CN103061216A - monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper - Google Patents

monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper Download PDF

Info

Publication number
CN103061216A
CN103061216A CN2013100266532A CN201310026653A CN103061216A CN 103061216 A CN103061216 A CN 103061216A CN 2013100266532 A CN2013100266532 A CN 2013100266532A CN 201310026653 A CN201310026653 A CN 201310026653A CN 103061216 A CN103061216 A CN 103061216A
Authority
CN
China
Prior art keywords
track
rail
rails
nut
turnout
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100266532A
Other languages
Chinese (zh)
Other versions
CN103061216B (en
Inventor
龚楠富
王国庆
尹忠文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Sixth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Sixth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN201310026653.2A priority Critical patent/CN103061216B/en
Publication of CN103061216A publication Critical patent/CN103061216A/en
Application granted granted Critical
Publication of CN103061216B publication Critical patent/CN103061216B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The invention discloses a monolithic rail bed and turnout lifting support arrangement structure of a subway short sleeper. The monolithic rail bed and turnout lifting support arrangement structure comprises point rails (1), frogs (2), guard rails (3) and rails (4). Specific rail lifting supports (5) are arranged below steel rails in overlapped sections of the point rails (1) and the rails (4), below the frogs (2) and below steel rails in overlapped sections of the guard rails (3) and the rails (4). Heightened rail lifting supports (6) are arranged below steel rails in joint sections of every two rails (4) between the point rails (1) and the frogs (2). Main-line track lifting supports (7) are arranged below steel rails of the rails (4) outside of the point rails (1) and the frogs (2). The monolithic rail bed and turnout lifting support arrangement structure has the advantages that three types of track lifting supports are designed to lift up the integrated rail bed, concrete buttresses in a buttress method are replaced, height can be adjusted optionally, elevation height of turnout rail tops can be well controlled, constructing quality for turnout pouring is improved, construction period of the turnout is shortened by 30-50%, and meanwhile the rail lifting supports are easy to dismantle and can be repeatedly used, so that construction cost is greatly saved.

