CN102587420A - 一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法 - Google Patents

一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法 Download PDF

Info

Publication number
CN102587420A
CN102587420A CN2012100310371A CN201210031037A CN102587420A CN 102587420 A CN102587420 A CN 102587420A CN 2012100310371 A CN2012100310371 A CN 2012100310371A CN 201210031037 A CN201210031037 A CN 201210031037A CN 102587420 A CN102587420 A CN 102587420A
Authority
CN
China
Prior art keywords
basement
stage
bored pile
supporter
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100310371A
Other languages
English (en)
Other versions
CN102587420B (zh
Inventor
李小玥
刘玉涛
曹跃军
厉航平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN201210031037.1A priority Critical patent/CN102587420B/zh
Publication of CN102587420A publication Critical patent/CN102587420A/zh
Application granted granted Critical
Publication of CN102587420B publication Critical patent/CN102587420B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明提供一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,包括以下步骤:步骤一:构建以钻孔灌注桩为主体的分隔围护结构,在相邻钻孔灌注桩之间穿插换撑型钢,将换撑型钢的一端埋入一期地下室的地下室楼板和传力带中;步骤二:浇筑二期地下室的地下室楼板时,将换撑型钢的另一端埋入二期地下室的地下室楼板中;步骤三:进行钻孔灌注桩和传力带的拆除,保留换撑型钢,绑扎连接钢筋,浇筑混凝土,使得一期地下室与二期地下室连接起来。能够很好地解决前后期施工部分的换撑问题,换撑效果好,并且能够以顺作的方式施工地下室结构,施工方便,换撑成本低。

Description

一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法
技术领域
本发明涉及建筑施工领域,具体涉及一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法。
背景技术
建筑施工项目的地下室施工中,由于场地、安全或资金等原因,常常需要进行分期施工,分期施工时常以钻孔灌注桩为分隔围护结构,施工完成后将钻孔灌注桩拆除,将前后两期地下室连成一体。为保证地下室能相互贯通成一整体,就必须处理好前后期施工部分的换撑问题。目前通常采用逆作的方式,即随着施工的进行自上而下逐次拆除钻孔灌注桩,以使前后期地下室连通,施工较为麻烦且换撑费用高。
发明内容
本发明所要解决的技术问题在于提供一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,能够很好地解决前后期施工部分的换撑问题,换撑效果好,并且能够以顺作的方式施工地下室结构,施工方便,换撑成本低。
为解决上述现有的技术问题,本发明采用如下方案:一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,包括以下步骤:
步骤一:在一期地下室与二期地下室之间构建以钻孔灌注桩为主体的分隔围护结构,在相邻钻孔灌注桩之间穿插换撑型钢,浇筑一期地下室的地下室楼板时,靠近钻孔灌注桩的一侧预留连接钢筋,并且将换撑型钢的一端埋入一期地下室的地下室楼板和传力带中;
步骤二:浇筑二期地下室的地下室楼板时,同样在靠近钻孔灌注桩的一侧预留连接钢筋,并且将换撑型钢的另一端埋入二期地下室的地下室楼板中;
步骤三:自上而下进行钻孔灌注桩和传力带的拆除,保留换撑型钢,绑扎一期地下室的地下室楼板与二期地下室的地下室楼板之间的连接钢筋,浇筑混凝土,使得一期地下室与二期地下室连接起来。
作为优选,所述步骤二中换撑型钢的另一端采用对焊接长。避免埋入二期地下室的地下室楼板中的换撑型钢过短。
作为优选,所述步骤一中的换撑型钢为口字型或者H型。
作为优选,所述地下室楼板为顶板或者底板时,在浇筑地下室楼板前,于地下室楼板上靠近钻孔灌注桩的一侧预埋钢板止水带。
有益效果:
本发明采用上述技术方案提供的一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,很好地解决了前后期施工部分的换撑问题,换撑效果好,并且能够以顺作的方式施工地下室结构,施工方便,换撑成本低。
附图说明
图1为本发明的一期地下室换撑施工平面示意图;
图2为图1中A-A面的剖视图;
图3为本发明的二期地下室换撑施工平面示意图;
图4为图3中B-B面的剖视图;
图5为本发明中拆除围护钻孔灌注桩后一期、二期地下室连接的示意图;
图6为图5中C-C面的剖视图。
具体实施方式
如图1至图6所示,一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,包括以下步骤:
步骤一:在一期地下室与二期地下室之间构建以钻孔灌注桩4为主体的分隔围护结构,在相邻钻孔灌注桩4之间穿插换撑型钢3,浇筑一期地下室的地下室楼板1时,靠近钻孔灌注桩4的一侧预留连接钢筋5,并且将换撑型钢3的一端埋入一期地下室的地下室楼板1和传力带2中;
步骤二:浇筑二期地下室的地下室楼板1时,同样在靠近钻孔灌注桩4的一侧预留连接钢筋5,并且将换撑型钢3的另一端埋入二期地下室的地下室楼板1中;
步骤三:自上而下进行钻孔灌注桩4和传力带2的拆除,保留换撑型钢3,绑扎一期地下室的地下室楼板1与二期地下室的地下室楼板1之间的连接钢筋5,浇筑混凝土,使得一期地下室与二期地下室连接起来。
所述步骤二中换撑型钢3的另一端采用对焊接长。步骤一中的换撑型钢3为口字型或者H型钢筋。传力带2起到临时支撑的作用。换撑型钢3的长度根据换撑型钢3的受力分析确定,换撑型钢3间距根据二期地下室基坑围护设计的换撑间距来确定。为了避免埋入二期地下室的地下室楼板中的换撑型钢过短,所述步骤二中换撑型钢3的另一端采用对焊接长。很好地解决了前后期施工部分的换撑问题,换撑效果好,并且能够以顺作的方式施工地下室结构,施工方便,换撑成本低。所述地下室楼板1为顶板或者底板时,在浇筑地下室楼板1前,于地下室楼板1上靠近钻孔灌注桩4的一侧预埋钢板止水带。

Claims (4)

1.一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,其特征在于:包括以下步骤:
步骤一:在一期地下室与二期地下室之间构建以钻孔灌注桩(4)为主体的分隔围护结构,在相邻钻孔灌注桩(4)之间穿插换撑型钢(3),浇筑一期地下室的地下室楼板(1)时,靠近钻孔灌注桩(4)的一侧预留连接钢筋(5),并且将换撑型钢(3)的一端埋入一期地下室的地下室楼板(1)和传力带(2)中;
步骤二:浇筑二期地下室的地下室楼板(1)时,同样在靠近钻孔灌注桩(4)的一侧预留连接钢筋(5),并且将换撑型钢(3)的另一端埋入二期地下室的地下室楼板(1)中;
步骤三:自上而下进行钻孔灌注桩(4)和传力带(2)的拆除,保留换撑型钢(3),绑扎一期地下室的地下室楼板(1)与二期地下室的地下室楼板(1)之间的连接钢筋(5),浇筑混凝土,使得一期地下室与二期地下室连接起来。
2.根据权利要求1所述的一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,其特征在于:所述步骤二中换撑型钢(3)的另一端采用对焊接长。
3.根据权利要求1所述的一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,其特征在于:所述步骤一中的换撑型钢(3)为口字型或者H型。
4.根据权利要求1所述的一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法,其特征在于:所述地下室楼板(1)为顶板或者底板时,在浇筑地下室楼板(1)前,于地下室楼板(1)上靠近钻孔灌注桩(4)的一侧预埋钢板止水带。
CN201210031037.1A 2012-02-13 2012-02-13 一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法 Active CN102587420B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210031037.1A CN102587420B (zh) 2012-02-13 2012-02-13 一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210031037.1A CN102587420B (zh) 2012-02-13 2012-02-13 一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法

Publications (2)

Publication Number Publication Date
CN102587420A true CN102587420A (zh) 2012-07-18
CN102587420B CN102587420B (zh) 2014-03-26

Family

ID=46476611

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210031037.1A Active CN102587420B (zh) 2012-02-13 2012-02-13 一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法

Country Status (1)

Country Link
CN (1) CN102587420B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040730A (zh) * 2015-06-29 2015-11-11 上海市基础工程集团有限公司 逆作基坑中围护灌注桩与地下室结构楼板连接处理方法
CN105386447A (zh) * 2015-09-06 2016-03-09 上海建工七建集团有限公司 一种施工现场后浇带换撑的施工方法
CN110055975A (zh) * 2019-04-25 2019-07-26 中建四局第四建筑工程有限公司 一种大跨度深基坑地下室分期施工方法及临时结构
CN110565981A (zh) * 2019-09-11 2019-12-13 上海建工一建集团有限公司 既有建筑物地下空间的增层方法及结构

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005120663A (ja) * 2003-10-16 2005-05-12 Takenaka Komuten Co Ltd 山留め壁の構造
KR20060023245A (ko) * 2004-09-09 2006-03-14 이재호 토목공사용 지하 흙막이벽 시공방법
CN101476331A (zh) * 2007-12-12 2009-07-08 中国二十冶建设有限公司 地下室基坑砼内支撑封闭爆破拆除方法
CN101614019A (zh) * 2008-11-11 2009-12-30 中铁四局集团建筑工程有限公司 紧临既有建筑物多层地下结构自支护施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005120663A (ja) * 2003-10-16 2005-05-12 Takenaka Komuten Co Ltd 山留め壁の構造
KR20060023245A (ko) * 2004-09-09 2006-03-14 이재호 토목공사용 지하 흙막이벽 시공방법
CN101476331A (zh) * 2007-12-12 2009-07-08 中国二十冶建设有限公司 地下室基坑砼内支撑封闭爆破拆除方法
CN101614019A (zh) * 2008-11-11 2009-12-30 中铁四局集团建筑工程有限公司 紧临既有建筑物多层地下结构自支护施工方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105040730A (zh) * 2015-06-29 2015-11-11 上海市基础工程集团有限公司 逆作基坑中围护灌注桩与地下室结构楼板连接处理方法
CN105040730B (zh) * 2015-06-29 2017-04-19 上海市基础工程集团有限公司 逆作基坑中围护灌注桩与地下室结构楼板连接处理方法
CN105386447A (zh) * 2015-09-06 2016-03-09 上海建工七建集团有限公司 一种施工现场后浇带换撑的施工方法
CN110055975A (zh) * 2019-04-25 2019-07-26 中建四局第四建筑工程有限公司 一种大跨度深基坑地下室分期施工方法及临时结构
CN110565981A (zh) * 2019-09-11 2019-12-13 上海建工一建集团有限公司 既有建筑物地下空间的增层方法及结构

Also Published As

Publication number Publication date
CN102587420B (zh) 2014-03-26

Similar Documents

Publication Publication Date Title
CN105803925A (zh) 一种预制钢管约束型钢混凝土墩柱与盖梁的快速连接方法
KR101519086B1 (ko) 프리캐스트 t형 거더를 이용한 교량 및 교량 시공방법
US20130008125A1 (en) Construction method for new underground structure
CN102587420B (zh) 一种以钻孔灌注桩作分隔围护的分期施工地下室换撑方法
CN102587412B (zh) 一种以地下连续墙作分隔围护的分期施工地下室换撑方法
CN103437346A (zh) 带树瘤的钢管桩及施工方法
JP4851881B2 (ja) 盛土構造物及び盛土構造物の補強方法
JP4347846B2 (ja) 橋脚補強方法
KR101084615B1 (ko) 피씨벽판을 이용한 선반식 옹벽 구조 및 그 시공방법
CN202280152U (zh) 一种在钢筋混凝土板底设置预埋件的结构
JP5901008B2 (ja) 壁板接合構造
JP2016205051A (ja) 構造物の施工方法
CN104234268B (zh) 一种预制排孔式剪力墙
KR101338376B1 (ko) 랩블록 연결 구조 및 이를 이용한 시공 방법
CN209837333U (zh) 用于后浇带位置的钢筋混凝土诱导带结构
CN103669878A (zh) 一种核心筒钢筋接驳方法
KR20120125109A (ko) 토사백 연결구
CN115262531A (zh) 一种地下连续墙兼做隔振屏障的成型及设计方法
JP2014206025A (ja) カルバート
KR20120132084A (ko) 합성교량 및 그 시공방법
CN106088433B (zh) 一种双向受力叠合板及其施工方法
CN202359574U (zh) 一种用于地下连续墙施工的双面钢模板
JP5344419B2 (ja) 擁壁用背面ブロック、擁壁の構築方法及び擁壁
CN110670626A (zh) 一种装配式基础模块及其快速施工的方法
CN203866857U (zh) 一种用于安装mini机柜的通用基座

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant