CN102562087B - Hydraulic drill follow-up pipe-shed construction method - Google Patents

Hydraulic drill follow-up pipe-shed construction method Download PDF

Info

Publication number
CN102562087B
CN102562087B CN201110410622.8A CN201110410622A CN102562087B CN 102562087 B CN102562087 B CN 102562087B CN 201110410622 A CN201110410622 A CN 201110410622A CN 102562087 B CN102562087 B CN 102562087B
Authority
CN
China
Prior art keywords
pipe
construction
canopy
drilling
rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110410622.8A
Other languages
Chinese (zh)
Other versions
CN102562087A (en
Inventor
何复生
朱家稳
李永丰
王声扬
杨戈
杨勇
唐开富
周忠林
王国炜
罗飚
胡光全
陈艳林
杨兴林
杨全勇
张智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
China Railway Erju 1st Engineering Co Ltd
Original Assignee
China Railway Erju Co Ltd
China Railway Erju 1st Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd, China Railway Erju 1st Engineering Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CN201110410622.8A priority Critical patent/CN102562087B/en
Publication of CN102562087A publication Critical patent/CN102562087A/en
Application granted granted Critical
Publication of CN102562087B publication Critical patent/CN102562087B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a hydraulic drill follow-up pipe-shed construction method. Two guide tracks are laid on a work site, which is perpendicular to an axis of a tunnel, on a construction tunnel face, and are used for realizing traveling of a drilling machine platform and positioning of a pipe-shed, during construction, packed hole drilling of a slurry protecting wall is formed by a hydraulic drill from a tunnel access opening at the outer edge of a frame via the drilling machine platform according to certain distances, drilling and follow-up pipe construction are carried out simultaneously, finally, advanced pre-supporting is formed, the purposes of increasing rigidity and bearing ability of a stratum and unevenly and normally distributing uniformly distributed load are achieved, surface subsidence in a follow-up frame digging process is reduced, and safety of civilization sites is ensured. In the method, the quantity of construction operators and the quantity of equipment are reduced, effects are improved, a pipe-shed circulating period is shortened, a construction schedule is ensured, and engineering manufacturing cost is reduced. The method is a brand-new pipe-shed construction method for an extremely shallow-buried and large-section tunnel, not only is convenient in construction when used for soil layers and loose, soft and unstable strata, but also is more favorable for controlling surface subsidence, and is safe and controllable.

Description

Water drilling follow-up pipe shed construction method
Technical field
The present invention relates to a kind of water drilling follow-up pipe shed construction method, this construction method is specially adapted to down to wear an ultra shallow and buries soil property and the unstable geology of loose weak and protect exceptional structure to construct.
Background technology
Some speedway can wear down the area of burying national historical relic, as elm god speedway can wear Ruins of Great Wall of the Qin Dynasty down, for protecting national historical relic, open cut can not pass through with cutting form, tunnel excavation method must be adopted to pass through.
Carry out follow-up pipe roof construction when protecting national historical relic, home and abroad there is no the construction technology in similar tunnel at present, can not for the construction method used for reference.
Summary of the invention
The technical problem to be solved in the present invention is: for above-mentioned situation, provides a kind of easy construction in soil layer and the unstable geology of loose weak, is beneficial to control surface settlement, is beneficial to the water drilling follow-up pipe shed construction method protecting national historical relic.
The object of the invention is realized by following technical proposals:
A kind of water drilling follow-up pipe shed construction method, at construction face place, two guide rails are laid perpendicular on the work-yard of tunnel axis, for drilling machine platform walking and pipe canopy location, in construction, pass through drilling machine platform, water drilling is adopted to form mud off packed hole drilling from tunnel's entrance and exit at a certain distance in framework outer, creep into while follow pipe construction, finally form leading pre-supporting, reach the rigidity and supporting capacity that improve stratum, the uneven normal distribution object of evenly distributed load, reduce surface settlement in follow-up framework digging process, guarantee cultural sight safety.
As preferably, the method comprises the steps: further
1) locate
1.1 preparations of construction: face build, personnel, facility, test and surveying work in place, reach requirements for starting construction;
1.2 smooth locations: mainly refer to smooth drilling machine construction place, for lower step operation provides work-yard;
1.3 lay track: at construction face place, lay two guide rails perpendicular on the work-yard of tunnel axis, for the walking of rig pylon, create conditions to later stage pipe canopy rig location, walking and construction;
1.4 drilling-machine shifter stage+module: install mobile platform on guide rail, platform is installed and human users for equipment;
1.5 rigs are installed and location: be fixed on platform by pipe canopy dedicated leveling rig, utilize the vernier device below drilling derrick vertically to locate, until meet designing requirement.
2) creep into
2.1 drill bits are selected and are connected: select drill bit according to stratum, and be connected with canopy pipe, rig by drill bit, namely drill bit and canopy pipe, canopy pipe and drill power head form sealed tube;
2.2 perforates: start rig, at a slow speed perforate, at the uniform velocity creep into, guarantee that its first pipe position meets design requirement;
2.3 mud offs: flushing liquor and water, be pumped into drill power head by slush pump, to canopy pipe steel pipe, to drill bit, finally from drill bit injection, impact soil layer, the rotary drilling under the dynamic action of rig of canopy pipe, the continuous cutting soil of drill bit, the powdery soil body be cut into and the flushing liquor at drill bit place and water are constantly stirred by rig power, and a part forms mud off, prevents hole wall collapse, reduce earth's surface differential settlement, finally realize the object of canopy pipe evenly distributed load; Another part mud is continuously supplemented and dilution by water under high pressure, then returned by canopy pipe and hole wall peripheral clearance, flows out from aperture, returns sedimentation basin precipitation and recycles and reuses; The effect of this part mud guarantees that drilling process is in flexible process all the time, thus decrease the frictional resistance in rig whole duct in drilling process, and the probability making rig affect the distribution of periphery resistance to shear of soil in drilling process reduces, and ensure that borehole accuracy;
2.4 to creep into, return adds pipe and whole hole: canopy pipe rotates and follows up under the drive of rig power, and one saves canopy pipe sets complete, and return adds pipe, until follow up to design attitude and whole hole;
3 slip castings
Slurries are by grouting pump, Grouting Pipe, be pressed in canopy pipe by cement paste, and canopy pipe slurries are filled rear cement paste and flowed out by drill bit, then return through annular gap, flow out from aperture, seal aperture, and then after-teeming 1-3 time of pressurizeing, underflow flows out stack and is as the criterion, and ensures clearance filled full.
The present invention is directed to special geologic condition; for protection exceptional structure, at construction face place, lay two tracks perpendicular on the level land of tunnel axis; for drilling machine platform walking and pipe canopy location, make not rely on guiding wall to carry out pipe roof construction with pipe bit machine and become a reality.
Beneficial effect of the present invention is as follows:
1 adopts water drilling technology to form mud off not only prevents hole wall collapse, decrease the frictional resistance in duct in drilling process simultaneously, drilling process is made to be in flexible process all the time, the probability causing rig to affect the distribution of periphery resistance to shear of soil in drilling process reduces, and the effect of mud off can ensure that the soil body of duct periphery can not saturated yielding on a large scale.
2 adopt pipe-following drilling technology, not only prevent duct to cave in and cause sedimentation, and set efficiency also raising (first pore-forming is intubate engineering method again, likely causes collapse hole, impacts to intubate, even causes serious sedimentation) greatly.Because canopy pipe is pipe canopy, be again drilling rod, form packed hole drilling, effectively retrain drill bit, reduce or prevent drilling tool deflection, ensure that the axiality of canopy pipe, ensure that the Drilling Precision of pipe canopy.
3 at construction face place, lay two guide rails perpendicular on the level land of tunnel axis, for the walking of rig moveable platform, rig is laid on a mobile platform, realize rig vertically and horizontal location by mobile platform, make not rely on guiding wall to carry out pipe roof construction with pipe bit machine and become a reality.
4 decrease constructing operation personnel, equipment, improve effect, shorten pipe canopy cycle period, ensure that the duration, reduce construction costs.
5, this method bury for an ultra shallow, the tunnel of big cross section, provide a kind of brand-new pipe shed construction method, the method not only easy construction in soil layer and the unstable geology of loose weak, and be more conducive to control surface settlement, safety is controlled.By the successful Application of this project, to the constructing tunnel of similar geological conditions, there is important directive significance.
Detailed description of the invention
Following non-limiting examples is for illustration of the present invention.
Embodiment
A kind of water drilling follow-up pipe shed construction method, at construction face place, two guide rails are laid perpendicular on the work-yard of tunnel axis, for drilling machine platform walking and pipe canopy location, in construction, pass through drilling machine platform, water drilling is adopted to form mud off packed hole drilling from tunnel's entrance and exit at a certain distance in framework outer, creep into while follow pipe construction, finally form leading pre-supporting, reach the rigidity and supporting capacity that improve stratum, the uneven normal distribution object of evenly distributed load, reduce surface settlement in follow-up framework digging process, guarantee cultural sight safety.
Specifically comprise the steps:
1) locate
1.1 preparations of construction: face build, personnel, facility, test and surveying work in place, reach requirements for starting construction;
1.2 smooth locations: mainly refer to smooth drilling machine construction place, for lower step operation provides work-yard;
1.3 lay track: at construction face place, lay two guide rails perpendicular on the work-yard of tunnel axis, for the walking of rig pylon, create conditions to later stage pipe canopy rig location, walking and construction;
1.4 drilling-machine shifter stage+module: install mobile platform on guide rail, platform is installed and human users for equipment;
1.5 rigs are installed and location: be fixed on platform by pipe canopy dedicated leveling rig, utilize the vernier device below drilling derrick vertically to locate, until meet designing requirement;
2) creep into
2.1 drill bits are selected and are connected: select drill bit according to stratum, and be connected with canopy pipe, rig by drill bit, namely drill bit and canopy pipe, canopy pipe and drill power head form sealed tube;
2.2 perforates: start rig, at a slow speed perforate, at the uniform velocity creep into, guarantee that its first pipe position meets design requirement;
2.3 mud offs: flushing liquor (i.e. water) is pumped into drill power head by slush pump, to canopy pipe steel pipe, to drill bit, finally penetrate from drill bit, impact soil layer, the rotary drilling under the dynamic action of rig of canopy pipe, the continuous cutting soil of drill bit, the flushing liquor (i.e. water) being cut into the powdery soil body and drill bit place is constantly stirred by rig power, a part forms mud off, prevent hole wall collapse, reduce earth's surface differential settlement, finally realize the object of canopy pipe evenly distributed load; Another part mud is continuously supplemented and dilution by water under high pressure, then returned by canopy pipe and hole wall peripheral clearance, flows out from aperture, returns sedimentation basin precipitation and recycles and reuses; The effect of this part mud guarantees that drilling process is in flexible process all the time, thus decrease the frictional resistance in rig whole duct in drilling process, and the probability making rig affect the distribution of periphery resistance to shear of soil in drilling process reduces, and ensure that borehole accuracy.
2.4 to creep into, return adds pipe and whole hole: canopy pipe rotates and follows up under the drive of rig power, and one saves canopy pipe sets complete, and return adds pipe, until follow up to design attitude and whole hole;
3 slip castings
Slurries are by grouting pump, Grouting Pipe, be pressed in canopy pipe by cement paste, and canopy pipe slurries are filled rear cement paste and flowed out by drill bit, then return through annular gap, flow out from aperture, seal aperture, and then after-teeming 1-3 time of pressurizeing, underflow flows out stack and is as the criterion, and ensures clearance filled full.
Adopt water drilling technology to form mud off and not only prevent hole wall collapse, decrease the frictional resistance in duct in drilling process simultaneously, drilling process is made to be in flexible process all the time, the probability causing rig to affect the distribution of periphery resistance to shear of soil in drilling process reduces, and the effect of mud off can ensure that the soil body of duct periphery can not saturated yielding on a large scale.
Adopt water drilling pipe-following drilling technology, not only prevent duct to cave in and cause sedimentation, and set efficiency also raising (first pore-forming is intubate engineering method again, likely causes collapse hole, impacts to intubate, even causes serious sedimentation) greatly.Because canopy pipe is pipe canopy, be again drilling rod, form packed hole drilling, effectively retrain drill bit, reduce or prevent drilling tool deflection, ensure that the axiality of canopy pipe, ensure that the Drilling Precision of pipe canopy.
At construction face place, lay two guide rails perpendicular on the level land of tunnel axis, for the walking of rig moveable platform, rig is laid on a mobile platform, realize rig vertically and horizontal location by mobile platform, make not rely on guiding wall to carry out pipe roof construction with pipe bit machine and become a reality.
The method reduces constructing operation personnel, equipment, improve effect, shorten pipe canopy cycle period, ensure that the duration, reduce construction costs, this method is buried for an ultra shallow, the tunnel of big cross section, provide a kind of brand-new pipe shed construction method, the method not only easy construction in soil layer and the unstable geology of loose weak, and be more conducive to control surface settlement, safety is controlled.By the successful Application of this project, to the constructing tunnel of similar geological conditions, there is important directive significance.

Claims (1)

1. a water drilling follow-up pipe shed construction method, is characterized in that: comprise the steps:
1) locate
1.1 preparations of construction: face build, personnel, facility, test and surveying work in place, reach requirements for starting construction;
1.2 smooth locations: refer to smooth drilling machine construction place, for lower step operation provides work-yard;
1.3 lay track: at construction face place, lay two guide rails perpendicular on the work-yard of tunnel axis, for the walking of rig pylon, create conditions to later stage pipe canopy rig location, walking and construction;
1.4 drilling-machine shifter stage+module: install mobile platform on guide rail, platform is installed and human users for equipment;
1.5 rigs are installed and location: be fixed on platform by pipe canopy dedicated leveling rig, utilize the vernier device below drilling derrick vertically to locate, until meet designing requirement;
2) creep into
2.1 drill bits are selected and are connected: select drill bit according to stratum, and be connected with canopy pipe, rig by drill bit, namely drill bit and canopy pipe, canopy pipe and drill power head form sealed tube;
2.2 perforates: start rig, at a slow speed perforate, at the uniform velocity creep into, guarantee that its first pipe position meets design requirement;
2.3 mud offs: water, drill power head is pumped into by slush pump, to canopy pipe steel pipe, to drill bit, finally penetrate from drill bit, impact soil layer, the rotary drilling under the dynamic action of rig of canopy pipe, the continuous cutting soil of drill bit, the powdery soil body be cut into and the water at drill bit place are constantly stirred by rig power, and a part forms mud off, another part mud is continuously supplemented and dilution by water under high pressure, then returned by canopy pipe and hole wall peripheral clearance, flow out from aperture, return sedimentation basin precipitation and recycle and reuse;
2.4 to creep into, return adds pipe and whole hole: canopy pipe rotates and follows up under the drive of rig power, and one saves canopy pipe has set
Finish, return adds pipe, until follow-up is to design attitude and whole hole;
3) slip casting
Slurries are by grouting pump, Grouting Pipe, be pressed in canopy pipe by cement paste, and canopy pipe slurries are filled rear cement paste and flowed out by drill bit, then return through annular gap, flow out from aperture, seal aperture, and then after-teeming 1-3 time of pressurizeing, underflow flows out stack and is as the criterion, and ensures clearance filled full.
CN201110410622.8A 2011-12-12 2011-12-12 Hydraulic drill follow-up pipe-shed construction method Active CN102562087B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110410622.8A CN102562087B (en) 2011-12-12 2011-12-12 Hydraulic drill follow-up pipe-shed construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110410622.8A CN102562087B (en) 2011-12-12 2011-12-12 Hydraulic drill follow-up pipe-shed construction method

Publications (2)

Publication Number Publication Date
CN102562087A CN102562087A (en) 2012-07-11
CN102562087B true CN102562087B (en) 2015-06-24

Family

ID=46408521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110410622.8A Active CN102562087B (en) 2011-12-12 2011-12-12 Hydraulic drill follow-up pipe-shed construction method

Country Status (1)

Country Link
CN (1) CN102562087B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107013221B (en) * 2017-05-26 2019-05-21 华东交通大学 Micro-disturbance pipe jacking construction method
CN107339114B (en) * 2017-06-08 2023-04-11 宁波市交通规划设计研究院有限公司 Mountain highway tunnel portal critical slope pre-balancing stable control structure and method
CN108825134B (en) * 2018-07-27 2024-07-16 深圳市市政设计研究院有限公司 Drill bit guiding system and arc-shaped long pipe shed construction method
CN109736823B (en) * 2018-11-30 2020-04-28 中铁十六局集团第一工程有限公司 Multi-working-face construction method for advanced large pipe shed of large-section tunnel
CN112198302B (en) * 2020-10-25 2022-12-16 中铁二局第一工程有限公司 Method and measuring tool for rapidly detecting mud content of fine aggregate
CN112696207A (en) * 2020-12-21 2021-04-23 中铁十局集团第七工程有限公司 Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel
CN113775294B (en) * 2021-11-09 2022-02-15 中国铁建重工集团股份有限公司 Follow-up pipe shed construction device and construction method while drilling

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06257376A (en) * 1993-03-05 1994-09-13 Fujita Corp Tunnel construction method and device therefor
EP0978626A1 (en) * 1998-08-04 2000-02-09 Beheersmaatschappij Verstraeten B.V. Method of constructing a tunnel lined with a tubing element
CN101691842A (en) * 2009-07-15 2010-04-07 中铁隧道股份有限公司 Three-arm hydraulic wagon drill and tunnel drilling and grouting construction method
CN101798931A (en) * 2010-03-12 2010-08-11 中铁隧道集团有限公司 Construction technology method of large-scale lead pipe roofs of tunnels and underground engineering without workshops

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06257376A (en) * 1993-03-05 1994-09-13 Fujita Corp Tunnel construction method and device therefor
EP0978626A1 (en) * 1998-08-04 2000-02-09 Beheersmaatschappij Verstraeten B.V. Method of constructing a tunnel lined with a tubing element
CN101691842A (en) * 2009-07-15 2010-04-07 中铁隧道股份有限公司 Three-arm hydraulic wagon drill and tunnel drilling and grouting construction method
CN101798931A (en) * 2010-03-12 2010-08-11 中铁隧道集团有限公司 Construction technology method of large-scale lead pipe roofs of tunnels and underground engineering without workshops

Also Published As

Publication number Publication date
CN102562087A (en) 2012-07-11

Similar Documents

Publication Publication Date Title
CN102562087B (en) Hydraulic drill follow-up pipe-shed construction method
CN100464055C (en) Construction method of shallow buried underground excavating tunnel super large section using PBA method
CN102966108B (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
US20120132424A1 (en) Method of drilling from a shaft for underground recovery of hydrocarbons
CN107059906A (en) A kind of method that utilization underground shaft robot applies major diameter open caisson
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN102748040B (en) Main structure for metro long-span station and pillar arching construction method thereof
CN103835661B (en) A kind of local excavation pre support mine shaft rising boring technique
CN105298507A (en) Underground pipe gallery construction method of machine performing open excavation on upper portion and tunneling on lower portion
CN203487528U (en) Underground river karst cave treatment structure for underwater pier drilled pile construction in beaded type karst area
CN103711492B (en) A kind of jacking-type cable sleeve channel construction method
CN104455726A (en) Pipe-jacking construction method for pipeline bottom grouting reinforcement
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN109736811A (en) A kind of vertical shaft machinery tunneling construction method
CN110259490B (en) Subway underground excavation station construction method
CN105696550A (en) Three axes agitating pile construction method capable of assisting in grooving of reinforced underground diaphragm wall
CN105909256A (en) Large-span weak surrounding rock tunnel construction method adopting face pre-reinforcement core soil reserving three-step temporary inverted arch technology
CN106121659A (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one
CN110055973A (en) Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time
CN102235010A (en) Treatment method for hanging sinking stop due to expansive soil in well sinking
CN105909265A (en) Heaving-prevention retrusive deep-hole grouting system and method for passing through existing shield tunnel
CN105256819A (en) Improving method for open caisson sinking construction in geology of sludge layer
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
US10267147B2 (en) Surface access borehole resource extraction method
CN110067561A (en) Under wear both wired Urban Underground mining sectbn construction methods

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160111

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING Co.,Ltd.

Address before: 610041, No. nine, No. 156, building B, high building, Xing Xing Road, Chengdu hi tech Zone, Sichuan

Patentee before: CHINA RAILWAY ERJU Co.,Ltd.

Patentee before: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20190123

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

Patentee after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

TR01 Transfer of patent right