CN102758520B - First level of scaffold during freezing and thawing period of soil body and building method - Google Patents

First level of scaffold during freezing and thawing period of soil body and building method Download PDF

Info

Publication number
CN102758520B
CN102758520B CN201210243644.4A CN201210243644A CN102758520B CN 102758520 B CN102758520 B CN 102758520B CN 201210243644 A CN201210243644 A CN 201210243644A CN 102758520 B CN102758520 B CN 102758520B
Authority
CN
China
Prior art keywords
bar
floor
vertical rod
soil body
springboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210243644.4A
Other languages
Chinese (zh)
Other versions
CN102758520A (en
Inventor
吕立军
刘双权
马云
鄢峰
黄占成
薛有
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Tianjin Corp Ltd
Original Assignee
Tianjin MCC20 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin MCC20 Construction Co Ltd filed Critical Tianjin MCC20 Construction Co Ltd
Priority to CN201210243644.4A priority Critical patent/CN102758520B/en
Publication of CN102758520A publication Critical patent/CN102758520A/en
Application granted granted Critical
Publication of CN102758520B publication Critical patent/CN102758520B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a first level of a support scaffold during the freezing and thawing period of a soil body and a building method. The first level of the scaffold comprises a horizontal rod and more than two vertical rods which are fixedly crossed with the horizontal rod; a wood springboard is arranged between the two vertical rods; a bottom horizontal rod is fixed at the lower end of one side of each vertical rod; and a wood wedge is arranged between the bottom horizontal rod and the wood springboard. The building method comprises the following steps of: building the horizontal rod and the vertical rods on the backfilled soil body according to the convention; constructing a platform reinforcing steel bar project and a template project; paving the wood springboard in a gap between the two vertical rods, wherein the wood springboard and the vertical rods are tightly arranged; arranging the bottom horizontal rod on one side of each of the vertical rod; fixing the bottom horizontal rod and the vertical rods in a connection way of double fasteners; plugging the wood wedge into the middle of the outer side of the fixed bottom horizontal rod and the wood springboard; and arranging the top head on the outer side of the wood wedge, wherein the top head nails a steel nail on the wood springboard and is used for preventing the wood wedge from moving.

Description

A kind of first floor scaffold building method between soil body thawing period
Technical field
The present invention relates to a kind of construction techniques, especially relate to the erection method of first floor support scaffolding between a kind of soil body thawing period.
Background technology
In construction work, support scaffolding construction is a large amount of to be existed, and scaffold building method is substantially identical.But for setting up of first floor scaffold, in prior art, common way is at vertical rod lower berth wood springboard, then sets up vertical rod and cross bar, finally sets up sweep the floor bar and bridging.But because first floor scaffold bottom is the soil body, between soil body thawing period, for traditional erection method, still often can occur scaffold upright rod sinking situation, more serious meeting causes scaffold cave-in accident.
Summary of the invention
The technical problem to be solved in the present invention overcomes above-mentioned deficiency of the prior art, there is provided a kind of scaffold subsidence problems solving scaffold and cause due to soil body freeze thawing, first floor support scaffolding structure and erection method between a kind of soil body thawing period preventing the generation of scaffold cave-in accident.
The technical scheme of scaffold of the present invention is: comprise horizon bar and the vertical rod of more than 2 piece that be fixedly installed crossing with horizon bar, wooden springboard is provided with between described vertical rod, the bottom of described vertical rod side is fixed with bar of sweeping the floor, described in sweep the floor between bar and wooden springboard and be provided with timber wedge.
First floor scaffold building method between a kind of soil body thawing period of the present invention, comprises the steps:
The first step. backfill the soil body routinely in set up horizon bar, vertical rod;
Second step carries out the construction of platform reinforced bar engineering and form work engineering;
3rd step lays wooden springboard between vertical rod space, and described wooden springboard and vertical rod are closely arrange;
Then 4th step arranges in the side of vertical rod and to sweep the floor bar, described in bar of sweeping the floor adopt the connected mode of pair fastener to be fixed with vertical rod;
Timber wedge is filled between the outside of the 5th step bar of sweeping the floor after fixation and wooden springboard;
6th step is in timber wedge arranged outside top, and described top, for follow closely on wooden springboard by steel nail, is moved in order to prevent timber wedge.
The height that bar of sweeping the floor in described step 4 is arranged is in wooden springboard epithelium position.
The invention has the beneficial effects as follows:
1. when setting up scaffold horizon bar, vertical rod, without the need to padding springboard below vertical rod, bar of sweeping the floor wouldn't be established, upper brace reinforced bar engineering and form work engineering normal construction, because its load when platform reinforced bar engineering, template construction is less, scaffold settling amount is minimum, can ignore, before the concrete of top to be built, between scaffold, lay wooden springboard, then establish bar of sweeping the floor, bar of sweeping the floor is close to wooden springboard as far as possible, finally will shift to an earlier date ready-made timber wedge fill in wooden springboard and sweep the floor between bar, and come directly towards with steel nail respectively outside timber wedge, move in order to prevent timber wedge.Therefore, the method takes the springboard of scaffold and bar of sweeping the floor is arranged before building, therefore construction period soil body freeze thawing is on the impact of final scaffold carrying nothing.
2. this method enforcement from before the vertical rod bearing load of prior art become vertical rod and sweep the floor the common bearing load of bar.
3. method is simple, can apply in building field large-scale popularization.
Accompanying drawing explanation
Fig. 1 is work progress flow chart.
Fig. 2 builds front scaffold molding effect figure.
Fig. 3 is Fig. 2 scaffold position of joints structure for amplifying schematic diagram.
Reference numeral: the wooden springboard 4 of 1 horizon bar 2 vertical rod 3 is swept the floor bar 5 timber wedge
Detailed description of the invention
In order to understand the present invention further, describe structure and the embodiment of technical solution of the present invention in detail below in conjunction with accompanying drawing:
Shown in composition graphs 1, Fig. 2, Fig. 3, between soil body thawing period of the present invention, first floor scaffold comprises horizon bar 1 and the vertical rod 2 of more than 2 piece that be fixedly installed crossing with horizon bar 1, wooden springboard 3 is provided with between described vertical rod 2, the bottom of described vertical rod 2 side is fixed with bar 4 of sweeping the floor, described in sweep the floor between bar 4 and wooden springboard 3 and be provided with timber wedge 4.
Between a kind of soil body thawing period of the present invention, first floor scaffold building method step is: first. backfill the soil body routinely in set up horizon bar, vertical rod, i.e. scaffold, the scaffold upper load formed because of horizon bar, vertical rod is less, therefore little on the impact between soil body thawing period.After having set up horizon bar, vertical rod, normally can carry out the construction of platform reinforced bar engineering and form work engineering; Then wooden springboard is laid in the space between vertical rod and vertical rod, requires that wooden springboard is as far as possible close with vertical rod, is namely closely arranged during laying; Then in the side of vertical rod root, horizontally set is swept the floor bar, described in sweep the floor the height that bar arranges should in wooden springboard epithelium position, the fixed form of its sweep the floor bar and vertical rod, then adopt the connected mode of pair fastener to be fixed; After fixing, between the outside of bar of sweeping the floor and wooden springboard, arrange top, timber wedge is filled in described top namely, then follows closely with steel nail on wooden springboard by timber wedge, moves in order to prevent timber wedge.
The present invention is arranged when facing and building due to sweep the floor bar and wooden springboard, and in whole work progress, soil body freeze thawing is minimum on scaffold impact, therefore effectively prevent scaffold.

Claims (2)

1. a first floor scaffold building method between soil body thawing period, is characterized in that, comprise the steps:
The first step. on the soil body of backfill, set up horizon bar, vertical rod according to a conventional method;
Second step carries out the construction of platform reinforced bar engineering and form work engineering;
3rd step lays wooden springboard between vertical rod space, and described wooden springboard and vertical rod are closely arrange;
4th step arranges in the side of vertical rod and to sweep the floor bar, described in bar of sweeping the floor adopt the connected mode of pair fastener to be fixed with vertical rod;
Timber wedge is filled between the outside of the 5th step bar of sweeping the floor after fixation and wooden springboard;
6th step is in timber wedge arranged outside top, and described top, for follow closely on wooden springboard by steel nail, is moved in order to prevent timber wedge.
2. first floor scaffold building method between a kind of soil body thawing period according to claim 1, is characterized in that, bar of sweeping the floor in described step 4 is arranged on wooden springboard epithelium position.
CN201210243644.4A 2012-07-13 2012-07-13 First level of scaffold during freezing and thawing period of soil body and building method Active CN102758520B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210243644.4A CN102758520B (en) 2012-07-13 2012-07-13 First level of scaffold during freezing and thawing period of soil body and building method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210243644.4A CN102758520B (en) 2012-07-13 2012-07-13 First level of scaffold during freezing and thawing period of soil body and building method

Publications (2)

Publication Number Publication Date
CN102758520A CN102758520A (en) 2012-10-31
CN102758520B true CN102758520B (en) 2015-03-11

Family

ID=47053150

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210243644.4A Active CN102758520B (en) 2012-07-13 2012-07-13 First level of scaffold during freezing and thawing period of soil body and building method

Country Status (1)

Country Link
CN (1) CN102758520B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105715043B (en) * 2016-01-29 2018-06-29 中国建筑第八工程局有限公司 A kind of formwork reinforcement system and construction method on high-supported formwork low-angle clear water inclined-plane
CN106013750A (en) * 2016-07-07 2016-10-12 山东枣建建设集团有限公司 Disc buckle direct insertion type support frame capable of being rapidly assembled and disassembled and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3818083A (en) * 1968-11-04 1974-06-18 Hambro Structural Systems Ltd Building method
US5022490A (en) * 1990-02-06 1991-06-11 Bil-Jax, Inc. Safety base for scaffolding
RU2143533C1 (en) * 1994-11-11 1999-12-27 Краузе-Верк Гмбх Унд Ко. Кг Work platform for construction scaffolding
CN201802060U (en) * 2010-09-14 2011-04-20 营口城华架体制造有限公司 Novel scaffold
CN202081639U (en) * 2011-05-25 2011-12-21 中油吉林化建工程有限公司 Steel truss tool type supporting structure for concrete framework industrial building templates

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3818083A (en) * 1968-11-04 1974-06-18 Hambro Structural Systems Ltd Building method
US5022490A (en) * 1990-02-06 1991-06-11 Bil-Jax, Inc. Safety base for scaffolding
RU2143533C1 (en) * 1994-11-11 1999-12-27 Краузе-Верк Гмбх Унд Ко. Кг Work platform for construction scaffolding
CN201802060U (en) * 2010-09-14 2011-04-20 营口城华架体制造有限公司 Novel scaffold
CN202081639U (en) * 2011-05-25 2011-12-21 中油吉林化建工程有限公司 Steel truss tool type supporting structure for concrete framework industrial building templates

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
扣件式钢管脚手架基础、连墙件搭设常见问题及预防对策;翟羽飞;《建筑安全》;20060815(第08期);59-60 *
脚手架及其防护;喻琪;《建筑安全》;19970828(第08期);38-41 *
高层建筑双排双立杆脚手架设计;安渊;《内蒙古科技与经济》;20071031(第20期);74-77 *

Also Published As

Publication number Publication date
CN102758520A (en) 2012-10-31

Similar Documents

Publication Publication Date Title
CN111411993A (en) Large-section tunnel supporting system penetrating through huge karst cave hall and construction method
CN103469939B (en) A kind of masonry filler wall and main body flexibly connect earthquake resistant structure and construction method thereof
CN104963689A (en) Three-step seven-procedure excavation method for tunnel
JP7427102B2 (en) Methods for improving the anti-slip and anti-fall safety of existing counterweight retaining walls
CN109356173A (en) A kind of pin-connected panel anchor bolt frame girder construction and its construction method
CN203654294U (en) Foundation pit supporting structure used in reverse building method
CN104294769B (en) A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement
CN207229131U (en) A kind of precipitous broken formation tunnel portal section supporting construction
CN107905251A (en) A kind of module prestressing force Retaining Wall and its assembly method
CN105178244A (en) Quick formwork erecting construction method for cast-in-place wave wall
CN107419731A (en) A kind of board-like double-row pile foundation pit support structure of counterfort and its construction method
CN104947681A (en) Super large super deep basement ground pit construction method
CN102758520B (en) First level of scaffold during freezing and thawing period of soil body and building method
CN103306295A (en) Rigid frame pile supporting and blocking structure
CN108149696A (en) The composite supporting construction and construction method that a kind of gib soil nail wall is combined with permanent anti-float anchor rod
CN102864796B (en) Construction spreading foundation adaptive to filled ground settlement and construction method
CN104632228B (en) Main track entering construction method for cross aisle and cross aisle
CN204690763U (en) Long side slope protection concrete continuous fast pouring drawing-die system
CN205839721U (en) A kind of novel offshore platform
CN203702164U (en) Subsurface excavation tunnel top bracing device adopting lifting jacks for movable support
CN201801843U (en) Overwater gravity type earth-retaining structure with anchoring structure
CN103669976A (en) Ancient pagoda correction
CN204001705U (en) Outer wall of basement single surface formwork constructing structure based on earth anchor truss
CN204023587U (en) A kind of novel environment friendly slope reinforcement structure
CN102493436A (en) Novel manual tunneling construction method of rectangular anti-slide pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 300301 Dongli District, flawless Street Jintang Highway Bridge No. ten

Patentee after: MCC TIANGONG GROUP TIANJIN CO., LTD.

Address before: 300301 Dongli District, Tianjin, Tianjin twenty Metallurgical Construction Co., Ltd.

Patentee before: Tianjin MCC20 Construction Co., Ltd.