Description

Metro short sleeper solid concrete roabed track lifting of turnout junction rack arrangement structure
Technical field
The present invention relates to a kind of support configuration structure that solid concrete roabed track switch is held up.
Background technology
The construction of metro short sleeper solid concrete roabed track switch, to adopt the construction of buttress method to live method commonly used, it is first on-site consolidation track switch, connect short sleeper and button accessory, with track jack jack-up track switch connector, by the mode of " watering 1 every 2 " the buttress template is installed and pours into a mould first the buttress concrete, after the buttress concrete strength reaches design strength 75%, remove the buttress template, take to carry out in the mode of a buttress bottom pad elevation accurate adjustment of whole track switch, pour into a mould again the Turnout Monolithic Track Bed concrete after the track switch physical dimension is up to standard.The method needs the secondary concreting, not only duty cycle long, increase construction cost, the buttress Construction Elevation is difficult to control, be prone to buttress and pour into a mould the afterwards high superelevation of turnout rail top mark or not foot phenomenon, also have the quality disease of the short sleeper of buttress place part " sky hangs " simultaneously.It is about 12~14 days that 1 group of P60kg/m singly opens traditional " buttress method " the construction technology construction period of short sleeper solid concrete roabed track switch employing for No. 9, and the construction period of double crossover is then longer.
In traditional " buttress method " construction technology of metro short sleeper solid concrete roabed track switch, the turnout baseplate place generally adopts the sleeper bottom pour mold to build concrete buttress to carry out leveling, on-the-spot construction adjustment difficulty is larger, quality is wayward, often cause the short sleeper planeness at turnout baseplate place inadequate, cause indivedual slide plates place to hang the sky unbalance stress or cause frictional resistance too large because of out-of-flatness.
Summary of the invention
The technical problem to be solved in the present invention: buttress height problem wayward and long in time limit when adopting the construction of buttress method in the metro short sleeper solid concrete roabed track switch construction provides a kind of track lifting support configuration structure with the whole picking-up of track switch.
Technical scheme:
A kind of metro short sleeper solid concrete roabed track lifting of turnout junction rack arrangement structure, comprise tongue, railway frog, guard rail and track, below the rail of the tongue of track switch and Orbital Overlap section, below the railway frog, below the rail of guard rail and Orbital Overlap section special track lifting support is set, the rail of the section of crossing of two strands of tracks below arranges and increases the track lifting support between tongue and the railway frog, and the rail of track below arranges main track track lifting support outside tongue and the railway frog.
The track lining screw mandrel is set between the metope of track and subway tunnel, and the track lining screw mandrel is comprised of transverse screw and sleeve, and transverse screw is installed in the nut of sleeve one end connection.
Track in the tongue outside is set up the slide plate suspender, and two suspension rod screw mandrels are installed in the overarm of slide plate suspender, and suspension rod screw mandrel upper end is equipped with nut, and the lower end connects with side's pad of being connected.
The both sides of the supporting plate in the middle of the special track lifting support are equipped with nut, and vertical screw rod is installed in the nut, and there is a horizontal through hole vertical screw rod upper end.
Increasing the track lifting support has two support rail plates, and two support rail plate installed inside are increased part, increases between the part for two to connect with connector, and the support rail plate outside is equipped with nut, and vertical screw rod is installed in the nut, and there is a horizontal through hole vertical screw rod upper end.
Main track track lifting support has two support rail plates, connects with connector between two support rail plates, and the support rail plate outside is equipped with nut, and vertical screw rod is installed in the nut, and there is a horizontal through hole vertical screw rod upper end.
Beneficial effect:
1. having designed three kinds of track lifting supports holds up whole railway roadbed, replaced the concrete buttress in the buttress method, but height free adjustment, it is high to control the turnout rail top mark, improved the track switch cast construction quality, accelerated the construction period of track switch, can shorten 30~50% construction period, the support that raises track simultaneously is easy to dismounting and can reuses, and has greatly saved construction cost;
2. rail arranged outside track lining screw mandrel on railway roadbed, horizontal level that can accurate adjustment track switch improves workmanship;
3. according to the characteristics of turnout baseplate structure: slide plate one side is withheld by elastic bar fastener and is fixed slide plate and rail, and opposite side does not have then that fastener is fixing easily to cause the slide plate out-of-flatness.For this characteristics, designed a kind of suspender and fastener jointly the power of holding come the leveling slide plate.Suspension rod nut that simultaneously can elevating sling comes the leveling slide plate, and the scene is easy to control and operation, and suspender also can be dismantled use repeatedly.
Description of drawings
Fig. 1 is railway frog section track lifting rack arrangement structural representation in the embodiment of the invention.
Fig. 2 is the section of crossing track lifting rack arrangement structural representation in the embodiment of the invention.
Fig. 3 is tongue section track lifting rack arrangement structural representation in the embodiment of the invention.
Fig. 4 is special track lifting supporting structure schematic diagram of the present invention.
Fig. 5 is the track lifting supporting structure schematic diagram of increasing of the present invention.
Fig. 6 is main track track lifting supporting structure schematic diagram of the present invention.
Fig. 7 is track lining screw structure schematic diagram of the present invention.
Fig. 8 is slide plate hanger structure schematic diagram of the present invention.
The specific embodiment
Embodiment: the construction of the short sleeper solid concrete roabed of simple turnout is as example in certain subway.Structure according to the railway roadbed of track switch, three kinds of track lifting supports have been designed: below the rail of the tongue 1 of track switch and track 4 overlay segments, below the railway frog 2, below the rail of guard rail 3 and track 4 overlay segments special track lifting support 5 is set, the rail of the section of crossing of two strands of tracks below arranges and increases track lifting support 6 between tongue 1 and the railway frog 2, and the rail of track below arranges main track track lifting support 7 outside tongue 1 and the railway frog 2.Need altogether to install main track track lifting support 7 covers, increase track lifting support 6 covers, special track lifting support 12 covers, track lining screw mandrel 26 covers.
The both sides of the supporting plate 21 in the middle of the special track lifting support 5 are equipped with nut, and vertical screw rod 10 is installed in the nut, and there is a horizontal through hole vertical screw rod 10 upper ends.The space that supporting plate 21 passes between rail and the railway roadbed holds up rail.The special track lifting support 5 of 12 covers has been installed altogether.
Increase track lifting support 6 two support rail plates 31 are arranged, lay respectively at the two one steel rails below on the same circuit, two support rail plate 31 installed inside are increased 32, two of parts and are increased usefulness connector 33 connections between the part 32, and the low transverse plane of connector 33 is just high than the top of rail like this; Support rail plate 31 outsides are equipped with nut, and vertical screw rod 10 is installed in the nut, and there is a horizontal through hole vertical screw rod 10 upper ends.Install altogether 6 and overlapped track lifting support 6.
Main track track lifting support 7 has two support rail plates 31, be installed in respectively the two one steel rails below on the same circuit, connect with connector 33 between two support rail plates 31, support rail plate 31 outsides are equipped with nut, vertical screw rod 10 is installed in the nut, and there is a horizontal through hole vertical screw rod 10 upper ends.
These 3 kinds of track lifting supports all can reach the purpose of adjusting orbit altitude by rotary vertically to screw rod 10.
Track lining screw mandrel 8 is set between the metope of track 4 and subway tunnel, and track lining screw mandrel 8 is comprised of transverse screw 11 and sleeve 12, and transverse screw 11 is installed in is connected with sleeve in the nut that an end connects.By rotation transverse screw 11, can adjust the horizontal level of track.
Track 4 in tongue 1 outside is set up slide plate suspender 9, and two suspension rod screw mandrels 42 are installed in the overarm 41 of slide plate suspender 9, and suspension rod screw mandrel 42 upper ends are equipped with nut, and the lower end connects with side's pad 43 of being connected.Pad 43 lower ends, side hold up slide plate 13.

Claims (6)

1. metro short sleeper solid concrete roabed track lifting of turnout junction rack arrangement structure, comprise tongue (1), railway frog (2), guard rail (3) and track (4), it is characterized in that: in the tongue (1) of the track switch rail below with track (4) overlay segment, railway frog (2) below, guard rail (3) arranges special track lifting support (5) with the rail below of track (4) overlay segment, the rail of the section of crossing of two strands of tracks (4) below arranges and increases track lifting support (6) between tongue (1) and the railway frog (2), and the rail of track (4) below arranges main track track lifting support (7) outside tongue (1) and the railway frog (2).
2. metro short sleeper solid concrete roabed track lifting of turnout junction rack arrangement structure according to claim 1, it is characterized in that: track lining screw mandrel (8) is set between the metope of track (4) and subway tunnel, track lining screw mandrel (8) is comprised of transverse screw (11) and sleeve (12), and transverse screw (11) is installed in sleeve is connected 12) in the nut that connects.
3. according to claim 2 or described metro short sleeper solid concrete roabed track lifting of turnout junction rack arrangement structure, it is characterized in that: the track (4) in tongue (1) outside is set up slide plate suspender (9), in the overarm (41) of slide plate suspender (9) two suspension rod screw mandrels (42) are installed, suspension rod screw mandrel (42) upper end is equipped with nut, the lower end connects with side's pad (43) of being connected, and side's pad (43) is positioned at the tongue (below of 1 downside slide plate (13).
4. according to claim 1,2 or 3 described metro short sleeper solid concrete roabed track lifting of turnout junction rack arrangement structures, it is characterized in that: the both sides of the supporting plate (21) in the middle of the special track lifting support (5) are equipped with nut, vertical screw rod (10) is installed in the nut, and there is a horizontal through hole vertical screw rod (10) upper end.
5. according to claim 1,2 or 3 described metro short sleeper solid concrete roabed track lifting of turnout junction rack arrangement structures, it is characterized in that: increasing track lifting support (6) has two support rail plates (31), two support rail plates (31) installed inside is increased part (32), increase between the part (32) for two and connect with connector (33), support rail plate (31) outside is equipped with nut, vertical screw rod (10) is installed in the nut, and there is a horizontal through hole vertical screw rod (10) upper end.
6. according to claim 1,2 or 3 described metro short sleeper solid concrete roabed track lifting of turnout junction rack arrangement structures, it is characterized in that: main track track lifting support (7) has two support rail plates (31), connect with connector (33) between two support rail plates (31), support rail plate (31) outside is equipped with nut, vertical screw rod (10) is installed in the nut, and there is a horizontal through hole vertical screw rod (10) upper end.
CN201310026653.2A 2013-01-24 2013-01-24 Monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper Active CN103061216B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310026653.2A CN103061216B (en) 2013-01-24 2013-01-24 Monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310026653.2A CN103061216B (en) 2013-01-24 2013-01-24 Monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper

Publications (2)

Publication Number Publication Date
CN103061216A true CN103061216A (en) 2013-04-24
CN103061216B CN103061216B (en) 2014-12-17

Family

ID=48104085

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310026653.2A Active CN103061216B (en) 2013-01-24 2013-01-24 Monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper

Country Status (1)

Country Link
CN (1) CN103061216B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105803876A (en) * 2014-12-29 2016-07-27 中铁二局工程有限公司 Switch rail and frog track-lifting auxiliary device and installation and construction method thereof
CN106192607A (en) * 2016-08-26 2016-12-07 中铁四局集团有限公司 Subgrade of metro steel reinforcement cage suspension binding clamping fixture and application thereof
CN113152161A (en) * 2021-04-25 2021-07-23 中国铁建重工集团股份有限公司道岔分公司 Steel switch tie switch device
CN114934412A (en) * 2022-06-08 2022-08-23 上海瑞纽机械股份有限公司 Switch substrate replacing device and using method thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0930398A1 (en) * 1998-01-19 1999-07-21 Franz Plasser Bahnbaumaschinen-Industriegesellschaft m.b.H. Correction method for the position of a railway track
CN2474566Y (en) * 2001-04-28 2002-01-30 上海理工大学附属二厂 Hydraulic rail jack
CN1837471A (en) * 2006-03-30 2006-09-27 中铁八局集团有限公司 Method for debugging bearing of double-block type ballastless track
CN2928927Y (en) * 2006-06-30 2007-08-01 马玉芝 Combined subway rail row clamp
CN201074289Y (en) * 2007-07-20 2008-06-18 中铁二十三局集团有限公司 Adjustable track panel supporting rack
KR20100001564U (en) * 2008-08-04 2010-02-12 한국철도공사 Tie lifter
CN102535277A (en) * 2012-02-28 2012-07-04 孙晓伟 Device for completely moving railway turnout
CN202337926U (en) * 2011-11-24 2012-07-18 金鹰重型工程机械有限公司 Track lifting device
JP2012180691A (en) * 2011-03-02 2012-09-20 Keikyu Kensetsu Co Ltd Method and equipment for relocating turnout and track panel
JP2012237110A (en) * 2011-05-10 2012-12-06 Daitetsu Kogyo Kk Method of replacing railway rail

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0930398A1 (en) * 1998-01-19 1999-07-21 Franz Plasser Bahnbaumaschinen-Industriegesellschaft m.b.H. Correction method for the position of a railway track
CN2474566Y (en) * 2001-04-28 2002-01-30 上海理工大学附属二厂 Hydraulic rail jack
CN1837471A (en) * 2006-03-30 2006-09-27 中铁八局集团有限公司 Method for debugging bearing of double-block type ballastless track
CN2928927Y (en) * 2006-06-30 2007-08-01 马玉芝 Combined subway rail row clamp
CN201074289Y (en) * 2007-07-20 2008-06-18 中铁二十三局集团有限公司 Adjustable track panel supporting rack
KR20100001564U (en) * 2008-08-04 2010-02-12 한국철도공사 Tie lifter
JP2012180691A (en) * 2011-03-02 2012-09-20 Keikyu Kensetsu Co Ltd Method and equipment for relocating turnout and track panel
JP2012237110A (en) * 2011-05-10 2012-12-06 Daitetsu Kogyo Kk Method of replacing railway rail
CN202337926U (en) * 2011-11-24 2012-07-18 金鹰重型工程机械有限公司 Track lifting device
CN102535277A (en) * 2012-02-28 2012-07-04 孙晓伟 Device for completely moving railway turnout

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105803876A (en) * 2014-12-29 2016-07-27 中铁二局工程有限公司 Switch rail and frog track-lifting auxiliary device and installation and construction method thereof
CN106192607A (en) * 2016-08-26 2016-12-07 中铁四局集团有限公司 Subgrade of metro steel reinforcement cage suspension binding clamping fixture and application thereof
CN106192607B (en) * 2016-08-26 2018-02-06 中铁四局集团有限公司 Subgrade of metro steel reinforcement cage suspension type binding clamping fixture and its application
CN113152161A (en) * 2021-04-25 2021-07-23 中国铁建重工集团股份有限公司道岔分公司 Steel switch tie switch device
CN114934412A (en) * 2022-06-08 2022-08-23 上海瑞纽机械股份有限公司 Switch substrate replacing device and using method thereof
CN114934412B (en) * 2022-06-08 2024-04-26 上海瑞纽机械股份有限公司 Switch substrate replacing device and using method thereof

Also Published As

Publication number Publication date
CN103061216B (en) 2014-12-17

Similar Documents

Publication Publication Date Title
RU2641572C2 (en) Method of transforming of roller on basis of ballast to wheel on basis of plates
CN104480810B (en) Low circuit continuous frame formula support rail girder construction and the construction method thereof of putting of middle low speed magnetic suspension
CN103061216B (en) Monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper
CN103306208A (en) Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
CN104404882B (en) A kind of bearing auxiliary installation mold and construction method thereof
CN103243649B (en) The system and method for a kind of cable saddle Fast Installation, location
CN107268348A (en) Subway column check pit construction method
CN204325821U (en) Middle low speed magnetic suspension is low puts circuit continuous frame formula support rail girder construction
KR20100117219A (en) Twin-block type train track for bridge, and replacing method of old train track using such twin-block type train track
CN206306232U (en) A kind of ballastless track slab mold
CN105350407B (en) A kind of three-dimensional adjusting apparatus of magnetic-levitation
CN104141264B (en) Plate-type slag-free orbit lays precision keeping method
CN203546526U (en) Friction-type automatic stepless heightening sleeper employing section bars
CN208586468U (en) The secondary scalable general railway roadbed of pouring type
CN203049390U (en) Turnout track lifting support
CN202359511U (en) Subway tunnel ditch and track bed one-time pouring formwork structure
JP6781682B2 (en) Construction method of track directly connected to sleepers and bearing bearing device used for this
CN207793771U (en) Middle low speed magnetic suspension traffic engineering is low to set circuit support rail beam
CN211900629U (en) Tunnel secondary lining concrete chute system
CN108098979A (en) A kind of PK sections concrete box girder precast segment template
CN203049389U (en) Cross-line track bed lifting support
CN203049392U (en) Track lifting support for track bed construction
CN207259875U (en) A kind of solid concrete roabed of pre-buried rail
CN202658485U (en) Formwork device for double-block ballastless track transverse expansion joint construction
CN203007752U (en) Ballastless road bed template fixed device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170418

Address after: The 401147 northern New District of Chongqing Municipality Temple Temple Street No. 26 Jin Cheng Lu

Patentee after: Sixth Engineering Co., Ltd. of China Railway No. 5 Engineering Group Co., Ltd.

Address before: 550003 Guiyang, Zhejiang Province, Guizhou Road No. 23

Co-patentee before: Sixth Engineering Co., Ltd. of China Railway No. 5 Engineering Group Co., Ltd.

Patentee before: CHINA RAILWAY NO.5 ENGINERING GROUP CO., LTD.

TR01 Transfer of patent right