CN102926553A - 铁丝网水泥砂浆加固空斗墙的方法 - Google Patents

铁丝网水泥砂浆加固空斗墙的方法 Download PDF

Info

Publication number
CN102926553A
CN102926553A CN201210480862XA CN201210480862A CN102926553A CN 102926553 A CN102926553 A CN 102926553A CN 201210480862X A CN201210480862X A CN 201210480862XA CN 201210480862 A CN201210480862 A CN 201210480862A CN 102926553 A CN102926553 A CN 102926553A
Authority
CN
China
Prior art keywords
cement mortar
walls
cavity wall
iron wire
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210480862XA
Other languages
English (en)
Inventor
蒋利学
王卓琳
李向民
许清风
郑乔文
郑士举
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SCI-TECH DEVELOPMENT CORP SHANGHAI CITY INST OF BUILDING SCIENCE
Shanghai Building Science Research Institute Group Co Ltd
Original Assignee
SCI-TECH DEVELOPMENT CORP SHANGHAI CITY INST OF BUILDING SCIENCE
Shanghai Building Science Research Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SCI-TECH DEVELOPMENT CORP SHANGHAI CITY INST OF BUILDING SCIENCE, Shanghai Building Science Research Institute Group Co Ltd filed Critical SCI-TECH DEVELOPMENT CORP SHANGHAI CITY INST OF BUILDING SCIENCE
Priority to CN201210480862XA priority Critical patent/CN102926553A/zh
Publication of CN102926553A publication Critical patent/CN102926553A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明涉及建筑工程领域,公开了一种铁丝网水泥砂浆加固空斗墙的方法,包括铁丝网、植入被加固空斗墙的穿墙销钉、水泥砂浆保护层。技术方案为,根据空斗墙的实际砌筑方法,选择眠砖与丁砖之间的砂浆灰缝布置穿墙销钉,通过销钉将铁丝网固定在墙面上,再在墙体表面进行水泥砂浆保护层施工。本方法可以显著提高空斗墙的受力性能和抗震性能,试验结果表明加固后空斗墙体的水平极限承载力比未加固墙体提高50%以上;同时铁丝网造价低廉、施工工艺简单、不需要搭设模板,特别适用于空斗墙砌体结构,尤其是解决既有村镇空斗墙结构强度不足以及加固技术受经济条件限制的问题。

Description

铁丝网水泥砂浆加固空斗墙的方法
技术领域
本发明涉及建筑工程领域,是一种利用铁丝网水泥砂浆加固空斗墙的结构加固修复方法。
背景技术
空斗墙房屋是我国长江中下游和华东地区村镇建筑的主要结构类型,量大面广。大部分地区空斗墙通常的做法是采用标准粘土砖,并以三斗一眠或五斗一眠砌法较为常见。通过调查发现,空斗墙房屋受力性能与抗震性能较实砌房屋差,且由于大部分空斗墙房屋都由农民自行建造,普遍存在层高较高、开间较大、构造措施不完善等问题,经过一定使用年限后存在不同程度的老化、开裂。为保证结构安全,提升空斗墙结构的抗震能力,需对空斗墙结构进行加固。由于空斗墙的特殊砌筑形式,斗砖位置的受力性能不良,而现有的各类砌体结构加固方法都是针对实砌墙体,其连接锚固措施及位置不适用于空斗墙结构。
发明内容
本发明旨在提供铁丝网水泥砂浆加固空斗墙的方法。
这种铁丝网水泥砂浆加固空斗墙的方法,其技术方案为,根据空斗墙的实际砌筑方式,选择丁砖与眠砖之间的砂浆灰缝布置铁丝制成的穿墙销钉,通过穿墙销钉固定纵横向的铁丝网,保护层采用水泥砂浆抹灰。通过铁丝网水泥砂浆面层与空斗墙的协同工作,提高既有空斗墙砌体的承载能力和抗震能力。
铁丝网水泥砂浆加固空斗墙的方法包括以下步骤:
(1)在墙面上打孔洞,并在孔洞内安装穿墙销钉;
打孔洞的位置为丁砖与眠砖之间的砂浆灰缝;
穿墙销钉交错分布,呈品字形;在水平方向上,相邻的两个穿墙销钉的距离为600~700mm;在垂直方向上,相邻的两个穿墙销钉的距离为800~900mm;
穿墙销钉长度为被加固墙体厚度加100mm~130mm;端头打成L型弯折段,长度40mm~50mm;销钉伸出墙面高度为10mm~15mm;优选的,采用8号铁丝为材料;
(2)在墙面上依次安装竖向加固铁丝和横向加固铁丝,分别形成纵向铁丝网和横向铁丝网,并且,竖向加固铁丝和横向加固铁丝用穿墙销钉在交叉处固定;
先铺设竖向加固铁丝,并且竖向加固铁丝与墙面空隙为5~12mm;然后铺设横向加固铁丝;
相邻的竖向加固铁丝之间距离为300~350mm;相邻的横向加固铁丝之间距离为360~480mm;
穿墙销钉与相邻横向加固铁丝上的其他穿墙销钉的垂直距离为360~480mm,与相邻竖向加固铁丝上的其他穿墙销钉的水平距离为300~350mm;
(3)在墙面上刷水泥浆结合层,再进行水泥砂浆分层抹灰,形成水泥砂浆保护层。
水泥砂浆抹灰时,先在墙面刷水泥浆结合层,再进行水泥砂浆分层抹灰,形成水泥砂浆保护层;水泥砂浆分层抹灰时,每层厚度不超过15mm(一般为5~15mm),水泥浆结合层与水泥砂浆保护层总厚度30mm~40mm。
本发明铁丝网水泥砂浆加固空斗墙的方法,具有以下技术效果:
能够显著提高空斗墙的承载能力,保证结构后续使用要求,提高抗震性能;技术含量低、施工便捷,普通工人经过简单技术培训就可以完成;采用铁丝和水泥砂浆为主要材料,造价低廉,经济代价小。
附图说明
图1为铁丝网水泥砂浆加固空斗墙的立面图。
图2为铁丝网水泥砂浆加固空斗墙在A-A方向的截面图。
图3为铁丝网水泥砂浆加固空斗墙在B-B方向的截面图。
图中1-竖向加固铁丝,2-横向加固铁丝,3、3a、3b、3c、3d-穿墙销钉,4-水泥浆结合层,5-水泥砂浆保护层,6-斗砖,7-丁砖,8-眠砖。
具体实施方式
参见图1、图2、图3,本发明提供一种铁丝网水泥砂浆加固空斗墙的方法,从被加固的空斗墙结构面开始,由内向外依次设有:被加固空斗墙表面所刷水泥浆结合层4、水泥砂浆保护层5、保护层内铺设的竖向加固铁丝1和横向加固铁丝2、连接墙体内外两侧铁丝网与被加固空斗墙的穿墙销钉3。结合附图对本发明的具体实施方式说明如下:
这种空斗墙的结构包括斗砖6、丁砖7和眠砖8,加固方法的步骤包括:
(1)根据空斗墙实际砌筑方式,选择丁砖7与眠砖8之间的砂浆灰缝,在墙面上画出穿墙销钉3的孔洞位置,尽量平均分布并且呈品字形布置;
采用电钻打孔,且孔径比穿墙销钉的直径大2mm~3mm;
每个孔洞配置一根穿墙销钉3;穿墙销钉选用直径为4mm的8号铁丝制成,长度为被加固墙体厚度加100mm~130mm;端头打成L型弯折段,长度40mm~50mm;销钉伸出墙面高度为10mm~15mm;
穿墙销钉与相邻横向加固铁丝上的其他穿墙销钉的垂直距离为360~480mm,与相邻竖向加固铁丝上的其他穿墙销钉的水平距离为300~350mm;具体为,穿墙销钉交错分布,呈品字形,如图1,垂直方向上,相邻的两个穿墙销钉3a、3b的间距为800~900mm;水平方向上,相邻的两个穿墙销钉3c、3d的间距为600~700mm;穿墙销钉3c或3d到3a和3b的水平方向上距离为300~350mm;穿墙销钉3a或3b到3c和3d的垂直方向上距离为360~480mm;穿墙销钉3a、3c和3d呈品字形分布;
(2)先沿穿墙销钉的位置布置竖向加固铁丝1,形成竖向铁丝网,并保证竖向加固铁丝1与墙面空隙不小于5mm(一般为5~12mm);后沿穿墙销钉的位置铺设横向加固铁丝2,形成横向铁丝网;竖向加固铁丝1与横向加固铁丝2用穿墙销钉3固定在一起;竖向加固铁丝1与横向加固铁丝2采用8号铁丝;
相邻的竖向加固铁丝之间距离为300~350mm;相邻的横向加固铁丝之间距离为360~480mm;
(3)在墙面刷一道水泥浆结合层4,再进行水泥砂浆分层抹灰,形成水泥砂浆保护层5;水泥砂浆强度等级采用M10,每层厚度不应超过15mm(一般为5~15mm);水泥浆结合层4和水泥砂浆保护层5的总厚度为30mm~40mm。
根据以上具体实施方式,设计了加固前后空斗墙的试件并进行低周反复荷载试验研究。试验结果表明,采用铁丝网水泥砂浆加固后空斗墙的水平极限承载力比未加固墙体提高50%以上。

Claims (9)

1.一种铁丝网水泥砂浆加固空斗墙的方法,所述的空斗墙结构包括丁砖、眠砖和斗砖,其特征在于,包括以下步骤:
(1)在墙面上打孔洞,并在孔洞内安装穿墙销钉;
(2)在墙面上依次安装竖向加固铁丝和横向加固铁丝,分别形成纵向铁丝网和横向铁丝网,并且,竖向加固铁丝和横向加固铁丝用穿墙销钉在交叉处固定;
(3)在墙面上进行水泥砂浆抹灰。
2.权利要求1所述铁丝网水泥砂浆加固空斗墙的方法,其特征在于,步骤(1)中所述的打孔洞的位置为丁砖与眠砖之间的砂浆灰缝。
3.权利要求1所述铁丝网水泥砂浆加固空斗墙的方法,其特征在于,步骤(2)中,先铺设竖向加固铁丝,并且竖向加固铁丝与墙面空隙为5~12mm;然后铺设横向加固铁丝;相邻的竖向加固铁丝之间距离为300~350mm;相邻的横向加固铁丝之间距离为360~480mm。
4.权利要求1所述铁丝网水泥砂浆加固空斗墙的方法,其特征在于,所述穿墙销钉交错分布;在水平方向上,相邻的两个穿墙销钉的距离为600~700mm;在垂直方向上,相邻的两个穿墙销钉的距离为800~900mm;穿墙销钉与相邻横向加固铁丝上的其他穿墙销钉的垂直距离为360~480mm,与相邻竖向加固铁丝上的其他穿墙销钉的水平距离为300~350mm。
5.权利要求1所述铁丝网水泥砂浆加固空斗墙的方法,其特征在于,步骤(1)中,所述孔洞的孔径比穿墙销钉的直径大2mm~3mm,并采用电钻打孔。
6.权利要求1所述铁丝网水泥砂浆加固空斗墙的方法,其特征在于,所述穿墙销钉、竖向加固铁丝和横向加固铁丝的材料为8号铁丝。
7.权利要求1所述铁丝网水泥砂浆加固空斗墙的方法,其特征在于,步骤(1)所述穿墙销钉长度为被加固墙体厚度加100mm~130mm;端头打成L型弯折段,长度40mm~50mm;销钉伸出墙面高度为10mm~15mm。
8.权利要求1所述铁丝网水泥砂浆加固空斗墙的方法,其特征在于,步骤(3)所述水泥砂浆强度等级为M10。
9.权利要求1所述铁丝网水泥砂浆加固空斗墙的方法,其特征在于,步骤(3)中,水泥砂浆抹灰时,先在墙面刷水泥浆结合层,再进行水泥砂浆分层抹灰,形成水泥砂浆保护层;水泥砂浆分层抹灰时,每层厚度不超过15mm,水泥浆结合层与水泥砂浆保护层总厚度30mm~40mm。
CN201210480862XA 2012-11-22 2012-11-22 铁丝网水泥砂浆加固空斗墙的方法 Pending CN102926553A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210480862XA CN102926553A (zh) 2012-11-22 2012-11-22 铁丝网水泥砂浆加固空斗墙的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210480862XA CN102926553A (zh) 2012-11-22 2012-11-22 铁丝网水泥砂浆加固空斗墙的方法

Publications (1)

Publication Number Publication Date
CN102926553A true CN102926553A (zh) 2013-02-13

Family

ID=47641469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210480862XA Pending CN102926553A (zh) 2012-11-22 2012-11-22 铁丝网水泥砂浆加固空斗墙的方法

Country Status (1)

Country Link
CN (1) CN102926553A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104405139A (zh) * 2014-12-03 2015-03-11 西南科技大学 石砌墙体加固方法
CN105298151A (zh) * 2014-07-24 2016-02-03 上海市建筑科学研究院(集团)有限公司 多层住宅增设电梯与抗震加固一体化建造方法
CN105908988A (zh) * 2016-04-20 2016-08-31 上海市建筑科学研究院 一种用竹筋水泥砂浆面层加固砌体墙的方法
CN107473656A (zh) * 2017-08-08 2017-12-15 合肥工业大学 一种发泡混凝土轻质材料及填充传统空斗墙体施工方法
CN108395185A (zh) * 2018-04-04 2018-08-14 云南驰宏资源综合利用有限公司 一种新型保温抹灰浆料及其使用方法
CN109441137A (zh) * 2018-12-19 2019-03-08 西安建筑科技大学 一种秸秆板材加固生土墙的施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010112908A (ko) * 2001-12-03 2001-12-22 이창남 강화외피첨가 골조보강공법
JP2006274621A (ja) * 2005-03-29 2006-10-12 Shimizu Corp 建築物の耐震補強構造
CN1978843A (zh) * 2005-12-09 2007-06-13 湖南大学 钢筋网砂浆薄层加固补强的施工方法
CN201011136Y (zh) * 2007-03-16 2008-01-23 中国建筑科学研究院 钢铰线、聚合物砂浆复合加固结构

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010112908A (ko) * 2001-12-03 2001-12-22 이창남 강화외피첨가 골조보강공법
JP2006274621A (ja) * 2005-03-29 2006-10-12 Shimizu Corp 建築物の耐震補強構造
CN1978843A (zh) * 2005-12-09 2007-06-13 湖南大学 钢筋网砂浆薄层加固补强的施工方法
CN201011136Y (zh) * 2007-03-16 2008-01-23 中国建筑科学研究院 钢铰线、聚合物砂浆复合加固结构

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘一斌: "高性能复合砂浆钢筋网加固空斗墙结构性能研究", 《万方学位论文》, 28 September 2011 (2011-09-28) *
廖娟等: "空斗墙采用钢板网片加固试验及应用", 《建筑技术》, vol. 32, no. 6, 16 June 2001 (2001-06-16), pages 373 - 374 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105298151A (zh) * 2014-07-24 2016-02-03 上海市建筑科学研究院(集团)有限公司 多层住宅增设电梯与抗震加固一体化建造方法
CN104405139A (zh) * 2014-12-03 2015-03-11 西南科技大学 石砌墙体加固方法
CN104405139B (zh) * 2014-12-03 2017-01-11 西南科技大学 石砌墙体加固方法
CN105908988A (zh) * 2016-04-20 2016-08-31 上海市建筑科学研究院 一种用竹筋水泥砂浆面层加固砌体墙的方法
CN107473656A (zh) * 2017-08-08 2017-12-15 合肥工业大学 一种发泡混凝土轻质材料及填充传统空斗墙体施工方法
CN107473656B (zh) * 2017-08-08 2019-09-13 合肥工业大学 一种发泡混凝土轻质材料及填充传统空斗墙体施工方法
CN108395185A (zh) * 2018-04-04 2018-08-14 云南驰宏资源综合利用有限公司 一种新型保温抹灰浆料及其使用方法
CN108395185B (zh) * 2018-04-04 2021-03-16 云南驰宏资源综合利用有限公司 一种保温抹灰浆料及其使用方法
CN109441137A (zh) * 2018-12-19 2019-03-08 西安建筑科技大学 一种秸秆板材加固生土墙的施工方法

Similar Documents

Publication Publication Date Title
CN103469939B (zh) 一种砌体填充墙与主体柔性连接抗震结构及其施工方法
CN102926553A (zh) 铁丝网水泥砂浆加固空斗墙的方法
CN102003080B (zh) 既有砌体建筑外套预制结构抗震加固结构及其加固方法
CN206189647U (zh) 一种新型填充墙砌体拉结筋构造
CN206503150U (zh) 一种玄武岩复合筋材锚杆格构梁支挡结构
CN103953114B (zh) 钢框架-配筋砌体剪力墙组合结构及其施工方法
CN207959612U (zh) 一种框架、剪力墙现浇结构用装配式轻质填充墙
CN103835413A (zh) 外包钢丝网砂浆板一字形边框发泡混凝土承重墙体及作法
CN204059760U (zh) 一种方钢柱柱芯自密实混凝土浇筑施工结构
CN103046764B (zh) 钢筋网细石混凝土加固预应力混凝土空心板的方法
CN104947846A (zh) 一种装配整体式框架填充轻质内墙板及其制备方法
CN104631674A (zh) 一种叠合楼板及其施工方法
CN103790168A (zh) 一种土钉墙在深基坑支护中的应用方法
CN203961014U (zh) 一种预制混凝土建筑结构
CN103046765B (zh) 防空洞加固后继续使用的施工工艺
CN205531668U (zh) 灌注桩基础装配式围墙
CN205171369U (zh) 一种pc梁斜拉桥索梁锚固构造
CN204475536U (zh) 带有刚性节点连接的钢筋混凝土预制构件
CN104675138B (zh) 一种用于隔声降噪改造的板式阳台加固方法
CN108035453B (zh) 一种有圈梁砌体结构的滑移隔震装置及其施工方法
CN115828381A (zh) 一种便于纠倾的配电房基础设计方法
CN105220809A (zh) 一种拱形顶板与牛腿桩的连接结构及其施工方法
CN104947948A (zh) 一种夯土墙体的加固方法
CN102926552A (zh) 钢绞线聚合物砂浆加固空斗墙的方法
CN108005405B (zh) 一种无圈梁砌体结构的滑移隔震装置及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 200032 Shanghai city Xuhui District Wanping Road No. 75

Applicant after: Shanghai Research Institute of Building Sciences (Group) Co., Ltd.

Applicant after: Science and Technology Development Company of SRIBS

Address before: 200032 Shanghai city Xuhui District Wanping Road No. 75

Applicant before: Shanghai Research Institute of Building Sciences (Group) Co., Ltd.

Applicant before: Sci-Tech Development Corp., Shanghai City Inst. of Building Science

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130213