CN102605950A - 单层工业厂房现浇混凝土双肢柱的施工方法 - Google Patents

单层工业厂房现浇混凝土双肢柱的施工方法 Download PDF

Info

Publication number
CN102605950A
CN102605950A CN2011100320487A CN201110032048A CN102605950A CN 102605950 A CN102605950 A CN 102605950A CN 2011100320487 A CN2011100320487 A CN 2011100320487A CN 201110032048 A CN201110032048 A CN 201110032048A CN 102605950 A CN102605950 A CN 102605950A
Authority
CN
China
Prior art keywords
concrete column
double component
double
component concrete
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100320487A
Other languages
English (en)
Inventor
王志义
李贵良
刘新立
康俊峰
郝春霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Construction Group Corp Ltd
Original Assignee
Hebei Construction Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Construction Group Corp Ltd filed Critical Hebei Construction Group Corp Ltd
Priority to CN2011100320487A priority Critical patent/CN102605950A/zh
Publication of CN102605950A publication Critical patent/CN102605950A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种单层工业厂房现浇混凝土双肢柱的施工方法,在施工现场支设双肢柱模架,所述双肢柱按其柱孔由下至上分层分段配置钢筋,支设模板,所述双肢柱柱孔由组合型模板一次配制成,所述双肢柱柱外设置四块单片模板组装件,通过脚手架操作平台向由下至上逐段构建的所述双肢柱模架输送泵送混凝土并现场浇筑振捣,形成全现浇钢筋混凝土双肢柱。

Description

单层工业厂房现浇混凝土双肢柱的施工方法
技术领域
本发明涉及建筑领域的一种施工方法,尤其是涉及一种单层工业厂房现浇混凝土双肢柱的施工方法。
背景技术
目前,单层工业厂房建筑领域中使用的双肢柱混凝土柱多为预制钢筋混凝土柱,在施工过程中,预制钢筋构件需要占用大量的施工场地,而且必须使用大型垂直运输起重设备进行大型构件吊装作业,费时费工费材,给现场工作人员的施工带来很多不便,而且存在很大的安全隐患。
发明内容
本发明的目的是提供一种单层工业厂房现浇混凝土双肢柱的施工方法,能够避免传统施工方法中占用大量的施工场地,而且必须使用大型垂直运输起重设备进行大型构件吊装作业的缺点,方便现场工作人员的施工。
为实现上述目的,本发明提供了一种单层工业厂房现浇混凝土双肢柱的施工方法,在施工现场支设双肢柱模架,所述双肢柱按其柱孔由下至上分层分段配置钢筋,支设模板,所述双肢柱柱孔由组合型模板一次配制成,所述双肢柱柱外设置四块单片模板组装件,通过脚手架操作平台向由下至上逐段构建的所述双肢柱模架输送泵送混凝土并现场浇筑振捣,形成全现浇钢筋混凝土双肢柱。
优选的,由下至上逐段浇筑所述双肢柱时,各段施工段留设于该段的上一段的所述双肢柱柱孔根部。
优选的,所述双肢柱的水平梁在所述双肢柱两侧对称设置,并设穿墙螺栓。
因此,本发明使用上述的单层工业厂房现浇混凝土双肢柱的施工方法,能够避免传统施工方法中占用大量的施工场地,而且必须使用大型垂直运输起重设备进行大型构件吊装作业的缺点,方便现场工作人员的施工。
下面通过实施例,对本发明的技术方案做进一步的详细描述。
具体实施方式
实施例
本实施例提供了一种单层工业厂房现浇混凝土双肢柱的施工方法,在施工现场支设双肢柱模架,所述双肢柱按其柱孔由下至上分层分段配置钢筋,支设模板,所述双肢柱柱孔由组合型模板一次配制成,所述双肢柱柱外设置四块单片模板组装件,通过脚手架操作平台向由下至上逐段构建的所述双肢柱模架输送泵送混凝土并现场浇筑振捣,形成全现浇钢筋混凝土双肢柱。脚手架平台搭建成四排纵向式,如此不仅更方便浇筑施工,还能够为柱间二次结构砌体的施工提供良好的操作平台。
本实施例在由下至上逐段浇筑所述双肢柱时,各段施工段留设于该段的上一段的所述双肢柱柱孔根部,如此便于施工方浇筑混凝土。
所述双肢柱的水平梁在所述双肢柱柱两侧对称设置,并设穿墙螺栓,以方便模板加固,水平梁部位的螺栓孔在后期装修阶段可做成假眼,达到清水混凝土的效果。
单根双肢柱一次浇筑混凝土的量不大,成批成规模浇筑混凝土便于商品混凝土供应和对混凝土质量的监控。
单根双肢柱模架一次配制耗材量小,投资少,配合清水混凝土模板及早拆模成套技术的应用可以加快模板、钢管等周转性工具的周转速度,大大节省周转性工具的投入使用量,降低施工成本并提高施工进度。
所述双肢柱柱孔内模可采用钢制连接角模、复塑多层板及木龙骨拼装,为了便于模板拆除,在所述双肢柱模板角连接部位以钢制抱角连件;内模以支撑和角支撑构成结构不变体系加固。所述双肢柱芯模采用钢管与外脚手架联结的方式加固以保证芯模整体位置的准确。所述双肢柱外模采用四片复塑多层板现场拼装而成,为防止四角漏浆,外模加工时连角处设企口与粘条贴。穿墙螺栓采用Φ16的对拉螺栓。所述双肢柱连梁处使用Φ18的塑料套管,以便重复使用。
本实施例摒弃了目前单层工业厂房在建设时一贯采用的使用预制双肢柱构件的做法,采用现浇混凝土双肢柱的方法进行施工,施工方法合理、可靠,具有省工、省地、省材、便捷高效及安全的优点,能够避免传统施工方法中占用大量的施工场地,而且必须使用大型垂直运输起重设备进行大型构件吊装作业的缺点,方便现场工作人员的施工。
最后应说明的是:以上实施例仅用以说明本发明的技术方案而非对其进行限制,尽管参照较佳实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对本发明的技术方案进行修改或者等同替换,而这些修改或者等同替换亦不能使修改后的技术方案脱离本发明技术方案的精神和范围。

Claims (3)

1.一种单层工业厂房现浇混凝土双肢柱的施工方法,其特征在于:在施工现场支设双肢柱模架,所述双肢柱按其柱孔由下至上分层分段配置钢筋,支设模板,所述双肢柱柱孔由组合型模板一次配制成,所述双肢柱柱外设置四块单片模板组装件,通过脚手架操作平台向由下至上逐段构建的所述双肢柱模架输送泵送混凝土并现场浇筑振捣,形成全现浇钢筋混凝土双肢柱。
2.根据权利要求1所述的单层工业厂房现浇混凝土双肢柱的施工方法,其特征在于:由下至上逐段浇筑所述双肢柱时,各段施工段留设于该段的上一段的所述双肢柱柱孔根部。
3.根据权利要求2所述的单层工业厂房现浇混凝土双肢柱的施工方法,其特征在于:所述双肢柱的水平梁在所述双肢柱两侧对称设置,并设穿墙螺栓。
CN2011100320487A 2011-01-25 2011-01-25 单层工业厂房现浇混凝土双肢柱的施工方法 Pending CN102605950A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100320487A CN102605950A (zh) 2011-01-25 2011-01-25 单层工业厂房现浇混凝土双肢柱的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100320487A CN102605950A (zh) 2011-01-25 2011-01-25 单层工业厂房现浇混凝土双肢柱的施工方法

Publications (1)

Publication Number Publication Date
CN102605950A true CN102605950A (zh) 2012-07-25

Family

ID=46523679

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100320487A Pending CN102605950A (zh) 2011-01-25 2011-01-25 单层工业厂房现浇混凝土双肢柱的施工方法

Country Status (1)

Country Link
CN (1) CN102605950A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610831A (zh) * 2019-01-07 2019-04-12 五冶集团上海有限公司 一种现代物流厂房地坪与高支模综合施工方法
CN114856086A (zh) * 2022-06-02 2022-08-05 合肥工业大学 一种重型厂房钢筋混凝土双肢排架柱及其施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04166518A (ja) * 1990-10-26 1992-06-12 Shigeki Nagase 鉄筋コンクリート基礎施工方法及び工場組立鉄筋
CN201272653Y (zh) * 2007-09-28 2009-07-15 中国二十冶建设有限公司 预制钢筋混凝土双肢柱的吊具
CN201377167Y (zh) * 2008-12-04 2010-01-06 中国二十冶建设有限公司 分段厂房柱高空拼装平台

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04166518A (ja) * 1990-10-26 1992-06-12 Shigeki Nagase 鉄筋コンクリート基礎施工方法及び工場組立鉄筋
CN201272653Y (zh) * 2007-09-28 2009-07-15 中国二十冶建设有限公司 预制钢筋混凝土双肢柱的吊具
CN201377167Y (zh) * 2008-12-04 2010-01-06 中国二十冶建设有限公司 分段厂房柱高空拼装平台

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
方孝新: "长25.75m格构式双肢柱定型组合钢模立式现浇施工", 《湖南农学院学报》, vol. 20, no. 5, 30 October 1994 (1994-10-30) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610831A (zh) * 2019-01-07 2019-04-12 五冶集团上海有限公司 一种现代物流厂房地坪与高支模综合施工方法
CN114856086A (zh) * 2022-06-02 2022-08-05 合肥工业大学 一种重型厂房钢筋混凝土双肢排架柱及其施工方法

Similar Documents

Publication Publication Date Title
CN111734031B (zh) 一种建筑密肋结构的快装快拆模壳体系及其施工工艺
CN103452350B (zh) 装配式电子厂房及其施工方法
CN103089004A (zh) 组合框模、构件框模、模架结构及其安装和拆卸方法
CN105275209A (zh) 一种异形空间曲面清水混凝土施工方法
CN102708934A (zh) 核电厂反应堆堆腔结构及堆腔建造方法
WO2020211175A1 (zh) 一种装配式钢筋混凝土桥墩及其施工方法
CN211114425U (zh) 一种预制钢管砼柱
CN106760502A (zh) 剪力墙端部圆柱施工方法
CN101487293A (zh) 梁柱节点不同强度等级混凝土浇筑方法
CN208965714U (zh) 一种装配式混凝土预制管廊主体框架结构
CN105839784B (zh) 拼装顶升式建筑施工方法
CN103485574B (zh) 一种造粒塔塔顶钢筋混凝土结构施工方法
CN113293694A (zh) 一种用于墩身高效施工的翻模框架结构及施工工艺
CN104153573B (zh) V型圆柱混凝土的浇筑模具及施工方法
CN205296197U (zh) 抗腐蚀工业厂房混凝土杯口式预制承台
CN205894670U (zh) 楼层间混凝土接茬施工的模板结构
CN102409848A (zh) 一种轻质密肋楼板和轻质密肋楼盖的施工成型方法
CN203022222U (zh) 砖混建筑支座整浇圈梁
CN102605950A (zh) 单层工业厂房现浇混凝土双肢柱的施工方法
CN206753037U (zh) 滑模施工用竖向钢筋定位架
CN104453235B (zh) 换流站防火墙施工工艺
CN202584747U (zh) 核电厂反应堆堆腔结构
CN204001713U (zh) V型圆柱斜线段混凝土浇筑模具
CN202108296U (zh) 一种拼装节式水箱塔架
CN204001714U (zh) V型圆柱混凝土的浇筑模具

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120725