CN102561521A - 螺栓偏差纠偏方法 - Google Patents

螺栓偏差纠偏方法 Download PDF

Info

Publication number
CN102561521A
CN102561521A CN2010105871814A CN201010587181A CN102561521A CN 102561521 A CN102561521 A CN 102561521A CN 2010105871814 A CN2010105871814 A CN 2010105871814A CN 201010587181 A CN201010587181 A CN 201010587181A CN 102561521 A CN102561521 A CN 102561521A
Authority
CN
China
Prior art keywords
bolt
concrete foundation
embedded bolt
existing concrete
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105871814A
Other languages
English (en)
Inventor
余祥兴
郑莆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN2010105871814A priority Critical patent/CN102561521A/zh
Publication of CN102561521A publication Critical patent/CN102561521A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明公开了一种已有预埋螺栓因预埋和安装过程中出现偏差的纠偏方法,它包括以下施工步骤:(a)在已有混凝土基础(1)上将偏移螺栓头(3)切割掉;(b)将已有混凝土基础(1)在预埋螺栓下段(4)周边的混凝土块(5)敲掉;并再次切割预埋螺栓下段(4)的顶部,使预埋螺栓下段(4)的顶部低于已有混凝土基础(1)顶部;(c)将正常螺纹杆头(6)和预埋螺栓下段(4)焊接,使焊接接头(7)低于混凝土基础(1)顶部。本发明具有施工简单,受力合理的优点,使加固结构工作状态更符合实际受力状况,保证安装设备运行安全可靠。

Description

螺栓偏差纠偏方法
技术领域
本发明涉及一种预埋螺栓因预埋和安装过程中出现偏差时的纠偏方法。
背景技术
在建筑钢结构柱安装或设备基础安装过程中,钢柱和设备基础对预埋螺栓的安装精度要求较高,且在安装过程中常常因为种种不可控制因素使柱或设备基础压弯预埋安装螺栓,或预埋过程中因施工等多种因素影响造成预埋螺栓与安装要求存在较大偏差。螺栓作为主要的承受拉力和剪力及限制位移构件,如果由于以上原因产生的偏差,目前采用的纠偏方法如下:
(1)、现在的处理方法常常是将螺栓用外力敲击使之视觉上满足要求,但实际上由于在外力敲击过程中常常破坏螺栓的螺纹,致使安装出现问题;或外力作用下螺栓反复修正而致使螺栓弯曲过大而疲劳,致使螺栓报废,且在较大外力作用下致使砼基础顶出现裂纹从而影响工程质量。
(2)、另一种处理方法是将螺栓上部弯曲部分切割掉,然后采用电渣压力焊或气压焊等方式将原螺栓下部与新螺栓焊接,待焊接完毕再用机械将螺栓连接鼓头部分将螺纹车出来,这将出现问题是焊接鼓头(直径增加)处本应加强处理,但因螺纹处理及设备预留洞过小,从而影响设备运行安全或设备安装,浪费时间,且由于操作空间的限制致使加工不便。
发明内容
本发明要解决的技术问题是:提供一种螺栓偏差纠偏方法,该方法施工简单、能迅速提高施工速度、工作可靠、不影响安装,以克服现有技术存在的破坏螺栓的螺纹,致使安装出现问题,或在较大外力作用下致使砼基础顶出现裂纹从而影响工程质量等不足。
本发明采用以下技术方案:它包括以下施工步骤:
(a)在已有混凝土基础1上将偏移螺栓头3切割掉;
(b)将已有混凝土基础1在预埋螺栓下段4周边的混凝土块5敲掉;并再次切割预埋螺栓下段4的顶部,使预埋螺栓下段4的顶部低于已有混凝土基础1顶部;
(c)将正常螺纹杆头6和预埋螺栓下段4焊接,使焊接接头7低于混凝土基础1顶部。纠偏步骤结束。
本发明通过设备将已有混凝土基础顶部螺栓弯曲部分切割掉,然后将螺栓切割处混凝土周围敲打开适当深度,将正常螺纹杆头与预埋螺栓下段焊接,焊接鼓出部分不影响螺栓功用与设备的安装,同时由于新焊接部分有螺纹,不需要在现场二次加工螺纹;同时由于设备基础安装完毕后需要二次浇注灌浆,因此螺栓基础敲开部分不需要修复工序及时间,达到受力合理,工期节约的目的。
附图说明
图1为混凝土基础顶正常预埋螺栓和产生偏移螺栓示意图;
图2为本发明示意图。
图中,1为已有混凝土基础,2为正常预埋螺栓,3为偏移螺栓头,4为预埋螺栓下段;5为切割偏移螺栓头3后的预埋螺栓下段4周边的混凝土块,6为正常螺纹螺杆头,7为焊接接头。
具体实施方式
本发明的实施实例:如图1所示:在已有混凝土基础1上有正常预埋螺栓2和安装过程中出现的偏移螺栓头3;需要对该偏移螺栓进行纠偏时,其步骤如下:
(a)在已有混凝土基础1上将偏移螺栓头3切割掉;
(b)将已有混凝土基础1在预埋螺栓下段4周边的混凝土块5敲掉;并再次切割预埋螺栓下段4的顶部,使预埋螺栓下段4的顶部低于已有混凝土基础1顶部;
(c)将正常螺纹杆头6和预埋螺栓下段4焊接,使焊接接头7低于混凝土基础1顶部。纠偏步骤结束。
上述步骤中,使焊接接头7低于混凝土基础1顶部,即是解决焊接接头7标高处不影响安装和不削弱螺栓强度等问题。

Claims (1)

1.一种螺栓偏差纠偏方法,其特征在于:它包括以下施工步骤:
(a)在已有混凝土基础(1)上将偏移螺栓头(3)切割掉;
(b)将已有混凝土基础(1)在预埋螺栓下段(4)周边的混凝土块(5)敲掉;并再次切割预埋螺栓下段(4)的顶部,使预埋螺栓下段(4)的顶部低于已有混凝土基础(1)顶部;
(c)将正常螺纹杆头(6)和预埋螺栓下段(4)焊接,使焊接接头(7)低于混凝土基础(1)顶部。
CN2010105871814A 2010-12-14 2010-12-14 螺栓偏差纠偏方法 Pending CN102561521A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105871814A CN102561521A (zh) 2010-12-14 2010-12-14 螺栓偏差纠偏方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105871814A CN102561521A (zh) 2010-12-14 2010-12-14 螺栓偏差纠偏方法

Publications (1)

Publication Number Publication Date
CN102561521A true CN102561521A (zh) 2012-07-11

Family

ID=46407996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105871814A Pending CN102561521A (zh) 2010-12-14 2010-12-14 螺栓偏差纠偏方法

Country Status (1)

Country Link
CN (1) CN102561521A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162292A (zh) * 2018-10-15 2019-01-08 中车长春轨道客车股份有限公司 预埋工字梁位置偏差的补救工艺
CN113084448A (zh) * 2021-04-15 2021-07-09 中铁十一局集团第三工程有限公司 一种火箭撬滑轨扣件快速修复方法
CN114277931A (zh) * 2022-01-07 2022-04-05 浙江西子联合工程有限公司 钢柱脚节点现场纠偏的方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4106035B2 (ja) * 2004-02-18 2008-06-25 財団法人電力中央研究所 鉄筋コンクリート製ブロックの接合方法
CN101550703A (zh) * 2009-05-06 2009-10-07 中国水电顾问集团西北勘测设计研究院 钢筋混凝土基础或桩承台的设计方法
WO2010019050A1 (en) * 2008-08-14 2010-02-18 Dr. Techn. Olav Olsen As Foundation for an offshore wind turbine generator and method of constructing and installing the foundation
CN201581501U (zh) * 2010-01-15 2010-09-15 赵正义 塔式结构与砼基础的定位连接构造

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4106035B2 (ja) * 2004-02-18 2008-06-25 財団法人電力中央研究所 鉄筋コンクリート製ブロックの接合方法
WO2010019050A1 (en) * 2008-08-14 2010-02-18 Dr. Techn. Olav Olsen As Foundation for an offshore wind turbine generator and method of constructing and installing the foundation
CN101550703A (zh) * 2009-05-06 2009-10-07 中国水电顾问集团西北勘测设计研究院 钢筋混凝土基础或桩承台的设计方法
CN201581501U (zh) * 2010-01-15 2010-09-15 赵正义 塔式结构与砼基础的定位连接构造

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
林丁未: "浅析工业设备地脚螺栓安装技术", 《科技信息(科学教研)》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162292A (zh) * 2018-10-15 2019-01-08 中车长春轨道客车股份有限公司 预埋工字梁位置偏差的补救工艺
CN113084448A (zh) * 2021-04-15 2021-07-09 中铁十一局集团第三工程有限公司 一种火箭撬滑轨扣件快速修复方法
CN113084448B (zh) * 2021-04-15 2023-02-24 中铁十一局集团第三工程有限公司 一种火箭撬滑轨扣件快速修复方法
CN114277931A (zh) * 2022-01-07 2022-04-05 浙江西子联合工程有限公司 钢柱脚节点现场纠偏的方法
CN114277931B (zh) * 2022-01-07 2024-01-02 浙江西子联合工程有限公司 钢柱脚节点现场纠偏的方法

Similar Documents

Publication Publication Date Title
CN103422512B (zh) 可更换预埋螺栓式风机组混凝土基础及其施工方法
CN203270599U (zh) 一种地脚螺栓预埋模具
CN108824431B (zh) 超灌桩头处理施工方法
CN102704667A (zh) 一种脚手架预埋装配式连墙装置
CN102021908A (zh) 一种用于预制方桩接桩的机械连接结构及施工方法
CN102561521A (zh) 螺栓偏差纠偏方法
CN102808635B (zh) 一种胀壳式内锚头预应力锚杆及其安装使用方法
CN103806446B (zh) 一种内撑扩张型锚杆
CN201486579U (zh) 一种钻凿锚杆孔定位装置
CN103628898B (zh) 一种用于防止巷道底鼓的连续墙支护方法
CN107964978B (zh) 风力发电机基础锚栓加固结构及基础锚栓断裂加固方法
CN106320529A (zh) 一种可回收再利用格构柱与楼板的连接系统及施工方法
CN204112379U (zh) 支护桩体内测斜管护筒
CN102477799A (zh) 砌体结构整体性加固方法
CN104805830B (zh) 非爆破岩石抗拔桩施工方法
CN103334433B (zh) 一种拔桩的施工方法
CN203856491U (zh) 组合式锚杆结构
CN204001665U (zh) 一种脚手架装配式连墙件
CN206220114U (zh) 一种八桩高桩承台基础
CN207092104U (zh) 一种钢管桩连接结构
CN105160188B (zh) 一种确定临近陷落柱破碎巷道支护长度的方法
CN204577154U (zh) 一种监测电缆防破坏装置
CN204282394U (zh) 一种风机基础及用于风机基础的预应力组件
CN210439327U (zh) 一种设备基础预埋螺栓孔组装模板
KR101217488B1 (ko) 기초파일 연장구조

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120711