (14) is consistent with concrete foundation longitudinal center spacing;
B, prefabricated positioning upright bar (7), retention bar (8), positioning vertical pole (9) and wood block filler (10)
Using 4 positioning upright bars (7) of steel bar meter, the Φ 14mm screw-thread steel that upright bar is 200mm long is positioned;Use steel bar meter 2 Root retention bar (8), retention bar are the Φ 20mm screw-thread steel of 715mm long;4 positioning vertical poles, positioning vertical pole are 860mm's long Φ 20mm screw-thread steel;2 wood block fillers are processed using timber, wood block filler is having a size of 40mmX80mmX560mm;
C, concrete foundation longitudinal centre line (11) and concrete foundation cross central line are popped up on concrete foundation (1) (12), 4 diameter 14mm then are bored on concrete foundation surface, depth is the positioning upright bar hole (13) of 100mm, and fixed by 4 Position upright bar (7) hammers into 4 positioning upright bar holes, the long 100mm in part that positioning upright bar is exposed on concrete foundation surface;
D, after 4 foundation bolts (2) respectively being screwed on a location nut (15), 4 anchor bolt boxs (14) are respectively put into In;
E, by 2 wood block fillers (10), direction is individually placed to basic longitudinal centre line both sides of the edge along the longitudinal centerline;
F, posting is installed
Posting is placed on 2 wood block fillers (10), 4 foundation bolts (2) are penetrated in the posting hole (6) of posting, And plain washer and adjusting nut (16) are installed, with the position of hand hammer adjustment posting, makes posting cross central line (5) and determine Position frame longitudinal centre line (4) is right with concrete foundation cross central line (12) and concrete foundation longitudinal centre line (11) respectively Together, foundation bolt (2) upper surface absolute altitude is then adjusted with adjusting nut (16), after reaching design requirement absolute altitude, fixed adjustment The position of nut (16) is substantially flush adjusting nut (16) lower surface with concrete foundation (1) upper surface;
G, 2 retention bars (8) are close to concrete foundation (1) upper surface and are welded on concrete foundation longitudinal center between two parties respectively On 2 positioning upright bars (7) of line (11) two sides;
H, after positioning 42 location nuts (15) that vertical pole (9) clamp cross central line two sides two-by-two, 2 positioning are welded on On vertical pole (9);
I, since foundation bolt (2) is mutual by positioning upright bar (7), retention bar (8), positioning vertical pole (9), location nut (15) It welds and positions, posting, adjusting nut (16), plain washer, wood block filler (10) are removed into after-pouring pea gravel concreten grouting material (3), un-rotatably foot bolt (2) when removing adjusting nut (16), it is pre- to reach can-type calcine furnace steel construction pillar foundation bolt Bury accurate positioning.
2. the pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts as described in claim 1, feature It is, in the step c, 2 lower margin spiral shells of positioning upright bar hole (13) setting in concrete foundation longitudinal centre line (11) two sides On bolt preformed hole (14) line of centres, and all in anchor bolt box (14) close to the one of concrete foundation (1) edge Side.
3. the pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts as described in claim 1, feature It is, in the step f, adjusting nut (16) lower surface is concordant with concrete foundation (1) upper surface.
CN201610135150.2A 2016-03-10 2016-03-10 The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts Active CN107178091B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610135150.2A CN107178091B (en) 2016-03-10 2016-03-10 The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610135150.2A CN107178091B (en) 2016-03-10 2016-03-10 The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts

Publications (2)

Publication Number Publication Date
CN107178091A CN107178091A (en) 2017-09-19
CN107178091B true CN107178091B (en) 2019-04-23

Family

ID=59830030

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610135150.2A Active CN107178091B (en) 2016-03-10 2016-03-10 The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts

Country Status (1)

Country Link
CN (1) CN107178091B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528568A (en) * 2019-08-30 2019-12-03 中国三冶集团有限公司 A kind of device and its application method of novel location base bolt

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360550B (en) * 2018-02-28 2019-12-03 五冶集团上海有限公司 A kind of steel construction direct-burried foundation bolt construction method
CN108222056B (en) * 2018-03-06 2020-09-08 防城港中一重工有限公司 Equipment foundation bolt group installation method
CN109487771A (en) * 2018-12-28 2019-03-19 中船勘察设计研究院有限公司 A kind of the static sounding counter force system and test method of mattess
CN111485574B (en) * 2020-04-21 2022-06-24 舜元建设(集团)有限公司 Positioning device and positioning construction method for embedded foundation bolts of steel column foundation
CN112144567A (en) * 2020-09-08 2020-12-29 中国二十冶集团有限公司 Fixing method of directly-buried foundation bolt
CN114934413A (en) * 2022-06-29 2022-08-23 中核华辰建筑工程有限公司 Group ground steel rail construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101137974B1 (en) * 2009-07-20 2012-04-20 한동흔 Method for foundation construction structure of pedestal
CN202913420U (en) * 2012-11-20 2013-05-01 中国十七冶集团有限公司 Reusable positioning device for installing foundation bolts
CN103114731A (en) * 2013-02-05 2013-05-22 山西太行建设开发有限公司 Rapid mounting method of steel structure workshop foundation bolts
CN103590416A (en) * 2013-11-01 2014-02-19 浙江水利水电学院 Pre-buried construction method for high-precision foundation bolts
CN204825945U (en) * 2015-07-30 2015-12-02 华北冶建工程建设有限公司 A fixture for fixing buried bolt in advance

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101137974B1 (en) * 2009-07-20 2012-04-20 한동흔 Method for foundation construction structure of pedestal
CN202913420U (en) * 2012-11-20 2013-05-01 中国十七冶集团有限公司 Reusable positioning device for installing foundation bolts
CN103114731A (en) * 2013-02-05 2013-05-22 山西太行建设开发有限公司 Rapid mounting method of steel structure workshop foundation bolts
CN103590416A (en) * 2013-11-01 2014-02-19 浙江水利水电学院 Pre-buried construction method for high-precision foundation bolts
CN204825945U (en) * 2015-07-30 2015-12-02 华北冶建工程建设有限公司 A fixture for fixing buried bolt in advance

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528568A (en) * 2019-08-30 2019-12-03 中国三冶集团有限公司 A kind of device and its application method of novel location base bolt
CN110528568B (en) * 2019-08-30 2021-11-12 中国三冶集团有限公司 Novel foundation bolt positioning device and using method thereof

Also Published As

Publication number Publication date
CN107178091A (en) 2017-09-19

Similar Documents

Publication Publication Date Title
CN107178091B (en) The pinpoint method of can-type calcine furnace steel construction pillar embedding anchor bolts
CN206091299U (en) A floor buried sleeve fixing device for aluminum alloy template
CN105525625A (en) Construction method and device of pre-embedded bolts of fixed steel column base
CN205735482U (en) A kind of structure of fixing built-in fitting
CN203247603U (en) High-position foundation bolt positioning device
CN108265741A (en) A kind of practical approach of foundation bolt construction positioning
CN105696800A (en) Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts
CN109024608A (en) The construction method that steel pipe column for contrary sequence method quickly positions
CN205894490U (en) Steel core concrete column and pile foundation connection structure
CN201284485Y (en) Fixing device of stone bolt
CN207332350U (en) The installation constitution of shock isolating pedestal in existing building base isolation reinforcement
CN103132494B (en) Embedded anchor cone accurate positioning method
JP3198237U (en) Reinforcing equipment for concrete structures
CN212742614U (en) Foundation inner stand column positioning and mounting structure
CN105569351A (en) Mounting construction technology of steel structure steel column
CN201915420U (en) Foundation of temporary gate building
CN108104136B (en) Foundation pit supporting structure and construction method thereof
CN204040495U (en) A kind of suspension fixing support rack of high-order cast-in fixing bolt
JP5787669B2 (en) Construction method of rising block
JP3678695B2 (en) Fixing method of column to concrete foundation
CN108360549A (en) Anchor pole bar planting foundation construction method of the mountainous region photovoltaic gradient more than 25 degree of angles
CN111576497B (en) Construction method of anti-floating anchor rod applied to underground space
CN216690431U (en) Steel pipe stand elevation adjusting device under finite space
JPH0742164A (en) Pillar erection execution method and pillar bottom support device
CN218508477U (en) Accurate positioner of buried bolt in advance

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant