CN207259875U - A kind of solid concrete roabed of pre-buried rail - Google Patents

A kind of solid concrete roabed of pre-buried rail Download PDF

Info

Publication number
CN207259875U
CN207259875U CN201721149453.6U CN201721149453U CN207259875U CN 207259875 U CN207259875 U CN 207259875U CN 201721149453 U CN201721149453 U CN 201721149453U CN 207259875 U CN207259875 U CN 207259875U
Authority
CN
China
Prior art keywords
concrete
sleeper
rail
buried
roabed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721149453.6U
Other languages
Chinese (zh)
Inventor
邹波
黄伟强
王金海
罗永明
宾奇标
鲁劲松
武岳青
谭文斌
朱鹏
钟立强
田敏
范政
张海
杨剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhong Tie Chengjian Group Co Ltd
Middle Iron Chengjian Group Second Engineering Co Ltd
China Railway Urban Construction Group Co Ltd
Second Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Original Assignee
Zhong Tie Chengjian Group Co Ltd
Middle Iron Chengjian Group Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhong Tie Chengjian Group Co Ltd, Middle Iron Chengjian Group Second Engineering Co Ltd filed Critical Zhong Tie Chengjian Group Co Ltd
Priority to CN201721149453.6U priority Critical patent/CN207259875U/en
Application granted granted Critical
Publication of CN207259875U publication Critical patent/CN207259875U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of solid concrete roabed of pre-buried rail, including concrete cushion, the concrete pad on concrete cushion, it is corresponding with concrete pad and supported by the concrete pad concrete sleeper, on the concrete sleeper and by the fixed rail of concrete sleeper positioning and with track jack will the concrete sleeper and rail rise to designed elevation after the cast-in-situ steel reinforced concrete layer that is poured to the concrete pad and concrete sleeper.The utility model is by the way of sleeper and rail is overlay, instead of the construction method of traditional pre embedded bolt, mainly pre embedded bolt is replaced to construct with sleeper, it is more convenient and efficient than a traditional pre embedded bolt construction method by being achieved that after an accurate adjustment in place, it is more advantageous to improving construction molding rate of solid concrete roabed, after overlaying sleeper and rail, concreting, last time accurate adjustment shaping, than conventional multi accurate adjustment simple and quick construction are carried out after being risen using track jack to designed elevation.

Description

A kind of solid concrete roabed of pre-buried rail
Technical field
It the utility model is related to the technical field of construction equipment, and in particular to a kind of solid concrete roabed of pre-buried rail.
Background technology
Now with the fast-developing and national long-term plan of China's economy, the increase of high speed railway construction mileage is very fast, Serve high ferro train industrial premises and storehouse before Monolithic Track Bed Construction it is more and more, as shown in Figure 1, current Monolithic Track Bed Construction Sequentially it is:Blinding concrete pours, and-solid concrete roabed reinforcing bar binding-pre embedded bolt-installation form-concreting and plucking-mixes Coagulate the die-filling installation of soil maintenance-steel rail laying (and accurate adjustment)-pre-buried rail medial angle steel-and second coagulation soil cast-concrete is supported Shield-locomotive presses road-comes into operation.The working procedure is cumbersome at present, and pre-embedded steel slab is horizontal and linear precision requires high, built-in fitting After adjustment, when track construction, carries out multiple accurate adjustment again, and multiple precision adjusts heavy workload and easily error, and one time concrete pours Solid concrete roabed reinforcing bar easily rocks off normal when building, and construction is slow, and long construction period, is unfavorable for the control of duration and cost.And Constructed by the way of common pre embedded bolt, since construction precision requires height, pre embedded bolt easily produces deviation, precision is surveyed Amount will repeatedly measure easy error, and construction cost is higher.
Utility model content
To overcome the shortcomings of luminous lamp house in the prior art, the utility model aim is to provide a kind of entirety of pre-buried rail Railway roadbed, reduces Monolithic Track Bed Construction cost, improves the installation accuracy of solid concrete roabed rail, saves the construction period.
In order to solve the above-mentioned technical problem, the utility model provides a kind of solid concrete roabed of pre-buried rail, including coagulation It is soil padding, the concrete pad on the concrete cushion, corresponding with the concrete pad and by the concrete The concrete sleeper of cushion block support, on the concrete sleeper and by the fixed rail of concrete sleeper positioning, with And after the concrete sleeper and rail are risen to designed elevation with track jack to the concrete pad and concrete sleeper into The cast-in-situ steel reinforced concrete layer that row pours.
Preferably, the distance between described concrete pad is 1500mm, and the thickness of the concrete cushion is 120mm.
In the preferred embodiment in the utility model, angle is additionally provided between the inner side of the rail and cast-in-situ steel reinforced concrete layer Steel and embedded bar, the angle steel are embedded in the inner side of the rail, and the embedded bar welds together simultaneously with the angle steel Oblique cutting is in the cast-in-situ steel reinforced concrete layer.
In the preferred embodiment in the utility model, it is embedded with the concrete sleeper for the first of lifting the pre-buried nylon Casing, the second pre-buried nylon sleeve for fastener for installing.
In the preferred embodiment in the utility model, the first pre-buried nylon sleeve is on the both sides edge of the concrete sleeper The cross central line extension of concrete sleeper;The second pre-buried nylon sleeve is located at the both ends of the concrete sleeper and along mixed The longitudinal direction extension of solidifying soil sleeper.
In the preferred embodiment in the utility model, connection fastener is equipped between the concrete sleeper and rail.
In the preferred embodiment in the utility model, upper surface and the concrete sleeper of the cast-in-situ steel reinforced concrete layer Upper surface flush.
Compared with prior art, the beneficial effects of the utility model are:
The solid concrete roabed of the pre-buried rail of the utility model is by the way of sleeper and rail is overlay, instead of the pre-buried spiral shell of tradition The construction method of bar, mainly replaces pre embedded bolt to construct with sleeper, by being achieved that in place after an accurate adjustment, than tradition One pre embedded bolt construction method is convenient and efficient, is more advantageous to improving construction molding rate of solid concrete roabed, overlays sleeper and rail Afterwards, concreting is carried out after being risen using track jack to designed elevation, last time accurate adjustment shaping, constructs than conventional multi accurate adjustment It is simple and efficient.By the way of concrete sleeper is overlay, the time of pre embedded bolt is reduced, while improves solid concrete roabed one-pass molding Rate, reduces Monolithic Track Bed Construction cost, improves the installation accuracy of solid concrete roabed rail, saves the construction period, the utility model Solid concrete roabed is simple in structure, design is reasonable, cost is relatively low, quick and easy for installation, and by improved solid concrete roabed, when construction can With an accurate adjustment in place, simultaneously as having concrete sleeper and high-strength concrete cushion block support, and its dead weight is bigger, no Easily shake and displacement, one-pass molding rate is high, and when practice of construction is more easy to operate than existing construction method at present, to the duration Saving, construction quality, which improve, to have very great help, and the solid concrete roabed of the utility model constructs follow-up similar overall road and has guidance to anticipate Justice.
Brief description of the drawings
, below will be to institute in embodiment or description of the prior art in order to illustrate more clearly of the technical solution of the utility model Attached drawing to be used is needed to be briefly described, it should be apparent that, drawings in the following description are only some of the utility model Embodiment, for those of ordinary skill in the art, without creative efforts, can also be attached according to these Figure obtains other attached drawings.
Fig. 1 is the structure diagram of the solid concrete roabed for the pre-buried rail that the utility model embodiment provides.
Embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the premise of creative work Lower all other embodiments obtained, shall fall within the protection scope of the present invention.
Fig. 1 is the structure diagram of the solid concrete roabed of the pre-buried rail of the utility model, the pre-buried rail of the utility model Solid concrete roabed, including concrete cushion 10, the concrete pad 20 on the concrete cushion 10 and the concrete mats Block 20 it is corresponding and supported by the concrete pad 20 concrete sleeper 30, on the concrete sleeper 30 and by institute Concrete sleeper 30 is stated to position the rail 40 of fixation and played the concrete sleeper 30 and rail 40 to design with track jack The cast-in-situ steel reinforced concrete layer 50 poured after absolute altitude to the concrete pad 20 and concrete sleeper 30, the cast-in-place steel The upper surface of reinforced concrete layer 50 and the upper surface flush of the concrete sleeper 30, are embedded to so that concrete sleeper 30 is overall In cast-in-situ steel reinforced concrete layer 50.Wherein concrete cushion 10 is C20 concrete, and cast-in-situ steel reinforced concrete layer 50 is C25 reinforcing bars The distance between concrete, the concrete pad 20 is 1500mm, and the thickness of the concrete cushion 10 is 120mm.This reality Mainly constructed with the solid concrete roabed of new pre-buried rail with concrete sleeper 30 instead of pre embedded bolt, pass through an accurate adjustment After achieve that in place, it is more convenient and efficient than a traditional pre embedded bolt construction method, be more advantageous to improving solid concrete roabed and once construct Ratio of briquetting, there is preferable control in duration, cost.
In order to allow rail 40 to be preferably fixed on railway roadbed, the inner side of the rail 40 and cast-in-situ steel reinforced concrete layer 50 it Between be additionally provided with angle steel 60 and embedded bar 70, the angle steel 60 is embedded in the inner side of the rail 40, the embedded bar 70 with The angle steel 60 welds together and oblique cutting is in the cast-in-situ steel reinforced concrete layer 50.
In addition, be embedded with the concrete sleeper 30 of the utility model for the first of lifting the pre-buried nylon sleeve, The second pre-buried nylon sleeve for fastener for installing, the first pre-buried nylon sleeve is on the both sides edge of the concrete sleeper 30 The cross central line extension of concrete sleeper, ensures in the transport and installation process of concrete sleeper 30, easy to staff Lifting operation;The second pre-buried nylon sleeve is located at the both ends of the concrete sleeper 30 and along the longitudinal direction side of concrete sleeper To extension, connection fastener (figure is set by the foregoing second pre-buried nylon sleeve between the concrete sleeper 30 and rail 40 In do not identify), ensure staff install connection fastener accuracy.The solid concrete roabed of the pre-buried rail of the utility model is main Sequence of construction is:Concrete cushion, which pours ,-solid concrete roabed reinforcing bar is bound-overlays concrete sleeper-steel rail laying-track jack extremely Designed elevation position-high-strength concrete cushion block paves sleeper-model sheetinstallat-concreting and plucking-concrete curing-steel Rail accurate adjustment-pre-buried rail medial angle steel-die-filling installation and second coagulation soil cast-concrete curing-locomotive pressure road-input make With.
The solid concrete roabed of the pre-buried rail of the utility model is by the way of sleeper and rail is overlay, instead of the pre-buried spiral shell of tradition The construction method of bar, mainly replaces pre embedded bolt to construct with sleeper, by being achieved that in place after an accurate adjustment, than tradition One pre embedded bolt construction method is convenient and efficient, is more advantageous to improving construction molding rate of solid concrete roabed, overlays sleeper and rail Afterwards, concreting is carried out after being risen using track jack to designed elevation, last time accurate adjustment shaping, constructs than conventional multi accurate adjustment It is simple and efficient.By the way of concrete sleeper is overlay, the time of pre embedded bolt is reduced, while improves solid concrete roabed one-pass molding Rate, reduces Monolithic Track Bed Construction cost, improves the installation accuracy of solid concrete roabed rail, saves the construction period, the utility model Solid concrete roabed is simple in structure, design is reasonable, cost is relatively low, quick and easy for installation, and by improved solid concrete roabed, when construction can With an accurate adjustment in place, simultaneously as having concrete sleeper and high-strength concrete cushion block support, and its dead weight is bigger, no Easily shake and displacement, one-pass molding rate is high, and when practice of construction is more easy to operate than existing construction method at present, to the duration Saving, construction quality, which improve, to have very great help, and the solid concrete roabed of the utility model constructs follow-up similar overall road and has guidance to anticipate Justice.
Above disclosed is only several preferred embodiments of the utility model, cannot limit this reality with this certainly With new interest field, therefore the equivalent variations made according to the utility model claims, still belong to the utility model and covered Scope.

Claims (7)

  1. A kind of 1. solid concrete roabed of pre-buried rail, it is characterised in that:Including concrete cushion, on the concrete cushion Concrete pad, it is corresponding with the concrete pad and supported by the concrete pad concrete sleeper, positioned at described By the concrete sleeper and steel on concrete sleeper and by the fixed rail of concrete sleeper positioning and with track jack The cast-in-situ steel reinforced concrete layer that rail pours the concrete pad and concrete sleeper after rising to designed elevation.
  2. 2. the solid concrete roabed of pre-buried rail according to claim 1, it is characterised in that:Between the concrete pad away from It is 120mm from the thickness for 1500mm, the concrete cushion.
  3. 3. the solid concrete roabed of pre-buried rail according to claim 1, it is characterised in that:The inner side of the rail and cast-in-place steel Angle steel and embedded bar are additionally provided between reinforced concrete layer, the angle steel is embedded in the inner side of the rail, the embedded bar Weld together with the angle steel and oblique cutting is in the cast-in-situ steel reinforced concrete layer.
  4. 4. the solid concrete roabed of pre-buried rail according to claim 1, it is characterised in that:It is embedded with the concrete sleeper The first pre-buried nylon sleeve for lifting, the second pre-buried nylon sleeve for fastener for installing.
  5. 5. the solid concrete roabed of pre-buried rail according to claim 4, it is characterised in that:The first pre-buried nylon sleeve exists The both sides of the concrete sleeper extend along the cross central line of concrete sleeper;The second pre-buried nylon sleeve is positioned at described The both ends of concrete sleeper simultaneously extend along the longitudinal direction of concrete sleeper.
  6. 6. the solid concrete roabed of pre-buried rail according to claim 4, it is characterised in that:The concrete sleeper and rail it Between be equipped with connection fastener.
  7. 7. the solid concrete roabed of pre-buried rail according to claim 1, it is characterised in that:The cast-in-situ steel reinforced concrete layer Upper surface and the upper surface flush of the concrete sleeper.
CN201721149453.6U 2017-09-08 2017-09-08 A kind of solid concrete roabed of pre-buried rail Active CN207259875U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721149453.6U CN207259875U (en) 2017-09-08 2017-09-08 A kind of solid concrete roabed of pre-buried rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721149453.6U CN207259875U (en) 2017-09-08 2017-09-08 A kind of solid concrete roabed of pre-buried rail

Publications (1)

Publication Number Publication Date
CN207259875U true CN207259875U (en) 2018-04-20

Family

ID=61920818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721149453.6U Active CN207259875U (en) 2017-09-08 2017-09-08 A kind of solid concrete roabed of pre-buried rail

Country Status (1)

Country Link
CN (1) CN207259875U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982044A (en) * 2021-03-24 2021-06-18 广西柳州钢铁集团有限公司 Construction process for quickly forming integral road bed of road junction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982044A (en) * 2021-03-24 2021-06-18 广西柳州钢铁集团有限公司 Construction process for quickly forming integral road bed of road junction

Similar Documents

Publication Publication Date Title
CN107217551A (en) A kind of assembly concrete-filled steel tube double-block type sleeper
CN202954299U (en) Template support structure for large-angle V-shaped pier and No.0 block of continuous rigid framework bridge
CN201268921Y (en) Reinforced bar split heads
CN207259875U (en) A kind of solid concrete roabed of pre-buried rail
CN204780622U (en) Girder 0# piece construction bracket
CN104947566A (en) Assembled grade crossing
CN206625260U (en) A kind of detachable late poured band support post
CN207062652U (en) A kind of city track traffic engineering assembled track laying device
CN103061216B (en) Monolithic rail bed and turnout lifting support arrangement structure of subway short sleeper
CN202359511U (en) Subway tunnel ditch and track bed one-time pouring formwork structure
CN104532691A (en) Ballastless track connected-block sleeper
CN204370248U (en) A kind of non-fragment orbit connects block type sleeper
CN209584870U (en) Pedestal structure for the prefabricated a variety of line style free cantilever erections segment of long line method
CN208917713U (en) Just beam ruggedized construction for switch section
CN209053449U (en) Suspension column connector regularization locating support
CN103835190A (en) Double-block concrete sleeper for installing auxiliary steel rails
CN208056471U (en) A kind of new reinforcing steel bar stirrup
CN209669702U (en) A kind of auxiliary device being accurately positioned bearing pad stone prepared screw-bolt hole
CN206941312U (en) A kind of assembly concrete-filled steel tube double-block type sleeper
CN208009464U (en) A kind of intelligence rail train ground stop basis structure and station
CN203200623U (en) Metro monolithic roadbed expansion joint pouring auxiliary device
CN207846878U (en) Positioning set for the cast-in-place medium-sized girder steel of small bore girder with rolled steel section en cased in concrete
CN203049390U (en) Turnout track lifting support
CN202658485U (en) Formwork device for double-block ballastless track transverse expansion joint construction
CN110185063A (en) A kind of wall vertical reinforcement fixed structure and its fixing means

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant