CN102751779A - 用于自动在替换能源和公共电网之间切换的转换开关 - Google Patents

用于自动在替换能源和公共电网之间切换的转换开关 Download PDF

Info

Publication number
CN102751779A
CN102751779A CN2012101190894A CN201210119089A CN102751779A CN 102751779 A CN102751779 A CN 102751779A CN 2012101190894 A CN2012101190894 A CN 2012101190894A CN 201210119089 A CN201210119089 A CN 201210119089A CN 102751779 A CN102751779 A CN 102751779A
Authority
CN
China
Prior art keywords
source
energy
energy storage
level
storage device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101190894A
Other languages
English (en)
Other versions
CN102751779B (zh
Inventor
N.A.克扎内基
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Reliance Controls Corp
Original Assignee
Reliance Controls Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Reliance Controls Corp filed Critical Reliance Controls Corp
Publication of CN102751779A publication Critical patent/CN102751779A/zh
Application granted granted Critical
Publication of CN102751779B publication Critical patent/CN102751779B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/02Circuit arrangements for ac mains or ac distribution networks using a single network for simultaneous distribution of power at different frequencies; using a single network for simultaneous distribution of ac power and of dc power
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • H02J9/062Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems for AC powered loads
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/70Hybrid systems, e.g. uninterruptible or back-up power supplies integrating renewable energies
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

被配置用于连接到诸如风轮机或者太阳电池板的非传统的全时间使用的或者间断使用的电源的自动转换开关选择性地连接作为主电源的该非传统的电源和作为次电源的公共得到的(utility-derived)电源。间断使用的电源包括诸如DC电池组的能量存储设备,以在低能量产生时段期间补充电力输送。该电力经由DC-AC变压器提供给AC负载。转换开关包括监视能量存储设备上的电压电平的输入端,并且当能量存储设备上的电压电平落到预设电平以下时将从主电源切换到公共电源。因此,超过变压器的额定值的负载状态将不会使变压器故障或者限制负载可用的电力。

Description

用于自动在替换能源和公共电网之间切换的转换开关
本申请要求2011年4月20日提交的美国临时申请第61/477,399号的优先权,其全部内容通过引用合并于此。
技术领域
在此公开的主题涉及用于自动在主电源和次电源之间切换的转换开关。更具体地,公开了用于自动在替换能源(alternative energy source)和公共电网(utility grid)之间切换的转换开关。
背景技术
历史上,已知提供转换开关以在公共电网不正常工作的情况下将负载从公共电网自动转换到备用发电机(generator)。例如,监视公共电网上存在的电压,如果该电压落到预设值以下,则转换开关切换到备用电源,比如发电机。此外,自动转换开关可以在将负载连接到发动机之前向发电机提供信号以启动引擎,并等待直到发电机正常工作。
随着替换电源及其相关联的电力转换设施的发展,可能希望提供除了公共电网之外的电源作为主电源。可以选择诸如光生伏打阵列(photovoltaicarray)或者风轮机的替换能源。但是,来自这样的替换源的电源是依赖于在给定时间存在的日光量或者风力而可变的。结果,替换的能源通常与能量存储设备组合使用。因为能量存储设备存储并提供DC电压,所以提供将DC电压转换为适于与负载连接的AC电压的变压器。
但是,传统的自动转换开关并不太适合于其中主要能源是替换能源并且次级能源是公共电网的应用。如上所述,典型的自动转换开关监视主要能源的电压电平,并且当该电压电平落到最小值以下时切换到次级源。但是,提供AC电压的变压器将尝试调整输出电压以维持标定AC电压,例如120VAC。如果替换能源不产生足够的电力来供应负载并且电池已经用尽,则变压器将经历故障状态并停机。需要人工介入来复位变压器,使自动转换开关的目的落空。此外,由于可变的能量产生,预期将需要比公共电网作为主要能源时更频繁地从替换能源切换到公共电网。
因此,希望提供适合于在替换能源作为主要能源并且公共电网作为次级源时使用的自动转换开关。
发明内容
在此公开的主题涉及配置用于连接到诸如风轮机、水轮机和太阳能电池板的非传统的、全部时间使用或间断使用的电源的自动转换开关。这些非传统电源的电力输出可以用于对DC电池组充电、直接对负载供电或者这些的组合。经由DC到AC变压器向AC负载提供电力。该转换开关被配置使得变压器得到的电力是主电源,并且公共电网得到的电力是备用电源。该转换开关在这两个电源在正常操作下都可用的假设下而工作。
当非传统电源不能维持满足负载需要的足够输出电力时,该转换开关将从变压器切换到公共电网。因为当电源不能产生提供给负载的所有电力时,DC电池补充电力,所以DC电池中剩余的能量提供非传统电源是否可以为负载提供足够的输出电力的指示。随着DC电池中的能量水平的降低,在电池的端子上呈现的DC电压通常也降低。通过检测电池组DC电压何时降到预设电平以下,该转换开关可以在变压器达到故障状态并停机之前切换电源。当负载电流超过变压器的额定值时但是在变压器达到故障状态并停机之前,该转换开关也将从变压器切换到公共电网。因此,超过变压器的额定值的临时负载情况将不会引起变压器的故障或者限制负载可用的电力。
根据本发明的一个实施例,一种用于选择性地将负载连接到作为主电源的替换能源和能量存储设备以及作为次电源的公共电网的开关包括:第一输入端,被配置为接收与能量存储设备中的能量水平对应的信号。至少一个致动器选择性地将主电源或次电源连接到该负载,以及电路产生作为能量存储设备中的能量水平的函数的、用于致动器选择性地将主电源或者次电源连接到该负载的控制信号。
根据本发明的另一方面,第二输入端被配置为接收与次电源的操作状态对应的信号,并且该电路还将致动器的控制信号产生为次电源的操作状态的函数。如果能量存储设备中的能量水平在预定阈值以下并且如果次电源的操作状态在预定范围内,则该电路产生的控制信号可以启动从主电源到次电源的转换。
根据本发明的另一方面,第三输入端被配置为接收与负载汲取的电流的量值对应的信号,并且所述电路还将该致动器的控制信号产生为负载汲取的电流的函数。如果次电源的操作状态在预定范围内并且如果能量存储设备中的能量水平在预定阈值以下或者负载汲取的电流的量值在预定阈值以上,则所述电路产生的控制信号可以启动从主电源到次电源的转换。
根据本发明的另一实施例,用于选择性地将第一电源和第二电源连接到负载的自动转换开关包括:第一输入端,电连接到第一电源;第二输入端,电连接到第二电源;以及输出端,电连接到负载。该第一电源包括替换能源和能量存储系统。至少一个致动器选择性地将第一输入端和第二输入端之一连接到该输出端。第一传感器测量与该第一电源的能量存储系统中的能量水平对应的第一操作参数;以及第二传感器测量该第二电源的第二操作参数。电路向致动器提供作为该第一和第二操作参数的函数的控制信号以将第一输入端或第二输入端连接到该输出端。
根据本发明的另一实施例,一种选择性地将负载连接到包括能量存储设备的第一电源或者连接到第二电源的方法,该方包括步骤:测量该能量存储设备中的能量的水平;如果该能量存储设备中的能量的水平大于预定阈值,则将该负载连接到第一电源;以及如果该能量存储设备中的能量的水平小于该预定阈值,则将该负载连接到第二电源。
附图说明
在附图中例示了在此公开的主题的各个示例实施例,附图中,通篇相同的参考标记表示相同的部分,并且其中:
图1是本发明的一个实施例的框图表示;
图2是例示根据本发明的一个实施例的转换开关的自动切换的流程图;
图3是并入了本发明的一个实施例的示例配电面板;
图4是移除封盖的图3的示例配电面板;以及
图5是控制根据本发明的一个实施例的转换开关的电路的框图表示。
在描述附图中例示的本发明的优选实施例时,为了清楚,将采取具体术语。但是,不意图将本发明限制于因此选择的具体术语,并且可以理解,每个具体术语包括以类似方式工作以实现类似目的的所有技术等效物。例如,经常使用词语“连接”、“附接”或与其类似的术语。它们不限于直接连接,而是包括通过其他元件连接,这样的连接被本领域技术人员视为是等效的。
具体实施方式
参考在以下描述中详细描述的非限制性实施例更全面地说明在此公开的主题的各个特征以及有益细节。
参考图1,电力产生系统10可以包括多个电源。电源可以是根据具体环境或应用需要的电源的任意适当组合。诸如光生伏打阵列的直流(DC)电源12产生具有DC电压的电力。该DC电压可以直接提供给DC总线20,也称为DC分发系统/网络或者DC链接,或者该DC电压可以经由DC到DC电力转换器22提供给DC总线20。诸如风轮机、水轮机等的交流(AC)电源14产生具有AC电压的电力。该AC电压经由AC到DC转换器24提供给DC总线20。因为这些替代的能源的每一个产生可变的电量,因此诸如电池的能量存储设备16也经由电力转换器26连接到DC总线20。电力转换器26管理在DC总线20和能量存储设备16之间的双向电力流,使得当电源产生超过负载38所需的能量的能量时,对能量存储设备16充电,并且当电源产生比负载38所需的能量更少的能量时,能量存储设备16放电,向负载38提供电力或者补充提供给负载38的电力。另外,与公共电网35的连接也是可用的。
提供转换开关40以选择性地将电负载38连接到电源。转换开关40包括第一输入端42和第二输入端44,每个输入端被配置为建立与电源之一的电连接。转换开关40还包括输出端46,被配置为建立与负载38的电连接。图1是线路图并且通过单线例示了输入端42和44以及输出端46中的每一个。不过,考虑每个端子可以包括单个连接或者多个连接(例如两个端子)以根据应用要求选择性地在单个电源线之间或者在多个电源线之间转换连接。根据另一实施例,来自每个源的一条电源线可以选择性地连接到负载,而来自每个源的另一电源线可以接合到公共连接。
根据本发明的一个实施例,第一输入端42连接到替换的能源,比如风轮机、水轮机或者光生伏打阵列,第二输入端44连接到公共电网35。再次参考图1,一个或多个AC能源14、一个或多个DC能源12、能量存储设备16或它们的任意组合可以连接到DC总线20。DC总线20经由变压器30连接到转换开关40,该变压器30将在DC总线20上存在的DC电压转换为适合于提供给负载38的AC电压。变压器30的输出端连接到转换开关40的第一输入端42。
开关51选择性地将第一输入端42或者第二输入端44连接到输出端46。尽管开关51被例示为单极双掷开关,但是可以使用任何适当的配置来连接各端,例如(非限制性地)双极单掷开关或两个单极单掷开关。第一输入端42电连接到开关51上的第一输入端52。第二输入端44电连接到开关51上的第二输入端54。来自开关51的输出端56电连接到输出端46。开关51的触点53可以机械或电控制以选择性地将开关51的输入端52或54之一连接到输出端56。可以通过可由操作者访问以在两个输入端52和54之间切换开关51的触点53的操作杆来提供机械操作。可由诸如螺线管的致动器或者被选择性地通电以在两个输入端52和54之间移动开关51的触点53的一对致动器来提供电操作。
转换开关40还包括控制电路50,其产生至少一个控制信号55以选择性地在开关51的第一输入端52或第二输入端54之间定位触点53。控制电路50从监视连接到转换开关40的电源的操作性能的多个传感器接收输入信号。根据本发明的一个实施例,如图1和图5所示,第一电压传感器62监视来自变压器30的AC输入电压的幅度。第二电压传感器64监视来自公共电网35的AC输入电压的幅度。电流传感器66监视由负载38汲取的电流的幅度。第三电压传感器68监视在能量存储设备16处存在的DC电压的幅度。根据本发明的替换实施例,考虑电压和/或电流传感器可以位于电力系统10的替换位置中或者替换组合中以监视电源的操作性能。
也参考图2,在步骤110,控制电路50从每个传感器读取指示每个电源的操作状态的值。在步骤120,控制电路50检查能量存储设备16处的电压电平处于可接受的电平。在能量存储设备16被放电时,DC电压的幅度开始下降。能量存储设备的放电表明替换的能源未产生满足负载38的电力需求的足够能量。如果能量存储设备中剩余的电荷落到最小电平以下,其不再能够完全补充替换能源以满足负载38的需求。在此操作点,变压器30将尝试维持AC输出电压的命令的量值;但是,随着在变压器30的输入处的电力不足,变压器可能进入故障状态,要求人工复位。为了防止变压器30进入故障状态,控制电路50可以预配置阈值,不希望允许能量存储设备16处的DC电压下降到该阈值以下。
如果能量存储设备16的DC电压电平大于阈值,则控制电路50前进到步骤130,并检查被负载38汲取的电流的幅度。控制电路50可以预配置最大电流值,不希望在该最大电流值以上操作变压器30,因为变压器通常具有短期电流额定值以及长期电流额定值。通过监视负载38汲取的电流的幅度,如果例如汲取的电流超过变压器30的长期电流额定值但是在电流超过变压器30的短期电流额定值、导致变压器30进入故障状态之前,转换开关40可以将负载38从替换能源断开并将负载38重新连接到公共电网35。如果能量存储设备16处的DC电压电平以及负载38汲取的电流两者都在操作限度内,则控制电路50产生控制信号55以将替换能源连接到负载38,如步骤150处所示。
如果能量存储设备16的电压电平小于阈值电平,则控制电路50前进到步骤140并检查公共电网35提供的AC电压的量值。类似地,如果能量存储设备16的DC电压电平在阈值电平以上而负载38汲取的电流超过其设置点,则控制电路50再次前进到步骤140并检查公共电网35提供的AC电压的量值。控制电路50可以预配置有针对来自公共电网35的AC电压的最小和/或最大值。如果来自公共电网35的AC电压操作在可接受的电平,则控制电路50产生控制信号55以将公共电网35连接到负载38,如步骤160所示。在将负载38连接到公共电网35之前检验公共电网35工作在可接受的参数内降低了对构成负载38的电系统或设备的损坏的可能性。
如果电源都未工作在期望的参数内,则控制电路50产生控制信号55以将替换能源连接到负载38,如步骤150所示。例如,如果能量存储设备16的DC电压电平小于变压器的操作需要的最小电压,或者负载汲取的电流超过变压器的操作希望汲取的最大电流,公共电网35也不在可接受的操作参数内,则继续从替换能源提供电力可以延长可以将电力提供给负载38的持续时间。变压器30将尝试维持命令的输出电压,并提供所需的电流,只要来自主电源的能量允许并且只要电流不超过变压器30的短期超载。因此,如果公共电网38不可用,则保持主电源连接到负载38可以允许在电压临时骤降(dip)或者电流尖峰期间提供电力。但是,如果公共电网35仍不可用并且主电源在其期望的操作参数以外太长时间,则变压器30将必然故障以防止损坏变压器30。
以周期或持续为基础进行图2例示的步骤。还参考图5,可以以数字或者模拟方式实现控制电路的组件。监视主电源或次电源的性能的每个传感器向控制电路50提供模拟信号。例如使用运算放大器实现的比较器将该信号与参考值相比较以确定每个电源是否工作在可接受的范围内。运算放大器的输出可以驱动离散逻辑门以及螺线管驱动器电路150或160。螺线管驱动器电路150或160致动螺线管170或180以选择性地定位开关51并将主电源或者次电源连接到负载38。因此,模拟电路可以持续监视每个电源的操作状态并据此选择适当的电源。可选地,控制电路50的一部分可以数字地在例如场可编程门阵列(FPGA)、专用集成电路(ASIC)中或者微处理器内实现。因此,数字电路可以根据设备内的指令执行而周期地监视操作参数。
无论如何实现,都希望在主电源和次电源之间的转换足够迅速地发生以避免负载38处的电力的可观察到的中断。因为转换开关40被配置为连接到作为主电源的可变的或者间断的能源并且连接到作为次要能源的公共电网,所以考虑转换开关40将需要比传统转换开关更频繁地在主电源和次电源之间切换。此外,除了在第一电源故障的情况下单独作为备用系统,这样的转换可以发生在正常操作状态下。希望在需要时,转换开关40断开主电源并迅速地重新连接次电源以最小化或者消除明显的切换指示,例如灯的闪烁或者电视画面的临时中断。结果,使用模拟电路设备实现控制电路50可以提供改进的响应性以及快速的切换能力。
应该理解,本发明在其应用方面不限于在此所述的结构的细节和组件的布置。本发明能够有其他实施例并且能够按各种方式实践或执行。对以上内容的变化和修改在本发明的范围内。还应理解,在此公开和定义的本发明扩展到所述的以及根据本文和/或附图显而易见的各个特征中的两个或多个的所有替换组合。所有这些不同的组合构成本发明的各个替换方面。在此所述的实施例说明了已知用于实践本发明的最佳模式,并将使本领域技术人员能够利用本发明。

Claims (18)

1.一种开关,用于选择性地将作为主电源的替换能源和能量存储设备以及作为次电源的公共电网连接到负载,该开关包括:
第一输入端,被配置为接收与能量存储设备中的能量水平对应的信号;
至少一个致动器,选择性地将主电源和次电源之一连接到该负载;以及
电路,产生作为能量存储设备中的能量水平的函数的、用于致动器选择性地将主电源或者次电源连接到该负载的控制信号。
2.如权利要求1的开关,其中如果能量存储设备中的能量水平在预定阈值以下,则该电路产生的控制信号启动从主电源到次电源的转换。
3.如权利要求1的开关,还包括第二输入端,被配置为接收与次电源的操作状态对应的信号,其中所述电路还将用于致动器的控制信号产生为次电源的操作状态的函数。
4.如权利要求3的开关,其中如果能量存储设备中的能量水平在预定阈值以下并且如果次电源的操作状态在预定范围内,则该电路产生的控制信号启动从主电源到次电源的转换。
5.如权利要求3的开关,还包括第三输入端,被配置为接收与所述负载汲取的电流的量值对应的信号,其中所述电路还将用于致动器的控制信号产生为所述负载汲取的电流的函数。
6.如权利要求5的开关,其中如果次电源的操作状态在预定范围内并且如果能量存储设备中的能量水平在预定阈值以下或者所述负载汲取的电流的量值在预定阈值以上,则所述电路产生的控制信号启动从主电源到次电源的转换。
7.如权利要求1的开关,其中所述电路包括模拟电设备。
8.一种自动转换开关,用于选择性地将第一电源和第二电源连接到负载,该自动转换开关包括:
第一输入端,电连接到第一电源,其中该第一电源包括替换能源和能量存储系统;
第二输入端,电连接到第二电源;
输出端,电连接到所述负载;
至少一个致动器,选择性地将第一输入端和第二输入端之一连接到所述输出端;
第一传感器,测量与第一电源的能量存储系统中的能量水平对应的第一操作参数;
第二传感器,测量第二电源的第二操作参数;以及
电路,向致动器提供作为第一和第二操作参数的函数的控制信号以将第一输入端或第二输入端连接到输出端。
9.如权利要求8的自动转换开关,其中第一传感器测量能量存储系统的DC电压电平,并且如果该DC电压电平在预定阈值以下,则所述电路启动从第一电源到第二电源的转换。
10.如权利要求9的自动转换开关,其中第二电源是公共电网,第二传感器测量公共电网的AC电压电平,并且如果该AC电压电平在希望的操作范围之外则所述电路中止从第一电源向第二电源的转换,并且如果该AC电压电平在希望的操作范围内,则所述电路完成从第一电源到第二电源的转换。
11.如权利要求8的自动转换开关,还包括第三传感器,其测量负载的第三操作参数。
12.如权利要求11的自动转换开关,其中所述第三操作参数是由负载汲取的电流值,并且如果该电流值在预定阈值以上,则所述电路启动从第一电源到第二电源的转换。
13.如权利要求12的自动转换开关,其中所述第二电源是公共电网,所述第二传感器测量公共电网的AC电压电平,并且如果该AC电压电平在希望的操作范围之外,则所述电路中止从第一电源向第二电源的转换,并且如果该AC电压电平在希望的操作范围内,则所述电路完成从第一电源到第二电源的转换。
14.如权利要求8的自动转换开关,其中所述电路包括模拟电设备。
15.一种选择性地将负载连接到包括能量存储设备的第一电源或者连接到第二电源的方法,该方法包括步骤:
测量该能量存储设备中的能量的水平;
如果该能量存储设备中的能量的水平大于预定阈值,则将该负载连接到第一电源;以及
如果该能量存储设备中的能量的水平小于该预定阈值,则将该负载连接到第二电源。
16.如权利要求15的方法,其中该第二电源是公共电网,并且还包括测量公共电网上存在的电压的幅度的步骤,以及其中仅在公共电网上存在的电压在可接受范围内时才进行将负载连接到第二电源的步骤。
17.如权利要求15的方法,还包括测量由负载汲取的电流的量值的步骤,其中:
如果能量存储设备中的能量的水平大于最小能量水平并且由负载汲取的电流的幅度小于最大电流水平,则进行将负载连接到第一电源的步骤;以及
如果能量存储设备中的能量的水平小于最小能量水平或者由负载汲取的电流的幅度大于最大电流水平,则进行将负载连接到第二电源的步骤。
18.如权利要求17的方法,其中该第二电源是公共电网,还包括测量在公共电网上存在的电压的幅度的步骤,以及其中仅在公共电网上存在的电压在可接受的范围内时才进行将负载连接到第二电源的步骤。
CN201210119089.4A 2011-04-20 2012-04-20 用于自动在替换能源和公共电网之间切换的转换开关 Expired - Fee Related CN102751779B (zh)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
US201161477399P 2011-04-20 2011-04-20
US61/477,399 2011-04-20
US13/350,964 2012-01-16
US13/350,964 US9583942B2 (en) 2011-04-20 2012-01-16 Transfer switch for automatically switching between alternative energy source and utility grid

Publications (2)

Publication Number Publication Date
CN102751779A true CN102751779A (zh) 2012-10-24
CN102751779B CN102751779B (zh) 2016-02-03

Family

ID=47020727

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210119089.4A Expired - Fee Related CN102751779B (zh) 2011-04-20 2012-04-20 用于自动在替换能源和公共电网之间切换的转换开关

Country Status (3)

Country Link
US (1) US9583942B2 (zh)
CN (1) CN102751779B (zh)
CA (1) CA2771760C (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104682543A (zh) * 2015-03-17 2015-06-03 四川省辛普森动力设备有限公司 一种基于直流变频发电机组的混合供电系统
CN105229476A (zh) * 2014-03-31 2016-01-06 Lg电子株式会社 电力确定装置和包括该电力确定装置的电子设备
CN107425518A (zh) * 2016-05-24 2017-12-01 太阳能安吉科技有限公司 混合电力系统中的负载管理
CN109494866A (zh) * 2018-10-16 2019-03-19 江苏万邦微电子有限公司 一种电源管理系统
CN111837306A (zh) * 2018-05-18 2020-10-27 Ls电气株式会社 自功率继电器及其误动作防止方法
CN113795995A (zh) * 2019-05-06 2021-12-14 维谛公司 用于共享混合式转换开关的系统和方法
CN117995600A (zh) * 2024-04-03 2024-05-07 浙江南洋输配电设备有限公司 一种双进线真空断路器隔离设备切换方法及真空隔离设备
US12061235B2 (en) 2019-05-06 2024-08-13 Vertiv Corporation System and method for shared hybrid transfer switch system with integrated relay self test

Families Citing this family (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9353524B2 (en) * 2011-07-12 2016-05-31 University Of Utah Research Foundation Emergency utility connection for mission critical facilities
JP5805776B2 (ja) * 2011-09-28 2015-11-10 京セラ株式会社 パワーコンディショナシステム及び蓄電パワーコンディショナ
JP5940309B2 (ja) * 2012-01-20 2016-06-29 京セラ株式会社 給電システム及び電源装置
US20130270912A1 (en) * 2012-04-16 2013-10-17 Hamilton Sundstrand Corporation System and method for providing time-controlled backup power to a load
US9825487B2 (en) * 2012-10-31 2017-11-21 Panasonic Intellectual Property Management Co., Ltd. Apparatus and electric power control method
US9711967B1 (en) * 2012-11-06 2017-07-18 Reliance Conrtols Corporation Off grid backup inverter automatic transfer switch
DE102012023426A1 (de) * 2012-11-29 2014-03-13 Kostal Industrie Elektrik Gmbh Elektrische Anordnung und elektrische Anlage mit einer elektrischen Anordnung
DE102012023424B4 (de) * 2012-11-29 2019-08-14 Kostal Industrie Elektrik Gmbh Energieverteilungsanlage mit einer Steuervorrichtung
US20140203649A1 (en) * 2013-01-18 2014-07-24 3L Power Llc Method and Apparatus for Integrating a Secondary Power Source into a Power Generation Plant
CN106208350B (zh) 2013-03-06 2020-12-01 华为技术有限公司 一种供电方法及装置
ES2497315B1 (es) * 2013-03-20 2015-07-09 Mateu Nierga, S.L. Instalación eléctrica asistida con distribuidor automático de entrada selectiva
US10256634B2 (en) 2013-05-17 2019-04-09 Ingeteam Power Technology, S.A. Power supply system and method for electronic converters
EP3011659A4 (en) 2013-06-18 2017-03-08 Hewlett-Packard Enterprise Development LP Automatic transfer switch module
US9673661B2 (en) 2013-10-24 2017-06-06 Kohler, Co. Transfer switch with monitor on load side
US9876354B2 (en) * 2014-05-21 2018-01-23 Eaton Corporation UPS systems and methods using coordinated static switch and inverter operation for generator walk-in
RU2017128311A (ru) * 2015-01-12 2019-02-14 Общество С Ограниченной Ответственностью "Сименс" Управляющее устройство для подачи напряжения смещения рч-переключателю
WO2016125128A1 (en) * 2015-02-06 2016-08-11 Lapiki (Pty) Ltd Electrical switching arrangement
CN106160176A (zh) * 2015-04-28 2016-11-23 台达电子企业管理(上海)有限公司 配电系统和电气系统
US10283966B2 (en) * 2015-07-31 2019-05-07 Bluvert Technologies Ltd. System and methods for power generation
EP4187746A1 (en) 2016-02-15 2023-05-31 PITT-Ohio Express LLC Combination wind/solar dc power system
EP3232529A1 (en) * 2016-04-14 2017-10-18 DET International Holding Limited Power supply arrangement
WO2017184822A1 (en) * 2016-04-20 2017-10-26 Concept By Us Corporation A photovoltaic sourced power station with integrated battery charge/discharge cycle
US10291028B2 (en) * 2016-07-29 2019-05-14 Cummins Power Generation Ip, Inc. Masterless distributed power transfer control
DE102016120115A1 (de) * 2016-10-21 2018-04-26 Konecranes Global Corporation Laufkran
NL2018592B1 (en) * 2017-03-28 2018-10-05 De Raay En Datema B V Three phase to single phase switching device.
KR102299604B1 (ko) * 2017-08-10 2021-09-07 엘에스일렉트릭(주) 에너지 저장 시스템
DE102017215981A1 (de) * 2017-09-11 2019-03-14 Audi Ag Verfahren zum Betreiben einer Vorrangschaltung zum Koppeln zumindest eines Verbraucherausgangs mit zumindest zwei Quelleneingängen sowie Vorrangschaltung
CN110071521B (zh) * 2018-01-23 2021-09-03 台达电子企业管理(上海)有限公司 配电设备及配电方法
CA3026685A1 (en) * 2018-12-06 2020-06-06 WATT Renewable Corporation An apparatus for managing energy input and energy ranking system
CN109474062A (zh) * 2018-12-26 2019-03-15 大连普阳铁路车辆配件有限公司 变压器低压侧开关自动合闸控制装置
US11431191B2 (en) 2019-07-24 2022-08-30 Constellation Energy Generation, Llc Methods and systems for providing power
WO2022036016A1 (en) * 2020-08-11 2022-02-17 Amber Solutions, Inc. Intelligent energy source monitoring and selection control system
WO2022203646A1 (en) * 2021-03-21 2022-09-29 Dice James Lamar Paradice process system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050006958A1 (en) * 2003-07-11 2005-01-13 Dubovsky Stephen M. Grid-connected power systems having back-up power sources and methods of providing back-up power in grid-connected power systems
CN1701481A (zh) * 2002-09-26 2005-11-23 Utc燃料电池有限责任公司 用于提供保证的功率给临界负载的系统
CN101212145A (zh) * 2006-12-31 2008-07-02 方大集团股份有限公司 光电幕墙光伏系统的电能补充方法和系统

Family Cites Families (42)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4398097A (en) * 1979-12-10 1983-08-09 Indian Head, Inc. Automatic transfer switch
US5210685A (en) * 1985-03-08 1993-05-11 Westinghouse Electric Corp. Uninterruptible power supply system and load transfer static switch for such a system
US4747061A (en) * 1986-03-17 1988-05-24 Westinghouse Electric Corp. Automatic transfer switch for a wide range of source voltage
US4672227A (en) * 1986-03-17 1987-06-09 Westinghouse Electric Corp. Automatic transfer switch with delay
US4894796A (en) * 1986-03-17 1990-01-16 Westinghouse Electric Corp. Automatic transfer switch with programmable display
US4760278A (en) * 1987-07-23 1988-07-26 Thomson Robert G Transfer switch
US4791255A (en) * 1987-12-11 1988-12-13 Westinghouse Electric Corp. Twin break transfer switch
US5081367A (en) * 1990-07-06 1992-01-14 Westinghouse Electric Corp. Electric power system with maintenance bypass for uninterruptible power supply using closed transition operation
US5182464A (en) * 1991-01-09 1993-01-26 Techmatics, Inc. High speed transfer switch
US5397868A (en) * 1993-09-28 1995-03-14 Eaton Corporation Transfer switch
US5638295A (en) * 1995-08-08 1997-06-10 Eaton Corporation Transfer switch system with subnetwork
US6137191A (en) * 1998-12-22 2000-10-24 S&C Electric Co. Source-transfer switching system and method
US6593670B2 (en) * 2000-12-22 2003-07-15 William J. Anderson Automatic transfer switch and engine control
US6590481B2 (en) * 2000-12-28 2003-07-08 Eaton Corporation Fast acting, electrically powered operator for transfer switch and transfer switch incorporating same
US6577216B2 (en) * 2001-02-06 2003-06-10 Eaton Corporation Fast acting transfer switch with confronting power switches oppositely actuated by single coil solenoid
US6801109B2 (en) * 2001-11-15 2004-10-05 Eaton Corporation Transfer switch including a circuit breaker housing
US6861930B2 (en) * 2001-11-15 2005-03-01 Eaton Corporation Transfer switch including a circuit breaker housing
US6965818B2 (en) * 2001-11-28 2005-11-15 Onan Corporation Mobile energy management system
US6849967B2 (en) * 2002-04-19 2005-02-01 Eaton Corporation Automatic transfer switch for microturbine and method of operation
US7362696B2 (en) * 2002-10-21 2008-04-22 General Electric Company Method and apparatus for automatic transfer switch
US7119457B1 (en) * 2003-02-11 2006-10-10 Reliance Controls Corporation Prioritized actuation system with overload protection for a generator transfer switch
US7353084B2 (en) * 2003-02-27 2008-04-01 Acutra, Inc. Generator controller
US20060028069A1 (en) * 2004-08-09 2006-02-09 Loucks David G Retrofit kit for converting a transfer switch to a switch for soft-load transfer, and soft-load power distribution system and method
US20060129798A1 (en) * 2004-11-30 2006-06-15 Allied Generators, Inc. Stand-by power generator monitoring system
US7336003B2 (en) * 2005-04-05 2008-02-26 Eaton Corporation Transfer switch and power system including the same
US6995327B1 (en) * 2005-04-11 2006-02-07 Eaton Corporation Four-way interlock system and bypass transfer switch employing the same
US7535129B2 (en) * 2006-05-17 2009-05-19 Twinsource, Llc Method and apparatus for transfer of a critical load from one source to a back up source using magnetically latched relays
US20080179958A1 (en) * 2007-01-26 2008-07-31 Eaton Corporation Automatic Transfer Switch With Monitor Mode and Method Employing the Same
US7898112B2 (en) * 2007-12-06 2011-03-01 Tigo Energy, Inc. Apparatuses and methods to connect power sources to an electric power system
KR101520988B1 (ko) * 2007-12-11 2015-05-28 안토니오 트리기아니 배터리 관리 시스템
US8000911B2 (en) 2008-05-06 2011-08-16 Schneider Electric USA, Inc. Automated hierarchical classification for utility systems with multiple sources
US7948117B2 (en) * 2008-07-21 2011-05-24 Eaton Corporation Transfer switch controller employing active inductive load control and transfer switch including the same
US20100019574A1 (en) 2008-07-24 2010-01-28 John Baldassarre Energy management system for auxiliary power source
CA2674372C (en) 2008-07-30 2016-02-09 Gen-Tran Corporation Automatic transfer switch
US20100141047A1 (en) 2008-12-10 2010-06-10 Gibbs Irving A Closed transition automatic transfer switch assembly and associated method
US20110057514A1 (en) 2009-09-08 2011-03-10 Eaton Corporation Power meter with transfer switch
KR101156533B1 (ko) * 2009-12-23 2012-07-03 삼성에스디아이 주식회사 에너지 저장 시스템 및 이의 제어 방법
JP5787127B2 (ja) * 2010-09-03 2015-09-30 富士電機株式会社 電力変換装置の保護回路
US9276408B2 (en) * 2010-10-29 2016-03-01 Eaton Corporation Automatic transfer switch responsive to serial communication message and power system including the same
US8754547B2 (en) * 2010-11-17 2014-06-17 Battelle Memorial Institute Controller for hybrid energy storage
US8823210B1 (en) * 2011-06-01 2014-09-02 Banpil Photonics, Inc. Integrated electronics for perpetual energy harvesting
US9136732B2 (en) * 2011-10-15 2015-09-15 James F Wolter Distributed energy storage and power quality control in photovoltaic arrays

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1701481A (zh) * 2002-09-26 2005-11-23 Utc燃料电池有限责任公司 用于提供保证的功率给临界负载的系统
US20050006958A1 (en) * 2003-07-11 2005-01-13 Dubovsky Stephen M. Grid-connected power systems having back-up power sources and methods of providing back-up power in grid-connected power systems
CN101212145A (zh) * 2006-12-31 2008-07-02 方大集团股份有限公司 光电幕墙光伏系统的电能补充方法和系统

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105229476A (zh) * 2014-03-31 2016-01-06 Lg电子株式会社 电力确定装置和包括该电力确定装置的电子设备
US10027164B2 (en) 2014-03-31 2018-07-17 Lg Electronics Inc. Power determining apparatus and electronic appliance including the same
CN105229476B (zh) * 2014-03-31 2018-11-06 Lg电子株式会社 电力确定装置和包括该电力确定装置的电子设备
CN104682543A (zh) * 2015-03-17 2015-06-03 四川省辛普森动力设备有限公司 一种基于直流变频发电机组的混合供电系统
CN107425518A (zh) * 2016-05-24 2017-12-01 太阳能安吉科技有限公司 混合电力系统中的负载管理
US12088106B2 (en) 2016-05-24 2024-09-10 Solaredge Technologies Ltd. Load management in hybrid electrical systems
US11728655B2 (en) 2016-05-24 2023-08-15 Solaredge Technologies Ltd. Load management in hybrid electrical systems
CN111837306B (zh) * 2018-05-18 2022-08-23 Ls电气株式会社 自功率继电器及其误动作防止方法
CN111837306A (zh) * 2018-05-18 2020-10-27 Ls电气株式会社 自功率继电器及其误动作防止方法
US11870235B2 (en) 2018-05-18 2024-01-09 Ls Electric Co., Ltd. Self-power relay and method for preventing malfunction thereof
CN109494866A (zh) * 2018-10-16 2019-03-19 江苏万邦微电子有限公司 一种电源管理系统
CN113795995A (zh) * 2019-05-06 2021-12-14 维谛公司 用于共享混合式转换开关的系统和方法
CN113795995B (zh) * 2019-05-06 2024-05-28 维谛公司 用于共享混合式转换开关的系统和方法
US12061235B2 (en) 2019-05-06 2024-08-13 Vertiv Corporation System and method for shared hybrid transfer switch system with integrated relay self test
CN117995600A (zh) * 2024-04-03 2024-05-07 浙江南洋输配电设备有限公司 一种双进线真空断路器隔离设备切换方法及真空隔离设备
CN117995600B (zh) * 2024-04-03 2024-06-11 浙江南洋输配电设备有限公司 一种双进线真空断路器隔离设备切换方法及真空隔离设备

Also Published As

Publication number Publication date
CA2771760C (en) 2017-11-07
US20120267957A1 (en) 2012-10-25
CN102751779B (zh) 2016-02-03
CA2771760A1 (en) 2012-10-20
US9583942B2 (en) 2017-02-28

Similar Documents

Publication Publication Date Title
CN102751779A (zh) 用于自动在替换能源和公共电网之间切换的转换开关
KR101412742B1 (ko) 독립형 마이크로그리드 제어 시스템 및 그 제어방법
WO2011052407A1 (ja) 切替回路、制御装置および発電システム
CN107005057B (zh) 用于在与公用电网断开期间协调风电场的控制的方法和控制器
KR102019087B1 (ko) 태양광 발전 에너지 저장시스템의 제어방법
CN110049897A (zh) 用于为电动车辆充电的充电站
JP2008099527A (ja) 電力系統に接続された自家発電設備における蓄電池設備および蓄電池設備の運転方法
KR101904815B1 (ko) Ess용 pcs 및 pcs 운전 방법
WO2019145999A1 (ja) 直流給電システム
KR101868350B1 (ko) 태양광발전장치 및 이의 운전방법
CN107370168B (zh) 电能存储设备
JP2016506710A (ja) バッテリをインバータに組み込むための安全概念
CN207542868U (zh) 一种配电冗余系统
KR20170052028A (ko) 배터리 관리를 위한 제어전원 공급시스템과 그 공급방법 및 이를 이용한 에너지저장시스템
JP7028252B2 (ja) 蓄電モジュールおよび電源システム
WO2016117315A1 (ja) 電力供給装置
US11277007B2 (en) Power conversion device, power system and method of suppressing reactive power in power system
WO2019074018A1 (ja) 直流給電システム
KR102623576B1 (ko) 무정전전원공급시스템 및 이를 이용하는 전력공급방법
CN203423488U (zh) 一种多向变流器
CN221669541U (zh) 一种脱扣可靠的断路器智能控制器
CN212162824U (zh) 一种微小型风光水多能互补分布式发电系统的快速停机装置
AT510356A1 (de) Notstromversorgungssystem zur ferngesteuerten wiederherstellung der eigenbedarfsspannung in umspannwerken nach einem stromausfall
KR20240029527A (ko) SoC에 따라 복수 동작 모드를 지원하는 배터리 시스템
KR20240000305A (ko) 전력변환장치

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160203

Termination date: 20170420

CF01 Termination of patent right due to non-payment of annual fee