CN102733613A - Vertical transportation method - Google Patents
Vertical transportation method Download PDFInfo
- Publication number
- CN102733613A CN102733613A CN2012101831291A CN201210183129A CN102733613A CN 102733613 A CN102733613 A CN 102733613A CN 2012101831291 A CN2012101831291 A CN 2012101831291A CN 201210183129 A CN201210183129 A CN 201210183129A CN 102733613 A CN102733613 A CN 102733613A
- Authority
- CN
- China
- Prior art keywords
- workshop section
- working section
- vertical
- hanging basket
- floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The invention discloses a vertical transportation method. According to the method, a bottom working section, an upper working section and lifting basket part sets are involved; the bottom working section is a vertical working section; according to the bottom working section, the lifting basket part set is used for transporting; the bottom of the bottom working section is positioned at the bottom of a building to be constructed; the top of the bottom working section is positioned in one floor of the building to be constructed; the upper working section is a vertical working section; according to the upper working section, the lifting basket part set is used for transporting; the bottom of the upper working section is positioned on one floor below the top of the bottom working section and is tightly pressed against one side of the bottom working section; the top of the upper working section is positioned on the top of the built floor; each lifting basket part set comprises a power winding device, a lifting cable and a lifting basket; objected to be transported can be transported to the required floor by the bottom working section and the upper working section; the vertical transportation method is not in conflict with other special transportation methods; a vertical transportation channel can be gradually lengthened along with the increasing of the building, the objects can be lifted and transported continuously, and the lifting line and the lifting time can be shortened; and the method is high in safety, and the conditions of rotation and swinging of a lifted unit plate can be avoided by a guide cable device.
Description
Technical field
The present invention relates to a kind of vertical transporting method, particularly a kind of vertical transporting method that is applicable to the operation of superelevation layer belongs to technical field of building construction.
Background technology
Along with the development of society, the demand of super highrise building is increasing.At present the construction material of super highrise building is to be transported on the discharging platform through the tower crane that civil engineering is built engineering, is dragged to then in the floor, accomplishes the vertical transport of constructional materials.But because the requirement of construction period of super highrise building, for example high-rise curtain wall is often in the main building half of constructing, the realization cross-operation of will constructing; Because the action of cross-operation is more, must cause being busy with one's work of tower crane, make vertical transport need queuing for a long time; The dismounting of discharging platform, installation, remove, install again mobile discharge platform by turns again.Cause workload very big; The position of on-the-spot construction elevator is the construction that must influence cell curtain wall, when main building is constructed the top, could remove construction elevator, carries out the closing at this position then and handles; And since superelevation layer curtain wall unit plate once lift can only be less than 4, be hung in to receive the influenced by wind pressure scope that floats also very big in the air, so the lifting time is longer; The handling of unit plate is hung under the effect that receives blast in the air through single rope handling unit plate, rotation and swing can occur.
Summary of the invention
The present invention provides a kind of vertical transporting method in order to overcome above-mentioned deficiency.
In order to achieve the above object, the technical scheme that the present invention adopts is: a kind of vertical transporting method comprises bottom workshop section, top workshop section and hanging basket parts group; Said bottom workshop section is a vertical sections, and uses the transportation of hanging basket parts group, and the bottom of bottom workshop section is positioned at the bottom in construction building, and the top end of bottom workshop section is positioned at the wherein one deck in construction building; Said top workshop section is a vertical sections, and uses the transportation of hanging basket parts group, and the bottom of top workshop section is positioned at a floor of the below, top of bottom workshop section, and abuts against a side of bottom workshop section, and the top of top workshop section is positioned at the top of the floor that has built up; Said hanging basket parts group comprises power wind, lifting rope, hanging basket; Said power wind is installed in the top of said each workshop section, and an end of lifting rope is wrapped in the power wind, and the other end and hanging basket are connected and fixed; Can will betransported the floor that thing is transported to be needed through bottom workshop section, top workshop section.
Preferably, along with the continuing to increase and build of construction building, the top of said top workshop section can add a plurality of and identic vertical transport workshop section of bottom workshop section and top workshop section.
Preferably, the both sides of said bottom workshop section and top workshop section are equipped with the guide line that vertically passes hanging basket.
Preferably, said bottom workshop section, top workshop section and the top and the bottom that increase the vertical transport workshop section that builds are equipped with the fall arrest baffle plate.
A kind of vertical transporting method of the present invention does not conflict with other special-purpose vertical transport mutually; Can not need to remove along with building increases the vertical transport passage that progressively extends midway; Can continuity carry out handling, shorten the handling circuit, also just shorten the handling time; Lift strongly professionally, improve safety, the control of favourable potential safety hazard; Use the guide line device more to overcome the situation that unit plate is hung in aerial generation rotation and swing.
Description of drawings
Below in conjunction with accompanying drawing technical scheme of the present invention is described further:
Accompanying drawing 1 is a kind of vertical transporting method sketch map of the present invention;
Wherein: 1, bottom workshop section; 2, top workshop section; 3, hanging basket parts group; 4, power wind; 5, lifting rope; 6, hanging basket; 7, guide line; 8, fall arrest baffle plate.
The specific embodiment
Be depicted as a kind of vertical transporting method of the present invention like accompanying drawing 1, comprise bottom workshop section 1, top workshop section 2 and hanging basket parts group 3; Said bottom workshop section 1 is a vertical sections, and uses 3 transportations of hanging basket parts group, and the bottom of bottom workshop section 1 is positioned at the bottom in construction building, and the top end of bottom workshop section 1 is positioned at the wherein one deck in construction building; Said top workshop section 2 is a vertical sections, and uses 3 transportations of hanging basket parts group, and the bottom of top workshop section 2 is positioned at a floor of the below, top of bottom workshop section 1, and abuts against a side of bottom workshop section 1, and the top of top workshop section 2 is positioned at the top of the floor that has built up; Said hanging basket parts group 3 comprises power wind 4, lifting rope 5, hanging basket 6, guide line 7; Said power wind 4 is installed in the top of said each workshop section; One end of lifting rope 5 is wrapped in the power wind 4; The other end and hanging basket 6 are connected and fixed, and the both sides of hanging basket 6 are provided with guided way, and guide line 7 vertically is arranged on the both sides of hanging basket 6; Pass the guided way of hanging basket 6 both sides, and be consistent with the height of the current workshop section at hanging basket parts group 3 place; The top and the bottom of workshop section 1 and top workshop section 2 are equipped with fall arrest baffle plate 8 in the bottom; Can will betransported the floor that thing is transported to be needed through bottom workshop section (1), top workshop section (2).
During construction, between the floor of building up, build earlier bottom workshop section 1, utilize hanging basket parts group 3 construction material to be transported to the top layer of bottom workshop section 1; When building increases when building, again in bottom workshop section 1 with increase and build top workshop section 2 between the top layer of building, at this moment can between will be transported to bottom workshop section 1 top layer construction material continue upwards transportation; When building continues to increase when building, can build more workshop section with reference to the mode of bottom workshop section 1 and top workshop section 2.
The described a kind of vertical transporting method of this embodiment uses multiplex's section coordinating operation, does not need to remove midway; Can continuity carry out handling, shorten handling circuit and handling time; Lift strongly professionally, improve safety, the control of favourable potential safety hazard; Use the guide line device more to overcome the situation that unit plate is hung in aerial generation rotation and swing; And along with the continuing to increase and build of construction building, the top of top workshop section can add a plurality of and identic vertical transport workshop section of bottom workshop section and top workshop section, has improved efficiency of construction greatly.
The foregoing description only is explanation technical conceive of the present invention and characteristics; Its purpose is to let the personage that is familiar with this technology can understand content of the present invention and implements; Can not limit protection scope of the present invention with this; All equivalences that spirit is done according to the present invention change or modify, and all should be encompassed in protection scope of the present invention.
Claims (4)
1. a vertical transporting method is characterized in that: comprise bottom workshop section (1), top workshop section (2) and hanging basket parts group (3); Said bottom workshop section (1) is a vertical sections, and uses hanging basket parts group transportations (3), and the bottom of bottom workshop section (1) is positioned at the bottom in construction building, and the top end of bottom workshop section (1) is positioned at the wherein one deck in construction building; Said top workshop section (2) is a vertical sections; And use hanging basket parts groups (3) to transport; The bottom of top workshop section (2) is positioned at a floor of the below, top of bottom workshop section (1); And abut against the bottom workshop section (1) a side, the top of top workshop section (2) is positioned at the top of the floor that has built up; Said hanging basket parts group (3) comprises power wind (4), lifting rope (5), hanging basket (6); Said power wind (4) is installed in the top of said each workshop section, and an end of lifting rope (5) is wrapped in the power wind (4), and the other end and hanging basket (6) are connected and fixed; Can will betransported the floor that thing is transported to be needed through bottom workshop section (1), top workshop section (2).
2. a kind of vertical transporting method according to claim 1; It is characterized in that: along with the continuing to increase and build of construction building, the top of said top workshop section (2) can add a plurality of and bottom workshop section (1) and identic vertical transport workshop section of top workshop section (2).
3. a kind of vertical transporting method according to claim 1 is characterized in that: the both sides of said bottom workshop section (1) and top workshop section (2) are equipped with the guide line (7) that vertically passes hanging basket (6).
4. according to the described a kind of vertical transporting method of above any claim, it is characterized in that: said bottom workshop section (1), top workshop section (2) and the top and the bottom that increase the vertical transport workshop section that builds are equipped with fall arrest baffle plate (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201210183129 CN102733613B (en) | 2012-06-06 | 2012-06-06 | Vertical transportation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201210183129 CN102733613B (en) | 2012-06-06 | 2012-06-06 | Vertical transportation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102733613A true CN102733613A (en) | 2012-10-17 |
CN102733613B CN102733613B (en) | 2013-12-18 |
Family
ID=46989858
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201210183129 Active CN102733613B (en) | 2012-06-06 | 2012-06-06 | Vertical transportation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102733613B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102943584A (en) * | 2012-11-16 | 2013-02-27 | 中国神华能源股份有限公司 | Silo and equipment lifting method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2384929Y (en) * | 1999-08-16 | 2000-06-28 | 焦作矿务局建筑安装工程总公司 | Self-raising gantry crane |
JP3523838B2 (en) * | 2000-10-26 | 2004-04-26 | 宮地建設工業株式会社 | Lift-up method and lift-up system |
CN101177225A (en) * | 2007-07-20 | 2008-05-14 | 郁荣 | Practice method of vertical hoisting transportation elevator and elevator for low-rise building |
CN102060199A (en) * | 2010-12-16 | 2011-05-18 | 山西太行建设开发有限公司 | Transportation method for constructing high mountain building |
CN102071812A (en) * | 2010-12-23 | 2011-05-25 | 中国一冶集团有限公司 | Method for vertically transporting building materials |
-
2012
- 2012-06-06 CN CN 201210183129 patent/CN102733613B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2384929Y (en) * | 1999-08-16 | 2000-06-28 | 焦作矿务局建筑安装工程总公司 | Self-raising gantry crane |
JP3523838B2 (en) * | 2000-10-26 | 2004-04-26 | 宮地建設工業株式会社 | Lift-up method and lift-up system |
CN101177225A (en) * | 2007-07-20 | 2008-05-14 | 郁荣 | Practice method of vertical hoisting transportation elevator and elevator for low-rise building |
CN102060199A (en) * | 2010-12-16 | 2011-05-18 | 山西太行建设开发有限公司 | Transportation method for constructing high mountain building |
CN102071812A (en) * | 2010-12-23 | 2011-05-25 | 中国一冶集团有限公司 | Method for vertically transporting building materials |
Non-Patent Citations (2)
Title |
---|
王向阳: "多层与高层建筑施工垂直运输机械选用", 《中国住宅设施》 * |
荣春堂: "垂直运输系统在高竖井开挖施工中的应用", 《四川水力发电》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102943584A (en) * | 2012-11-16 | 2013-02-27 | 中国神华能源股份有限公司 | Silo and equipment lifting method |
CN102943584B (en) * | 2012-11-16 | 2015-07-01 | 中国神华能源股份有限公司 | Silo and equipment lifting method |
Also Published As
Publication number | Publication date |
---|---|
CN102733613B (en) | 2013-12-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201809036U (en) | Hanging hopper with detachable chassis | |
CN102212630A (en) | Construction method for replacing cooling wall of blast furnace by utilizing movable hanging scaffold | |
CN103790390B (en) | The glass plate Lift-on/Lift-off System of large-span domes Glass Curtain Wall Construction and construction method thereof | |
CN201276399Y (en) | Apparatus hoisting mechanism for tall building floor non-steel platform | |
CN107304631A (en) | The installation method and system of a kind of high-rise building large area cell cube curtain wall block | |
CN102635225A (en) | Equipment hoisting platform and method for super high-rise buildings | |
CN102777048A (en) | Vertical transportation device | |
CN206562264U (en) | A kind of hanging device for transport outside high-rise building | |
CN203794533U (en) | Light portable mobile lifting equipment | |
CN204626998U (en) | A kind of attached lift scaffold discharging platform | |
CN203373022U (en) | Self-lifting type cableway transportation device | |
CN206337831U (en) | A kind of discharging platform of construction | |
CN204124984U (en) | Two cage building hoist | |
CN203947758U (en) | Novel hydraulic automatic climbing discharging platform | |
CN203531352U (en) | Hanging type movable working platform for storage tank maintenance | |
CN202324567U (en) | Moving type large-scale operation platform | |
CN102733613B (en) | Vertical transportation method | |
CN103274310A (en) | Self-lifting type cableway transporting device | |
CN204126237U (en) | A kind of elevator hoistway construction platform | |
CN204001751U (en) | Super high steel structure construction overhanging unloading platform | |
CN202729527U (en) | Vertical conveying device | |
CN203781713U (en) | High slope support material transport device | |
CN103982046A (en) | Lifting and installation method of buckling restrained braces | |
CN204198306U (en) | A kind of device for purlin lifting in building operation | |
CN203499232U (en) | Attached lifting scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |