CN112696207A - Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel - Google Patents

Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel Download PDF

Info

Publication number
CN112696207A
CN112696207A CN202011517136.1A CN202011517136A CN112696207A CN 112696207 A CN112696207 A CN 112696207A CN 202011517136 A CN202011517136 A CN 202011517136A CN 112696207 A CN112696207 A CN 112696207A
Authority
CN
China
Prior art keywords
pipe
drilling
grouting
pipe shed
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011517136.1A
Other languages
Chinese (zh)
Inventor
南勇
代永学
陈鹏
王涛
管军升
朱倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seventh Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
Seventh Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seventh Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical Seventh Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority to CN202011517136.1A priority Critical patent/CN112696207A/en
Publication of CN112696207A publication Critical patent/CN112696207A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a construction method of an overlong large pipe shed of a shallow-buried bias-pressure underground excavation tunnel, which comprises the following steps of: a: measurement and positioning: the concrete position of every pipe canopy is put out according to the design drawing, on-spot on the spot to the measurement group, adopts the cement nail to make accurate mark to marked obvious sign is done to the orifice position to the paint that is striking, numbers the pipe canopy position. The invention has the advantages of high pore-forming speed, simple and convenient operation, convenient control, high pore-forming speed, simple and convenient control, and safe, accurate and efficient pore-forming construction because the drilling rod is arranged by adopting a wired guide instrument to control the drilling direction, the drilling parameters can be fed back in real time, and the pipe shed pipe is arranged by using the wedge palm inclined plate guide drill bit to adjust the pipe shed pipe.

Description

Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel
Technical Field
The invention relates to the technical field of construction of an overlong large pipe shed of a tunnel, in particular to a construction method of an overlong large pipe shed of a shallow-buried bias subsurface tunnel.
Background
The overlength large pipe shed is simply called a large pipe shed which is a supporting form of a tunnel and is generally used for a tunnel opening section, because the covering layer of the tunnel opening section is shallow, the pipe shed technology can be used for strengthening and supporting the support and is used for reinforcing and supporting surrounding rocks so as to ensure safe tunnel entry and smooth tunneling, and the pipe shed technology is generally carried out simultaneously with grouting.
Local collapse easily appears in the super large and large pipe roof construction process drilling process in current tunnel, needs the propelling movement pipe after the drilling, and the pore-forming speed is slow, can not feed back drilling parameter in real time, and drilling accuracy is low, has certain potential safety hazard.
Disclosure of Invention
The invention aims to provide a construction method for a super-long large pipe shed of a shallow-buried bias subsurface tunnel, which has the advantages of one-step completion of drilling and pipe laying, controllable collapse of drilled holes, elimination of pushing pipes after drilling, higher hole forming speed, real-time feedback of drilling parameters, low drilling precision and high safety, and solves the problems that the existing construction process for the super-long large pipe shed of the tunnel is easy to cause local collapse in the drilling process, the pipes need to be pushed after drilling, the hole forming speed is low, the drilling parameters cannot be fed back in real time, the drilling precision is low and certain potential safety hazards exist.
In order to achieve the purpose, the invention provides the following technical scheme: the construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground excavation tunnel comprises the following steps:
a: measurement and positioning: the measuring group performs field lofting on the specific position of each pipe shed according to a design drawing, adopts a cement nail as an accurate mark, and uses striking paint to obviously mark the position of an orifice so as to number the positions of the pipe sheds;
b: setting up an operation platform: the drilling machine platform is erected by I-shaped steel I20a, the length of the platform is 9M, the height of the drilling machine platform is processed according to the actual size of a construction site, the step pitch is set to be 2M, square wood strips 8cm multiplied by 8cm in thickness are fully paved at the top of the drilling machine platform, the space between upright columns is 1.5M multiplied by 1.5M, the space between cross beams at the top of the upright columns is 1.5M, the space between longitudinal beams is 1.5M, the node connection of the I-shaped steel adopts 2 steel plates 0.36M multiplied by 0.22M multiplied by 0.01M to match with 4 bolts M20mm long by 70mm, the steel plates are welded with the I-shaped steel, the bottom of the upright columns is welded with the steel plates 0.36M multiplied by 0;
c: and (3) opening a pipe shed: before construction, a measurer carries out careful retesting on a position point of a lofted pipe shed, an error-out person needs to adjust and position a hole, a debugging angle is required to be charged by a specially-assigned person, retesting is carried out to ensure no error, the hole of the pipe shed is drilled at a low speed on a closed tunnel face by a geological water drill, the hole is drilled at a normal drilling speed after the drilling depth is 20cm, and high-pressure water is pumped into a power head of a drilling machine through a mud pump to jet out high-pressure water from a drill bit to impact a soil layer;
d: processing a pipe shed: processing a phi 108 multiplied by 8mm pipe shed by adopting a table type multipurpose drilling machine, considering the factors that adjacent steel pipe joints must be staggered and are limited by site construction conditions according to the length of the long pipe shed, wherein the length of a first lower pipe of an odd-number hole is 3m, the length of a middle section is 6m, the length of a last lower pipe is 3m, the length of an even-number hole is 6m at most, the length of a screw thread is 150mm, the screw thread is a spiral square wire with the diameter of 2mm, one end of a steel pipe is an inner wire, the other end of the steel pipe is an outer wire, and the processing end of the screw thread is right and;
e: positioning a drilling machine in place: the drilling machine is required to be coincided with a set lofting point, the position of the drilling machine must be accurately checked, and repeated adjustment is carried out by a method combining leveling, hanging and drill rod guiding, so that the axis of a drill rod of the drilling machine is ensured to be coincident with the axis of a pipe shed;
f: drilling: after the drilling machine is debugged, a drilling tool is installed for positioning and drilling, after the drilling is finished, a pipe shed steel pipe and a wired guide instrument are installed for drilling, the plane position, the direction and the external insertion angle of the hole are accurately measured, the construction angle is accurately determined by adopting a mutual detection method of a horizontal ruler and the guide instrument, each hole is numbered, the collapse of adjacent hole sites in the drilling process is not prevented, and construction of at least one hole site is carried out at intervals each time;
g: and (3) guiding control: the position of the drill bit is provided with a wire director signal rod, the drilling direction of the drill bit is changed by utilizing a wedge type drill bit capable of adjusting the direction according to the difference between the position and the direction of the drill bit in the drilling process and the design track, and the precision is controlled: in order to ensure the construction precision of the pipe shed, a wired guider is adopted to control the horizontal precision of a drill rod, a wedge palm inclined plate guide drill bit is used for adjusting the pipe shed pipe for construction, and a probe is arranged at the position of 200mm behind the guide drill bit for ensuring safe, accurate and efficient construction;
h: grouting: after the pipe shed is constructed, the orifice sealing device is adjusted, grouting is started from the orifice, grout adopts cement paste, the grout flows through the pipe shed and starts to flow back from the annular gap outside the pipe head steel pipe, air in the pipe is exhausted through the exhaust hole arranged on the orifice sealing device, after the grout flows out of the exhaust hole, the exhaust hole is closed, the grout is continuously poured, the grout is filled in the steel pipe and the surrounding gap, pressure maintaining measures are required for grouting, the annular gap is kept pressed against the one-way valve to be sealed with the switch water return valve and the orifice, and the pressure maintaining in the pipe shed is realized by the one-way valve and the orifice sealing.
Preferably, in the step B, in order to ensure the safety of the operation platform and the stability of the temporary inverted arch structure, a support system is arranged below the temporary inverted arch of the tunnel, and the setting requirement of the support system is the same as the platform reinforcing requirement.
Preferably, in the step C, under the drilling action of the drilling machine, the soil body continuously cut by the drill bit is continuously cut into a powdery soil body, and the powdery soil body is continuously stirred with the high-pressure water at the drill bit through the power of the drilling machine, a part of the soil body forms a slurry retaining wall to prevent the collapse of the hole wall and reduce the uneven settlement of the ground surface, so as to finally realize the purpose of uniform load of the pipe shed, the other part of the slurry continuously supplements and dilutes through the high-pressure water, flows out from the hole opening, returns to the sedimentation tank for sedimentation and recycling, and is discharged to the drilling tool to install the pipe shed.
Preferably, the position where the drilling machine is arranged in the step E is not less than 1m from the working surface, after the drilling machine is arranged, strict positioning and orientation are carried out according to the drilling requirement, and the parallel lines of the drilling rod extend and are fixed, so that the drilling guide effect of the drilling machine is achieved.
Preferably, during the drilling in the step F, a shed pipe steel pipe with the diameter of 108mm and the wall thickness of 8mm is directly used as a drill rod to form full-hole drilling and effectively restrain the drill bit, a wedge plate alloy drill bit with the diameter of 150mm is installed at the front end of the steel pipe, two small holes with the diameter of about 6mm are formed at the front end of the drill bit, a slurry pump fills the shed pipe with flushing liquid, then the flushing liquid is sprayed out through the small holes at high pressure, cutting and breaking the soil body, performing reparative cutting on the soil body during the rotary jacking process of the drill bit wedge-shaped plate to form a slurry retaining wall, forming a hole slightly larger than the pipe diameter on the soil body, forming slurry by stirring the in-situ layer residue soil and flushing fluid, allowing the slurry to flow out from a gap between the pipe wall and the soil body until the slurry flows to the hole opening, the circulating shed pipe continuously advances, the drill is drilled at intervals from bottom to top when drilling, the drill is kept at low speed and low pressure when the drill is started, and the pressure is properly applied after the hole is drilled for 2.0 m.
Preferably, in the step G, a special sensor is installed in the drill bit, the sensor is connected to a PLD display screen outside the drill bit through a wired cable, when the drilling rig drills in a uniform rotation, a drill rod track is substantially straight, the direction of the pilot drill bit in the construction process is controlled by information fed back by the display screen, and the pilot instrument system comprises a receiver and a probe which are in wired connection.
Preferably, the grouting slurry in the step H adopts cement slurry, and the grouting parameters are as follows: the water-cement ratio of cement paste is 1:1, the grouting pressure is 0.5-0.8 MPa, and grouting parameters are properly adjusted according to actual geological conditions and under the condition of meeting design requirements in construction.
Preferably, the grouting of the pipe roof in the step H follows the principle of 'first two sides and then middle, and from thin to thick', the grouting construction is started from two ends, the grouting is pushed towards the vault direction of the tunnel, the concentration of the grouting slurry is lower at the beginning, the grouting slurry is gradually thickened to the designed concentration, the water cement ratio of the cement slurry is 1:1, the mixing of the cement slurry is uniform, the cement slurry has good fluidity and viscosity, the mixing of the cement slurry is carried out strictly according to the designed mixing ratio, and the stirring work cannot be stopped until the grouting is finished.
Preferably, grouting of the pipe shed in the step H is carried out strictly according to the design pressure, the pressure is controlled to be 0.5-0.8 MPa, the pipeline smoothness and the mechanical operation condition are checked before grouting, the tunnel face is sealed before grouting to ensure that no grouting leaks in the grouting process, gaps between the steel pipe and the periphery are filled with the grouting, the grouting amount must meet the design requirements, the grouting sequence is that a hole is low firstly and a hole is high secondly, a water-free hole is firstly injected and a water hole is then injected, and the grouting is carried out symmetrically from two arch legs to the arch crown.
Compared with the prior art, the invention has the following beneficial effects:
1. according to the construction method, the pipe shed is used as a drill rod, drilling and pipe laying are completed at one time, so that the collapse of the drilled hole can be controlled, a pushing pipe after drilling is omitted, the hole forming speed is high, the operation is simple, and the control is convenient;
2. according to the invention, the drilling direction can be controlled by adopting the wired guide instrument to control the drilling rod, the drilling parameters can be fed back in real time, the wedge palm inclined plate is used for guiding the drill bit to adjust the pipe shed pipe for drilling, the safe, accurate and efficient construction of hole forming is ensured, and the guide instrument system comprises a receiving instrument and a probe rod which are in wired connection;
3. according to the invention, the rock mass ahead of the excavation is supported by the advancing large pipe shed, so that effective protection is formed for tunneling construction, the safety of tunneling construction is ensured, the construction speed is high, and the supporting effect is good.
Drawings
FIG. 1 is a process flow diagram of the pipe shed guiding pipe-following drilling method of the present invention;
FIG. 2 is a schematic diagram of a guiding deviation correcting system of the present invention;
FIG. 3 is a schematic representation of a pilot bit according to the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-3, the construction method of the ultra-long large pipe shed of the shallow-buried bias underground excavation tunnel comprises the following steps:
a: measurement and positioning: the measuring group performs field lofting on the specific position of each pipe shed according to a design drawing, adopts a cement nail as an accurate mark, and uses striking paint to obviously mark the position of an orifice so as to number the positions of the pipe sheds;
b: setting up an operation platform: the drilling machine platform is erected by I-shaped steel I20a, the length of the platform is 9M, the height of the drilling machine platform is processed according to the actual size of a construction site, the step pitch is set to be 2M, square wood strips 8cm multiplied by 8cm in thickness are fully paved at the top of the drilling machine platform, the space between upright columns is 1.5M multiplied by 1.5M, the space between cross beams at the top of the upright columns is 1.5M, the space between longitudinal beams is 1.5M, the node connection of the I-shaped steel adopts 2 steel plates 0.36M multiplied by 0.22M multiplied by 0.01M to match with 4 bolts M20mm long by 70mm, the steel plates are welded with the I-shaped steel, the bottom of the upright columns is welded with the steel plates 0.36M multiplied by 0;
c: and (3) opening a pipe shed: before construction, a measurer carries out careful retesting on a position point of a lofted pipe shed, an error-out person needs to adjust and position a hole, a debugging angle is required to be charged by a specially-assigned person, retesting is carried out to ensure no error, the hole of the pipe shed is drilled at a low speed on a closed tunnel face by a geological water drill, the hole is drilled at a normal drilling speed after the drilling depth is 20cm, and high-pressure water is pumped into a power head of a drilling machine through a mud pump to jet out high-pressure water from a drill bit to impact a soil layer;
d: processing a pipe shed: processing a phi 108 multiplied by 8mm pipe shed by adopting a table type multipurpose drilling machine, considering the factors that adjacent steel pipe joints must be staggered and are limited by site construction conditions according to the length of the long pipe shed, wherein the length of a first lower pipe of an odd-number hole is 3m, the length of a middle section is 6m, the length of a last lower pipe is 3m, the length of an even-number hole is 6m at most, the length of a screw thread is 150mm, the screw thread is a spiral square wire with the diameter of 2mm, one end of a steel pipe is an inner wire, the other end of the steel pipe is an outer wire, and the processing end of the screw thread is right and;
e: positioning a drilling machine in place: the drilling machine is required to be coincided with a set lofting point, the position of the drilling machine must be accurately checked, and repeated adjustment is carried out by a method combining leveling, hanging and drill rod guiding, so that the axis of a drill rod of the drilling machine is ensured to be coincident with the axis of a pipe shed;
f: drilling: after the drilling machine is debugged, a drilling tool is installed for positioning and drilling, after the drilling is finished, a pipe shed steel pipe and a wired guide instrument are installed for drilling, the plane position, the direction and the external insertion angle of the hole are accurately measured, the construction angle is accurately determined by adopting a mutual detection method of a horizontal ruler and the guide instrument, each hole is numbered, the collapse of adjacent hole sites in the drilling process is not prevented, and construction of at least one hole site is carried out at intervals each time;
g: and (3) guiding control: the position of the drill bit is provided with a wire director signal rod, the drilling direction of the drill bit is changed by utilizing a wedge type drill bit capable of adjusting the direction according to the difference between the position and the direction of the drill bit in the drilling process and the design track, and the precision is controlled: in order to ensure the construction precision of the pipe shed, a wired guider is adopted to control the horizontal precision of a drill rod, a wedge palm inclined plate guide drill bit is used for adjusting the pipe shed pipe for construction, and a probe is arranged at the position of 200mm behind the guide drill bit for ensuring safe, accurate and efficient construction;
h: grouting: after the pipe shed is constructed, the orifice sealing device is adjusted, grouting is started from the orifice, grout adopts cement paste, the grout flows through the pipe shed and starts to flow back from the annular gap outside the pipe head steel pipe, air in the pipe is exhausted through the exhaust hole arranged on the orifice sealing device, after the grout flows out of the exhaust hole, the exhaust hole is closed, the grout is continuously poured, the grout is filled in the steel pipe and the surrounding gap, pressure maintaining measures are required for grouting, the annular gap is kept pressed against the one-way valve to be sealed with the switch water return valve and the orifice, and the pressure maintaining in the pipe shed is realized by the one-way valve and the orifice sealing.
And B, in order to ensure the safety of the operation platform and the stability of the temporary inverted arch structure, a supporting system is arranged below the temporary inverted arch of the tunnel, and the setting requirement of the supporting system is the same as the platform reinforcing requirement.
And C, under the drilling action of a drilling machine, continuously cutting the soil body into a powdery soil body by the drill bit, continuously stirring the powdery soil body with high-pressure water at the drill bit by the power of the drilling machine, forming a part of the soil body into a slurry protective wall, preventing the collapse of the hole wall, reducing the uneven settlement of the ground surface, and finally realizing the purpose of uniform load of the pipe shed, continuously supplementing and diluting the other part of the slurry by the high-pressure water, flowing out of the hole, returning to a sedimentation tank for sedimentation and recycling, and unloading the drilling tool to install a pipe shed steel pipe for drilling after drilling for 1.5 m.
And E, the position where the drilling machine is arranged is preferably not less than 1m away from the working surface, after the drilling machine is arranged, strict positioning and orientation are carried out according to the drilling requirement, and the parallel lines of the drilling rod are extended and fixed to achieve the guiding effect of drilling by the drilling machine.
And F, directly using a box pipe steel pipe with the diameter of 108mm and the wall thickness of 8mm as a drill rod during drilling to form full-hole drilling and effectively restrain the drill bit, installing a wedge plate alloy drill bit with the diameter of 150mm at the front end of the steel pipe, wherein two small holes with the diameter of about 6mm are formed at the front end of the drill bit, filling the box pipe with washing liquid by a slurry pump, spraying the washing liquid at high pressure through the small holes to cut and break the soil body, performing reparative cutting on the soil body during the rotating jacking process of the wedge plate of the drill bit to form a slurry protection wall, forming a hole slightly larger than the diameter of the soil body by the soil body, stirring the residue soil in the original layer with the washing liquid to form slurry, enabling the slurry to flow out from the gap between the pipe wall and the soil body until the slurry flows to the hole opening, continuously advancing the box pipe, drilling from bottom to top, drilling at a separation hole, keeping low speed and.
And G, a special sensor is arranged in the drill bit and is connected with the PLD display screen outside the pipe through a wired cable, when the drilling machine drills in a constant-speed rotating mode, the track of the drill rod is basically straight, the direction of the guide drill bit in the construction process is controlled by information fed back by the display screen, and the guide instrument system comprises a receiving instrument and a probe which are in wired connection.
And (H) adopting cement slurry for grouting in the step (H), wherein the grouting parameters are as follows: the water-cement ratio of cement paste is 1:1, the grouting pressure is 0.5-0.8 MPa, and grouting parameters are properly adjusted according to actual geological conditions and under the condition of meeting design requirements in construction.
And H, grouting the pipe shed in the step H according to the principle that two sides are arranged in sequence and the slurry is concentrated from thin to thick, the grouting construction is started from two ends and is pushed towards the vault of the tunnel, the concentration of the slurry for grouting is a little bit at the beginning, the slurry is gradually concentrated to the designed concentration, the water-cement ratio of the cement slurry is 1:1, the slurry is uniformly mixed, the slurry has good fluidity and viscosity, the mixing of the cement slurry is carried out strictly according to the designed mixing ratio, and the stirring work cannot be stopped until the grouting is finished.
And H, grouting the pipe shed in the step H, strictly performing grouting according to the design pressure, controlling the pressure to be 0.5-0.8 MPa, checking the smooth pipeline and mechanical operation condition before grouting, sealing the tunnel face before grouting to ensure that no slurry leaks in the grouting process, filling the gaps between the steel pipe and the periphery with the grouting amount which must meet the design requirement, wherein the grouting sequence is that a low hole is firstly formed and a high hole is formed, a water-free hole is firstly filled and a water hole is then filled, and the grouting is performed symmetrically from two arch legs to the arch crown.
Follow-up with the drill bit is carried out during drilling, a phi 108 sectional seamless steel pipe with the wall thickness of 8mm is adopted, threaded mantle wires are adopted for connection, seams are fully welded, the length of a thread section of the threaded nipple is 150mm, the drill rod is prohibited from rotating during drilling, the drill bit and the drill rod are prevented from being disconnected, the drill drop phenomenon is avoided, in order to prevent underground water and soil loss and control settlement, a drilling principle of medium and small water quantity, low rotating speed, medium and low pressure and rapid feeding is adopted during construction of a pipe shed, the pump pressure is controlled to be 0.4-0.8 MPa during drilling, the pump quantity is preferably 20-50L/min, the medium and low pressure is kept, the medium and low pressure and medium speed drilling are carried out, an orifice return valve is installed at an orifice after the pipe shed is drilled, the water pressure is controlled, the return water quantity in the hole during drilling is ensured to be: and each time a section of pipe shed is followed, a guide instrument is required to be used for checking the construction angle, and if deflection is found, a wedge-shaped drill bit is immediately used for correcting the angle.
The position and the direction of the drill bit under the ground can be accurately measured in the drilling process, and the drilling direction of the drill bit is changed by using the drill bit (generally a wedge-shaped drill bit) with the direction being adjustable at any time according to the difference between the position and the direction of the drill bit and the design track in the drilling process, so that the pipe shed is arranged according to the design requirement.
The probe is internally provided with a special sensor which is directly powered by 15V direct current, and the display screen displays the inclination angle (horizontal angle) and the facing angle (the direction of the guide plate, namely the guide plate is upward and is 12 o' clock face) of the drill bit.
If the drilling angle is set to be lower, the drill bit can be adjusted to 12 points, namely the guide plate faces upwards and is directly jacked, at the moment, due to the fact that the inclined surface area of the guide plate bottom plate is large, an upward force is applied, the track of the drill bit moves upwards, meanwhile, the deviation rectification at 6 points enables the track of the drill bit to face downwards, 9 points and 3 points are respectively in left and right deviation rectification directions, if the angle is proper, the drilling machine can drill at a constant speed in a rotating mode, at the moment, the track of the drill rod is generally straight, and the deviation of a final hole can be controlled within 5 per thousand.
In summary, the following steps: according to the construction method of the overlength large pipe shed of the shallow-buried bias-pressure underground excavation tunnel, peripheral surrounding rocks outside an arch excavation line are enabled to form a reinforced protection ring in advance through pipe shed grouting, ideal excavation conditions are created through the protection ring, a continuous pipe shed rod body is used for supporting in an unearthed rock body to form a whole joist, the load transmitted to a primary support by the surrounding rocks is reduced, the main pressure of the damaged surrounding rocks after excavation is transferred to the peripheral grouting reinforced surrounding rocks under the combined supporting action of continuous large pipe shed supporting, radial anchor rod grouting and the like, the tunnel supporting is enabled to bear a small amount of surrounding rock pressure, the combined action of the supporting and the surrounding rocks is fully exerted to support so as to maintain the stability of the supporting, and the safety of tunneling construction and primary supporting is effectively guaranteed.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (9)

1. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground excavation tunnel is characterized by comprising the following steps of:
a: measurement and positioning: the measuring group performs field lofting on the specific position of each pipe shed according to a design drawing, adopts a cement nail as an accurate mark, and uses striking paint to obviously mark the position of an orifice so as to number the positions of the pipe sheds;
b: setting up an operation platform: the drilling machine platform is erected by I-shaped steel I20a, the length of the platform is 9M, the height of the drilling machine platform is processed according to the actual size of a construction site, the step pitch is set to be 2M, square wood strips 8cm multiplied by 8cm in thickness are fully paved at the top of the drilling machine platform, the space between upright columns is 1.5M multiplied by 1.5M, the space between cross beams at the top of the upright columns is 1.5M, the space between longitudinal beams is 1.5M, the node connection of the I-shaped steel adopts 2 steel plates 0.36M multiplied by 0.22M multiplied by 0.01M to match with 4 bolts M20mm long by 70mm, the steel plates are welded with the I-shaped steel, the bottom of the upright columns is welded with the steel plates 0.36M multiplied by 0;
c: and (3) opening a pipe shed: before construction, a measurer carries out careful retesting on a position point of a lofted pipe shed, an error-out person needs to adjust and position a hole, a debugging angle is required to be charged by a specially-assigned person, retesting is carried out to ensure no error, the hole of the pipe shed is drilled at a low speed on a closed tunnel face by a geological water drill, the hole is drilled at a normal drilling speed after the drilling depth is 20cm, and high-pressure water is pumped into a power head of a drilling machine through a mud pump to jet out high-pressure water from a drill bit to impact a soil layer;
d: processing a pipe shed: processing a phi 108 multiplied by 8mm pipe shed by adopting a table type multipurpose drilling machine, considering the factors that adjacent steel pipe joints must be staggered and are limited by site construction conditions according to the length of the long pipe shed, wherein the length of a first lower pipe of an odd-number hole is 3m, the length of a middle section is 6m, the length of a last lower pipe is 3m, the length of an even-number hole is 6m at most, the length of a screw thread is 150mm, the screw thread is a spiral square wire with the diameter of 2mm, one end of a steel pipe is an inner wire, the other end of the steel pipe is an outer wire, and the processing end of the screw thread is right and;
e: positioning a drilling machine in place: the drilling machine is required to be coincided with a set lofting point, the position of the drilling machine must be accurately checked, and repeated adjustment is carried out by a method combining leveling, hanging and drill rod guiding, so that the axis of a drill rod of the drilling machine is ensured to be coincident with the axis of a pipe shed;
f: drilling: after the drilling machine is debugged, a drilling tool is installed for positioning and drilling, after the drilling is finished, a pipe shed steel pipe and a wired guide instrument are installed for drilling, the plane position, the direction and the external insertion angle of the hole are accurately measured, the construction angle is accurately determined by adopting a mutual detection method of a horizontal ruler and the guide instrument, each hole is numbered, the collapse of adjacent hole sites in the drilling process is not prevented, and construction of at least one hole site is carried out at intervals each time;
g: and (3) guiding control: the position of the drill bit is provided with a wire director signal rod, the drilling direction of the drill bit is changed by utilizing a wedge type drill bit capable of adjusting the direction according to the difference between the position and the direction of the drill bit in the drilling process and the design track, and the precision is controlled: in order to ensure the construction precision of the pipe shed, a wired guider is adopted to control the horizontal precision of a drill rod, a wedge palm inclined plate guide drill bit is used for adjusting the pipe shed pipe for construction, and a probe is arranged at the position of 200mm behind the guide drill bit for ensuring safe, accurate and efficient construction;
h: grouting: after the pipe shed is constructed, the orifice sealing device is adjusted, grouting is started from the orifice, grout adopts cement paste, the grout flows through the pipe shed and starts to flow back from the annular gap outside the pipe head steel pipe, air in the pipe is exhausted through the exhaust hole arranged on the orifice sealing device, after the grout flows out of the exhaust hole, the exhaust hole is closed, the grout is continuously poured, the grout is filled in the steel pipe and the surrounding gap, pressure maintaining measures are required for grouting, the annular gap is kept pressed against the one-way valve to be sealed with the switch water return valve and the orifice, and the pressure maintaining in the pipe shed is realized by the one-way valve and the orifice sealing.
2. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground-excavated tunnel according to claim 1, characterized in that: and B, in order to ensure the safety of the operation platform and the stability of the temporary inverted arch structure, a supporting system is arranged below the temporary inverted arch of the tunnel, and the setting requirement of the supporting system is the same as the platform reinforcing requirement.
3. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground-excavated tunnel according to claim 1, characterized in that: and C, under the drilling action of the drilling machine, continuously cutting the soil body into a powdery soil body by the drill bit, continuously stirring the powdery soil body and high-pressure water at the drill bit by the power of the drilling machine, forming a part of the soil body into a slurry protective wall, preventing the collapse of the hole wall, reducing the uneven settlement of the ground surface, and finally realizing the purpose of uniform load of the pipe shed, continuously supplementing and diluting the other part of the slurry by the high-pressure water, flowing out of the hole, returning to the sedimentation tank for sedimentation and recycling, and unloading the drilling tool to install the pipe shed steel pipe for drilling after drilling for 1.5 m.
4. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground-excavated tunnel according to claim 1, characterized in that: and E, preferably, the position of the drilling machine arranged in the step E is not less than 1m away from the working surface, and after the drilling machine is arranged, strict positioning and orientation are carried out according to the drilling requirement, so that the parallel lines of the drilling rod are extended and fixed to achieve the drilling guide effect of the drilling machine.
5. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground-excavated tunnel according to claim 1, characterized in that: and F, directly using a box pipe steel pipe with the diameter of 108mm and the wall thickness of 8mm as a drill rod during drilling to form full-hole drilling and effectively restrain the drill bit, installing a wedge plate alloy drill bit with the diameter of 150mm at the front end of the steel pipe, wherein two small holes with the diameter of about 6mm are formed at the front end of the drill bit, filling the box pipe with washing liquid by a slurry pump, spraying the washing liquid at high pressure through the small holes to cut and break the soil body, performing rotary jacking on the wedge plate of the drill bit to simultaneously perform cutting on the soil body to form a slurry protection wall, forming a hole slightly larger than the pipe diameter on the soil body, stirring the residue soil in the original layer with the washing liquid to form slurry, allowing the slurry to flow out from a gap between the pipe wall and the soil body until the slurry flows to the hole opening, so that the box pipe continuously moves forwards, drilling from bottom to top to the hole to separate the hole for drilling, maintaining low speed and.
6. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground-excavated tunnel according to claim 1, characterized in that: and G, a special sensor is arranged in the drill bit, the sensor is connected with the PLD display screen outside the pipe through a wired cable, when the drilling machine drills in a constant-speed rotating mode, the track of the drill rod is basically straight, the direction of the guide drill bit in the construction process is controlled by information fed back by the display screen, and the guide instrument system comprises a receiving instrument and a probe which are in wired connection.
7. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground-excavated tunnel according to claim 1, characterized in that: and (E) adopting cement slurry for grouting in the step H, wherein the grouting parameters are as follows: the water-cement ratio of cement paste is 1:1, the grouting pressure is 0.5-0.8 MPa, and grouting parameters are properly adjusted according to actual geological conditions and under the condition of meeting design requirements in construction.
8. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground-excavated tunnel according to claim 1, characterized in that: and H, grouting the pipe shed in the step H according to the principle that two sides are arranged in sequence, the middle is arranged in sequence, and the grouting construction is started from two ends and is propelled towards the vault of the tunnel, the concentration of the grouting slurry is lower at the beginning and is gradually thickened to the designed concentration, the water-cement ratio of the cement slurry is 1:1, the slurry is uniformly mixed, the fluidity and the viscosity are good, the mixing of the cement slurry is carried out strictly according to the designed mixing ratio, and the stirring work cannot be stopped until the grouting is finished.
9. The construction method of the overlong large pipe shed of the shallow-buried bias-pressure underground-excavated tunnel according to claim 1, characterized in that: grouting and grouting for the pipe shed in the step H are carried out strictly according to the design pressure, the pressure is controlled to be 0.5-0.8 MPa, the pipeline smoothness and the mechanical operation condition are checked before grouting, the tunnel face is closed before grouting to ensure that no grouting leaks in the grouting process, the steel pipe and surrounding gaps need to be filled with grouting, the grouting amount needs to meet the design requirements, the grouting sequence is that low holes are arranged firstly and high holes are arranged secondly, water holes are arranged firstly and water holes are arranged secondly, and the grouting is carried out symmetrically from two arch legs to the arch crown.
CN202011517136.1A 2020-12-21 2020-12-21 Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel Pending CN112696207A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011517136.1A CN112696207A (en) 2020-12-21 2020-12-21 Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011517136.1A CN112696207A (en) 2020-12-21 2020-12-21 Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel

Publications (1)

Publication Number Publication Date
CN112696207A true CN112696207A (en) 2021-04-23

Family

ID=75509223

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011517136.1A Pending CN112696207A (en) 2020-12-21 2020-12-21 Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel

Country Status (1)

Country Link
CN (1) CN112696207A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113187499A (en) * 2021-05-13 2021-07-30 中铁十六局集团第二工程有限公司 Weathering alteration belt TBM card machine escaping method
CN114658449A (en) * 2022-04-29 2022-06-24 中国一冶集团有限公司 Tunnel underground excavation pipe shed guide pipe drilling construction precision control method
CN117779841A (en) * 2023-12-29 2024-03-29 中交城乡建设规划设计研究院有限公司 Anti-slip pipe shed support road base protection method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5072656A (en) * 1991-02-12 1991-12-17 Nabors Industries, Inc. Method and apparatus for controlling the transfer of tubular members into a shelter
JP2008111227A (en) * 2006-10-27 2008-05-15 Taisei Corp Construction method and connection structure of multiple tunnel and connection structure of tunnel and pipe roof forming multiple tunnel
CN101260784A (en) * 2008-04-23 2008-09-10 北京首尔工程技术有限公司 Tunnel advanced support air circulated drilling construction method and drilling tool
CN101798930A (en) * 2010-03-24 2010-08-11 中铁十二局集团有限公司 Rapid construction method of high-pressure water-rich fault zone of tunnel
CN102562087A (en) * 2011-12-12 2012-07-11 中铁二局股份有限公司 Hydraulic drill follow-up pipe-shed construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5072656A (en) * 1991-02-12 1991-12-17 Nabors Industries, Inc. Method and apparatus for controlling the transfer of tubular members into a shelter
JP2008111227A (en) * 2006-10-27 2008-05-15 Taisei Corp Construction method and connection structure of multiple tunnel and connection structure of tunnel and pipe roof forming multiple tunnel
CN101260784A (en) * 2008-04-23 2008-09-10 北京首尔工程技术有限公司 Tunnel advanced support air circulated drilling construction method and drilling tool
CN101798930A (en) * 2010-03-24 2010-08-11 中铁十二局集团有限公司 Rapid construction method of high-pressure water-rich fault zone of tunnel
CN102562087A (en) * 2011-12-12 2012-07-11 中铁二局股份有限公司 Hydraulic drill follow-up pipe-shed construction method

Non-Patent Citations (9)

* Cited by examiner, † Cited by third party
Title
姜昌银: "公路隧道洞内超前管棚支护施工技术", 《中国新技术新产品》 *
宋连东: "浅议超长大管棚施工技术在黄土隧道中的应用", 《石家庄铁路职业技术学院学报》 *
张元凯: "Ⅰ级风险隧道公跨隧管棚施工技术", 《知识经济》 *
张瑞明: "高原不良地质隧道进洞施工技术", 《西藏科技》 *
杨文平等: "大管棚法处理隧道下穿公路的施工技术", 《四川建筑》 *
梁斌琦: "定向钻进指引系统在长大管棚施工中的应用", 《价值工程》 *
王辉: "超前大管棚支护技术在恩施大峡谷旅游公路木槽岩隧道中的应用", 《中国高新技术企业》 *
田兵: "马来西亚浅埋暗挖隧道下穿城市主干道施工技术研究", 《价值工程》 *
陈立龙: "曲线地段超长大管棚施工工艺探讨", 《中国工程咨询》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113187499A (en) * 2021-05-13 2021-07-30 中铁十六局集团第二工程有限公司 Weathering alteration belt TBM card machine escaping method
CN114658449A (en) * 2022-04-29 2022-06-24 中国一冶集团有限公司 Tunnel underground excavation pipe shed guide pipe drilling construction precision control method
CN117779841A (en) * 2023-12-29 2024-03-29 中交城乡建设规划设计研究院有限公司 Anti-slip pipe shed support road base protection method

Similar Documents

Publication Publication Date Title
CN112696207A (en) Construction method of overlong large pipe shed of shallow-buried bias-pressure underground excavation tunnel
CN108661655B (en) Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine
CN102943466B (en) Construction method for miniature steel pipe concrete pile to penetrate through roadbed layer for reinforcing soft foundation construction
CN109595004B (en) Tunnel two-expansion four-expansion excavation method
CN101737012B (en) Drilling bit for guiding horizontal roatatably-jetting construction and construction method thereof
CN103306687A (en) Construction method for deformation control via horizontal whirling jet grouting of long cantilever in soft-rock tunnel
CN101503961A (en) Use method of underground obstacles blasting in shield-tunneling construction
CN111577136A (en) High-pressure jet grouting pile hole guiding construction integrated device and construction method thereof
CN110130901A (en) On across both wired Urban Underground mining sectbn construction methods
CN110344842A (en) Main traffic road pipe curtain construction is worn under Subway tunnel
CN105951749A (en) Construction method for reinforcement treatment of soft foundation steel pipe pile in confined space
CN106437796B (en) A kind of lithostratigraphy shield tunnel end ruggedized construction and reinforcement means
CN109596112B (en) Measuring method for controlling long-distance construction of large-diameter shield tunneling machine to smoothly go out of tunnel
CN108487924A (en) A kind of reinforcement means of soft coal level gob side entry driving thin coal pillar
CN212671560U (en) High-pressure jet grouting pile hole guiding construction integrated device
CN105019917A (en) Impact drilling type advanced jet grouting pipe shed construction device and construction method
CN116335679B (en) Pipe curtain support and horizontal jet grouting pile combined closed loop advanced support method
CN112252310A (en) Method for deep foundation pit waterproof curtain construction by adopting high-pressure jet grouting pile machine
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN204920977U (en) Spray tube canopy construction equipment is revolved in advance to percussion drilling formula
LU102928B1 (en) Pipe jacking construction method for crossing mixed gravel layer and sandstone layer
CN115681613A (en) Pipe jacking construction method for silt silty clay layer construction
CN201554375U (en) Guide horizontal jet grouting construction drill bit
CN103615265A (en) Horizontal whirl spraying construction method of soft rock tunnel
CN208039234U (en) A kind of engineering pile in solution cavity geology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210423

RJ01 Rejection of invention patent application after publication